Insp Repts 50-324/87-04 & 50-325/87-04 on 870223-27. Violation Noted:Failure to Follow Welding Procedure Spec Parameters
ML20205N034
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 03/13/1987
From: Blake J, Coley J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20205N001 List:
References
50-324-87-04, 50-324-87-4, 50-325-87-04, 50-325-87-4, NUDOCS 8704020565
Download: ML20205N034 (10)


See also: IR 05000324/1987004

Text

,

[>R Cterf,b

UNITED STATES

o.

NUCLEAR REGULATORY COMMISSION

"

yN

REGloN 11

p

.g

j

101 MARIETTA STREET, N.W.

  • '-

's

ATL ANTA, GEoRCI A 30323

%

%F

&

.....

Report Nos.: 50-325/87-04 and 50-324/87-04

Licensee: Carolina Power and Light Company

P. O. Box 1551

Raleigh, NC 27602

Docket Nos.:

50-325 and 50-324

License Nas.:

DPR-71 and DPR-62

Facility Name:

Brunswick 1 and 2

Inspection Conducted:

February 23-27, 1987

Inspector:

d,

lu

__ 3 -12-87

t

J.

rey

Date Sig ed

.

(

//

Approved by:

)w

nJj o

7

37

J. J B1 kti, Chief

Date Signed

Mat i

s and Processes Section

Di

si n of Reactor Safety

SUMMARY

Scope:

This routine, unannounced inspection was conducted in the areas of

inservice inspection (Generic Letter 84-11), and welding activities for the

existing weld overlay repairs.

Results: One violation was identified - Failure to Follow Welding Procedure

Specification Parameters

paragraph 7.e.

.

I

B704020565 870318

PDR

ADOCK 05000324

G

PDR

J

_.

.

.

.

REPORT DETAILS

1.

Persons Contacted

Licensee Employees

,

C. R. Dietz, General Manager

  • J. W. Chase, Assistant to General Manager
  • J. A. Smith, Director, Administrative Support
  • M. B. Kesmodel, Supervisor, Document Control
  • E. R. Eckstein, Manager, Technical Support
  • J. Titrington, Supervisor, Engineering
  • L. Wheatley, Project Engineer Inservice Inspection
  • W. J. Dorman, Supervisor, Quality Assurance
  • K. E. Enzor, Director, Regulatory Compliance
  • R. M. Poulk, Senior Specialist, Regulatory Compliance
  • G. J. Oliver, Manager, Site Planning and Control
  • T. H. Wyllie, Manager, Engineering and Construction
  • W. Murray, Corporate Licensing

Other licensee employees contacted included engineers, technicians,

operators, mechanics, security force members, and office personnel.

NRC Resident Inspector

  • B. Ruland, Senior Resident Inspector
  • Attended exit interview

2.

Exit Interview

The inspection scope and findings were summarized on_ February 27, 1987,

with those persons indicated in paragraph 1 above.

The inspector

described the areas inspected and discussed in detail the inspection

findings.

No dissenting ' comments were received from the licensee. The

following new item was identified during this inspection.

(0 pen) Violation 325/87-04-01, Failure to Follow Welding Procedure

Specification Parameters, paragraph 7.e.

The licensee did not identify as proprietary any of the materials provided

to or reviewed by the inspector during this inspection.

,

3.

Licensee Action on Previous Enforcement Matters

This subject was not addressed in the inspection.

_

_ _ _ _ _ _

.

.

2

P

4.

Unresolved Items

Unresolved items were not identified during the inspection.

5.

Independent Inspection Effort

Construction Progress

The inspector conducted a general inspection of the Unit 1 Reactor-

Building and Rod Shack B to observe construction progress and construction

activities such as welding, material handling and control, housekeeping

and storage.

Within the areas examined, no violations or deviation were identified.

6.

Inservice Inspection (ISI)

During the current Brunswick 1, Reload 5, Outage, Carolina Power and Light

(CP&L) has divided the scope of the ISI work among the following vendors

and CP&L organizations:

(1) General Electric (GE) will perform code and

augmental ultrasonic examinations, (2) CP&L's Corporate Quality Assurance

Department (Materials and Quality Section) will perform the surface.

examinations, (3) Site Quality Control (QC) will perform the visual

examinations and, (4) CP&L will perform the existing overlay repairs using

Power Cutting Inc. welding operators that :have been qualified to _ CP&L's

welding procedures.

