Other: L-2021-142, Westinghouse Report LTR-REA-21-1-NP, Revision 1, St. Lucie Nuclear Plant, Units 1 and 2, Subsequent License Renewal: Unit 1 Reactor Vessel, Vessel Support, and Bioshield Concrete Exposure Data, May 26, 2021, L-2024-109, Schedule for Subsequent License Renewal Environmental Review, ML21272A264, ML25148A213
|
MONTHYEARL-2021-142, Westinghouse Report LTR-REA-21-1-NP, Revision 1, St. Lucie Nuclear Plant, Units 1 and 2, Subsequent License Renewal: Unit 1 Reactor Vessel, Vessel Support, and Bioshield Concrete Exposure Data, May 26, 20212021-08-0303 August 2021 Westinghouse Report LTR-REA-21-1-NP, Revision 1, St. Lucie Nuclear Plant, Units 1 and 2, Subsequent License Renewal: Unit 1 Reactor Vessel, Vessel Support, and Bioshield Concrete Exposure Data, May 26, 2021 Project stage: Other ML21215A3142021-08-0303 August 2021 Application for Subsequent Renewed Facility Operating Licenses Project stage: Request ML21272A2642021-10-18018 October 2021 Notice of Intent to Conduct Scoping Process and Prepare an Environmental Impact Statement Project stage: Other ML21337A1282021-11-0303 November 2021, 16 December 2021 November 3, 2021, St. Lucie Plant, Units 1 and 2, Subsequent License Renewal Application Public Environmental Scoping Meetings Project stage: Request ML21337A1962021-12-16016 December 2021 Public Scoping Meeting Summary for the Environmental Review of the Subsequent License Renewal Application for St. Lucie Plant, Units 1 and 2 Project stage: Meeting ML22039A1962022-02-0909 February 2022 License Renewal Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application Project stage: Approval ML22101A2282022-04-25025 April 2022 Summary of the Environmental Remote Audit Related to the Review of the Subsequent License Renewal Application Project stage: Approval ML22101A2272022-04-25025 April 2022, 2 May 2022 Summary of the Environmental Remote Audit Related to the Review of the Subsequent License Renewal Application Project stage: Request ML22124A0082022-05-0505 May 2022 Issuance of Environmental Scoping Summary Report Associated with the U.S. Nuclear Regulatory Commission Staffs Review Project stage: Approval L-2024-109, Schedule for Subsequent License Renewal Environmental Review2024-07-0303 July 2024 Schedule for Subsequent License Renewal Environmental Review Project stage: Other L-2024-110, Environmental Protection Plan Report, Unusual or Important Environmental Event - Manatee in Intake2024-07-10010 July 2024 Environmental Protection Plan Report, Unusual or Important Environmental Event - Manatee in Intake Project stage: Request L-2025-012, Supplement to Subsequent License Renewal Application Environmental Repot2025-02-0303 February 2025 Supplement to Subsequent License Renewal Application Environmental Repot Project stage: Supplement ML25078A0712025-04-0202 April 2025 Letter to Robert Coffey, St. Lucie Nuclear Plant, Units 1 and 2 -License Renewal Regulatory Audit Regarding Environmental Review of Subsequent License Renewal Application Supplement Project stage: Approval ML25148A2132025-06-10010 June 2025 Supplemental Audit - Letter to Applicant Project stage: Other ML25349A1622025-12-15015 December 2025 EIS for License Renewal of Nuclear Plants, Supplement 11, 2nd Renewal Re Subsequent License Renewal St. Lucie Plant, Units 1, 2, Draft Report for Comment Project stage: Draft Other ML25267A0082025-12-22022 December 2025 Letter to Robert Coffey Notice of Availability of Environmental Impact Statement Re Subsequent License Renewal of St. Lucie Plant Draft Report for Comment Project stage: Draft Other 2022-05-05
[Table View] |
Text
Mr. Robert Coffey Vice President, Nuclear &
Chief Nuclear Officer Florida Power & Light Company 700 Universe Boulevard Mail Stop: EX/JB Juno Beach, FL 33408
SUBJECT:
ST. LUCIE PLANT, UNITS 1 AND 2 - NOTICE OF INTENT TO CONDUCT SCOPING PROCESS AND PREPARE AN ENVIRONMENTAL IMPACT STATEMENT (EPID NO. L-2021-SLE-0003)
Dear Mr. Coffey:
By letter dated August 3, 2021, (Agencywide Documents Access and Management System (ADAMS) Accession Package No. ML21215A314), Florida Power & Light Co. (FPL) submitted to the U.S. Nuclear Regulatory Commission (NRC) an application for subsequent license renewal of Renewed Facility Operating License Nos. DPR-67 and NPF-16 for St. Lucie Plant, Units 1 and 2 (SLP), respectively. As stated in a letter to you dated September 24, 2021 (ADAMS Package Accession No. ML21246A091), the NRC staff determined that the application is acceptable for docketing and that the staff will proceed with its detailed technical review. In support of the application and in accordance with Title 10 of the Code of Federal Regulations (10 CFR) Part 51 and Part 54, FPL also submitted an environmental report. This letter provides information related to the NRC staffs environmental review of the application.
The NRC staff has prepared a Notice of Intent (NOI) advising the public that the NRC intends to conduct a scoping process to gather the information necessary to prepare a plant-specific supplement to NUREG1437, Generic Environmental Impact Statement for License Renewal of Nuclear Plants (ADAMS Package Accession No. ML13107A023), related to the review of the application for the subsequent renewal of the St. Lucie Plant, Units 1 and 2 operating licenses.
Enclosed is a copy of the NOI that will be forwarded to the Office of the Federal Register for publication.
Pursuant to 10 CFR 51.28, FPL is invited to participate in the environmental scoping process.
As discussed in the NOI, the NRC staff is providing the public with the opportunity to participate in environmental scoping meetings to be held on November 3, 2021. The meetings will be in the form of online webinars and will be transcribed. At these meetings, the NRC staff will present an overview of the safety and environmental review processes and describe how these processes will be implemented for the review of the SLP subsequent license renewal application. The NRC staff will also provide members of the public an opportunity to provide comments.
October 14, 2021
R. Coffey If you have any questions on this matter, please contact Mr. Lance Rakovan via e-mail at Lance.Rakovan@nrc.gov.
Sincerely, Robert B. Elliott, Chief Environmental Review License Renewal Branch Division of Rulemaking, Environment, and Financial Support Office of Nuclear Material Safety and Safeguards Docket Nos. DPR-67 and NPF-16
Enclosure:
Federal Register Notice cc w/encl: Listserv Signed by Elliott, Robert on 10/14/21