ML20246N038

From kanterella
Jump to navigation Jump to search
Forwards Mod to 890808 Application for Amends to Licenses DPR-24 & DPR-27,consisting of Tech Spec Change Request 134, Removing Unit 2 Capsule in Fall 1990 Refueling Outage & Capsule P in Fall 1996 & Modifying Page 15.3.1-8a
ML20246N038
Person / Time
Site: Point Beach  
Issue date: 08/31/1989
From: Britt R
WISCONSIN ELECTRIC POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20246N044 List:
References
CON-NRC-89-104 NUDOCS 8909080023
Download: ML20246N038 (3)


Text

_

t

.g.

Wisconsin

' Electnc POWER COMPANY 231 W Michigan. Po Box 2046. Milwaukee, WI 53201 (414)291-2345

' NRC 104 August-31, 1989 10 CFR 50.59 10 CFR 50.90 U. S. NUCLEAR REGULATORY COMMISSION Document Control Desk Mail' Station ~Pl-137 Washington,-D.C.

20555 Gentlemen:

DOCKETS 50-266 AND 50-301 MODIFICATION TO TECHNICAL SPECIFICATION CHANGE REQUEST 134 REACTOR VESSEL SURVEILLANCE CAPSULE REMOVAL SCHEDULE POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 By letter dated August 8, 1989, Wisconsin Electric Power Company (Licensee) submitted Technical Specification Change Request 134.

That request proposed that Unit.2 reactor vessel surveillance Capsule S be withdrawn in Fall 1995 and Capsule P be withdrawn in Fall 1998.

It also proposed a change to Technical Specification page 15.3.1-8a to acknowledge our participation in the Babcock and Wilcox Master-Integrated Reactor Vessel Surveillance Program and briefly describe our current capsule withdrawal schedule.

That schedule was based on the requirements of 10 CFR 50, Appendix H, and ASTM E185-82.

ASTM E185-82 states

"...the withdrawal schedule of the final two capsules is adjusted by the lead factor so the exposure of tne second to last capsule does not exceed the peak end-of-life (EOL) fluence on the inside surface of the vessel, and so~the exposure of the final capsule does not exceed twice the.EOL vessel inside surface peak fluence."

At the time of our August 8 submittal we believed the Unit 2 estimated maximum EOL fluence at the insidggsurfage of the reactor vessel to be approximately 3.5x10 n/cm.

Capsule S would see that fluence about Fall 1995 and Capsule P would see 150% of that fluence in 1998.

We subsequently have learned of calculations done by Westinghouse,

.which'show that implementation of super low leakage cores (L4P) with hafnium absorbers beginning with the Unit 2 Fall 1989 Outage, will result in a significant reduction in EOL fluence not only in the vessel weld region but also in the remainder of the beltline vessel bh

.6

[ 00I i i E

Asubsa ornzanskncvnipwho m

U.S. NRC Document Control Desk August 31, 1989 Page 2 plate / forging regions.

Accordingly, we now estimate that maximumUnit2EOLfastneutronexposurewillbe2.92x10}ge 2

n/cm.

Thus, in order to satisfy the requirements of 10 CFR 50, Appendix H and ASTM E185-82, a modification to the proposed withdrawal schedule is necessary.

1 Accordingly, Wisconsin Electric hereby submits a modification to Technical Specification Change Request 134, substantially revising aur original request.

We propose to remove the Unit 2 Capsule S in Fall 1990 refueling outage and Capsule P in Fall 1996 refueling outage.

These withdrawal dates closely correspond to the estimated recc+0r vessel beltline forging fast neutron exposure levels at EOL and 150% EOL (See Table 1 for fluence comparisons).

You may note that the target fluence for Capsule S slightly exceeds the projected EOL fluence for the vessel.

This will allow some margin in the l

event that the Capsule S exposure is overestimated as has occurred with some other capsules.

With this margin there should be little i

risk that the capsule data would represent a fluence level significantly less than the expected vessel EOL maximum.

This is consistent with a recommendation made by Westinghouse.

Additionally, we propose to modify page 15.3.1-8a to acknowledge the fact that we are participants of the Babcock and Wilcox Master Integrated Reactor Vessel Surveillance Program and to briefly i

describe the data points to which the new schedule corresponds.

Please note that this page is also affected by Technical Specification Change Request 126 submitted August 3, 1969; however, that change is not reflected here.

The proposed Technical l

Specification pages are attached with changes indicated by margin bars.

As required by 10 CFR-50.91(a), we have evaluated these changes in accordance with the standards specified in 10 CFR 50.92(c) to determine if the change constitutes a significant hazards consideration.

The revised surveillance capsule withdrawal schedule

.will provide reactor vessel materials data more representative of that predicted at EOL and 150% EOL.

These changes also satisfy the requirements of 10 C?R 50, Appendix H, and ASTM E185-82.

Therefore, these changes will not increase the probability or consequences of an accident previously analyzed nor will they involve a reduction in a margin of safety.

These changes cannot create a new or different kind of accident since they involve only a schedule change which brings Point Beach into compliance with the regulations.

Therefore, these changes do not involve a significant hazards consideration.

-_-__-______________n

h,;g M y %. '

y-lM

.h.,

.[

U.S.-NRC Document Control: Desk-L7 August 31, 19.89 Fage:3E F

$' )

f J

.Please contact us.if you have'any questions concerning this request; l i, +, '

[:

Very.truly yours, u

/

.R..W.

Britt 1

Chairman of.the Board;&

Chief Executive. Officer i

1 Enclosures gopiesito NRC;' Regional Administrator,' Region III

.g NRC Resident Inspector L:

?

Subscribed and.swo n'to!before me b:

this y day'of'./

mM: 1989.

':&h;s-y

[l Jotary-Public,.. State.of.Wiscphsin

~

Y_jg/J,r/ffB My Commission expires:

i

>$p _

q T

i y

i

,h'..*

t e

T d

1_ d

_._E

___._.___1_.__

. _ _ _ _ _