The inspector examined documents, activities, and records of each of

the above vendor /CP&L organizations to determine whether ISI was being

conducted in accordance with applicable procedure, regulatory requirements

and licensee commitments. The applicable code for 2nd intervals examina-

tions is the American Society of Mechanical Engineers Boiler 'and Pressure

Vessel (ASME B&PV) Code Section XI,1980 edition winter 1981.

However,

since CP&L started the 2nd interval early in order to have both Units

utilizing the same code edition, 1st interval examinations completed

during this outage will be performed in accordance with ASME B&PV Code,

Section XI, 1977 edition with addenda through summer 1978,

a.

Review of Procedures (73052) Units 1&2

i

The inspector reviewed the procedure indicated below to determine -

whether the procedures were consistent with regulatory requirements

and licensee commitments. The procedures were also reviewed in the

area of procedure approval, requirements for. qualification of non-

destructive examination (NDE) personnel, and compilation of required

records; and if applicable, division of responsibility between the

licensee and contractor personnel. Welding procedures used to perform

the existing weld overlay repairs on the recirculation system will be

discussed in detail on paragraph 7 of this report. The following ISI

examination procedures were reviewed:

-

-

-

. .

-

-

-

-

, --

~-

- .

-_

_-.

.

.

.

3

.

Organization

Procedure ID/ Title

GE

UT-51, Revision 2, Procedure for Automated

Ultrasonic Examination of Dissimilar Metal

Welds.

GE

UT-30, Revision 15, Procedure for Ultrasonic

Examination of Austenitic Welds for IGSCC.

GE

UT-43, Revision 9, _ Procedure for Ultrasonic

Examination of Pipe Welds Using Automated

Equipment.

CP&L Corporate NDE

NDEP-10, Training, Qualification and Certi-

fication

of

Nondestructive

Examination

Personnel, Revision 7.

CP&L Cc porate NDE

NDEP-20,

Training,

Qualification

and

Certification

of

Visual

Examination

Personnel

for

Inservice

Inspection,

Revision 4.

CP&L Corporate NDE

NDEP-201,

Liquid

Penetrant

Examination

(Visible Dye, Solvent Removable)

Revision 10.

CP&L Corpartate NDE

NDEP-301, Magnetic Particle Examination (Dry

Powder, Prods or Yoke) Revision 6.-

CP&L Corporate NDE

NDEP-1000, Additional Examination Criteria

for PSI /ISI Surface Examinations, Revision 1.

CP&L Corporate NDE

NDEP-1010,

Recording

Data- from Direct

Visual,

Liquid

Penetrant and Magnetic

Particle Examinations, Revision 0.

CP&L Corporate NDE

NDEP-1011, Weld Joint Identification Marking

~

on Nuclear Power Plant Piping, Revision 0.

Site QC

NDEP-611, Revision 4, VT-1 Visual Examina-

tion of Nuclear Power Plant Components.

Site QC

NDEP-612, Revision 4, VT-2, Visual Examina-

tion of Nuclear Power Plant Plan Components.

Site QC

NDEP-613, Revision 5, VT-3, Visual Examina-

tion of Nuclear Power Plant Components.

.

4

.

Organization

Procedure ID/ Title

'

Site QC

NDEP-614, Revision 6, VT-4, Visual Examina-

tion of Nuclear Power Plant Components.

Site QC

Periodic

Test:

PT-91.0.52,

VT-3/VT-4

Examination of Component Supports.

(1) The inspector reviewed procedures UT-51, UT-30 and UT-43 to

ascertain whether they had been reviewed and approved in

accordance with the licensee's established QA procedures. The

procedures were reviewed for technical adequacy-and conformance

with ASME,Section V, Article 5 and other licensee commit-

ments/ requirements in the below listed areas:

type of

apparatus used; extent of coverage of weldments; calibration

'

requirements; search units; beam angles; DAC curves; reference

level for monitoring discontinuities; method for demonstration

penetration; limits for evaluating and recording indications;

recording significant indications and; acceptance limits.

(2) The inspector reviewed procedure NDEP-201 to ascertain whether

it had been reviewed and approved in accordance with the

licensee's established QA procedures.

The procedure was

reviewed for technical adequacy and conformance with ASME,

Section V, Article 6 and other licensee commitments / requirements

in the below listed areas: specified method; penetrant material

identification; penetrant materials

analyzed 'for

sulfur;

penetrant materials analyzed for total . halogens; acceptable

pre-examination surface; drying time; method of penetrant

application; surface temperature; solvent removal; surface

drying prior to developing; type of developer; examination

technique; evaluation technique; and procedure requalification.

(3) The inspector reviewed procedure NDEP-301 to ascertain whether

it had been reviewed and approved in accordance with the

licensee's established QA procedures.

