Monthly Operating Rept for Nov 1986
ML20211P999
Person / Time
Site: Millstone Dominion icon.png
Issue date: 11/30/1986
From: Gibson J
NORTHEAST NUCLEAR ENERGY CO.
To:
Shared Package
ML20211P990 List:
References
NUDOCS 8703020468
Download: ML20211P999 (5)


Text

_

OPERATING DATA REPORT DOCKET NO. 50-336 DATE 12/9/86 i

L COMPLETED BY J. GIBSON I-TELEPHONE (203) 447-1791 EXT. 4431 OPERATING STATUS' 1.

Unit'Name:

Millstone' Unit 2 Notes Items 21 and 22 cumulative 2.

Reporting Period:

November 1986 are weighted averages. Unit 3.

Licensed Thermal Power (MWt):

2700 operated at 2560 MW Thermal 4.

Nameplate Rating (Gross MWe):

909 prior to its uprating to 5.

Design Electrical Rating (Net MWe):

870 the current 2700 MW Thermal 6.

Maximum Dependable Capacity (Gross MWe):

888.75 Power Level.

r 7.

Maximum Dependable Capacity (Net MWe):

857.25 8.

If Changes Occur in Capacity Ratings (Items Number 3 Through 7)

Since Last Report, Give Reasons:

N/A 9.

Power Level To Which Restricted, If Any (Net MWe):

N/A 10.

Reasons For Restrictions, If Any:

N/A This Month Yr.-to-Date Cumulative 11.

Hours In Reporting Period 720 8016 95832 12.

Number Of Hours Reactor Was Critical 0

6192.9 68730.6 13.

Reactor Reserve Shutdown Hours 0

0 2205.5 14.

Hours Generator On-Line 0

6058.7 64776.4 468.2 15.

Uni.t, Reserve Shutdown Hours 0

0 164251601 16.

Gross' Thermal Energy Generated (MWH) 0 16147799 17.

Gross Elec. Energy Generated (MWH) 0 5219000 53560479 18.

Net Electrical Energy Generated (MWH) (-1857) 5020302 51341521 19.

Unit Service Factor 0

75.6 67.6 20.

Unit Availability Factor 0

75.6 68.1 21.

Unit Capacity Factor (Using MDC Net) 0 73.1 63.3 22.

Unit Capacity Factor (Using DER Net) 0 72.0 62.3 23.

Unit Forced Outage Rate 0

2.4 16.2 24.

Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):

25.

If Shut Down At End Of Report Period, Estimated Date of Startup: DECEMBER 12, 1986 26.

Units In Test Status (Prior to Commercial Operation):

Forecast Achieved INITIAL CRITICALITY N/A N/A INITIAL ELECTRICITY N/A N/A COMMERCIAL OPERATION N/A N/A 8703020468 861212 DR ADOCK 05000336 PDR

I J

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-336 UNIT Millstone Unit 2

'DATE 17/g/g6 COMPLETED BY J. Gibson TELEPHONE (203) 447-1791 Ext. 4431

' MONTH NOVEMBER, 1986~

DAY AVERAGE DAILY POWER LEVEL DAY-AVERAGE DAILY POWER LEVEL (MWe-Net)

(MWe-Net) 1 0

17 0

2 0

18 0-3 0

19 0

4 0

20 0

5 0

21 0

6 0

22 0

7 0

23-0 8

0 24 0

9 0

25 0

10 0

26 0

11 0

27 0

12 0

28 0

13 0

29 0

14 0

30 0

15 0

31 16 0

INSTRUCTIONS

-On this format, list the average daily unit power level in MWe-Net for each day in the reporting month.

Compute to tiie nearest whole megawatt.

i y

UNIT SHUTDOWNS AND POWER REDUCTIONS.

DOCKET NO. 50-336-UNIT NAME Millstone 2 DATE 12/9/86

. COMPLETED BY'J. GIBSON REPORT MONTH NOVEMBER, 1986

' TELEPHONE (203) 447-1791.

EXT. 4431 l

2 No.

Date Type Duration Reason Method of Licensee Systeg Compogent Cause & Corrective (Hours)

Shutting Event Code Code -

. Action to 3

Down Reactor Report #

Prevent Recurrence 5-9-20-86 5

720

'C

' 1' N/A N/A N/A Continuation of' Refueling and Maintenance Outage-from previous month.

1 2

3

'4-F:

Forced Reason:

Method:

Exhibit G - Instructions S:

Scheduled A-Equipment Failure (Explain) 1-Manual for Preparation of Data

~

B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refueling 3-Automatic Scram Event Report (LER) File D-Regulatory Restriction 4-Continued from (NUREG-0161)

E-Operator Training & License Examination previous month F-Administrative 5-Power Reduction 5'

l G-Operational Error (Explain)

(Duration = 0)

Exhibit 1 - Same Source H-Other (Explain) 9-Other (Explain)

Docket No. 50-336' Date 12/9/86 Unit Name Millstone 2 Completed By J. GIBSON Telephone (203) 447-1791 EXT. 4431 CORRECTIVE MAINTENANCE

SUMMARY

FOR SAFETY RELATED EQUIPMENT REPORT MONTH NOVEMBER, 1986 DATE SYSTEM COMPONENT MAINTENANCE ACTION 11/10/86 Containment Spray P43A Containment Spray Pump

. Cleaned electrical contacts.

11/19/86 Reactor Coolant &

PDT-111B - RCS Flow Loop #1 Replaced forced motor assembly in Vessel DP Transmitter

transmitter.

11/6/86 Process and Area RM 81328 - Radiation Monitor Replaced Source Drive Motor.

Radiation Monitoring 11/16/86 Reactor Protection RPS Channel A Linear Power Repaired J-6 Connector.

System Range Drawer 11/30/86 Reactor Protection Matrix and Trip Path Relays Replaced CD-3 Relay.

System 11/24/86 Reactor Protection Channel B Trip Bistable Replaced Bistable System I

D:ckst N:. 50-336 Date:

N/W/u6 Completed By: G. Neron Telephone: (203) 447-1791 EXT. 4417 REFUELING INFORMATION REQUEST 1.

Name of facility: Millstone 2 2.

Scheduled date for next refueling shutdown:

Currently in end of cycle 7 refueling / maintenance outage.

3.

Schedule date for restart following refueling: December 1986 4.

Will refueling or resumption of operation thereafter require a technical

,y specification change or other license amendment?

')

~

Ng 5.

Scheduled date(s) for submitting licensing action and supporting information:

Two Technical Specification change requests related to the Reactor Coolant System Flow Rate were submitted on October 24, 1986 and October 27, 1986.

The Technical Specification change request to revise 10CFR50, Appendix G.

Heat Up and Cooldown Curves, was submitted on October 20, 1986.

6.

Important licensing considerations associated with refueling, e.g.,

new or different fuel design or supplier, unreviewed design or performance analysis methods, significant changes in fuel design, new operating procedures:

None 7.

The number of fuel assemblies (a) in the core and (b) in the spent fuel storage pool:

(a) In Core:

217 (b) 512 8.

The present licensed spent fuel pool storage capacity and the size of any increase in licensed storage capacity that has been requested or is planned, in number of fuel assemblies:

Currently 1112 The 1112 available locations reflects the re-racked Spent Fuel Pool.

The re-racking of the Unit 2 Spent Fuel Pool has been completed.

9.

The projected date of the last refueling that can be discharged to the spent fuel pool assuming the present licensed capacity:

1994, Spent Fuel Pool, Full Core off load capacity is reached.

1998, Core Full, Spent Fuel Pool.

These numbers are based on the recently re-racked Spent Fuel Pool.