MONTHYEARML20206T8691986-07-0303 July 1986 Forwards Action Plan for Performance Improvement. Plan Addresses 851226 Event & Includes Prioritization Process Which Identifies Actions That Will Be Completed Before Restart.Review Requested Project stage: Other ML20197C6821986-10-30030 October 1986 Forwards Response to 860530 Request for Addl Info Necessary for Preparation of SER Supporting Plant Restart. Instrumentation & Control Sys & non-nuclear Instrumentation Schematic Drawings Will Be Sent Separately Project stage: Request ML20207A9541986-11-0606 November 1986 Notification of 861119 Meeting W/Util in Bethesda,Md to Brief NRC Mgt on Status of Facility Performance Improvement Program.Agenda Encl Project stage: Request ML20213F7001986-11-0606 November 1986 Forwards Request for Addl Info Re Sys Review & Test Program. Questions Include Sys & Components Controlled in Tech Specs, Including Containment Isolation Valves,Core Flood Tanks & Pressure Boundary Isolation Valves Project stage: RAI ML20214D1621986-11-17017 November 1986 Advises That Response to 861106 Request for Addl Info Re Sys Review & Test Program Will Be Submitted by 861205 Project stage: Request ML20214V4931986-12-0505 December 1986 Forwards Response to J Stolz 861106 Request for Addl Info Re List of Selected Sys Which Are Part of Sys Review & Test Program Project stage: Request ML20205J0971987-03-11011 March 1987 Safety Evaluation Re Sys Selected for Facility Sys Review & Test Program.Sys Constitutes Adequate Scope for Sys Review & Test Program Project stage: Approval ML20205J0851987-03-11011 March 1987 Forwards Safety Evaluation Re Sys Selected for Facility Sys Review & Test Program.List of Selected Sys Acceptable.Salp Input Also Encl Project stage: Approval ML20214M3101987-05-22022 May 1987 Forwards SER Based on Review of Rod Swap Methodology Rept for Startup Physics Testing & 870211 & 0311 Supplemental Info.Rod Swap Methodology Acceptable for Rod Worth Measurement of Reload Cores for Plants Project stage: Approval 1986-12-05
[Table View] |
Text
e suun SACRAMENTO MUNICIPAL UTILITY DISTRICT O 6201 S Street, P.O. Box 15830. Sacramento CA 95852-1830,1916) 452-3211 AN ELECTRIC SYSTEM SERVING THE HEART OF CALIFORNIA November 17, 1986 JEW 86-873 312.5/JL Director of Nuclear Reactor Regulation Attention:
Mr. John F. Stolz, Chief Operating Reactors Branch 4 U.
S. Nuclear Regulatory Commission Washington, DC 20555
Dear Mr. Stolz:
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION ON SYSTEM REVIEW AND TEST PROGRAM We have received your November 6, 1986 letter requesting additional information on our System Review and Test Program.
Your letter also requested a schedule for our response.
We have reviewed the questions prepared by your contractor, Idaho-National Engineering Laboratory, and believe a comprehensive response can be submitted by December 5, 1986.
Our response will clarify the scope of our program and provide justification for not including some systems and components listed in your letter.
Sincerely,
. A$
s puty General Manager, Nuclear cc:
S. Miner (NRC, Bethesda)
T.
D'Angelo (NRC, Rancho Seco) 0 T0 1 >