Submits Revised Schedule for 1985-86 SALP Board Meetings for Region V
ML20215E441
Person / Time
Site: Columbia, Diablo Canyon, San Onofre, Rancho Seco, 05000000, Trojan
Issue date: 08/22/1985
From: Martin J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Jennifer Davis, Harold Denton, Taylor J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE), NRC OFFICE OF NUCLEAR MATERIAL SAFETY & SAFEGUARDS (NMSS), Office of Nuclear Reactor Regulation
Shared Package
ML20215E267 List:
References
FOIA-86-197 850822, NUDOCS 8610150301
Download: ML20215E441 (2)


Text

.

G

.* stPEasy WG " We '%

.d UNITED STATES

' 4* g NUCLEAR REGU TORY COMMISSION hg, o, c 1450 MARIA LANE. SUITE 210 {

5

  • e .e

[ ',. (, WALNUT CREEK. CALIFORNIA 94596

.6 ' ]G1Y4&L

- - . ,i August 22, 1985 cl;<A l.uf

~

MEMORANDUM FOR: Harold R. Denton, Director, NRR John G. Davis, Director, NMSS Janes M. Taylor, Director IE Clemens J. Heltemes, Jr. , Director AEOD FROM: J. B. Martin, Regional Administrator

SUBJECT:

REVISED SCHEDULE FOR 1985-1986 SALP BOARD MEETINGS

. FOR REGION V .

Reference:

Memorandum for Regional Administrators from J. M. Taylor, dtd July 8, 1985; Subj ect: SALP Reviews and Evaluations of Facilities with New Operating Licenses Further review and discussion with I&E headquarters, regarding the referenced memorandum, has resulted in the following SALP schedule changes:

(1) San Onofre has been changed to an eighteen month interval, ,

(2) the Trojan interval has been reduced to twelve months due to past and recently identified concerns, (3) the WNP-2 interval was reduced one month, and (4) the Rancho Seco and Diablo Canyon proposed licensee meeting dates were changed.

Accordingly, the Region V SALP schedule is as follows:

i l

l 8610150301 861003' 1

, PDR FOIA /

I HOLMES86-197 PDR

l REGIONAL PROPOSED I

~

EVALUATION g<' BOARD LICENSEE UNITS PERIOD MEETING MEETING

~

Rancho Seco 12/01/83 - 05/31/85 08/07/85 09/06/85*+  ;

o.

Diablo Canyon 07/01/84 - 07/31/85 09/19/85* 10/23/85*

Palo Verde 04/01/84 - 09/30/85 11/06/85* 12/09/85*

Trojan 11/01/84 - 10/31/85* 12/12/85* 01/22/86*

WP-2 02/01/85 - 01/31/86* 03/05/86* 04/23/86*

San Onofre 10/01/84 - 03/31/86* 05/07/86* 06/18/86*

Rancho Seco 06/01/85 - 05/31/86 07/08/86 08/20/86 Diablo Canyon 08/01/85 - 07/,31/86 09/11/86 10/22/86 Palo Verde 10/01/85 - 09/30/86 11/05/86 12/11/86 TROJAN 11/01/85 - 10/31/86 12/10/86 01/22/87 WP-2 02/01/86 - 07/31/87 12/13/84 San Onofre 04/01/86 - 11/30/87 .

  • Indicates changes from July 18, 1985 schedule.

+ Indicates this date is subject to further change.

This schedule replaces the previous schedule provided by Region V letter dated July 18, 1985. Any questions regarding this schedule should be directed to A. E. Chaffee (FIS 463-3753).

' B.7tcs h f /4 1 (vJ. B. Martin Regional Administratot cc: J. Carter, NRR F. J. Hebdon, AEOD B. Faulkenberry J. Crews R. Scarano Branch Chiefs, RV Section Chiefs, RV DRS&P Inspectors, RV Director, Division Reactor Projects -