Official Transcript of Proceedings NUCLEAR REGULATORY COMMISSION

Title:

Advisory Committee on Reactor Safeguards Docket Number: (n/a)

Location: teleconference Date: Tuesday, October 5, 2021 Work Order No.: NRC-1708 Pages 1-55 NEAL R. GROSS AND CO., INC.

Court Reporters and Transcribers 1716 14th Street, N.W., Suite 200 Washington, D.C. 20009 (202) 234-4433

1 1

2 3

4 DISCLAIMER 5

6 7 UNITED STATES NUCLEAR REGULATORY COMMISSIONS 8 ADVISORY COMMITTEE ON REACTOR SAFEGUARDS 9

10 11 The contents of this transcript of the 12 proceeding of the United States Nuclear Regulatory 13 Commission Advisory Committee on Reactor Safeguards, 14 as reported herein, is a record of the discussions 15 recorded at the meeting.

16 17 This transcript has not been reviewed, 18 corrected, and edited, and it may contain 19 inaccuracies.

20 21 22 23 NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1323 RHODE ISLAND AVE., N.W.

(202) 234-4433 WASHINGTON, D.C. 20005-3701 www.nealrgross.com

1 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION

+ + + + +

689TH MEETING ADVISORY COMMITTEE ON REACTOR SAFEGUARDS (ACRS)

+ + + + +

TUESDAY OCTOBER 5, 2021

+ + + + +

The Advisory Committee met via Videoconference, at 1:00 p.m. EDT, Matthew W. Sunseri, Chairman, presiding.

COMMITTEE MEMBERS:

MATTHEW W. SUNSERI, Chairman JOY L. REMPE, Vice Chairman RONALD G. BALLINGER, Member VICKI M. BIER, Member CHARLES H. BROWN, JR. Member VESNA B. DIMITRIJEVIC, Member GREGORY H. HALNON, Member JOSE MARCH-LEUBA, Member DAVID A. PETTI, Member NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

2 DESIGNATED FEDERAL OFFICIAL:

ZENA ABDULLAHI ALSO PRESENT:

MORRIS BYRAM ANDREI BURGHELEA ANDERS GILBERTSON MATHEW PANICKER HANH PHAN MEHDI REISI FARD NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

3 CONTENTS Opening remarks by ACRS Chairman By Chair Matthew Sunseri 4 Framatome's LTR ANP-10349P, GALILEO Implementation of LOCA Methods By Member March-Leuba and Mr. Burghelea 7 Presentation by Staff By Mr. Panicker 16 Opening statement from staff on Draft Regulatory Guide 1.247 By Dave Petti and Mehdi Reise Fard 32 Presentation on Draft Regulatory Guide 1.247 Endorsing Non-light water reactor PRA standard By Anders Gilbertson 39 Second part of staff presentation of Regulatory Draft Guidance 1.247 By Hanh Phan 47 Closing of meeting By Chair Sunseri 55 NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

4 1 P R O C E E D I N G S 2 (1:01 p.m.)

3 CHAIR SUNSERI: All right. Good 4 afternoon. It is one o'clock Eastern Time. This is 5 Matt Sunseri and I'm now going to call to order the 6 689th full committee meeting of the Advisory Committee 7 on Reactor Safeguards.

8 I am Matthew Sunseri, Chair of the ACRS.

9 I'll now call the roll to verify quorum and that 10 effective communications exist. I'll start with Ron 11 Ballinger.

12 MEMBER BALLINGER: Here.

13 CHAIR SUNSERI: Dennis Bley? I can't 14 remember if he's supposed to be here today or not.

15 Vicki Bier?

16 MEMBER BIER: Here.

17 CHAIR SUNSERI: Charles Brown? Charles 18 Brown? Vesna Dimitrijevic?

19 MEMBER DIMITRIJEVIC: I am here.

20 CHAIR SUNSERI: Greg Halnon?

21 MEMBER HALNON: Here.

22 CHAIR SUNSERI: Jose March-Leuba?

23 MEMBER MARCH-LEUBA: Here.

24 CHAIR SUNSERI: Dave Petti?

25 MEMBER PETTI: Here.

NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

5 1 CHAIR SUNSERI: Joy Rempe?

2 MEMBER REMPE: Here.

3 CHAIR SUNSERI: Myself. I think that is 4 everybody. Did I miss anybody?

5 Okay. So Charles Brown? Dennis Bley?

6 And Walt Kirchner's not available either. So we do 7 have a quorum and we will proceed.

8 MEMBER BROWN: I'm here.

9 CHAIR SUNSERI: Okay.

10 MEMBER BROWN: It's Charlie. Couldn't 11 get my mute unmiked.

12 CHAIR SUNSERI: Your mute unmiked. Okay.

13 MEMBER BROWN: Right. That was 14 deliberate.

15 CHAIR SUNSERI: Right, right. I have two 16 left thumbs also.

17 Okay. ACRS was established by the Atomic 18 Energy Act and is governed by the Federal Advisory 19 Committee Act. The ACRS section of U.S. NRC public 20 website provides information about the history of the 21 ACRS and provides documents such as our charter, bylaws, 22 Federal Register notices for meetings, letter reports, 23 and transcripts for all full and subcommittee meetings 24 including the slides presented at the meeting. The 25 Committee provides its advice on safety matters to the NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

6 1 Commission through its publically available letter 2 reports.

3 The Federal Register notice announcing 4 this meeting was published on September 24th, 2021, 5 and provided an agenda and instructions for interested 6 parties to provide written documents or request 7 opportunities to address the Committee. The 8 Designated Federal Officer for this meeting is Ms. Zena 9 Abdullahi.

10 During this week's sessions, we plan to 11 complete two letter reports. We plan to begin our 12 deliberations of work group review of agency research, 13 leading up to, ultimately, our biannual report. And 14 we will be providing a briefing to the Commission on 15 selected topics.

16 During today's meeting the committee with 17 consider the following; and both of these are to let 18 the two letter reports that we will produce this week.

19 The first one is Framatome Topical Report on GALILEO 20 implementation of loss of coolant accident methods.

21 The second topic is Draft Reg Guide 1.247 endorsing 22 non-light water reactor probabilistic risk assessment 23 standards. Portions of the GALILEO topic may be closed 24 to protect the confidential and proprietary 25 information.

NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

7 1 A communications channel had been arranged 2 to allow members of the public to listen in on the 3 presentation and committee discussions. We have 4 received no written comments or requests to make oral 5 statements from members of the public regarding today's 6 session. There will be an opportunity for public 7 comment. We have set aside time in the agenda for 8 comments from members of the public attending or 9 listening in, and we will call for those comments at 10 the appropriate time. Written comments may be 11 forwarded to Ms. Zena Abdullahi, the Designated Federal 12 Officer.

13 A transcript of the open portion of the 14 meeting is being kept and it is requested that the 15 speakers identify themselves and speak with sufficient 16 clarity and volume so that they may be readily heard.

17 Additionally, participants should mute themselves 18 when not speaking.

19 I do not have any other pertinent opening 20 remarks to make. I will call on the members. Any 21 questions about the agenda or any comments that any 22 of the members would like to make before we get started?

23 All right, then. It looks like I will turn 24 to Member March-Leuba for the first topic and that's 25 the Framatome GALILEO implementation of the loss of NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

8 1 coolant accident methods.

2 MEMBER MARCH-LEUBA: Thank you, Mr.

3 Chairman. Thank you. Yes, we are going to be hearing 4 from Framatome and the staff about their Topical Report 5 ANP-10349P, GALILEO implementation of LOCA methods.

6 We heard many technical details about this 7 topic in our subcommittee meeting, September 21st, and 8 we are going to hear a summary now in the open session.

9 We do have a closed phone number or MS Teams room ready 10 in case we have to do some proprietary discussions, 11 but I don't anticipate having to do that.

12 With that said, I would like to give the 13 floor to Framatome to start their presentation.

14 MR. OTTO: This is Ngola. I will go ahead 15 and share my screen. Just want to make sure that works 16 for everyone.

17 MEMBER MARCH-LEUBA: I can see it.

18 MR. OTTO: Okay. Perfect.

19 MEMBER MARCH-LEUBA: So Andrei, 20 Framatome, whoever is going to talk. You have the 21 floor.

22 MR. BURGHELEA: Yes. I am here. Can you 23 hear me?

24 MEMBER MARCH-LEUBA: Yes.

25 MR. BURGHELEA: Great. So, my name is NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

9 1 Andrei Burghelea. I'm an engineer with Framatome in 2 the Westinghouse and C-LOCA group. This presentation 3 is about our implementation of the GALILEO fuel 4 performance code in our LOCA methods. And if you go 5 to the next slide, please, Ngola?

6 So I'm going to give you a brief 7 introduction, describe what is intended with this 8 topical report, how it is accomplished, and why it is 9 acceptable, and a short summary. Next slide. Thank 10 you.

11 So, currently, Framatome has two 12 evaluation models for LOCA that are approved and are 13 S-RELAP5 based. S-RELAP5 is our thermal hydraulics 14 code. A small break LOCA, which is the Topical Report 15 EMF-2328(P)(A), originally approved in March of 2001, 16 and supplemented later on with Supplement 1, which was 17 approved in December of 2016.

18 The small break LOCA evaluation model uses 19 the RODEX2 field performance code and is an Appendix 20 K-type method, so it's a conservative evaluation model.

21 For the large break LOCA, we have a 22 realistic large break LOCA evaluation model, which is 23 described in the Topical Report EMF-2103(P)(A) Revision 24 3. That was approved in June of 2016 and it uses a 25 fuel performance code COPERNIC.

NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

10 1 These are realistic evaluation methods.

2 So it's a best-estimate process. Both of these LOCA 3 evaluation models are applicable to Westinghouse 3-loop 4 and 4-loop plants and combustion engineering plants.

5 Basically, plants that have a bottom reflood.

6 MEMBER REMPE: So, this is Joy, and during 7 the subcommittee discussions, there were some questions 8 related to what else limits the applicability of these 9 methods. And I know we talked about burnup and some 10 other things like that, but I was thinking about this 11 a bit more since our subcommittee week, and I'm thinking 12 about what's being emphasized right now with industry.

13 There's an effort underway to try and go to higher 14 burnups. There's an effort to think about 15 accident-tolerant fuels.

16 Could you talk a little bit about, other 17 than it's applicable to Westinghouse 3- and 4-loop and 18 CE plants, what else are the limits associated with 19 the applicability of this methodology?

20 MR. BURGHELEA: So, right. Distinctly, 21 each method itself has its own limits. For instance, 22 for small break LOCA, we do have -- the method is 23 approved for both Zircaloy-4 and M5 cladding.

24 For realistic LOCA, it is only approved 25 for M5 cladding. The current burnups are not the NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

11 1 extended burnups we are talking about in the ATFFM 2 program, in the advance fuel methods. So they're just 3 regular fuel, and for each one of them, let's just say 4 for the small break LOCA, the limit of applicability 5 includes a limitation or condition that allows it to 6 be applied up to 10 percent of the break spectrum.

7 And for large break LOCA, there's a lot 8 more. There's like 13 limitations and conditions there 9 that kind of put limits on where it can be applied and 10 under what conditions.

11 MEMBER REMPE: So there's somewhere in the 12 document, or in the staff's SE, that says this cannot 13 be used for anything above 5 percent enriched fuel?

14 MR. BURGHELEA: I think that would be a 15 question that the staff would answer later on.

16 MEMBER REMPE: But your report doesn't say 17 we don't tend to use this for anything above 5 percent 18 enriched fuel?

19 MR. BURGHELEA: I think we say that we 20 intend to use them for the same applications that the 21 current methods are approved for. We are not extending 22 the applicability of these methods to anything that 23 includes high enriched fuel or higher burnup.

24 MEMBER REMPE: Okay. Thank you.

25 MR. BURGHELEA: Sure.

NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

12 1 MEMBER MARCH-LUEBA: This is Jose, for the 2 record, Andrei. We are -- I mean, you have submitted, 3 and it's currently review, two topical reports of 4 extended enrichment and burnups, correct?

5 MR. BURGHELEA: Right. Yes. And if we 6 go to the next slide, I was going to mention that.

7 So, the purpose of this topical report is 8 to add GALILEO to the LOCA methods. So it's 9 supplementing the existing methods to include GALILEO.

10 It does not address any of the future objectives that 11 Framatome has.

12 Increased enrichment, increased burnup, 13 chromia-doped fuel, chromium-coated cladding, these 14 are blocks that will come later on. And in the big 15 picture, this GALILEO implementation is one block in 16 this entire endeavor.

17 It serves us because GALILEO is one of the 18 foundational -- or a piece of the foundation that we 19 are building upon. It is the fuel performance code 20 that adds, or will add in the future, there capabilities 21 to our methods.

22 But, currently, this is just the vanilla 23 implementation with the same capabilities as the 24 existing methods. All the other capabilities will be 25 added later on, or are added with separate topical NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

13 1 reports that are, or have been, already submitted.

2 MR. BYRAM: Hello. This is Morris Byram, 3 licensing. Jose, I wanted to clear up something I 4 thought I heard. You asked the question if both the 5 increased enrichment and increased burnup topical 6 reports had been submitted. We have only submitted 7 the increased enrichment topical report. The high 8 burnup topical report has not been submitted yet.

9 MEMBER MARCH-LEUBA: Oh, my mistake. I 10 thought it was submitted to NRC in August. But I might 11 have the wrong information.

12 MR. BYRAM: I just wanted to clear that 13 up so we wouldn't be going under any -- yes. Thank 14 you.

15 MEMBER MARCH-LEUBA: All right.

16 MR. BURGHELEA: Okay. We can go to the 17 next slide, then. So, how is this implementation of 18 GALILEO accomplished? For the small break LOCA part, 19 this is basically a reflection of the topical report 20 content. There are the steps that we perform in there 21 to evaluate the regulatory requirements, in this case 22 NUREG-800 and Appendix K, 210 CFR 50. And then define 23 these requirements in terms of analysis purpose, 24 transient class, power plant class, figure of merit.

25 Establish an assessment database, which NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

14 1 in our case includes the LOFT test, only ones that have 2 nuclear fuel. And for small break LOCA include the 3 L3-6/L8-1 series of tests. These were also previously 4 included in Supplement 1 to EMF 2328, so it gives us 5 a baseline for comparison.

6 And then we described the EM changes and 7 present our results, which are the assessment of those 8 LOFT small break tests and a sample problem.

9 Next slide, please. For a realistic large 10 break LOCA, the implementation follows a very similar 11 approach. Obviously, there are some particular 12 changes that are specific to large break LOCA and to 13 realistic methods.

14 So, in terms of regulatory requirements, 15 there are two Regulatory Guides that direct 16 implementation and development of best-estimate 17 models, 1.157 and 1.203. And for the realistic large 18 break LOCA implementation, we took advantage of the 19 graded approach for EMDAP described in Appendix B2 Reg 20 Guide 1.203 given the limited scope changes to the 21 evaluation model.

22 We then, again, describe the evaluation 23 model requirements in the same terms as above, but for 24 large break LOCA we also include the PIRT review and 25 define an assessment base. Again, LOFT tests for large NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

15 1 break are only ones to include nuclear fuel. And in 2 this assessment database, we included the L2-3, L2-5, 3 LP 02-6, and LP-LB-1 series of tests from LOFT. Again, 4 these were previously included in EMF-2103 Rev. 3.

5 We then describe the evaluation model 6 changes and presented the results of the assessment 7 for the LOFT large break LOCA tests mentioned above, 8 and the results of a sample problem.

9 Okay. Next slide. Thank you.

10 So, was it acceptable? GALILEO is an 11 acceptable fuel performance code that has been approved 12 recently, November last year. The evaluation model 13 is an evolution that adds one fuel performance code 14 with the same functionality as the ones existing in 15 the current approved methods.

16 For the small break LOCA tests, the 17 assessment with LOFT showed good agreement with the 18 data, and the sample problem shows good agreement with 19 the current method.

20 Similarly, for the large break LOCA method, 21 the assessments show good agreement with the LOFT large 22 break LOCA tests and good agreement with the current 23 methods for the sample problem.

24 Next slide. And in summary, it is a 25 straightforward process. It's basically adding the NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

16 1 same functionality for the existing fuel performance 2 codes, COPERNIC and RODEX2, and implementing GALILEO 3 with the exact same capabilities.

4 It's an EM revolution that is supporting 5 future objectives. In both cases, the analysis 6 workflow for both methods remains unchanged. And the 7 assessments against benchmarks and the comparison to 8 the approved methods, the current approved methods, 9 show good agreement.

10 And that would be all.

11 MEMBER MARCH-LEUBA: Andrei --

12 MR. BURGHELEA: Yes, please?

13 MEMBER MARCH-LEUBA: Thank you, Andrei.

14 I think you were going to say you're done.

15 MR. BURGHELEA: Yes.

16 MEMBER MARCH-LEUBA: Okay. I spoke too 17 early. First, I'd like to correct the record. When 18 I said that extended burnup was expected in August of 19 2022, I was mistaken. The chromia-doped fuel LTR is 20 expected in August of 2022.

21 So, with that, any questions for Framatome 22 from the members, ACRS members? If not, let's move 23 to the staff, staff the presentation.

24 So Mathew, whenever you're ready.

25 MR. PANICKER: Yes.

NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

17 1 MEMBER MARCH-LEUBA: We can see your 2 slides.

3 MR. PANICKER: My name is Mathew Panicker.

4 I belong to the Nuclear Materials and Fuel Analysis 5 Branch in the Division of Safety Systems in NRR. I 6 will be talking about how the GALILEO code is 7 implemented in Framatome LOCA methods.

8 Next slide, please. I will have a few 9 slides. First thing is a summary of what we are going 10 to review, the diagrams. Some applicability of 11 regulations and guidance. Implementation of S-RELAP5, 12 which is the thermal-hydraulics code, and as a result, 13 the realistic large break LOCA analysis. Well deal 14 the implementation of S-RELAP5 and eventually in the 15 small break LOCA and some conclusions.

16 Next, please. In the Framatome realistic 17 large break LOCA methodologies, here we note the 18 accepted version, version 3, which used S-RELAP5 19 COPERNIC combination. COPERNIC is a best-estimate fuel 20 performance code, which was approved early 2000 or 21 around that time.

22 That combination is used in the 23 initialization conditions for thermal-hydraulics code, 24 which eventually will be used in large break LOCA.

25 In the small break LOCA, EMF2328, which was a supplement NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

18 1 approved in 2016, used a S-RELAP5/RODEX2 combination.

2 RODEX2 is a fuel performance code, which was earlier 3 than COPERNIC. And the combination is used in the 4 initialization conditions for thermal-hydraulics core, 5 which are normally used for small break LOCA analysis.

6 The new code, which is GALILEO, was 7 approved in late 2020 and the code is best-estimate 8 code that uses latest available data. The code models 9 thermal and mechanical behavior of the fuel rods during 10 normal and transient operations.

