ML20207N257

From kanterella
Jump to navigation Jump to search
Insp Repts 50-456/86-60 & 50-457/86-50 on 861027-1211.No Violation or Deviation Noted.Major Areas Inspected:Review Actions on Previous Insp Items & Preoperational Test Procedures Review.Five Open & One Unresolved Item Noted
ML20207N257
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 01/07/1987
From: Dunlop A, Ring M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20207N215 List:
References
50-456-86-60, 50-457-86-50, NUDOCS 8701140083
Download: ML20207N257 (7)


See also: IR 05000456/1986060

Text

-

.

.

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Reports No. 50-456/86060(DRS);50-457/86050(DRS)

Docket Nos. 50-456; 50-457

Licenses No. NPF-59; CPPR-133

Licensee: Commonwealth Edison Company

Post Office Box 767

Chicago, IL 60690

Facility Name: Braidwood Station, Units 1 and 2

Inspection At: Braidwood Site, Braidwood, Illinois

Inspection Conducted: October 27 through December 11, 1986

Inspector:

A. Dunlop, Jr. M Q[

/ - T-/ 7

f

Date

Wha.,h

I-1- f7

Approved By:

M. A. Ring, Chief

,Date

-

Test Programs Section

J_nspe_c_t_ ion Summary

Inspection _on October 27 through December l 19861 _ Reports No. 50-456/_8_6060(DR_Sjl

No. 50-457/86050(DRS))

Areas Inspec_te_d: Routine, announced safety inspection to review actions on

previous inspection items (92701); preoperational test procedures review

(70304,70334); preoperational test procedure verification (70311);

preoperational test results evaluation (70322, 70534); and preoperational test

results verification (70329).

Results: Of the five areas inspected, no violations or deviations were

identified in the report. However, 5 open items and I unresolved item are

documented in the body of the report which require action by the licensee and

the NRC or both,

e7011gh$h$$56

.

>

PDR

PDR

O

,

-

.

DETAILS

1.

Persons Contacted

Commonwealth Edison Company (CECO)

M. J. Wallace, Project Manager

C. J. Tomashek, Project Startup Superintendent

  • P. L. Barnes, Regulatory Assurance Supervisor
  • T. W. Simpkin, Regulatory Assurance
  • T. J. Lewis, Startup Staff, NOVA

M. Inserra, TRB Supervisor /PSG

E. Nagy, Group Leader

  • H. D. Pontious, Regulatory Assurance

W. C. Mammoser, Project Engineering Department (PED)

J. Basek, System Test Engineer

Additional station technical, operational, and administrative personnel

were contacted by the inspector during the course of the inspection.

  • Denotes those attending the exit meeting on December 11, 1986.

2.

Action on Previous Inspection Items

(Closed) Open Item (456/85026-03(DRS)):

This item concerned the review

of test results package for BwPT SI-10, " Safety Injection." The licensee

has approved the test results and the inspector has completed the review

with no further comments.

This item is considered closed.

No violations or deviations were identified.

3.

Preoperational Test Procedure Review

The inspector reviewed the following preoperational test procedures

against the FSAR, Safety Evaluation Report (SER), proposed Technical

Specifications, and Regulatory Guides 1.68.

BwPT EF-10, Revision 3, " Unit One Engineered Safety Features"

No violations or deviations were identified.

4.

Preoperational Test Procedure Verification

The inspector reviewed the following preoperational test procedures and

verified that they were written, reviewed, and approved by licensee

management in accordance with the requirements of Regulatory Guide 1.68

and the licensee's QA Manual:

BwPT AB-10, Revision 2 and Retest 52, " Boric Acid Processing System"

BwPT AR-14, Revision 0, " Area Radiation Monitoring (Loop 4)"

>

l

L

,

.

.

