ML20246L943

From kanterella
Jump to navigation Jump to search
Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-313/89-10 & 50-368/89-10
ML20246L943
Person / Time
Site: Arkansas Nuclear  
Issue date: 07/11/1989
From: Milhoan J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Campbell G
ARKANSAS POWER & LIGHT CO.
References
NUDOCS 8907190032
Download: ML20246L943 (1)


See also: IR 05000313/1989010

Text

-.

-

-

-_

.- -

-

-

-

-

,

,

,.g---,

t 39

f . e-

3

.. .'Ini,Riply'R fi dTob .

'

g g g g-

g'

  • Dockets:- 50-313/89-10-

'50,-368/89-10 ,

~

'

,

L

,e

.

,

Ark'ansas Power & Light Company

'

. ATTN:D Mr. Gene., Campbell

.Vice President, Nuclear-

..

Operations

>

P.O. Box 551~

Little Rock,' Arkansas'.72203

_

+

- Gentlemen:

{

Thank you for your' letter of June 14,-1989, in response to our letter and:

~

,

Ne!. ice of Violation dated May 15,.1989. We have reviewed your reply and find

it responsive to the concerns raised in our Nbtice of Violation. We will

.

review the implementation of your corrective actions during a future inspection

to determine that full' compliance has been achieved and will be maintained.

,

Sincerely,

!

James L. Milhoan, Director

,..

Division of Reactor Projects

'

cc:

! Arkansas Nuclear.0ne

ATTN:

N. S. Carns, Director

",

Nuclear Operations

P.O. Box 608-

Russellv111e', Arkansas .72801

Arkansas Radiation Control Program Director

bec to DMB (IE01) w/ copy of licensee ltr

bec distrib. by RIV w/ copy of licensee ltr:

RRI

R. D. Martin, RA

RPB-DRSS

SectionChief(DRP/A)

-Lisa Shea, RM/ALF

RIV File

DRP

MIS System

"

RSTS Operator

ProjectEngineer(DRP/A)

DRS

,

C. Harbuck, NRR Project Manager (MS:

13-D-18)

-C. Poslusny, NRR Project Manager (MS:

13-D-18)

RIV:DRP/A 01

C:DRP/A

DRP

ATHowell;df

[4 - DDChamberlain

JLMilhoan

8

'7/tl/89

7/li/89

7/ Ji/89

.

k

8907190032 890711

PDR

ADOCK 05000313

ij

Q

PDC

)

1 ____1 _ ___ _______ i__________.

_ _ _ _

_

)

t e .,

-r

-

,.

-

.-

c

.

.

,

.

ARKANSAS POWER & LIGHT COMPANY

_s

June 14, 1989

i

  • h

.,

JLN ?. 7 S89

$

@

OCAN068903

..

J. L. Milhoan, Director

Division of Reactor Projects

U. S. Nuclear Regulatory Commission

Region IV

611 Ryan Plaza Drive, Suite 1000

Arlington, Texas 76011

SUBJECT:

Arkansas Nuclear One - Units 1 and 2

Dccket Nos. 50-313/50-368

License Nos. DPR-5l. and NPF-6

Response to Inspec fon Report

50-313/89-10 and 50-368/89-10

Dear Mr. Milhoan:

I

Pursuant to the provisions of 10CFR2.201, a response to the violations

identified in the subject inspection report is submitted.

Very truly yours,

E. C. Ewing

General Manager

Plant Support

CEC:PLM:djm

attachment

cc w/att: U. S. Nuclear Regulatory Commission

Document Control Desk

Mail Station P1-137

Washington, C.C.

20555

)

j

g-91-2.36

1

. , ,

gjy j

weu.ca ucoce sour- uricities sysreu

,

-

e

i

- - _ _ -

[

'Att: chm:nt to.0CAN068903

'

,

'4

-Jun3:14, 1989:

4

,t

V

Page 1

-1

Notice of Violation

'

A .-

Unit 1, TS 6.8.1 requires that written procedures be established,

implemented, and maintained covering the. activities recommended

in Appendix A of Regulatory Guide 1;33, November 1972.

Appendix

.A, Item 8.b(1)(j) requires procedures for the surveillance tests,

'

inspections, and calibrations of the emergency core cooling

system. . Plant Test Procedure (PTP) 1304.013, Revision 8, "HPI/LPI

and Reactor Building Spray Flow Inst. Surv. Red Channel," has

-

been. established in accordance with this TS aquirement.

Section 8.7 of PTP 1304.013 provides instructions for the

calibration of Transmitter PDT-1401 which provides a flow signal

for Train A of the low pressure injection and decay heat removal

.

. systems. These instructions require isolation and venting of the

transmitter prior to actual calibration.

Contrary to the above, on March 14, 1989, Transmitter PDT-1402

was inadvertently isolated when the work instructions directed

that Transmitter PDT-1401 be calibrated.

