MONTHYEARML20322A4522020-11-17017 November 2020 Notice of Meeting with Framatome, Inc. to Discuss the Pre-Application for the Model Nos. MAP-12 and MAP-13 Packages Project stage: Meeting ML20357A3922020-12-0707 December 2020 Enclosure 2: Presentation Project stage: Other ML20357A3902020-12-22022 December 2020 Summary of December 7, 2020 Meeting with Framatome, Inc., Enclosure 1: Meeting Participants Project stage: Meeting ML21090A3222021-03-31031 March 2021 Framatome MAP-12 and MAP-13 Shipping Container, Amendment Project stage: Request ML21113A1762021-04-22022 April 2021 Acceptance Letter for Framatome'S Amendment Request for Model No. MAP-12, MAP-13 Package Project stage: Acceptance Review ML21343A2292021-12-16016 December 2021 71-9319.R13 Letter, Revision No. 13 of Certificate of Compliance No. 9319, for the Model Nos. Map-12 and Map-13 Transportation Packages Project stage: Other ML21343A2282021-12-17017 December 2021 Safety Evaluation Report, Revision 13 Project stage: Approval 2021-12-16
[Table View] |
|
---|
Category:Letter
MONTHYEARML24297A6082024-10-23023 October 2024 Inspection Report No. 71-009319/2024-201 - Framatome, Inc. (MAP-12 at Tn Fabrication) ML24177A2622024-06-25025 June 2024 Framatome, Inc., Intent to Request an Amendment of Docket 71-9319, MAP-12 and MAP-13 Shipping Container ML23033A3472023-02-0606 February 2023 Letter - Revision No. 14 of Certificate of Compliance No. 9319, for the Model Nos. MAP-12 and MAP-13 Transportation Packages ML21113A1762021-04-22022 April 2021 Acceptance Letter for Framatome'S Amendment Request for Model No. MAP-12, MAP-13 Package ML21090A3222021-03-31031 March 2021 Framatome MAP-12 and MAP-13 Shipping Container, Amendment ML20314A0872020-11-0909 November 2020 Framatome, Inc - Intent to Request an Amendment ML19352E6892019-12-17017 December 2019 Docket Nos. Stn 50-528, 50-529, and 50-530, License No. NPF-41, NPF-51, and NPF-74 - NRC Certified Cask User Registration ML19259A2332019-09-17017 September 2019 Letter to T. Tate Revision No. 12 of Certificate of Compliance No. 9319, for the Model Nos. MAP-12 and MAP-13 Transportation Packages (W/Enclosure 2) ML19011A0132019-01-10010 January 2019 Letter to T. Tate Revision No. 11 of Certificate of Complaince No. 9319, for the Model Nos. MAP-12 and MAP-13 Transporation Packages (W/ Enclosure 2) ML18172A0482018-06-19019 June 2018 Letter to T. Tate Revision No. 10 of Certificate of Compliance No. 9319, for the Model Nos. MAP-12 and MAP-13 Transportation Package (W/Enclosure 2) ML18064A0772018-03-0101 March 2018 Letter to T. J. Tate: Revision No. 9 of Certificate of Compliance No. 9319, for the Model Nos. MAP-12 and MAP-13 Transportation Packages (W/Enclosure 2) ML0932902002009-11-18018 November 2009 10 CFR 71.95 Report of Non-Compliance with Certificate of Compliance USA/9319/B(U)F-96, Revision, for the Model No. MAP-12/MAP-13 Package ML0918704232009-07-0101 July 2009 10 CFR 71.95 Report of Non-Compliance with Certificate of Compliance USA/9319/B(U)F-96, Revision 1, Model Nos. MAP-12/MAP-13 Packages 2024-06-25
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 22, 2021 Mr. Timothy J. Tate, Manager Environmental, Health, Safety and Licensing Framatome Inc.
2101 Horn Rapids Road Richland, WA 99354
SUBJECT:
AMENDMENT REQUEST FOR THE MODEL NO. MAP-12, MAP-13 PACKAGE
Dear Mr. Tate:
By letter dated March 31, 2021, (Agencywide Documents Access and Management System Accession No. ML21090A322), you submitted an application for a revision of the Certificate of Compliance (CoC) No. 9319 for the Model No. MAP-12, MAP-13 package. The U.S. Nuclear Regulatory Commission staff performed an acceptance review of your amendment request and determined it contains sufficient technical information in scope and depth to allow the staff to complete a detailed technical review.
We have established a schedule for the review and estimated that the staff may need approximately 250 hours0.00289 days <br />0.0694 hours <br />4.133598e-4 weeks <br />9.5125e-5 months <br /> to complete its review, with an additional $50,000 in contractual work support for the criticality review. The schedule allows for the staff to issue a request for additional information (RAI) in October 2020. If your RAI responses are satisfactory, and based on the staffs evaluation, the CoC may be issued in January 2021.
Please reference Docket No. 71-9319 and EPID L-22020-LLA-0247 in future correspondence related to this request. If you have any questions regarding this matter, I may be contacted at (301) 415-7505.
Sincerely, Signed by Saverot, Pierre on 04/22/21 Pierre M. Saverot, Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 71-9319 EPID L-2020-LLA-0247
Ltr ML21113A176 OFFICE NMSS/DFM/STLB NMSS/DFM/STLB NMSS/DFM/STLB NMSS/DFM/STLB NAME PSaverot PS SFigueroa SF JMcKirgan JM PSaverot PS DATE Apr 22, 2021 Apr 22, 2021 Apr 22, 2021 Apr 22, 2021