BwPT EM-11, Revision 1, " Strong Motion Seismic Instrumentation System"

BwPT FC-10, Revision 0 and Retest 37, " Fuel Pool Cooling and Cleanup"

BwPT PR-10, Revision 0, " Process Radiation Monitoring Miscellaneous

Monitors (Safety-Related)"

BwPT PR-14, Revision 1 and Retest 129, " Process Radiation Monitoring

Loop 3"

BwPT PR-16, Revision 1, " Wide Range Gas Monitor (WRGM) Radiation Detector

Monitor"

BwPT PS-12, Revision 1, " Process Sampling - Hydrogen Monitors"

BwPT VD-15, Revision 2, "Intergrated Diesel Gen., Misc. Elect. and Switch

Gear Room Ventilation"

BwPT VP-10, Revision 2, " Containment Ventilation"

BwPT VP-11, Revision 2, " Containment Ventilation"

BwPT VQ-11, Revision 1, "Off Gas System Hydrogen Recombiners"

No violations or deviations were identified.

5.

Preoperational Test Results Evaluation

The inspector reviewed the results of the below listed preoperational

test procedures to verify all test changes were identified and approved

in accordance with administrative procedures; all test deficiencies were

appropriately resolved, reviewed by management and retested as required;

test results were evaluated by appropriate engineering personnel and

specifically compared with acceptance criteria; data was properly

recorded, signed, dated, and documented as test deficiencies, as

necessary; test packages were reviewed by QA for adequacy of contents;

and test results were approved by appropriate personnel.

BwPT EF-10, Revision 3, " Unit One D aineered Safety Features"

BwPT EF-11, Revision 2, "ECCS Full Flow"

'

BwPT SI-10, Revision 0, " Safety Injection"

With respect to EF-10, the inspector has the following comments:

a.

(1) Test Change Request (TCR) No. 31 changed the required starting

time for the reactor containment fan coolers (RCFCs) from less

than 20 seconds to 20 - 40 seconds.

The licensee's

justification for the TCR was in response to deficiency

EF-10-239, which states that Technical Specification

Table 3.3-5 start time of 40 seconds is applicable. However,

the time stated in the table includes the time required to

i

2

. - _ -

._ .

. - .

. _ _ _

_

-

-

.

start and load the emergency diesel generator (10 seconds).

The timing in the test does not include a diesel generator

start and as such, the required starting time should be

30 seconds or less.

Since all the RCFCs did start in less

than 30 seconds in the test, this is not a concern of the fans

performance.

However, the corrective action for the deficiency

is not correct and the test procedcre is also in error.

The

licensee has written a Test Procedure Open Item (TPOI) EF-50-09

to correct the Unit 2 test procedure.

(2) TCR No. 25 repositioned the point of contact on two permanently

installed jumpers and then returned them to their original

location.

The procedure should have required an independent

verification when moving these jumpers.

In addition the

procedure should be made clearer in that there are two jumpers

that are being repositioned.

The licensee has initiated TPOI

EF-50-07 to correct the Unit 2 test procedure.

(3) The notes prior to steps 9.65.96 and 9.70.96 are not correct in

that they state that certain valves will be verified as not

repositioning after an ESF signal is reset in the following steps.

The repositioning of the valves had been verified in p evious

steps in the test procedure and not in the steps following the

notes.

The licensee has initiated TPOI EF-50-06 to correct

the Unit 2 test procedure.

(4) Sections 9.65 and 9.70 did not verify that valve 1AF057B would

remain open after the ESF signal was removed.

This function was

tested in BwPT AF-10.

The licensee has initiated TPOI EF-10-08

to correct the Unit 2 test procedure to ensure the feature is

checked in EF-50.

(5) It was noted that throughout the test there were numerous typos,

steps incorrectly marked as acceptance criteria, acceptance

criteria steps not listed in Section 4, and although Train A and

B tests are identical, their designated acceptance criteria steps

l

were different.

Theseinconsistencieswherealsothesubjectof

a Quality Assurance Finding in audit QAA 20-86-EF10-1.

Even

though the test contained these errors, it appeared that the test

adequately tested the design features of the ESF System.

The

licensee has initiated AIR R20-86-054 to correct these

inconsistencies in the completed test package

!

To ensure that the Unit 2 test procedure is updated for items (1),

(2), (3), and (4) above, they will be considered an open item

(457/86050-01(DRS)) pending incorporation of the TPOIs into the

Unit 2 preoperational test, EF-50.

b.