11 Framatome, through ANP-10349, which is the 12 current topical report, is supplementing the GALILEO 13 methodology to its realistic large break LOCA and small 14 break LOCA methodologies. Next, please.

15 Some of the applicable regulations, the 16 common one is 10 CFR 50.46, acceptance criteria for 17 ECCS; 10 CFR Part 50; GDC 35, which is evidence in core 18 cooling. The guidance of chapter 6.3 of SRP provides 19 guidance for performing system review of the ECCS; and 20 15.6.5, loss of coolant accidents of the SRP.

21 Next, please. Regarding the use of 22 GALILEO as a supplement to COPERNIC in the realistic 23 large break LOCA, the broadest analysis to S-RELAP5, 24 thermal-hydraulic fuel and thermal-hydraulic 25 calculations in realistic large break LOCA.

NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

19 1 The evaluation was done through audit, 2 which lasted for some time because it was a virtual 3 audit. The staff had access to documents for a longer 4 period of time than conventional audit. And it issued 5 the ARS to confirm the documentation of the 6 GALILEO/S-RELAP5 combination hybrid scheme, which is 7 elaborated in the topical report, as well as the closed 8 session to the ACRS.

9 And small break LOCA sensitivity analysis.

10 The LOFT tests were written, the four of them, in 11 combination, they used all configurations of the 12 reactor, scaled-down reactor, with the LOCA fuel. So 13 it is benchmarked using the coupled S-RELAP5/GALILEO.

14 And there was a sample problem, which is 15 a normal Westinghouse 3-loop reactor, which this 16 problem presented in the approved realistic large break 17 LOCA evaluation methodology topical report, EMF-2103.

18 The same problem was repeated using the new code, 19 GALILEO. We verified for the results from LOFT tests 20 and sample problem results. It indicates reasonable 21 agreement between GALILEO and COPERNIC combinations.

22 Next slide, please. Part of the small 23 break LOCA, the GALILEO code supplements the RODEX2 24 in small break LOCA analysis for S-RELAP5 25 thermal-hydraulic calculations.

NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

20 1 Again, the GALILEO was introduced into the 2 -- is used to input into S-RELAP5. For verification 3 of their methodology, two LOFT tests were used to assess 4 the base for the supplemental small break LOCA 5 evaluation model and benchmarked using the combined 6 S-RELAP5/GALILEO.

7 As soon as the sample problem was done, 8 which was done for EMF-2328, using both RODEX2 and 9 GALILEO. The sample problem results indicated 10 reasonable agreement between GALILEO and RODEX2.

11 Next slide, please. The staff found that 12 the process and the results from the supplemental 13 evaluations model for both large break and small break 14 LOCAs supplements both COPERNIC and RODEX2 with 15 GALILEO. Both LOFT tests and the sample problem 16 results shows that there is a reasonable agreement 17 between GALILEO and COPERNIC, RODEX2, or both realistic 18 large break LOCA and small break LOCA.

19 Realistic large break LOCA and small break 20 LOCA supplemental evaluations model, which is in 21 ANP-10349, which is the current topical report that's 22 the subject of discussion, satisfies applicable 23 regulations and guidance in the SRP.

24 The staff is going to put one of the 25 conclusions: Framatome shall publish the approved NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

21 1 version of ANP-10349 as a supplemental topical report 2 to the final approved versions of large break LOCA and 3 small break LOCA.

4 MEMBER MARCH-LEUBA: I know we talked 5 about this in the subcommittee; are they going to issue 6 two supplementals? One for EMF-2103, another one for 7 2328, with the same topical report? Actually how you 8 do this? I assume youve talked to Framatome and you 9 guys have a process forward to accomplish this.

10 Because the way normally you would do it, you have an 11 approved methodology, EMF-2103, and if you want to 12 modify it, you issue a supplemental to that report.

13 And then you issue a supplemental to 2328. So do you 14 want them to issue two reports with the same content?

15 MR. PANICKER: No, the EMF and the 16 ANP-10349 has both large break LOCA and small break 17 LOCA.

18 MEMBER MARCH-LEUBA: Correct, but in the 19 limitation you say that they have to issue a 20 supplemental to two existing reports. I was asking 21 if you have talked to Framatome about how they're going 22 to implement this --

23 MR. PANICKER: I talked to -- I havent 24 talked to them specifically, but my understanding is 25 that they may have only one, ANP-10349, for both.

NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

22 1 MEMBER MARCH-LEUBA: Sure. Sure, that 2 makes sense.

3 MR. PANICKER: Otherwise they are to do 4 two of them with replacing both codes in the two of 5 them.

6 MEMBER MARCH-LEUBA: It's an 7 administrative question; it's not a technical question.

8 I'm sure, when there is a will, there is a way.

9 MR. BYRAM: Jose, this is Morris Byram 10 again. We state in the topical report itself that this 11 is a supplement to both the small break and the realistic 12 large break LOCA topicals. And we're going to make 13 that statement in the submittal letter that we send 14 to the NRC, as well. So, right now, we're expecting 15 it to be a standalone topical report, and those 16 statements are made within the topical report in the 17 submittal letter.

18 MEMBER MARCH-LEUBA: And you think that 19 will be sufficient, right? I think so.

20 MR. BYRAM: Yes. Framatome believes so.

21 Yes.

22 MR. OTTO: This is Ngola. We did have a 23 discussion about that with Framatome, and the goal is 24 for us to put a statement in our summary and also for 25 them to, when they send the approved version, to include NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

23 1 that in their letter. And that's what we had agreed 2 on as far as addressing this issue.

3 MEMBER MARCH-LEUBA: Yeah. Okay. And on 4 an also administrative or non-technical question, we 5 talked during our subcommittee meeting, which was 6 relatively close, September 21st, that you were going 7 to issue a revised SER. Where are we on that step?

8 Because I haven't seen it.

9 MR. OTTO: Yes. Our schedule for issuing 10 a final safety evaluation is at the end of the month.

11 I do have a markup of that, that shows the changes 12 that we discussed with respect to -- there was a comment 13 the last time that you mentioned about when we used 14 the word replace or replaced, to say we're replacing 15 the old codes with this code. We changed the language.

16 So instead of saying replace, we did updated language 17 to say supplement or supplements or supplemented. And 18 that's in -- it occurs in maybe 12 times or so in the 19 safety evaluation, so we did go and make those updates.

20 MEMBER MARCH-LEUBA: Any other changes?

21 Let me tell you where I'm coming from. Probably within 22 the hour we'll be reading a letter, and hopefully voting 23 on it this afternoon. I am going to get some pushback 24 from members of the Committee saying that, how are we 25 approving the publication of an SER we have not seen?

NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

24 1 So can you describe us any other changes you made to 2 the one we have seen? The word replace, we understand 3 that's, yes, a typo, but --

4 MR. PANICKER: We're going to introduce 5 a couple of conditions, which were subject (audio 6 interference) in the ACRS letter. But those have to 7 be modified or amended, and that we'll discuss --

8 (Simultaneous speaking.)

9 MEMBER MARCH-LEUBA: Let me ask Ngola and 10 Framatome. If we delay issuing the letter until 11 November, would that be a problem for you guys? I mean, 12 we can finish the letter today, but since we have not 13 seen -- I mean, if you are issuing some two new 14 limitations that we haven't seen, I don't see how we 15 can recommend publication if we haven't seen it.

16 MR. OTTO: I think we can have a discussion 17 during the letter writing session with respect to some 18 of the recommendations that you have. We do have a 19 presentation that kind of outlines what are plans are.

20 And then, based on that, we can move forward with 21 respect to the changes we made.

22 MEMBER MARCH-LEUBA: We're working on the 23 FACA rules, and during the letter writing only ACRS 24 talks unless there is a factual error.

25 MR. OTTO: Okay.

NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

25 1 MEMBER MARCH-LEUBA: Or we ask you 2 specifically. So if you do have a presentation ready, 3 now is the time to do it. During the letter writing, 4 you won't be able to do it.

5 MR. PANICKER: We can do that now.

6 MR. OTTO: Okay.

7 MEMBER MARCH-LEUBA: Please do, because 8 in the letter writing only ACRS members talk and make 9 decisions. And we ask questions and you answer. And 10 youre only allowed to interrupt us if there is a factual 11 error.

12 MR. OTTO: Okay.

13 (Pause.)

14 MR. PANICKER: Shall I proceed?

15 MEMBER REMPE: You know, your responding 16 to ACRS Subcommittee recommendations. Those are 17 comments from individual members. There's no such 18 thing as an ACRS Subcommittee recommendations, so I'm 19 puzzled by that slide that was briefly on the screen.

20 MR. PANICKER: Okay.

21 MEMBER MARCH-LEUBA: Yeah, but -- okay, 22 so, that was the wrong title, but you can still put 23 the information.

24 MR. PANICKER: Okay. The recommendation 25 from the letter was: the SE report should incorporate NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

26 1 the demonstrated range of applicability the 2 methodology. The staff should --

3 MEMBER MARCH-LEUBA: Yes. That was a 4 recommendation from an individual member, which was 5 me.

6 MR. PANICKER: Okay.

7 MEMBER MARCH-LEUBA: Not from the 8 Committee.

9 MR. PANICKER: Okay.

10 MEMBER MARCH-LEUBA: And it's perfectly 11 okay. I mean, I just gave you some advice, saying that 12 during the full committee, I will argue with my 13 colleagues to create a recommendation from the 14 Committee. I gave you a heads-up during the 15 subcommittee, okay? But it was only my recommendation.

