REVISED COPY OPERATING DATA REPORT DOCKET NO 50 - 335 DATE 11/13/86 COMPLETED BY N. W. GRANT TELEPHONE 305/694/4432 OPERATING STATUS
- 1. UNIT NAME:
ST. LUCIE UNIT 1
- 2. REPORTING PERIOD: OCTOBER 1986
- 3. LICENSED THERMAL POWER (MNT):
2700
_4.
NAMEPLATE RATING (GROSS MWE):
850
- 5. DESIGN ELECTRICAL RATING (NET MWE):
830
- 6. MAXIMUM DEPENDABLE CAPACITY (GROSS MKE):
872
- 7. MAXIMUM DEPENDABLE CAPACITY (NET MWE):
839
- 8. IF CHANGES OCCUS IN CAPACITY RATINGS (ITEMS NUMBER 3 THROUGH 7)
SINCE LAST REPORT, GIVE REASONS:
- 9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWE)________________________
- 10. REASONS FOR RESTRICTIONSe IF ANY:
_____________________________________L___________________________________
MONTHLY
-YTD-CUMULATIVE
- 11. HOURS IN REPORT PERIOD:
745 7296 86448.0
- 12. NUMBER OF HOURS REACTOR WAS CRITICAL _____
745 0 6960.0 l 63108.7
- 13. REACTOR RESERVE SHUTDOWN HOURS __________
0.0 0.0 205.3
- 14. HOURS GENERATOR ON-LINE _________________
745.0 6889.6 62691.7
- 15. UNIT RESERVE SHUTDOWN HOURS _____________
0 0
39.3
- 16. GROSS THERMAL ENERGY GENERATED (MWH) 1998087 18400074 159292341
- 17. GROSS ELECTRICAL ENERGY GERERATED (MWH) 657650 6130430 52186935
- 18. NET ELECTRICAL ENERGY GENERATED (MWH) 624337 5819335 49253127
- 19. UNIT SERVICE FACTOR _____________________
100.0 94.4 72.5 l
- 20. UNIT AVAILABILITY FACTOR ________________
100.0 94.4 72 6
- 21. CAPACITY FACTOR (USING MDC NET) 99.9 96.2 l 71.3
- 22. CAPACITY FACTOR (USING DER NET) 101.0 96.1 69.9
- 23. UNIT FORCED OUTAGE RATE _________________
0 1.3 4.1
- 24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS :
REFUELING 3/21/86, 8 WEEKS _____________________________________________
- 25. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
8703180517 870316 ADOCKOSOOOggO PDR R
o.
REVISED COPY OPERATING DATA REPORT DOCMET NO 50 - 389.
DATE 11/13/86 COMPLETED BY N. W. GRANT TELEPHONE 305/694/4432 OPERATING STATUS
- 1. UNIT NAMEt ST. LUCIE.
UNIT 2
- 2. REPORTING PERID0! OCTOBER 1986
- 3. LICENSED THERMAL POWER (MWT)* ______________ 2700
- 4. NAMEPLATE RATING (GROSS MWE)! ______________
854
- 5. DESIGN ELECTRICAL RATING (NET MWE)*
830
- 6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE)!
882
- 7. MAXIMUM DEPENDABLE CAPACITY (NET MWE)!
839
- 8. IF CHANGES OCCUS IN CAPACITY RATINGS (ITEAS NUMBER 3 THROUGH 7) r SINCE LAST REPORT, GIVE REASONS! ________________________________________
- 9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWE)________________________
- 10. REASONS FOR RESTRICTIDHS, IF ANY! _______________________________________
MONTHLY
-YTD-CUMULATIVE
- 11. HOURS IN REPORT PERID0! _________________
745 7296 29345 9 I
- 12. NUMBER OF HOURS REACTOR WAS CRITICAL _____
745 0 5862.7 23911 6
- 13. REACTOR RESERVE SHUTDOWN HOURS __________
6.0 0.0 0.0
- 14. HOURS GENERATOR ON-LINE _________________
745.0 5791.5 23363 8
- 15. UNIT RESERVE SHUTDOWN HOURS _____________
0 0
0 l
- 16. GROSS THERMAL ENERGY GENERATED (MWH) 1994252 15450637 60097170
- 17. GROSS ELECTRICAL ENERGY GERERATED (MWH) 645239 5164670 20071350
- 18. NET ELECTRICAL ENERGY GENERATED (MWH) 631452 4890223 18961266 i
i
- 19. UNIT SERVICE FACTOR _____________________
100 0 79.4 82 4 l
- 20. UNIT AVAILABILITY FACTOR ________________
100.0 79.4 82 4
- 21. CAPACITY FACTOR (USING MDC NET) 101.0 80.0 l 82.5l
- 22. CAPACITY FACTOR (USING DER NET) 102.1 80.8 81 9
- 23. UNIT FORCED OUTAGE RATE _________________
e 1.3 86
- 24. SHUTDOWNS SCHEDULED OVER NEXT 4 MONTHS
- l i
- 25. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUPt i
(
.. -..