Responds to NRC Re Schedule for Implementation of 10CFR50.48 Fire Protection Mods.Mods Completed W/Exception of Four Listed Items.Items 1 & 2 Will Be Completed by 1988 Refueling Outage.Items 3 & 4 Will Be Completed by 871231
ML20214K008
Person / Time
Site: Trojan File:Portland General Electric icon.png
Issue date: 05/20/1987
From: Cockfield D
PORTLAND GENERAL ELECTRIC CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
TAC-55560, TAC-55831, NUDOCS 8705280288
Download: ML20214K008 (2)


Text

(

.+

ammes D

D biVdIIIY David W. Cockfield Vice President, Nuclear May 20, 1987 Trojan Nuclear Plant Docket 50-344 License NPF-1 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington DC 20555

Dear Sir:

Implementation Schedule for Title 10, Code of Federal Regulations, Part 50.48 (10 CFR 50.48)

Fire Protection Modifications This letter is in response to the Nuclear Regulatory Commission (NRC)

April 10, 1987 letter related to the schedule for implementation of 10 CFR 50.48 for Trojan.

In the NRC letter, it was stated that fire pro-tection and alternate or dedicated shutdown system modifications required to meet 10 CFR 50.48 be completed by the end of the 1988 refueling outage (June 1988). Portland Concral Electric Company (PGE) was requested to notify the NRC in writing if this schedule is not correct, and to keep the NRC apprised of any schedule delays, and of the completion of the 10 CFR 50.48 modifications.

Pursuant to your request, all 10 CFR 50.48 firo protection modifications for the Trojan Nuclear Plant have been completed with the following exceptions:

1.

Installation of a new remote shutdown panel and related 10 CFR 50.48 modifications as described in PGE's February 18, 1987 letter to the NRC.

2.

Installation of a 1-hr-rated fire barrier around one channel of cables for a new neutron source range monitor and removal of a 2-minute time delay for suppression system actuation in Fire Area El, as described in the PGE May 31, 1985 letter to the NRC (which trans-mitted Amendment 1 to the 10 CFR 50 Appendix R Review).

3.

Installation of one additional sprinkler head to the water curtain between Fire Areas A4 and A4a, as described in the PGE May 8, 1987 letter to the NRC.

8705280288 870520 PDR ADOCK 05000344 F

PDR Ob th 12t sw ssmon street. Portana O<egon 97204

/

Pbetla 1d M MCostixwy Document Control Desk May 20, 1987 Page 2 4.

Upgrading of a 1.5-hr-rated fire wall between the Control Building Train B switchgear room and the Train A electrical auxiliary room to a 3-hr-rated wall, as described in the PCE November 13, 1986 letter to NRC Region V.

Items 1 and 2 above will be completed by the end of the 1988 refueling outage (about June 1988). Items 3 and 4 will be completed by December 31, 1987, as previously committed to in the referenced submittals.

Sincerely, c:

Mr. John B. Martin Regional Administrator, Region V U.S. Nuclear Regulatory Commission Mr. David Kish, Director State of Oregon Department of Energy Mr. R. C. Bare NRC Resident Inspector Trojan Nuclear Plant i