16 The full committee had not voted on it.

17 MR. PANICKER: Okay.

18 MEMBER MARCH-LEUBA: I know, its process, 19 but it's important.

20 So if we could see those slides again, you 21 can still present them and we may -- but start thinking 22 about what would be consequences if we delay our letter 23 to the next full committee.

24 MEMBER REMPE: And lets think, also, 25 Jose, that if they're trying to anticipate what a NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

27 1 recommendation is and they're going to change the 2 report, it's very much out of process. They would have 3 to update the draft SE and then let us see it 30 days 4 in advance and discuss it, and then write a letter based 5 on the new report.

6 I think it would be better to stay in 7 process. Stick with the SE that they have, wave us 8 write the letter with some suggested changes, and go 9 forward. I think this is a bit unusual for the staff 10 to be so forward-leaning on this.

11 MEMBER MARCH-LEUBA: I understand what 12 you're saying. And at this point I would ask the 13 parliamentarian. I'm perfectly happy to write a letter 14 on the draft SE, and when the staff reconciles or if 15 they say, we have updated the SER to acknowledge your 16 recommendations, and here it is.

17 MEMBER REMPE: Because what the letter has 18 in it may change based on our discussions during letter 19 writing. And so they're chasing a moving target, is 20 what I'm trying to say.

21 MEMBER MARCH-LEUBA: Okay. So at this 22 point I'm going to ask the Chairman, since we don't 23 have a parliamentarian in town. Matt, I don't know 24 if you have been following the situation.

25 One option, Plan A, is to continue with NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

28 1 our letter with the draft SE as we know it and issue 2 it. Another option, Plan B, would be to wait until 3 an updated SE exists and we will reconsider it either 4 in November or December and issue a letter then. And 5 I guess that's it.

6 CHAIR SUNSERI: Well, I mean, it's bad 7 choices either way, right?

8 MEMBER MARCH-LEUBA: I kind of like Joy's 9 proposal: issue the letter on the draft SE, and during 10 reconciliation the staff can tell us, this is how we 11 addressed your comments, and we'll tell them thank you 12 very much, if we agree with them.

13 It's the fastest and easiest way. I think 14 what Joy suggested is the fastest and easiest way.

15 MEMBER REMPE: And it's the way we normally 16 do things. If they wanted to change the report, they 17 could have withdrawn it after the subcommittee meeting 18 and said, we think ACRS has brought up a major issue 19 and we don't want to go forward with this until we send 20 you an updated SE.

21 But, with fairness to the staff, chasing 22 a moving target based on what they heard in a 23 subcommittee meeting, and may not appear in the letter 24 when it's all said and done, or we may have new findings 25 that they didn't address and they can keep updating NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

29 1 things a lot. So this is just the normal way things 2 progress.

3 MEMBER MARCH-LEUBA: Yeah. And 4 furthermore, the issues I raised are minor. They're 5 more editorial than real technical problems. So I'm 6 voting with Joy. But, Matthew, I think you have the 7 last voice.

8 CHAIR SUNSERI: Well, I mean, either way 9 is acceptable. I mean, I'm going to lean on the 10 subcommittee chair, if you feel confident to proceed 11 forward with a letter report on a draft document. And 12 then we can write a letter at any time on anything, 13 right? When is it final?

14 MEMBER MARCH-LEUBA: Okay. So we're 15 proceeding with our plan. And staff you can save the 16 -- sorry you had to prepare so much slides for this, 17 but you can save it for the reconciliation package when 18 you receive our letter. And maybe when we do the 19 letter, those recommendations won't even be there, 20 because, as I said, they're minor. They're editorial.

21 MR. OTTO: Not a problem. You know, we'll 22 wait for the letter and then we'll address whatever 23 comments in the final safety evaluation.

24 MEMBER MARCH-LEUBA: Excellent. Any 25 member of the Committee wants to make any comments or NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

30 1 questions?

2 Any member of the public want to make any 3 comments or questions?

4 CHAIR SUNSERI: So the members of the 5 public would have to unmute their Teams channel and 6 then make their comment.

7 MEMBER MARCH-LEUBA: I don't hear anybody, 8 Matt. So, Mr. Chairman, I hand over the Committee back 9 to you. I will suggest that we have our 10- to 15-minute 10 break and transition to letter writing.

11 CHAIR SUNSERI: Let me see what time is 12 it? 10:42, yes, we can do that. That's a good 13 recommendation. So we will go onto recess until two 14 o'clock, and then at two o'clock we will begin the 15 read-in of your -- you have a draft ready to go, right, 16 Jose?

17 MEMBER MARCH-LEUBA: Yes, it is.

18 CHAIR SUNSERI: Okay.

19 MEMBER MARCH-LEUBA: It's short.

20 CHAIR SUNSERI: We'll proceed with that.

21 All right. We are recessed until 2:00 p.m.

22 (Whereupon, the above-entitled matter went 23 off the record at 1:43 p.m. and resumed at 3:45 p.m.)

24 CHAIR SUNSERI: All right. It's 3:45.

25 This is Matt Sunseri. We'll reconvene the 689th ACRS NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

31 1 meeting. I'm going to start with a roll call since 2 this is a new topic.

3 Ron Ballinger?

4 MEMBER BALLINGER: Here.

5 CHAIR SUNSERI: Charles Brown?

6 MEMBER BROWN: Here.

7 CHAIR SUNSERI: Vesna Dimitrijevic?

8 MEMBER DIMITRIJEVIC: Here.

9 CHAIR SUNSERI: Greg Halnon?

10 MEMBER HALNON: Here.

11 CHAIR SUNSERI: Jose March-Leuba?

12 MEMBER MARCH-LEUBA: I'm back here.

13 CHAIR SUNSERI: Dave Petti?

14 MEMBER PETTI: Here.

15 CHAIR SUNSERI: Joy Rempe?

16 MEMBER REMPE: Here.

17 CHAIR SUNSERI: And myself. So that's the 18 expected crowd right now. And I forgot to check, do 19 we have the court reporter back on? I see him on my 20 list, so I guess so.

21 All right. We will get started here, then.

22 This topic is on Draft Reg Guide 1.247, endorsing 23 non-light water reactor probabilistic risk assessment 24 standard.

25 And I'm going to turn to Member Petti to NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

32 1 lead this discussion. Dave?

2 MEMBER PETTI: Okay. So this is a 3 follow-up from the subcommittee meeting we had earlier.

4 We're going to hear from the staff. But, before that, 5 I guess we're going to hear from RES management if they 6 would like to make an opening statement.

7 MR. REISI FARD: Good afternoon. My name 8 is Mehdi Reise Fard, I'm the branch chief for the 9 Performance and Reliability Branch in the Office of 10 Nuclear Regulatory Research.

11 First of all, I want to thank the committee 12 for the opportunity to present the draft of Reg Guide 13 1.247, which is the acceptability of probabilistic risk 14 assessment results for advanced non-light water reactor 15 risk-informed activities.

16 As you'll hear today in the staff 17 presentation, this guidance, you'll be able to call 18 on our team and find PRA information and risk-informed 19 approaches in our regulatory activities related to 20 advanced non-light water reactor.

21 I want to start with a few points about 22 the driver behind the non-light water reactor PRA 23 acceptability project. The organization and execution 24 of the staff's effort to develop and publish Reg Guide 25 1.247 have been a substantial and unprecedented NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

33 1 undertaking given the project scope and the timeframes 2 the NRC staff committed to meet.

3 In January 2019, the Nuclear Energy 4 Innovation and Modernization Act -- or NEIMA -- was 5 signed into law, which created a driving force for the 6 NRC to prepare for anticipated new applications for 7 advanced reactors.

8 Before NEIMA, the staff had no near-term 9 plans to endorse a consensus standard for advanced 10 non-light water reactor PRA.

11 However, NEIMA accelerated the need for 12 the standards of local inter-organizations to publish 13 and for the NRC to endorse a consensus standard for 14 advanced non-light water reactor PRA.

15 So the staff had to quickly organize and 16 plan for their efforts in anticipation of the 17 publication of the PRA standard.

18 Besides the accelerated schedule, another 19 unique aspect of this standard endorsement is that the 20 scope of this standard is broader than the scope of 21 any previously considered or endorsed PRA consensus 22 standard.

23 The scope includes all radiological 24 hazards -- sources, hazards, plant operating states, 25 and all levels of analysis. Because of the NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

34 1 relationship between the non-light water reactor and 2 related light water reactor PRA standards, and because 3 we anticipate endorsing the future light water reactor 4 PRA standards, the staff recognized early the need to 5 endorse positions on the non-light water reactor PRA 6 standard to ensure positions under non-light water 7 reactor PRA standard would be consistent with 8 anticipated future endorsements.

9 I'll also highlight a few points about the 10 process and the staff efforts so far. As I stated 11 earlier, staff developed an aggressive schedule to 12 issue this Reg Guide.

13 Staff have achieved key project milestones 14 to date. Developing this guidance required extensive 15 coordination across different groups to establish the 16 staff position with a singular and consistent 17 narrative.

18 Given the NRC's completion schedule and 19 the projects complexity, several steps in the 20 publication process are performed in parallel.

21 Therefore, the internal concurrence review process is 22 somewhat dynamic.

23 We are currently considering feedback on 24 the Reg Guide and slight adjustments in the schedule 25 to address the feedback.

NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

35 1 With that, I conclude my opening remarks.

2 We greatly appreciate this opportunity today and we 3 look forward to your comments.

4 MEMBER PETTI: Okay. Thank you. So now 5 I guess we'll go to the slides and either Anders or 6 Hanh, whoever's going to start.

