RA-19-0001, License Amendment Request to Revise Technical Specifications to Adopt Risk- Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b7 October 2019Duke Energy
Hamilton T
License Amendment Request to Revise Technical Specifications to Adopt Risk- Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4bRequest
ML19311C3417 November 2019Tanya Hood
Plant Licensing Branch II
Acceptance Review: Shearon Harris License Amendment Request for TSTF-505Acceptance Review
ML20141L62320 May 2020Tanya Hood
Plant Licensing Branch II
Audit Plan Requested Licensing Action for Technical Specifications Task Force (TSTF) Traveler TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF (Risk-Informed TSTF) Initiative 4BOther
ML20175A57524 June 2020Tanya Hood
Plant Licensing Branch II
Audit Plan Supplement in Support of Review of License Amendment Request to Revise TS to Adopt TS Task Force Traveler Tstf-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF (Risk-Informed TSTF) Initiative 4Other
RA-20-0223, Supplement to Application to Revise Harris Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b27 July 2020Duke Energy
Maza K
Supplement to Application to Revise Harris Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4bSupplement
ML20274A04629 September 2020Tanya Hood
Plant Licensing Branch II
Request for Additional Information Regarding License Amendment Request to Adopt TSTF-505, Revision 2RAI
RA-20-0321, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-505, Revision 2, Provide Risk-Informed Extended Comple11 November 2020Duke Energy
Maza K
Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-505, Revision 2, Provide Risk-Informed Extended CompletiResponse to RAI
ML20329A3817 December 2020Tanya Hood
Plant Licensing Branch II
Regulatory Audit Summary Regarding License Amendment Request to Adopt Risk Informed Completion Times Technical Specification Task Force-505, Rev. 2, Provide Risk-Informed Completion Times (EPID L-2019-LLA-0218Other
ML21047A3142 April 2021Undine Shoop
Plant Licensing Branch II
Issuance of Amendment No. 184 Regarding Technical Specifications Task Force (TSTF) Traveler TSTF-505, Revision 2, Provide Risk Informed Extended Completion Times RITSTF Initiative 4BApproval
ML21116A2074 May 2021Tanya Hood
Plant Licensing Branch II
Correction to Amendment No. 184 Regarding TSTF Traveler TSTF-505, Rev. 2, Provide Risk Informed Extended Completion Times - RITSTF Initiative 4BOther