Proposed Tech Specs Pages Re one-time Exigent License Amend to Allow Operation W/Number of Indications Previously Identified as Tube End Anomalies & Multiple Tube End Anomalies in OTSG Tubes
ML20249B267
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 06/18/1998
From:
FLORIDA POWER CORP.
To:
Shared Package
ML20249B265 List:
References
NUDOCS 9806220247
Download: ML20249B267 (4)


Text

.

~

j FLORIDA POWER CORPORATION CRYSTAL RIVER UNIT 3 DOCKET NO. 50-302/ LICENSE NO. DPR-72 ATTACHMENT B EXIGENT LICENSE AMENDMENT REQUEST #228, REVISION 0 ONCE THROUGH STEAM GENERATOR TUBE SURVEILLANCE PROGRAM Proposed Technical Specification Change Pages I (Shaded) i 1

E p

'#$$o$[ M o$o2 PM

e .

. Procedures, Programs and Manuals 5.6 5.6 Procedures, Programs and Manuals 5.6.2.10 OTSG Tube Surveillance Program (continued)

8. Plugging / Sleeving Limit means the extent of ,

degradation beyond which the tube shall be restored to serviceability by the installation of a sleeve or removed from service because it may become unserviceable prior to the next inspection and is equal to 40% of the nominal tube or sleeve wall thickness. No more than five thousand sleeves may be installed in each 0TSG.

l

9. Unserviceable describes the condition of a tube if it leaks or contains a defect large enough to affect its structural integrity in the event of an Operating Basis Earthquake a loss-of-coolant accident,oramainsteamiineorfeedwaterline break, as specified in 5.6.2.10.3.c, above.
10. Tube Inspection means an inspection of the entire OTSG tube as far as possible.
b. The OTSG shall be determined OPERABLE after completing the corresponding actions (plug or sleeve all tubes exceeding the plugging /sleevin limit and all tubes containing through-wall cracks required by Table l

5.6.2-2 (and Table 5.6.2-3 if he provisions of Specification 5.6.2.10.2.d are utilized). Defective tubes may be repaired in accordance with the B&W process (or method) equivalent to the method described in report BAW-2120P.

l There are a~ number of'0TSG tubes that? exceed the tubs plugging / sleeving limit as a result of-tube end '

anomalies. :These tubes will be repaired during the

next refueling outage-(11R). An analysis has been i performed which confirms.that operability of the CR-3 l OTSGs will not be impacted with those tunes inservice unti1 the next' refueling' outage _(11R).

5.6.2.11 Secondary Water Chemistry Program j This program provides controls for monitoring secondary water chemistry to inhibit steam generator tube degradation and low ,

pressure turbine disc stress corrosion cracking. The program )

shall include:

a. Identification of a sampling schedule for the critical variables and control points for these variables .
b. Identification of the procedures used to measure the values of the critical variables; (continued)

Crystal River Unit 3 5.0-17 Amendment No. MB l

A

. . FLORIDA POWER CORPORATION CRYSTAL RIVER UNIT 3 DOCKET NO. 50-302/ LICENSE NO. DPR-72 ATTACHMENT C EXIGENT LICENSE AMENDMENT REQUEST #228, REVISION 0 ONCE THROUGH STEAM GENERATOR TUBE SURVEILLANCE PROGRAM Proposed Technical Specification Change Pages (Revision Bars)

. Procedures, Programs and Manuals

. 5.6 5.6 Procedures, Programs and Manuals ,

5.6.2.10 OTSG Tube Surveillance Program (continued)

8. Plugging / Sleeving Limit means the extent of degradation beyond which the tube shall be restored to serviceability by the installation of a sleeve or removed from service because it may become unserviceable prior to the next inspection and is equal to 40% of the nominal tube or sleeve wall thickness. No more than five thousand sleeves may be installed in each OTSG.
9. Unserviceable describes the condition of a tube if it leaks or contains a defect large enough to affect its structural integrity in the event of an Operating Basis Earthquake a loss-of-coolant accident, or a main steam line or feedwater line break, as specified in 5.6.2.10.3.c, above.
10. Tube Inspection means an inspection of the entire OTSG tube as far as possible.
b. The OTSG shall be determined OPERABLE after completing the corresponding actions exceeding the plugging /slee(plug vin limit or andsleeve all tubes all tubes l containing through-wall cracks required by Table 5.6.2-2 (and Table 5.6.2-3 if he provisions of Specification 5.6.2.10.2.d are utilized). Defective tubes may be repaired in accordance with the B&W process (or method) equivalent to the method described in report BAW-2120P.

There are a number of OTSG tubes that exceed the tube plugging / sleeving limit as a result of tube end anomalies. These tubes will be repaired during the next refueling outage (llR). An analysis has been performed which confirms that operability of the CR-3 OTSGs will not be impacted with those tubes inservice until the next refueling outage (11R).

5.6.2.11 Secondary Water Chemistry Program This program provides controls for monitoring secondary water chemistry to inhibit steam generator tube degradation and low pressure turbine disc stress corrosion cracking. The program shall include:

a. Identification of a sampling schedule for the critical variables and control points for these variables;
b. Identification of the procedures used to measure the values of the critical variables; (continued)

Crystal River Unit 3 5.0-17 Amendment No.