7 MR. GILBERTSON: Yes. Thank you. Good 8 afternoon, committee members. My name is Anders 9 Gilbertson. I am a reliability and risk analyst in 10 the Office of Nuclear Regulatory Research.

11 I'll be presenting today with Hanh Phan 12 who is a senior reliability and risk analyst in the 13 Office of Nuclear Reactor Regulation. And we'll be 14 presenting to you on the staff's development of the 15 trial use Reg Guide 1.247.

16 Next slide, please. This is slide 2 for 17 anyone on the phone.

18 So first, I will go over a brief background 19 followed by discussions of the regulatory paradigm and 20 the staff development approach for Reg Guide 1.247, 21 and then a comparison with Reg Guide 1.200, which is 22 the starting point or the foundational document for 23 1.247.

24 I will then wrap up my portion with a 25 discussion of the novel staff positions in Reg Guide NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

36 1 1.247. And after that, Hanh Phan will talk more about 2 the staff endorsement of the non-LWR PRA standard and 3 NEI 20-09, the industry peer-review guidance document.

4 And then he'll conclude with the discussion 5 of the next steps in our process.

6 So slide 3, please.

7 Okay. So Mehdi already touched on that 8 first point. So I won't spend time on that. So I'll 9 just move on to the second point.

10 The staff, after the effort was organized, 11 we worked toward developing a draft white paper that 12 related to a set of non-LWR PRA acceptability issues 13 that were under consideration for Reg Guide 1.247.

14 Subsequent to making that publicly 15 available, the staff did hear public feedback on the 16 white paper, which helped inform the development of 17 the Reg Guide.

18 The publication of the non-LWR PRA standard 19 in February of this calendar year was a substantial 20 effort by the ASME and ANS Joint Committee on Nuclear 21 Risk Management -- or JCNRM -- and the staff did 22 participate in the process, the consensus standard 23 development process.

24 So we did provide feedback and offer 25 technical expertise to that end. Regarding NEI 20-09, NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

37 1 likewise, that document was largely modeled after the 2 industry guidance on PRA peer review for LWRs in NEI 3 17-07, which was endorsed in Reg Guide 1.200, revision 4 three. But like the PRA standard, the development of 5 NEI 20-09 was also informed by NRC feedback.

6 Later on -- or I guess earlier this last 7 month, the staff issued a draft version of the trial 8 use Reg Guide 1.247 in advance of the ACRS subcommittee 9 briefing. And that was the first opportunity the public 10 has had to review the actual contents of the proposed 11 regulatory guide.

12 We've already heard some feedback, both 13 from the subcommittee and from members of the public, 14 in particular the JCNRM, some of the JCNRM members.

15 And staff are presently eager to hear and are actively 16 considering all feedback on this draft as we finalize 17 the Reg Guide for publication.

18 Following publication, there will be a 19 trial use period. The length of that trial use period 20 will depend on a number of activities including gaining 21 sufficient experience with the use and application of 22 Reg Guide 1.247 to help inform any needed changes to 23 the Reg Guide and JCNRM publication of multiple other 24 LWR consensus PRA standards, which the non-LWR PRA 25 standard is intimately related to and will eventually NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

38 1 be brought into alignment with those LWR PRA standards.

2 Okay. Slide 4, please.

3 So now I'd like to talk generally about 4 the regulatory paradigm that Reg Guide 1.247 is expected 5 to operate in. Regarding regulatory requirements, Reg 6 Guide 1.247 is not intended to meet any one specific 7 requirement. However, like Reg Guide 1.200, it is used 8 to determine the acceptability of a PRA that is used 9 to support a regulatory decision.

10 Now, at the moment, a PRA is currently 11 required for new Part 52 applications. However, while 12 it's not required for Part 50 application, a PRA may 13 be used in support of such an application. Reg Guide 14 1.247 is expected to eventually be applicable to 10 15 CFR Part 53 on the risk-informed technology-inclusive 16 regulatory framework for advanced reactors. But the 17 Reg Guide won't speak to that and doesn't speak to it 18 now because that is -- it's an incomplete activity and 19 the staff don't -- we avoid talking to future activities 20 in Reg Guides.

21 So, the next point. I'll talk in a few 22 slides about a few general comparisons, like I said, 23 but at a higher level I wanted to point out that the 24 use of Reg Guide 1.247 in risk-informed decision making 25 is intended to reduce the need for an in-depth review NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

39 1 of PRA by the staff.

2 Now, this is different from Reg Guide 3 1.200, which relates more to obviating the need. And 4 this is primarily because of the difference in the scope 5 of regulatory activities addressed in the two Reg 6 Guides.

7 In particular, Reg Guide 1.200 is primarily 8 used for voluntary risk-informed regulatory 9 activities, whereas Reg Guide 1.247 may be used for 10 a PRA that is required by a regulation and to establish 11 a licensing basis. In that regard, the staff will have 12 greater regulatory latitude in the context of Reg Guide 13 1.247 to request additional information as needed since 14 the PRA under consideration is being used to meet 15 regulatory requirements.

16 Now, talking about the term application.

17 In Reg Guide 1.200, that term is used mostly to refer 18 to voluntary regulatory activities occurring after the 19 issuance of a license. However, because of the range 20 of potential regulatory activities for non-LWRs that 21 Reg Guide 1.247 may be used for, the term application 22 in Reg Guide 1.247 refers to both initial licensing 23 regulatory activities and risk-informed regulatory 24 activities that follow the issuance of a license 25 certification or permit.

NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

40 1 And finally, peer reviews are an integral 2 part of the non-LWR PRA standard. The non-LWR PRA 3 standard requires a peer review of the PRA and provides 4 requirements on the performance of a peer review. And 5 further, NEI 20-09 provides industry guidance on the 6 peer review process. And Hahn will go into that in 7 a little more detail.

8 And so if --

9 MEMBER DIMITRIJEVIC: I have a question.

10 MR. GILBERTSON: Yes.

11 MEMBER DIMITRIJEVIC: If I could just 12 summarize what I just heard. Are you basically saying 13 that peer review of the PRA would not only be required 14 for risk-informed application, but also for the 15 licensing submittals for like design certification and 16 things like that, is that what you just said?

17 MR. GILBERTSON: They are not required as 18 a regulatory requirement. However, if someone wants 19 to use Reg Guide 1.247 to demonstrate the acceptability 20 of their PRA, included as part of that the staff have 21 endorsed those peer-review requirements that are in 22 the PRA standard and we've endorsed the PRA standard 23 -- the non-LWR PRA standards approach to having a peer 24 review be performed.

25 So it's --

NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

41 1 MEMBER DIMITRIJEVIC: So there is a 2 difference of the current situation. That's what I'm 3 trying to say.

4 MR. GILBERTSON: Yes. Yes. Thats --

5 MEMBER DIMITRIJEVIC: Okay. All right.

6 MR. GILBERTSON: -- that is correct.

7 MEMBER DIMITRIJEVIC: Okay.

8 MR. GILBERTSON: Yes. Okay. We can move 9 on to slide 5 now.

10 Okay. So I'll talk a little bit now about 11 a slightly more direct comparison of Reg Guides 1.247 12 and 1.200.

13 Just to go over some of the similarities, 14 you know, most of the PRA elements in Reg Guide 1.247 15 have analogous elements in Reg Guide 1.200.

16 Both documents provide guidance on what 17 is an acceptable PRA using voluntary consensus 18 standards in a peer-review process, acceptability of 19 a PRA for an application and documentation needed to 20 support a regulatory decision.

21 Both guidance documents provide a list that 22 includes, but is not limited to, hazards and hazard 23 groups that should be considered in the development 24 of a PRA. And the scope of both documents includes 25 addressing all hazards and hazard groups.

NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

42 1 Now, regarding some of the differences --

2 notable differences, as I mentioned before, Reg Guide 3 1.247 relates to the PRA acceptability for a PRA that 4 may be used to meet regulatory requirements. Which, 5 again, is different from the voluntary regulatory 6 activities under Reg Guide 1.200.

7 There are four novel staff positions in 8 Reg Guide 1.247 and I'll go into that on the next slide.

9 Regarding risk significance, determination, guidance 10 on making that determination includes that relative 11 risk-significance criteria should be used to develop 12 the PRA. However, that doesn't mean that the use of 13 absolute or relative risk-significance criteria may 14 not occur in an application. And that will be 15 application specific. So that's just to say that you 16 could have an application that is only focused on 17 absolute risk-significance criteria to determine 18 what's important.

19 And then finally, consistent with the 20 approach in the non-LWR PRA standard, Reg Guide 1.247 21 does not refer to discrete levels of PRA analysis like 22 level one, level two, or level three.

23 So we have taken the same approach where 24 it's a -- it's starting from initiator and the analysis 25 extends all the way out to consequence.

NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

43 1 Slide 7, please.

2 Okay. So now I'll just go over some of 3 these novel staff positions. Regarding the first one, 4 I should make a slight correction. You know, that says 5 plant operating states for all POSes. What that should 6 really say is plant operating states for all types of 7 POSes.

8 So what that means is that we've 9 acknowledged that there may be more than one type of 10 a given plant operating state. For example, for at 11 power for, as we have talked about it, for low-power 12 -- for light water reactors.

13 So there could be a type of at power plant 14 operating state that is distinct enough from the normal 15 steady state operation of a plant, such as online 16 refueling. They're refueling at full power kind of 17 thing.

18 Reg Guide 1.200 does address the low-power 19 shutdown mode of operation for LWRs, but it's limited 20 to consideration of internal events and for up to a 21 level two PRA.