With respect to BwPT EF-11, the inspector has the following

comments:

l

(1) Deficiency EF-11-AK stated that the IB Containment Spray (CS)

l

pump's flow in the injection phase was less than 3795 gpm (i.e.

l

3787 gpm).

The corrective action was to add the eductor flow

3

. - _

-

.

._

_

c-

.

-.

of.141 gpm to obtain a flow greater than 3795 gpm. This is

incorrect as the FSAR, Section 6.5.2.2, requires the flow to

the spray rings to be greater than 3795 gpm (eductor flow does

.not go to the spray rings).

The second statement in the

-corrective action states that the note after acceptance Criteria

4.2 is applicable so the flow is acceptable.

This is incorrect

since the note pertains to the CS pumps in the recirculation

phase and not the injection phase.

This is considered an

unresolved item (456/86060-01(DRS)) pending license ev61uation

as to how the acceptance criteria was met.

(2)' Deficiency 'EF-11-24 stated that the eductor flow was greater

than the expected 140 gpm (i.e. 141 gpm).

The corrective action

states that.the acceptance criteria total flow should be greater.

than 3795 gpm. .This is incorrect as the flow for the injection

phase per the FSAR should be 3795 gpm to the spray rings and 130

gpm eductor flow for a total flow of 3925 gpm.

The second statement in the corrective action accepting the

eductor flow as-is is acceptable.

i

(3) Step 9.5.55 has acceptance criteria signs for the CS pumps during

the injection phase although there is no acceptance criteria

L

listed in Section 4.

.Since the test has been completed, the only

corrective action necessary will be to ensure that the Unit 2

'

preoperational test contains applicable acceptance criteria.

!

This will be considered an open item (50-457/86050-02(DRS))

I

pending incorporation of the procedural deficiencies into the

Unit 2 test.

The incorrect corrective action to the deficiencies listed above are

further examples'of violation 86052-01 discussed in Inspection Report

No. 50-456/86052. It appears that the resolution to these deficiencies

'

i

showed a lack of understanding of the Engineered Safety Features and

Containment Spray systems.

.

l

No violations or deviations were identified.

However, a portion of this

area requires further licensee justification for CS pump flow rates and is

considered unresolved; portions require _. incorporation _ of TPOI's into Unit 2

,

tests; and portions are further examples of inadequate corrective action

for violation 86052-01 in Report No. 50-456/86052.

j

6.

Preoperational Test Results Verification

i'

The inspector reviewed the following preoperational test procedures and

verified that results were reviewed against approved acceptance criteria

'

i

and an evaluation of the test results had been performed in accordance

with Regulatory Guide 1.68 and the licensee's Startup Manual.

i

f

BwPT AB-10, Revision 2 and Retest 52, " Boric Acid Processing System"

t

BwPT AR-14, Revision'0, " Area Radiation Monitoring (Loop 4)"

BwPT EM-11, Revision 1, " Strong Motion Seismic Instrumentation System"

!

l

I

4

..

.- . -

.- - -

-

- . - _- - - - - , _ - . -

. - _ - _ . .-

-

.

BwPT FC-10, Revision 0 and Retest 37, " Fuel Pool Cooling and Cleanup"

BwPT PR-10, Revision 0, " Process Radiation Monitoring Miscellaneous

Monitors (Safety-Related)"

BwPT PR-11, Revision 3 and Retest 120, " Process Radiation Monitoring

Loop 1"

BwPT PR-13, Revision 1 and Retest 124, " Process Radiation Monitoring

Loop 3"

BwPT PR-14, Revision 1 and Retest 129, " Process Radiation Monitoring

Loop 4"

BwPT PR-16, Revision 1, " Wide Range Gas Monitor (WRGM) Radiation Detector

Monitor"

BwPT PS-12, Revision 1, " Process Sampling - Hydrogen Monitors"

BwPT VD-15, Revision 2, "Intergrated Diesel Gen., Misc. Elect and Switch

Gear Room Ventilation"

BwPT VP-10, Revision 2, " Containment Ventilation"

BwPT VP-11, Revision 2, " Containment Ventilation"

,

BwPT VQ-11, Revision 1, "Off Gas System Hydrogen Recombiners"

With respect to VP-10, the inspec' tor has the following comment:

a.