This action caused the

loss of decay heat removal flow indication and the subsequent

-i

securing of the decay heat removal pump by the operators due to

loss of indicated flow.

This is a Severity Level IV violation. '(Supplement I)(313/8910-02)

Resporse to Violation 313/8910-02

(1) The reason for the violation if admitted:

AP&L does admit the violation occerred as stated.

The incorrect

actions resulted from a personnel error by the Instrumentation

.and Controls technician who failed to accurately verify the

instrument tag number prior to isolating the component.

.A

contributing cause was an error in the maintenance surveillance

procedure which specified the location of PDT-1401 as the "B"

decay heat vault rather than the correct location of the "A"

decay heat vault.

(2) The corrective steps which ham been taken and the results achieved:

When the incorrect transmitter was isolated and flow indication

was lost, decay heat flow was secured.

Operations contacted the

technician who immediately unisolated PDT-1402, restoring flow

indication for the "B"

train cf decay heat.

Associated

maintenance activities were discontinued until the problem was

investigated and resolved.

Decay heat flow was restored within 13

,

minutes from the time it was secured by Operations.

Y-

_

_-

__

-. _ . - _ _ - _ -

[.

Attschm:nt'to SCAN 068903'

.

"~

Juna-14,:1989!

.

.7

.Pcon 2

.

,.

.

(3) The corrective steps'which will be taken to avoid further violations:

To prevent'further violations,;the surveillance procedure has-

been changed to indicate the cc rrect location of PDT-1401 as the

"A" decay heat vault. .. Additionally, Maintenance Supervisors.were

advised of the circumstances of the event and were requested to

review the event with their groups, stressing attention to

detail.

These reviews have been conducted. We believe these

. actions will preclude similar violations in the future.

(4) The date when' full compliance will be achieved:

Full compliance was achieved immediately following the event

March 14, 1989.

l

l

,

f ,I .

)

w___--_--.

- -

_ _ _ _ - _ _

Att: chm:nt to BCAN068903

,

Juna 14, 1989

.

,

, Paga 3

.

Notice of Violation

B.

10CFR50.62 states in Section (d) that an implementation schedule

is required from licensee to indicate " final implementation" by

the second refueling outage after July 26, 1984, or, if

justified, a later date should be mutually agreed upon by the

Commission and the licensee.

The second refueling outage

implementation deadline was extended to the third refueling

outage for ANO-2 in a March 2, 1987, letter from the Office of

Nuclear Reactor Regulation (NRR) ANO, Unit 2, Project Manager to

Mr. T. G. Campbell.

Cor,trary to the above, the third refueling outage for ANO-2

following the July 26, 1984, date, 2R6, was completed in May of

1988, and no ATWS related equipment was installed by that date.

Further, no request for scheduler extension had been requested

by AP&L or approved by the NRC.

This is a Severity Level IV violation.

(Supplement I)(368/8910-03)

Response to Violation 368/8910-03

Since before the publication of the Final Rule on Anticipated Transients

Without Scram (ATWS) in July of 1984, the Arkansas Power & Light Company

(AP&L) has actively participated in the Comoustion Engineering Owner's Group

(CEOG) effort to satisfactorily resolve the ATWS concerns as they relate to

Arkansas Nuclear One, Unit 2 (ANO-2).

These efforts were directed at

participating in the development of an effective and reasonable regulation

during the initial rule making and subsequently, following issuance of the

final rule, at appropriately satisfying the technical requirements to

implement the ATWS rule (10CFR50.62) on ANO-2.

Appropriate ATWS modifications for ANO-2 and its sister CE plants (San

Onofre Nuclear Generating Station 2 and 3 (SONGS 2 and 3), and Waterford Unit 3)

have presented a unique set of problems due to the integrated Plant

Protection System (PPS) design on these units which make it difficult and

expensive to achieve diversity between Emergency Feedwater (EFW) control

and Reactor Trip System (RTS) control to the extent considered by the Staff

to be a necessary requirement of the ATWS rule. The CEOG has submitted two

generic topical reports, CEN-315 and CEN-349, which have addressed the

safety benefits to be gained from complete diverse actuation of EFW versus

the cost to engineer, and install a system to accomplish this requirement.

The results have been an almost negligible imp'rovement in safety with an

accompanying cost that is quite significant.

Following the submittal of CEN-315 and 349, the NRC, in correspondence dated

January 11, 1988, from Mr. George Knighton to Messrs. Kenneth P. Baskin and

James C. Holcomb, provided the Staff evaluation of these documents and

concluded that sufficient EFW and RTS diversity did not exist for ANO-2,

,

SONGS 2&3 and Waterfurd 3.

That correspondence further directed these plants

- _ - _ _ _ _ _ _ _ - _ _ _ _ _ -

-

- --___ _ - _ _ __ - __

,

Attachment to SCAN 068903

.