22 So like Mehdi had mentioned at the 23 beginning, Reg Guide 1.247 goes well beyond the scope 24 of Reg Guide 1.200.

25 Regarding internal fire low-power shutdown NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

44 1 types of plant operating states, there were no 2 requirements developed for this PRA scope item in the 3 non-LWR PRA standard. So accordingly, for applications 4 that include internal fire PRA for low-power shutdown 5 types POSes, the acceptability of the PRA would be 6 determined based on the related staff positions in 7 Section C.

8 And then finally, with that point, I wanted 9 to note that research -- the Office of Research has 10 initiated an effort -- a research effort into developing 11 the guidance on an acceptable method for developing 12 an internal fire PRA for low-power shutdown types of 13 plant operating states. So that is an in-progress effort 14 that we've initiated relatively recently.

15 As far as the radiological consequence PRA 16 element, the staff position is largely driven by 17 anticipated licensing modernization project -- or LMP 18 -- applications, which will require analysis of 19 frequency and consequence of radiological risk. For 20 applications that do not use LMP, it is still considered 21 important to meet the Commission expectations as 22 expressed in various policy statements.

23 And then I want to just briefly apologize.

24 That last bullet there for radiological consequence, 25 the they, that pronoun there is referring to risk NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

45 1 surrogates. So the point really is just that it is 2 possible that risk surrogates could be used, which would 3 be consistent with Commission direction.

4 However, such surrogates would need a 5 strong justification for how and why they represent 6 the consequence-risk metrics and how they would meet 7 those Commission expectations, which is generally 8 expected to be fairly challenging. And I should also 9 point out that the non-LWR PRA standard does not 10 accommodate the use of risk surrogates. It talks about 11 intermediate risk metrics that may be used in the course 12 of an analysis, but not a surrogate, if you will.

13 And then, finally, for risk integration, 14 the staff position on risk integration is -- again, 15 is anchored in the Commissions expectations as it 16 relates to policy statements and meeting the 17 quantitative health objectives.

18 Another aspect of the staff position is 19 that although a specific type of application may not 20 use relative importance measures, the criteria for 21 determining risk significance during the development 22 of a PRA should always relate to relative importance 23 measures.

24 And then, risk reporting thresholds are 25 not considered in the staff position in Reg Guide 1.247, NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

46 1 as those are considered on an application-specific 2 basis. And application-specific guidance beyond that 3 for LMP is expected to be developed in the future, but 4 it was not included within the scope of Reg Guide 1.247.

5 So that concludes my portion of the 6 presentation. I would like to now hand it off to Hahn 7 Phan unless there are any questions. Okay. Thank you.

8 Hahn?

9 MR. PHAN: Thank you, Anders. Good 10 afternoon. My name is Hahn Phan. Im a senior PRA 11 analyst in NRR, Division of Advanced Reactors. In the 12 second half of this presentation, I will focus on the 13 staff positions documented in Appendix A of Reg Guide 14 1.247.

15 Before getting to them, I would like to 16 briefly outline the scope of this Reg Guide. The staff 17 guidance and position in Reg Guide 1.247 applied to 18 all non-light water reactors, risk-informed regulatory 19 activities, and for all applications including 20 construction permits and operating license under 10 21 CFR Part 50 and the standard design certification 22 combined license, standard design approval, and 23 manufacturing license under 10 CFR Part 52.

24 Furthermore, Reg Guide 1.247 is the Reg Guide 25 coordinating with the ongoing 10 CFR Part 53 rulemaking NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

47 1 effort.

2 However, this Reg Guide only applies to 3 the stationary non-LWRs, which miss that. The reactors 4 that are constructed at an off-site facility and 5 subsequently transported and installed at the site are 6 those modular reactors, which could be relocated to 7 multiple sites. They are not covered by this Reg Guide.

8 Next slide, please. Slide nine.

9 Reg Guide 1.247 endorsed all 18 technical 10 elements in the non-LWR PRA standard I've listed on 11 this slide. In addition to that, it endorsed the 12 definition and risk assessment application guidance, 13 the PRA configuration control, the peer review 14 requirements, the newly developed methods and the note 15 in the nonmandatory appendices of the standard.

16 Next, please. Slide 10.

17 You may wonder and ask why there are so 18 many, over 100 staff positions in the Reg Guides. How 19 significant are they? What does that mean to the 20 attribute condition of the standard and so on?

21 First, I want to highlight that the non-LWR 22 PRA standard is in essence an American national 456-page 23 standard, which includes approximately 247 high-level 24 requirements; 1,233 supporting requirements; 670 notes 25 in the nonmandatory appendices; 238 definitions and NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

48 1 all the technical discussions in the main chapters.

2 On those, these numbers look big. It 3 should be recognized that about 80 percent of the 4 requirements in the PRA standard was taken as-is from 5 the light water reactor PRA standard, which many of 6 these requirements have been endorsed in Reg Guide 7 1.200.

8 During the first part of last year, the 9 NRC staff reviewed the standard and submitted 489 10 comments out of 1,319 total comments portionate 11 (phonetic).

12 During the recirculation ballot, the NRC 13 staff provided an additional 70 comments out of the 14 total 86 comments submitted.

15 Next, please. Slide 11.

16 However, the JCNRM did not incorporate all 17 NRC comments. For about 20 of 70 staff comments, the 18 JCNRM proposed and said that these comments need to 19 be addressed in the light water reactor PRA standard 20 first.

21 Eight comments would consider as 22 regulatory issue. Some comments was a stretch and fell 23 short in satisfying the staff expectation.

24 Some comments were not fully addressed by 25 the JCNRM. In addition to this, some staff position NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

49 1 in Reg Guide 1.247 was developed to be consistent with 2 the position in Reg Guide 1.200, revision three. And 3 some new consideration, the staff identified after 4 balloting.

5 Next please, slide 12.

6 So similar to Reg Guide 1.200, it's 7 supporting requirements in the PRA standard is binned 8 into one of the three groups. No objection; no 9 objection with clarification; or no objection subject 10 to the following qualification.

11 Regarding the staff position in the Reg 12 Guides, its position is categorized into either the 13 second or third group. The second group no objection 14 with clarification.

15 It's missed that. The staff has no 16 objection to the requirement. However, the 17 requirements as written, its not clear. And 18 therefore, the staff provided its understanding of the 19 requirements.

20 So if not that, the position it assigned 21 to the third group, no objection subject to the 22 following qualification, which missed that. These 23 positions, the staff has a technical concern with the 24 requirements and will write a qualification to resolve 25 the concern.

NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

50 1 Next, please. Slide 13.

2 There are currently 147 staff endorsement 3 positions in Reg Guide 1.247, Appendix A. 33 are 4 qualifications, and 114 are clarifications.

5 Within these positions, many of them are 6 considered to be more substantive than the others.

7 These positions are relevant to the low-power and 8 shutdown external events, errors of commission, risk 9 significance, and reporting requirements.

10 In general, the staff advised that the ASME 11 ANS, A-S-1.4-2021 PRA standard for non-light water 12 reactors is reasonable.

13 This can be used to assess the 14 acceptability of a PRA performed to support an 15 application while taking into consideration the staff 16 position in Reg Guide 1.247.

17 Note that these staff positions may change 18 after considering the ACRS comments. On those, there 19 are 147 staff positions in the record. If compared 20 against the technical information and requirements in 21 the PRA standard, the overall findings is not that 22 significant.

23 The staff continues to revise the records 24 by engaging with the public and JCNRMs to reduce the 25 numbers of staff position and modify the text, if NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

51 1 needed, to make the Reg Guides easy to follow.

2 Next, please. Slide 14.

3 The staff also endorsed NEI 20-09 in Reg 4 Guide 1.247, which is the guidance to conduct a peer 5 review for a non-LWR PRA.

6 NRC staff received revision zero of any 7 (audio interference) last year on June 1st. The staff 8 reviewed and provides observation to NEI's during three 9 public meetings.

10 NEI addressed the staff comments and 11 submitted revision one on May 5th this year. NEI 12 20-09's revision 1 is based on a related PRA 13 peer-reviewed guidance documents.

14 NEI 17-07, revision two, entitled 15 Performance of PRA Peer Reviews Using the ASME ANS PRA 16 Standard as Endorsed by Reg Guide 1.200, Revision 3.

17 The staff finds that the guidance in NEI's 18 20-09 revision 1 is acceptable and thus endorsed the 19 documents with no exception.

20 Next, please. Slide 15.

21 This is my last slide on the part. The 22 staff did address comments from the ACRs and the 23 external stakeholders. The staff to hold public 24 meetings in early November to go over the ACRS feedback 25 and gather public comments.

NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

52 1 The staff to issue Reg Guide 1.247 for trial 2 use by early next year. Note that the staff has not 3 yet set the duration for the trial-use periods depending 4 on timing of the next revision of the non-standard UR 5 (phonetic) PRA standard. The Part 50 and 53 (audio 6 interference) and feedback from the early users.

7 The staff will continue to brief ACRS on 8 future changes to the Reg Guides. I have now come to 9 the end of the presentation. Thank you so much for 10 your time, and at this point we will take any questions 11 that you may have.

12 MEMBER PETTI: Yes. This is Dave. Just 13 a question, have you made any changes since our 14 subcommittee meeting in September?

15 MR. PHAN: Not yet. We took --

16 MEMBER PETTI: Not yet. Thank you.

17 Other members, questions, comments?

18 Okay.

19 MEMBER DIMITRIJEVIC: Hi, this is Vesna.

20 I have a question for Hanh. Are you expecting that 21 those things where you have, you know, the -- this --

22 main comments will be resolved in the next PRA standards 23 and that will change the position? You know, in that 24 third category.

25 MR. PHAN: Would you please be more NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

53 1 specific on which areas?