The test procedure stated that the RCFCs should start in 20-45

seconds.

In the PED approval letter dated May 1, 1986, PED stated

that the start time should have been less than 40 seconds per

Technical Specifications.

Since all fans did start in less than

30 seconds it was not a concern.

However, as discussed in

Paragraph 5.a.(1), the start time used as the acceptance criteria

should be less than 30 seconds and not less than 40 seconds.

The

licensee has initiated TPOI VP-50-01 to address this concern for

Unit 2.

This item will be considered an open item (457/86050-03(DRS))

pending incorporation of the TPOI into BwPT VP-50.

b.

With respect to VP-11, the inspector has the following concern:

Some of the fans (e.g. IVP01CA, 1VP02CA, and IVP02CB) in the test

did not meet their flow acceptance criteria.

Deficiencies VP-11-E,

L, and M were initiated in each case and closed stating that the

flow is acceptable because it agrees with the Braidwood Station

Testing, Adjusting, Balancing (TAB) Report.

The inspector's review

j

determined that the flow data in the test had not been corrected for

'

density.

This function is performed by the Project Engineering

Department, (PED); however, there is no mention in the test that the

flows have to be corrected for density, who will perform it, nor are

.the corrected values recorded in the test for the station to use as a

i

i

l

5

l

-

.-.

_ , - - . . . .

--

. . _ , _ . .

-

. . _ .

_.

<

_t

.,

,

f

.

reference. The inspector has requested that PED provide the corrected

flow data to the inspector for review. This will be considered an

open item (456/86060-02(DRS)) pending receipt of the corrected flow

data.

The closure of these deficiencies based on the TAB report appear to be

in error.

Since PED performs the calculations for corrected flow,

the~ deficiencies should have been closed to those calculations that

proved that the flows were adequate or to an evaluation as to why

the flows are acceptable. This inadequate corrective action for a

deficiency is a further example of violation 86052-01 discussed in

Inspection Report 50-456/86052.

<

With respect to VQ-11, the inspector has the following comment:

c.

1

FSAR Table 6.2.59 lists the hydrogen recombiner reaction chamber gas

temperature as 1325 F maximum.

The acceptance criteria in the test

procedure requires the temperature to be between 1302 F and 1348* F

which is in conflict with the FSAR's maximum temperature requirement.

The data obtained during the test was at or below 1325* F and as such

4

is not a concern.

The licensee has initiated TPOI VQ-51-002 to

address this conflict for Unit 2.

This will be considered an open

,

item (457/86050-04(DRS)) pending incorporation of the TPOI into

,

j

VQ ol.

.

No violations or deviations were identified.

However, portions of this

area require additional information; portions require incorporation of

TP01s into Unit 2 test procedures; and portions contain further examples

.

of inadequate corrective action for violation (50-456/86052-01) in

Inspection Report No.50-456/86052.

'7.

Open Items

Open items are matters which have been discussed with the licensee, which

will be reviewed further by the inspector, and which involve some action

on the part of NRC or licensee or both. Open items disclosed during the

_

inspection are discussed in Paragraphs 5.a, 5.b.(3), 6.a, 6.b, and 6.c.

8.

Unresolved Items

An unresolved item is a matter about which more information is required

in order to ascer'ain whether it is an acceptable item, an open item, a

,

deviation, or a v.olation.

Unresolved items disclosed in the inspection

l

report are discussed in Paragraph 5.b.(1).

- 9.

Exit Interview

f

The inspector met with licensee representatives (denoted in Paragraph 1)

'

throughout and at the conclusion of the inspection and summarized the

scope and findings of the inspection activities.

The licensee acknowledged

the findings.

After discussions with the licensee, the inspectors have

,

'

determined there is no proprietary data contained in this inspection report.

l

l

i

6

L