,,

"

Juns 14, 1989

.-

a

Prge 4

.

.

to either provide the required independence and diversity for these systems

-

.or request an exemption.

In regard to the last option, ti.:. correspondence

contained Staff guidance for such an exemption request.

Following the subject written guidance as well as verbal direction received

during meetings with the Staff, AP&L as well as the other affected CEOG

members submitted requests for exemption from the portion of the ATWS rule

which required diverse and independent means to actuate EFW.

That request

was subsequently denied, in the case of ANO-2 by correspondence dated

February 16, 1989 (2CNA028903).

Additional meetings with the Staff have led to efforts by the CEOG to

reevaluate other design options, besides the one discussed in the exemption

request, to determine if a less costly solution c.mid be found to achieve

an acceptable level of diversity between EFW and Ris.

The CEOG has

proposed an alternate design (although this design contains some areas of

concern) to the staff and it is being evaluated at this time.

It has been

the position of AP&L, in accordance witn the CEOG, that the only design

option that fully complies with 10CFR50.62 in all aspects is a fully

redundant, Class IE EFW system such as was~ discussed in our request for

partial exemption (November 3, 1988, 2CAN118801).

As has been stated

earlier, that design is quite costly (3-5 million dollars) and the

supporting analysis indicates that the incremental safety improvement in

installing such a system is quite small (49 X 10~7 severe ATWS events

per reactor year).

The resulting value/ impact ratio (VIR) is comparable to

that discussed in the Statements of Consideration to the Final Rule which

related to the addition of extra safety valves on CE units, but was rejected

by the Commission because of the unfavorable VIR.

Further progress on a resolution of this issue is pending the results of

the Staff raview of the CEOG's alternate design proposal which is presently

underway.

(1) The reason for the violation if admitted:

AP&L admits that a violation of NRC regulations occurred.

The original ANO-2 ATWS implementation schedule called for the

required modification to be installed by the second refueling outage

l

following the date of the Final Rule.

In the case of ANO-2 this

would have been our fifth refueling outage (2R5).

AP&L recognized

very early that such a schedule could not be met and therefore .otified

the Commission in our correspondence of October 15, 1985 (2CAN148508),

that our schedule would be extended to 2R6.

As the review of the second CE topical (CEN-349), continued, it becanne

.

l

clear that our 2R6 implementation schedule could not be completed.

Internal correspondence prior to the end of 2R6 indicates that the

.

need to extend the implementation of ANO-2 ATWS modifications was

I

l

recognized as necessary.

At this point, AP&L failed to formally

q

1

t

____

.

Attachm nt co BCAN068903

..

'

'e '

June 14, 1989

,,;' Page 5

.,

request, on the ANO-2 docket, an extension for ATWS modifications

t

beyond 2R6.

AP&L believes that the discussions on going with the

Staff during this period addressed the status of ATWS implementation

on ANO-2, nonetheless, that changing status was not documented by

correspondence.

Further confusion with regard to the ATWS modifications

implementation date was introduced by our November 3, 1988, exemption

request which incorrectly identified 2R7 as the third refueling

outage following the date of the Final Rule.

This fact was discussed

previously in AP&L's March 29, 1989, response to the exemption denial

(2CAN038910).

(2) The corrective jteps which have been taken and the results achieved:

(3) The corrective steps which will be taken to avoid further violations:

The corrective steps which have been taken are twofold.

First, the

Commission has been informed in the correspondence referenced above

(2CAN038910) of the status regarding implementation on ANO-2 of

10CFR50.62 required modifications.

Secondly, we have reviewed our

commitment tracking system to verify that these ATWS milestones,

such as AP&L's commitment in our previously referenced correspondence

to install our Diverse Scram System (DDS) and Diverse Turbine Trip

(DTT) function during 2R7, are correctly identified and tracked.

Likewise, once the EFW actuation diversity issue is resolved, any

required plant modifications that result from.that action will be

tracked until implemented and closed out.

To prevent future violations with regard to implementation schedule,

an additional tracking system entry has been made with a date of

approximately six months prior to the start of refueling outage 2R8 to

flag EFW actuation modifications.

That tracking entry requires

the review of the status of these modifications relative to their

implementation during 2R8 and subsequent notification of the Commission

if that schedule cannot be met for any reason.

(4) The date when full compliance will be achieved:

As stated previously, AP&L will install the Diverse Scram System (DDS)

and Diverse Turbine Trip (DTT) functions during our seventh refueling

outage (2R7) currently scheduled to begin in September, 1989.

The

schedule for implementation of the remaining ATWS requirement, diverse

and independent means to actuate EFW, cannot be determined at this

time.

The actual schedule (2R8 or later) is a function of the

complexity of the final acceptable design solution which will not

likely be known for several months.

-

_ _ _ _ _ _ _ _ _ . _ _ - _ _ _ _ _ -