2 MEMBER DIMITRIJEVIC: Okay. When -- for 3 every of these, the, you know, supporting the 4 requirements, you have a three out, but one is that, 5 you know, the accepted need clarification and then the 6 third one is, you know, need the -- how do you call 7 the third one. I don't have a slide. If you go back 8 to that -- right. No objection subject to the following 9 qualification.

10 Do you think that next version of the 11 standards will address some of those third categories?

12 MR. PHAN: Personally, I don't think so.

13 MEMBER DIMITRIJEVIC: Why?

14 MR. PHAN: For example, the fire during 15 low power and shutdowns, there are no requirements for 16 fires during low power and shutdown in the standard.

17 So within a couple years, that what I think when we 18 will issue a revision, I don't think that's sufficient 19 time to address that concern.

20 So that qualification position will be 21 opened until then. For other areas like errors of 22 commission or risk significance, the staff is working 23 on the white paper and engaged the industry on those 24 topics.

25 Hopefully, we resolve those items before NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

54 1 the issuance of the next revision. So there are 33 2 qualification position; hopefully, we will resolve 3 about half of them by then.

4 MEMBER DIMITRIJEVIC: Okay. Thank you.

5 MR. PHAN: Thank you.

6 MEMBER PETTI: Other members? Okay, how 7 about members of the public? You can unmute, identify 8 yourself, ask your question.

9 CHAIR SUNSERI: Members of the public may 10 have to press *6 to unmute.

11 MEMBER PETTI: Well, not hearing anything, 12 I guess we can close this session, Mr. Chairman, and 13 turn it back over to you. I thank the staff for the 14 presentations.

15 CHAIR SUNSERI: Yes. Thank you, Dave, and 16 thank you, staff, for the presentation.

17 At this time -- excuse me. At this time 18 we do not have a draft letter report quite ready yet.

19 We'll pick that up tomorrow. So we've kind of -- weve 20 reached the end of our, at least, published agenda for 21 today.

22 (Whereupon, the above-entitled matter went 23 off the record at 4:27 p.m.)

24 25 NEAL R. GROSS COURT REPORTERS AND TRANSCRIBERS 1716 14th STREET, N.W., SUITE 200 (202) 234-4433 WASHINGTON, D.C. 20009-4309 www.nealrgross.com

Trial Use RG 1.247 Acceptability of Probabilistic Risk Assessment Results for Advanced Non-Light Water Reactor Risk-informed Activities Briefing for the Advisory Committee on Reactors Safeguards Full Committee Anders Gilbertson Hanh Phan, Reliability and Risk Analyst Senior Reliability and Risk Analyst Office of Nuclear Regulatory Research Office of Nuclear Reactor Regulation October 5, 2021 1

Presentation Outline

  • Background
  • Next steps 2

Background

  • NEIMA signed into law in January 2019; Staff immediately began organizing effort to endorse the NLWR PRA standard
  • Staff issued draft white paper on NLWR PRA acceptability issues 1/15/2021 (ML21015A434)
  • RG 1.247 trial use period will allow experience to be gained and lessons learned on its use
  • NRC has participated throughout the consensus standards development process, including providing feedback on proposed PRA standards and industry guidance documents 3

RG 1.247 Regulatory Paradigm

  • RG 1.247 may be used to meet regulatory requirements related to the use of PRA
  • The use of RG 1.247 helps reduce the need for an in-depth review of the PRA (RG 1.200 relates to obviating the need)
  • RG 1.247 defines an application more broadly to accommodate design, construction, and operational regulatory activities
  • Peer reviews are important for establishing confidence in a PRA for RIDM and required by the NLWR PRA standard 4

RG 1.247 Development Approach

- Organization and substance of content in RG 1.247 broadly mimics that of RG 1.200

  • Staff positions in RG 1.247 consider the close relationships between the NLWR and LWR PRA standards
  • Staff have considered the potential impact on future endorsements of LWR PRA standards 5

RG 1.247 v. RG 1.200 Comparison Some Similarities Some Differences Most PRA elements addressed in RG 1.247 have an RG 1.247 directly relates to meeting regulations analog in RG 1.200 Both provide guidance to applicants and licensees on: RG 1.247 provides staff positions on the acceptability

  • What is an acceptable PRA of PRA technical aspects for NLWRs that have not previously been provided for LWRs in RG 1.200
  • The use of voluntary consensus standards and an acceptable peer review process
  • Plant Operating State Analysis for all POSs
  • Demonstrating the acceptability of a PRA for an
  • Internal fire PRA for LPSD-types of POSs application
  • Radiological consequence
  • PRA documentation needed to support a regulatory
  • Risk Integration decision Both provide a table that includes, but is not limited to RG 1.247 provides specific guidance on determining hazards that should be considered in the development risk significance and the use of relative and absolute of a PRA importance measures Both address all hazards and hazard groups RG 1.247 does not refer to discrete levels of PRA analysis such as Level 1, Level 2, or Level 3 PRA 6

Novel Staff Positions in RG 1.247 PRA Element Some Considerations

  • In addition to the possibility of PRAs for multiple LPSD-types of POSs, the staff position considers that there may be more than one type of at-power POS (e.g., online Plant Operating refueling)

States for all POSs

  • Staff position considers the potential need for a similar staff position for LWRs in the future Internal fire PRA for
  • Staff position accounts for the potential need for a similar staff position for LWRs LPSD-types of POSs
  • NRC initiating a research project to develop guidance
  • LMP applications evaluate frequency and radiological consequence risk
  • It is important to meet Commission expectations as expressed in various policy Radiological statements Consequence
  • Though not required, Commission direction in SRM-SECY-82-102 dictates that they may be used
  • Basis for staff position relates to meeting Commission expectations, as expressed in the Advanced Reactor Policy Statement, which in turn references the Safety Goal Policy Statement and the importance of meeting the QHOs Risk Integration
  • Unless justified, relative risk significance criteria should be used to develop the PRA.
  • Staff determination of PRA acceptability does not include consideration of risk reporting thresholds 7

Regulatory and Applicability Aspects

  • RG 1.247 applies to risk-informed NLWR regulatory activities under:

- 10 CFR Part 50 (construction permit, operating license)

- 10 CFR Part 52 (standard design certification, combined license, standard design approval, manufacturing license)

  • RG 1.247 applies to stationary NLWRs only 8

Endorsed Technical Elements All 18 technical elements in NLWR PRA standard:

1. Plant Operating State Analysis 10. Seismic PRA
2. Initiating Event Analysis 11. Hazards Screening Analysis
3. Event Sequence Analysis 12. High Wind PRA
4. Success Criteria Development 13. External Flooding
5. Systems Analysis 14. Other Hazards PRA
6. Human Reliability Analysis 15. Event Sequence Quantification
7. Data Analysis 16. Mechanistic Source Term Analysis
8. Internal Flood PRA 17. Radiological Consequence Analysis
9. Internal Fire PRA 18. Risk Integration and ASME/ANS RA-S-1.4-2021:
  • Definitions and risk assessment application
  • PRA configuration control
  • Notes in the nonmandatory appendices
  • Peer review requirements
  • Newly developed methods 9

Some Background Information

  • NLWR PRA standard includes about:

- 247 high level requirements (HLRs)

- 1,233 supporting requirements (SRs)

- 617 notes in the nonmandatory appendices

- 238 definitions

  • About 80% of the requirements in the NLRW PRA standard were taken as-is from the set of LWR PRA standards
  • NRC staff submitted 489 comments during the first consideration ballot (May 2020)
  • NRC staff submitted 70 comments during recirculation ballot (August 2020) 10

Bases for the Staff Positions

  • JCNRM did not address about 20 staff comments during ballot process stating that comment needs to be addressed first in the LWR Level 1/LERF PRA standard
  • 8 comments were considered as regulatory issues
  • Some comments were not satisfactorily addressed during balloting
  • Some comments were not fully addressed by the JCNRM
  • Staff positions in RG 1.247 were developed to be consistent with the staff positions in RG 1.200, Rev. 3
  • New considerations after balloting 11

Staff Position Categories Each staff position is categorized into:

  • No objection - The staff has no objection to the requirement
  • No objection with clarification - The staff has no objection to the requirement, however, clarified its understanding of these requirements Generally speaking, this includes cases where a statement is judged to be ambiguous enough to be mis-interpreted and the acceptability of the PRA may be impacted
  • No objection subject to the following qualification - The staff has a technical concern with the requirement and provided a qualification to resolve the concern Generally speaking, this includes cases where a statement is judged to have a specific technical issue and the acceptability of the PRA may be impacted 12

Staff Positions on NLWR PRA Standard

  • There are currently 147 staff endorsement positions in RG 1.247, Appendix A

- 33 qualifications

- 114 clarifications

  • Staff positions may change after considering ACRS comments 13

Endorsement of NEI 20-09 PRA Peer Review Guidance

  • NRC staff received NEI 20-09, Rev. 0 on June 1, 2020
  • Staff reviewed and provided observations during a public meetings
  • NEI addressed and submitted Rev. 1 of NEI 20-09 on May 5, 2021
  • NEI 20-09, Rev. 1, is based on a related industry PRA peer review guidance document, NEI 17-07, Rev. 2, Performance of PRA Peer Reviews Using the ASME/ANS PRA Standard, as endorsed by RG 1.200, Rev. 3
  • The staff finds that the guidance in NEI 20-09, Rev. 1, is acceptable and thus endorses NEI 20-09, Rev. 1, without exception, in RG 1.247, Section C.2.2 14

