August 10, 2020 Ms. Annette Pope Director, Organizational Effectiveness Westinghouse Columbia Fuel Fabrication 5801 Bluff Road Hopkins, SC 29061-9121 USA
SUBJECT:
U.S. NUCLEAR REGULATORY COMMISSIONS SCHEDULE UPDATE FOR THE LICENSE RENEWAL REVIEW OF THE WESTINGHOUSE COLUMBIA FUEL FABRICATION FACILITY
Dear Ms. Pope:
The U.S. Nuclear Regulatory Commission (NRC) staff has updated the schedule for its review of Westinghouse Electric Company, LLCs (Westinghouses) license renewal application for its Columbia Fuel Fabrication Facility (SNM-1107). The NRC staff considered, as appropriate, the information submitted by Westinghouse on July 20, 2020, in response to the information request (Agencywide Documents Access and Management System [ADAMS] Accession No. ML20202A678) regarding the review schedule. As stated in the letter dated June 30, 2020 (ADAMS Accession No. ML20178A293), the NRC staff is committed to completing its environmental impact statement (EIS) of the Westinghouses Columbia Fuel Fabrication Facility license renewal application in the most efficient and effective manner possible.
The NRC staff will use the analysis conducted to date to the fullest extent possible to prepare the EIS. The NRC staff must also comply with the requirements for completing an EIS in Part 51 of Title 10 of the Code of Federal Regulations (10 CFR). Accordingly, the NRC staff has established a schedule for the license renewal review that provides for the NRC staff to prepare the EIS and issue the license renewal decision within 18 months from issuance of the Federal Register (FR) notice announcing NRC staffs intent to prepare an EIS and the beginning of the scoping process. The FR notice was published on July 31, 2020 (85 FR 46193). The enclosure to this letter provides the license renewal review schedule, including major milestones. The schedule was developed based on the EIS process as required by 10 CFR Part 51, guidance in NUREG-1748, the current status of the environmental review, and Westinghouses tentative due dates for key milestones in the Phase II Remedial Investigation Work Plan activities under the Consent Agreement with the South Carolina Department of Health and Environmental Control, as appropriate. The anticipated schedule can change depending on the findings of our technical review or other factors. This target completion date also assumes Westinghouse will provide timely and high-quality responses to NRCs requests for additional information and submittals. We will promptly communicate any significant changes to this schedule.
Additionally, the NRC staff estimates that completing the review of your submittal will require approximately 2444 staff hours which corresponds to about $679,432, and $700K contract dollars.
A. Pope 2
Furthermore, the NRC staff continues to encourage Westinghouse to keep the NRC staff informed of any changes to the Phase II Interim Remedial Investigation activities and schedule.
If you have any questions regarding the license renewal review, please contact Marilyn Diaz at 301-415-7110, or via e-mail to Marilyn.Diazmaldonado@nrc.gov.
In accordance with 10 CFR Section 2.390, Public inspections, exemptions, requests for withholding, of the NRCs Agency Rules of Practice and Procedure, a copy of this communication will be available electronically for public inspection in the NRC Public Document Room, or from the NRCs ADAMS. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/readingrm/adams.html.
Sincerely, Damaris Marcano, Acting Chief Fuel Facility Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No.: 70-1151 License No.: SNM-1107
Enclosure:
Westinghouse Electric Company, LLC Columbia Fuel Fabrication Facility License Renewal Schedule cc: N. Parr, Westinghouse K. Taylor, SCDHEC westinghouse_ff@listmgr.nrc.gov
A. Pope 3
SUBJECT:
U.S. NUCLEAR REGULATORY COMMISSIONS SCHEDULE UPDATE FOR THE LICENSE RENEWAL REVIEW OF THE WESTINGHOUSE COLUMBIA FUEL FABRICATION FACILITY JTappert, NMSS KMcCurry, RII LWilkins, OCA JWeil, OCA KCoyne, NMSS CRegan, NMSS AKock, NMSS LClark, OGC DATED: August 10, 2020 DISTRIBUTION:
Public TVukovinsky, RII TClark, NMSS DMcIntyre, OPA RHannah, RII EMichel, RII JTrefethen, NMSS ADAMS Accession Number: ML20217L372
- via email OFFICE NMSS/REFS/
ERMB*
NMSS/DFM/
FFLB*
NMSS/DFM/
FFLB*
NMSS/REFS/
ERMB*
NMSS/DFM/
FFLB*
NAME DDiazToro MDiaz ELee JQuintero DMarcano DATE 08/03/2020 08/04/2020 08/04/2020 08/04/2020 08/10/2020 OFFICIAL RECORD COPY
Enclosure Westinghouse Electric Company, LLC Columbia Fuel Fabrication Facility License Renewal Schedule Docket 70-1151 SNM -1107 Milestone Anticipated Date Notice of Intent to prepare an environmental impact statement (EIS) and begin the scoping process published in the Federal Register, 85 FR 46193 July 31, 2020 (completed)
Start of scoping comment period July 31, 2020 (completed)
End of 30-day scoping comment period August 31, 2020 Issuance of Requests for Additional Information to Westinghouse September 2020 Publication of Draft EIS1 2 for a 45-day comment period April 2021 Publication of the Final EIS3 November 2021 Licensing Decision and Record of Decision4 December 2021 1 The draft EIS anticipated publication date assumes Westinghouse submits a high-quality RAI responses and submittals in a timely manner. Currently, the NRC staff assumes a 30-day RAI response time.
2 The draft EIS anticipated publication date considers, but is not directly linked to, the Phase II Interim Remedial Investigation tentative schedule and activities but. When the Phase II Interim Remedial Investigation Report is submitted, the NRC staff would review and evaluate the scope and results to understand the impacts, if any, to the development of the EIS and determine next steps, as appropriate.
3 See note 2.
4 The NRC, per 10 CFR 51.100(a)(ii), must wait 30 days after publication of the Environmental Protection Agency FRN stating that the final EIS has been issued.