ML21048A346

From kanterella
Jump to navigation Jump to search

Westinghouse Electric Company, LLC - Acceptance for Reviewof Request for Alternate Disposal Approval and Exemption for Specified Columbia Fuel Fabrication Waste (Enterprise Project Identifier L 2021-LLA-0013)
ML21048A346
Person / Time
Site: Westinghouse
Issue date: 02/18/2021
From: David Tiktinsky
NRC/NMSS/DFM/FFLB
To: Malek E
Westinghouse
Tiktinsky D
References
EPID L-2021-LLA-0013
Download: ML21048A346 (3)


Text

February 18, 2021 Ms. Elise Malek, Licensing Manager Westinghouse Electric Company 5801 Bluff Road Hopkins, South Carolina, 29061-9121 USA

SUBJECT:

WESTINGHOUSE ELECTRIC COMPANY, LLC, ACCEPTANCE FOR REVIEW OF REQUEST FOR ALTERNATE DISPOSAL APPROVAL AND EXEMPTION FOR SPECIFIED COLUMBIA FUEL FABRICATION WASTE (ENTERPRISE PROJECT IDENTIFIER L-2021-LLA-0013)

Dear Ms. Malek:

The U.S. Nuclear Regulatory Commission (NRC) staff has received your letter dated February 8, 2021 (Agencywide Documents Access and Management System (ADAMS)

Accession Number ML21039A719), submitting Westinghouse Electric Company, LLCs request for alternate disposal approval and exemption for specified low-activity radioactive materials from the Columbia Fuel Fabrication Facility, License No. SNM-1107, for certain waste containing radioactive materials under Title 10 of the Code of Federal Regulations (10 CFR)

Section 20.2002.

We have completed our acceptance review of your submittal and have identified no administrative omissions or deficiencies that would prevent us from proceeding with a detailed review. Your submittal has been assigned Enterprise Project Identification Number (EPID)

L-2021-LLA-0013. Please reference this EPID Number and Docket Number 07001151 in any future correspondence associated with this request.

Please note that the NRC staffs technical review of your submittal may identify issues that require additional information. Based on our preliminary evaluation, urgency of the request and projection of current review schedules, we anticipate completing our formal review by March 15, 2021. This date could change depending on the findings of our technical review, urgent assignments, or other factors. We will promptly communicate any significant changes to this schedule. In addition, the NRC staff estimates that completing the review of your submittal will require approximately 40 staff hours which corresponds to about $11,160 ($279/hr.).

In accordance with 10 CFR, Section 2.390, Public inspections, exemptions, requests for withholding, of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of the NRCs ADAMS. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

E. Malek 2 If you have any questions regarding this communication, please contact me at 301-415-8740, or via e-mail to David.Tiktinsky@nrc.gov.

Sincerely, David H. Digitally signed by David H.

Tiktinsky

/RA/

Tiktinsky Date: 2021.02.18 17:25:19

-05'00' David Tiktinsky, Senior Project Manager Fuel Facility Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No.: 70-1151 License No.: SNM-1107 cc: westinghouse_ff@listmgr.nrc.gov

ML21048A349 *via e-mail OFFICE NMSS/DFM/FFLB/PM* NMSS/DFM/FFLB/LA* NMSS/DFM/FFLB/BC*

NAME DTiktinsky ELee JZimmerman DATE 02/ 17/2021 02/17/2021 02/18/2021