Next Steps

  • Consider feedback from ACRS and external stakeholders
  • Public meeting - early November 2021
  • Issue RG 1.247 for trial use - early 2022
  • Duration of the trial-use period will depend on timing of the next published versions of PRA standards, rulemakings, and feedback from early uses
  • Brief ACRS on future changes to the RG 57

Acronyms

  • ACRS - Advisory Committee on Reactors Safeguards
  • ANS - American Nuclear Society
  • ASME - American Society of Mechanical Engineers
  • 10 CFR - Title 10 of the Code of Federal Regulations
  • JCNRM - Joint Committee on Nuclear Risk Management
  • LPSD - low-power and shutdown
  • LWR - light-water reactor
  • NEI - Nuclear Energy Institute
  • NLWR - non-light water reactor
  • NRC - Nuclear Regulatory Commission
  • QHO - quantitative health objective
  • POS - plant operating state
  • RG - regulatory guide
  • RIDM - risk-informed decision making 16

GALILEO Implementation in LOCA Methods (ACRS Full Committee)

Andrei Burghelea 10/05/2021

CONTENT Introduction What is intended How it is accomplished Why it is acceptabled Summary GALILEO Implementation in LOCA Methods - ACRS Committee Meeting - 10/05/21 2

Introduction and Background Current LOCA topical reports - S-RELAP5 based:

  • EMF-2328P-A (March 2001) and EMF-2328 Supplement 1P-A (December 2016)
  • Current fuel performance code - RODEX2
  • RLBLOCA
  • EMF-2103P-A Revision 3 (June 2016)
  • Current fuel performance code - COPERNIC
  • Realistic EM (BEPU)

Applicable to Westinghouse (3 and 4 loop) and Combustion Engineering plants GALILEO Implementation in LOCA Methods - ACRS Committee Meeting - 10/05/21 3

What is intended Purpose of new topical report is to add the fuel performance code GALILEO to LOCA methods

  • GALILEO (ANP-10323P-A Revision 1) - Approved November 2020 Supplementing the RLBLOCA EM and SBLOCA EM to include GALILEO Support future Framatome objectives (addressed separately)
  • Increased enrichment and burnup
  • Chromia-doped fuel and Chromium coated cladding GALILEO Implementation in LOCA Methods - ACRS Committee Meeting - 10/05/21 4

How it is accomplished - SBLOCA Implementation Regulatory Requirements

  • Analysis purpose, transient class, power plant class
  • Figures of merit Assessment Data Base
  • Only LOFT tests include nuclear fuel - LOFT Small Break Tests L3-6 / L8-1 EM Changes Assessment Results for LOFT Small Break Tests L3-6 / L8-1 Sample Problem GALILEO Implementation in LOCA Methods - ACRS Committee Meeting - 10/05/21 5

How it is accomplished - RLBLOCA Implementation Regulatory Requirements

  • RG 1.203 - Graded Approach to EMDAP EM Requirements
  • Analysis purpose, transient class, power plant class
  • Figures of merit
  • PIRT Review Assessment Base
  • Only LOFT tests include nuclear fuel

Why it is acceptable GALILEO an acceptable FPC EM evolution adding one FPC with the same functionality as current methods Assessment Results for LOFT SBLOCA Tests - good agreement with data SBLOCA Sample Problem - good agreement with current method Assessment of LOFT LBLOCA Tests - good agreement with data RLBLOCA Sample Problem - good agreement with current method GALILEO Implementation in LOCA Methods - ACRS Committee Meeting - 10/05/21 7

Summary Straight forward process COPERNIC/RODEX2 GALILEO EM evolution supporting future objectives Analysis workflow unchanged for both methods Assessments against benchmarks show good results Comparisons to current approved methods show good agreement GALILEO Implementation in LOCA Methods - ACRS Committee Meeting - 10/05/21 8

Acronyms BEPU - Best-Estimate Plus Uncertainty EM - Evaluation Model EMDAP - Evaluation Model Development and Assessment Process FPC - Fuel Performance Code LOCA - Loss-of-Coolant Accident LOFT - Loss of Fluid Test LBLOCA - Large Break LOCA RLBLOCA - Realistic LBLOCA SBLOCA - Small Break LOCA TR - Topical Report GALILEO Implementation in LOCA Methods - ACRS Committee Meeting - 10/05/21 9

Trademarks COPERNIC, GALILEO and S-RELAP5 are trademarks or registered trademarks of Framatome or its affiliates, in the USA or other countries.

GALILEO Implementation in LOCA Methods - ACRS Committee Meeting - 10/05/21 10

DOE Acknowledgment and Disclaimer Acknowledgment: This material is based upon work supported by the Department of Energy under Award Number DE-NE0008818.

Disclaimer: This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof. The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof.

GALILEO Implementation in LOCA Methods - ACRS Committee Meeting - 10/05/21 11

Any reproduction, alteration, transmission to any third party or publication in whole or in part of this document and/or its content is prohibited unless Framatome has provided its prior and written consent.

This document and any information it contains shall not be used for any other purpose than the one for which they were provided. Legal action may be taken against any infringer and/or any person breaching the aforementioned obligations.

GALILEO Implementation in LOCA Methods - ACRS Committee Meeting - 10/05/21 12

NRC STAFF EVALUATION OF FRAMATOME TOPICAL REPORT ANP-10349P, REVISION 0, GALILEO IMPLEMENTAION IN LOCA METHODS OPEN SESSION Mathew Panicker Nuclear Methods and Fuel Analysis Branch (NRR/DSS/SFNB)

ACRS Full Committee Meeting October 5, 2021 1

PRESENTATION OUTLINE

Background

Applicable Regulation and Guidance GALILEO Implementation in S-RELAP5 and RLBLOCA GALILEO Implementation in S-RELAP5 and SBLOCA GALILEO Implementation in LOCA EM - Conclusion 2

BACKGROUND RLBLOCA

  • EMF-2103-P-A, Revision 3 (2016) - used S-RELAP5/COPERNIC combination for initialization conditions for thermal hydraulics (T-H)

Code.

SBLOCA

  • EMF-2328 (2001) and its Supplement (2016) - used S-RELAP5/RODEX2 Combination for Initialization Conditions for T-H Code.

Fuel Performance Code GALILEO

  • ANP-10323-P Revision 1, Approved in 2020
  • The GALILEO code models the thermal-mechanical behavior of the fuel rods during normal operation and transient scenarios.

Framatome intends to supplement GALILEO methodology to its RLBLOCA and SBLOCA methodology.

3

APPLICABLE REGULATION &

GUIDANCE 10 CFR 50.46, "Acceptance Criteria for Emergency Core Cooling Systems (ECCS) for Light-Water Nuclear Power Reactors" 10 CFR Part 50 Appendix A, "General Design Criteria for Nuclear Power Plants," General Design Criterion (GDC) 35, "Emergency core cooling" Chapter 6.3, Emergency Core Cooling System, of the Standard Review Plan (SRP) provides guidance for performing the system review of the ECCS.

Chapter 15.6.5, Loss of Coolant Accidents, of the SRP provides guidance for performing reviews of loss of coolant accident (LOCA) analyses 4

GALILEO IMPLEMENTATION IN S-RELAP5 AND RLBLOCA EM

  • GALILEO code is added analysis to S-RELAP5 T-H fuel and T-H Calculations in RLBLOCA methodology.

Staff Evaluation

  • Conducted audit and issued RAIs to confirm documentation for GALILEO/S-RELAP5 Hybrid scheme and SBLOCA sensitivity analysis.
  • Verified the LOFT tests used to assess the base for the supplemental RLBLOCA EM and benchmarked using the coupled S-RELAP5/GALILEO.
  • Sample problem is similar to the problem presented in the approved RLBLOCA evaluation and methodology TR was solved (Appendix B, EMF-2103-P-A, Revision 3).

Results

  • The LOFT Tests and Sample problem results indicate reasonable agreement between GALILEO and COPERNIC.

5

GALILEO IMPLEMENTATION IN S-RELAP5 AND SBLOCA EM

  • GALILEO code supplements RODEX2 in SBLOCA analysis for S-RELAP5 T-H fuel and T-H Calculations.

Staff Evaluation

  • The LOFT tests were used to assess the base for the supplemental SBLOCA EM and benchmarked using the coupled S-RELAP5/GALILEO.
  • Sample problem is similar to the problem presented in the approved RLBLOCA evaluation and methodology TR was solved (EMF-2328 P-A).

Results

  • The LOFT Tests and Sample problem results indicate reasonable agreement between GALILEO and RODEX2.

6

GALILEO IMPLEMENTATION IN LOCA EM - CONCLUSIONS The NRC staff found that the process and the results from the supplemental evaluation model (ANP-10349P) for both RLBLOCA and SBLOCA supplements both COPERNIC and RODEX2 with GALILEO.

LOFT tests and sample problems results shows there is reasonable agreement between GALILEO and COPERNIC/RODEX2 for both RLBLOCA and SBLOCA analyses.

RLBLOCA and SBLOCA supplemental evaluation models (ANP-10349) satisfies applicable regulations and guidance in SRP.

Framatome shall publish the approved version of ANP-10349P as supplemental TR to the final approved versions of EMF-2103 and EMF-2328.

7

ACRONYMS CE Combustion Engineering ECCS Emergency Core Cooling System EM Evaluation Model FPC Fuel Performance Code LBLOCA Large Break Loss of Coolant Accident LOCA Loss-of-Coolant Accident LOFT Loss-of-Fluid PWR Pressurized Water Reactor RLBLOCA Realistic Large Break LOCA SBLOCA Small Break LOCA SRP Standard Review Plan T-H Thermal Hydraulics W Westinghouse Electric Company 8