MONTHYEARCNL-21-026, License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b (SQN-TS-20-03)2021-08-0505 August 2021 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b (SQN-TS-20-03) Project stage: Request ML21239A0712021-08-27027 August 2021 Acceptance of License Amendment Request to Adopt TSTF-505, Revision 2 Project stage: Acceptance Review ML21246A0532021-09-15015 September 2021 Regulatory Audit in Support of Review of the Application to Adopt Risk-Informed Extended Completion Times RITSTF Initiative 4B Project stage: Approval CNL-21-001, Application to Modify the Technical Specification Table 3.3.1-1, Reactor Trip System Instrumentation (SQN-TS-21-01)2021-11-29029 November 2021 Application to Modify the Technical Specification Table 3.3.1-1, Reactor Trip System Instrumentation (SQN-TS-21-01) Project stage: Request ML21336A3942021-12-0101 December 2021 NRR E-mail Capture - Audit Questions for Sequoyah Units 1 and 2 - LAR to Adopt TSTF-505, Revision 2 (L-2021-LLA-0145) Project stage: Approval ML22035A0182022-02-0303 February 2022 NRR E-mail Capture - Audit Questions (Eeb follow-up) for Sequoyah Units 1 and 2 LAR to Adopt TSTF-505, Revision 2 (L-2021-LLA-0145) Project stage: Approval ML22046A2742022-02-15015 February 2022 NRR E-mail Capture - Audit Question (Snsb 02) for Sequoyah Units 1 and 2 LAR to Adopt TSTF-505, Revision 2 (L-2021-LLA-0145) Project stage: Approval ML22125A1422022-03-22022 March 2022 1 and 2 - March 22, 2022 e-mail - Sequoyah TSTF-505 LAR Supplemental Information Project stage: Approval ML22108A2822022-04-27027 April 2022 Summary of Regulatory Audit Regarding the License Amendment Request to Revise TS to Adopt TSTF 505, Rev. 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b Project stage: Other CNL-22-023, Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritstf2022-04-28028 April 2022 Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritstf Project stage: Supplement ML22118A3332022-04-28028 April 2022 Submittal of Sequoyah Nuclear Plant, Units 1 and 2 - Updated Final Safety Analysis Report Amendment 30 Project stage: Request CNL-22-034, Second Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b (SQN-TS-20-03)2022-05-13013 May 2022 Second Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b (SQN-TS-20-03) Project stage: Supplement ML22146A3322022-05-26026 May 2022 NRR E-mail Capture - Request for Additional Information Related to Sequoyah Nuclear Plants LAR to Adopt TSTF-505 Project stage: RAI CNL-22-069, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritstf.2022-07-0101 July 2022 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritstf. Project stage: Response to RAI ML22196A0732022-07-15015 July 2022 NRR E-mail Capture - (External_Sender) State Notification for Sequoyah Units 1 and 2 Amendment Issuance - TSTF-505 RICT (L-2021-LLA-0145) Project stage: Other ML22210A1182022-08-24024 August 2022 Issuance of Amendment Nos. 358 and 352 Regarding Technical Specifications Task Force Traveler TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4B Project stage: Approval ML22259A2042022-09-29029 September 2022 Correction to Amendment Nos. 358 and 352 Regarding Technical Specifications Task Force Traveler TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4B Project stage: Other 2022-03-22
[Table View] |
Text
From:
Buckberg, Perry To:
Taylor, Andrew Charles Cc:
Hulvey, Kimberly Dawn; Wrona, David
Subject:
Sequoyah 1 and 2 - Acceptance of License Amendment Request to Adopt TSTF-505, Revision 2 (EPID L-2021-LLA-0145)
Date:
Friday, August 27, 2021 8:37:00 AM
- Andy,
By letter dated August 5, 2021, (Agencywide Documents Access and Management System (ADAMS) Accession No. ML21217A174), the Tennessee Valley Authority (TVA or the licensee) submitted a license amendment request (LAR) for Sequoyah Nuclear Plant, Units 1 and 2. The purpose of this communication is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this LAR. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with 10 CFR 50.69, an amendment to the license (including the technical specifications) must fully describe the changes requested, and following, as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review, as compared to the detailed technical review, there may be instances in which issues that impact the NRC staff's ability to complete the detailed technical review are identified, despite completion of an adequate acceptance review.
You will be advised of any further information needed to support the NRC staff's detailed technical review by separate correspondence.
Based on the information provided in your submittal, the NRC staff has estimated that this request will take approximately 2247 hours0.026 days <br />0.624 hours <br />0.00372 weeks <br />8.549835e-4 months <br /> to complete, excluding any contractor hours, if appropriate. The NRC staff expects to complete this review by August 27, 2022, 12 months from the date of this acceptance. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, and the contractor resources will be communicated during the routine interactions with the assigned project manager.
These estimates are based on the NRC staff's initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities. Additional delay may occur if the submittal is provided to
the NRG in advance or in parallel with industry program initiatives or pilot applications.
If you have any questions, please contact me at (301) 4151383 or by e-mail at Perry.Buckberg@nrc.gov.
- Thanks, Perry Buckberg Senior Project Manager / Agency 2.206 Petition Coordinator U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation office: (301)415-1383 perry.buckberg@nrc.gov Mail StopO-8B1a, Washington, DC, 20555-0001