MONTHYEARCNL-21-026, License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b (SQN-TS-20-03)2021-08-0505 August 2021 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b (SQN-TS-20-03) Project stage: Request ML21239A0712021-08-27027 August 2021 Acceptance of License Amendment Request to Adopt TSTF-505, Revision 2 Project stage: Acceptance Review ML21246A0532021-09-15015 September 2021 Regulatory Audit in Support of Review of the Application to Adopt Risk-Informed Extended Completion Times RITSTF Initiative 4B Project stage: Approval CNL-21-001, Application to Modify the Technical Specification Table 3.3.1-1, Reactor Trip System Instrumentation (SQN-TS-21-01)2021-11-29029 November 2021 Application to Modify the Technical Specification Table 3.3.1-1, Reactor Trip System Instrumentation (SQN-TS-21-01) Project stage: Request ML21336A3942021-12-0101 December 2021 NRR E-mail Capture - Audit Questions for Sequoyah Units 1 and 2 - LAR to Adopt TSTF-505, Revision 2 (L-2021-LLA-0145) Project stage: Approval ML22035A0182022-02-0303 February 2022 NRR E-mail Capture - Audit Questions (Eeb follow-up) for Sequoyah Units 1 and 2 LAR to Adopt TSTF-505, Revision 2 (L-2021-LLA-0145) Project stage: Approval ML22046A2742022-02-15015 February 2022 NRR E-mail Capture - Audit Question (Snsb 02) for Sequoyah Units 1 and 2 LAR to Adopt TSTF-505, Revision 2 (L-2021-LLA-0145) Project stage: Approval ML22125A1422022-03-22022 March 2022 1 and 2 - March 22, 2022 e-mail - Sequoyah TSTF-505 LAR Supplemental Information Project stage: Approval ML22108A2822022-04-27027 April 2022 Summary of Regulatory Audit Regarding the License Amendment Request to Revise TS to Adopt TSTF 505, Rev. 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b Project stage: Other CNL-22-023, Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritstf2022-04-28028 April 2022 Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritstf Project stage: Supplement ML22118A3332022-04-28028 April 2022 Submittal of Sequoyah Nuclear Plant, Units 1 and 2 - Updated Final Safety Analysis Report Amendment 30 Project stage: Request CNL-22-034, Second Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b (SQN-TS-20-03)2022-05-13013 May 2022 Second Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b (SQN-TS-20-03) Project stage: Supplement ML22146A3322022-05-26026 May 2022 NRR E-mail Capture - Request for Additional Information Related to Sequoyah Nuclear Plants LAR to Adopt TSTF-505 Project stage: RAI CNL-22-069, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritstf.2022-07-0101 July 2022 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritstf. Project stage: Response to RAI ML22196A0732022-07-15015 July 2022 NRR E-mail Capture - (External_Sender) State Notification for Sequoyah Units 1 and 2 Amendment Issuance - TSTF-505 RICT (L-2021-LLA-0145) Project stage: Other ML22210A1182022-08-24024 August 2022 Issuance of Amendment Nos. 358 and 352 Regarding Technical Specifications Task Force Traveler TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4B Project stage: Approval ML22259A2042022-09-29029 September 2022 Correction to Amendment Nos. 358 and 352 Regarding Technical Specifications Task Force Traveler TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4B Project stage: Other 2022-03-22
[Table View] |
Text
Sequoyah Nuclear Plant, Post Office Box 2000, Soddy Daisy, Tennessee 37384 April 28, 2022 10 CFR 50.4 10 CFR 50.71(e) 10 CFR 54.37(b)
U. S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike One White Flint North Rockville, MD 20852-2746 Sequoyah Nuclear Plant, Units 1 and 2 Renewed Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328
Subject:
Updated Final Safety Analysis Report Amendment 30
Reference:
TVA letter to NRC, Updated Final Safety Analysis Report Amendment 29, dated October 28, 2020 Consistent with the requirements of 10 CFR 50.4(b)(6) and 10 CFR 50.71(e), enclosed for Sequoyah Nuclear Plant (SQN) Units 1 and 2, are two compact discs (CD-ROM) that contain Amendment 30 of the Updated Final Safety Analysis Report (UFSAR).
The Tennessee Valley Authority (TVA) has marked this Amendment for redaction as indicated by Regulatory Issue Summary 2015-17, "Review and Submission of updates to Final Safety Analysis Reports, Emergency Preparedness Documents, and Fire Protection Documents,"
dated December 23, 2015, using the criteria provided by the Nuclear Regulatory Commission (NRC) in SECY-04-191. to this letter is a copy redacted according to the marking for NRC Public Use. provides the Non-Public Use version, which is marked, but not redacted. TVA has marked the information as "Security-Related Information - Withhold Under 10 CFR 2.390.
Internally to TVA, access to the UFSAR will not be restricted.
A brief description and summary of the 10 CFR 50.59 safety evaluations of changes, tests, and experiments, reportable pursuant to 10 CFR 50.59 is being submitted under separate cover Security Related Information - Withhold Under 10 CFR 2.390 This letter is decontrolled when separated from Enclosure 2
Security Related Information - Withhold Under 10 CFR 2.390 This letter is decontrolled when separated from Enclosure 2 U.S. Nuclear Regulatory Commission Page 2 April 28, 2022 In accordance with 54.37(b), TVA SQN has not identified new systems, structures, and components that would have been subject to an aging management review or evaluation of time-limited aging analyses in accordance with 10 CFR 54.21 since the referenced letter.
There are no new regulatory commitments contained in this letter. If you have any questions concerning this submittal, please contact Mr. Jeffrey Sowa, SQN Licensing Manager, at (423) 843-8129.
I certify that I am duly authorized by TVA, and that, to the best of my knowledge and belief, the information contained herein accurately presents changes made since the previous submittal, necessary to reflect information and analyses submitted to the Commission or prepared pursuant to Commission requirements.
Respectfully, Thomas Marshall Site Vice President Sequoyah Nuclear Plant
Enclosures:
- 1. Redacted Updated Final Safety Analysis Report - Amendment 30 (Public Use Only)
- 2. Updated Final Safety Analysis Report - Amendment 30 (Non-Public Use) cc (w/ Enclosures):
NRC Regional Administrator - Region II NRC Senior Resident Inspector - Sequoyah Nuclear Plant NRC Project Manager - Sequoyah Nuclear Plant AREVA Nuclear Power, Inc.
Attn: Mr. Bob Clarke 3315 Old Forest Road OF-11 Lynchburg, Virginia 24501
- Reneau, William Christopher Digitally signed by Reneau, William Christopher Date: 2022.04.28 08:18:37
-04'00'
ENCLOSURE 1 SEQUOYAH NUCLEAR PLANT REDACTED UPDATED FINAL SAFETY ANALYSIS REPORT AMENDMENT 30 (PUBLIC USE ONLY)
(PROVIDED ON ENCLOSED COMPACT DISC)
Content on Enclosed Compact Disc File Name UFSAR AMENDMENT 30 FINAL Redacted.pdf Size 86,307 KB Sensitivity Level Redacted for Public Use
Security Related Information - Withhold Under 10 CFR 2.390 ENCLOSURE 2 SEQUOYAH NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT AMENDMENT 30 (NON-PUBLIC USE)
(PROVIDED ON ENCLOSED COMPACT DISC)
Content on Enclosed Compact Disc File Name UFSAR AMENDMENT 30 FINAL.pdf Size 91,633 KB Sensitivity Level Non-Public Use