The procedure was

,

reviewed for technical adequacy and for conformance with

ASME Section V, Article 7,

and other licensee commitments /

requirements in the below listed areas:

examination method;

contrast of dry powder particle color with background; viewing

conditions; examination overlap and directions; pole or prod

spacing; current or lifting power (yoke) and; acceptance

l

criteria.

(4) The inspector reviewed visual examination procedures N0EP.611,

NDEP.612, NDEP.613, NDEP,614 and PT-91.0.52 to determine whether

they contained sufficient instructions to assure that the

following parameters were specified and controlled within the

.

-

-

-

-

-

- -

- -

-

..

. -

- - -

.

5

.

limiti permitted by the applicable code, standard, or any

additional specification requirement: method - direct visual,

remote visual or translucent visual; application - hydrostatic

testing, fabrication procedure, visual examination of welds,

leak testing, etc.; how visual examination is to be performed,

type of surface condition available; method or tool for surface

preparation, if any; whether direct or remote viewing is used;

special illumination, instruments, or equipment to be used, if

any; sequence of performing examination, when applicable; data

to be tabulated, if any acceptance criteria is specified and

consistent with the applicable code section or controlling

specification; and report form completion.

b.

Examiner Qualifications (73052 & 73753)

(1) CP&L Corporate NDE

The inspector reviewed the qualification documentation for the

below listed NDE examiners in the following areas: employer's

name; person certified; activity qualified to perform; effective

period of certification; signature of employer's designated

representative, basis used for certification; and annual visual

acuity, color vision examination and periodic recertifica-

tion.

Method Level

Examiners

MT

PT

VT

RT

VT

E.B.

III

III

III

J.H.C.

II

II

II

J.M.G.

II

II

II

L.P.J.

II

II

II

A.D.L.

II

II

II

D.R.L.

II

II

II

II

E.W.M.

II

II

II

N.V.P.

II

II

I

II

G.M.T.

II

II

II

II

II

(2) General Electric

The inspector verified GE's ultrasonic examiner qualifications

for the inspector of intergranular stress corrosion cracking

(IGSCC) in accordance with EPRI/BWROG/NRC training and qualifica-

tion agreement.

This was done by comparing GE's personnel

status log against EPRI's monthly qualification status summary.

The following individuals were certified as follows:

-

.

6

.

Method Level-

EPRI

EPRI

EPRI

Data

Data

Name

VT

IGSCC

Sizer

O' Lay

Coll.

Analysis

R. Anderson

II

x

-

-

-

-

R. Bendele

II

x

.

-

x

-

R. Bonniwell

II

x

-

-

--

-

B. Bouck

II

x

x

x

-

-

J. L. Briggs

III

-

-

-

x

-

T. L. Brinkman

III

x

x

x -

x

T. R. Brinkman

III

x

x

x

x

x

J. P. Carson

II

x

,

E. Catron

II

x

B. M. Dummer

III

x

x

x

x

x

M. Evich

II

x

V. Gruno

II

x

T. Kimball

II

x

x

x

x

B. Lester

II

x

x

x

x

W. Money

II

x

x

R. Parr

II

x

R. A. Seals

III

x

x

x

x

)

S. Whiddon

II

x

x

x

T. R. White

II

x

x

x

x

c.

Observation of Work Activities - Unit 1 (73753)

Generic Letter 84-11 initiated a reinspection program for piping

susceptible to IGSCC.

In accordance with the above guidance CP&L

plans to perform the following inspection during the present Unit i

-

refueling outage:

.

7

.

(1) unrepaired austenitic stainless steel welds

(2) IE Notice 84-41 inconel butter welds

(3) existing weld overlay repairs

The inspector observed the following in process examinations on the

inconel butter welds:

Weld No. IB32-12-BR-K6

Weld No. 1832-12-BR-J6

In addition to the above, the inspector reviewed video tape of the

examinations performed on the following welds:

Weld No. 28" B32A-1 inconel butter examination

Weld No. 28 B32A-3 IGSCC examination

The above welds were examined with the GE SMART UT system using

examiners qualified in accordance with the EPRI/BWR06/NRC Training

and Qualification Agreement.

Within the areas examined, no violation or deviation was identified.

7.

Existing Weld Overlay Repairs - Unit 1 (73753 & 55055)

There are currently 32 weld overlay repairs on Brunswick-1. These are

designed repairs; however, as-built dimensions show that many meet the

standard guidance as propcsed in the draft of NUREG-0313 Revision 2.

The

length and surface finish of these repairs do not allow UT inspection

using the EPRI qualified technique; therefore, reinspection will require

lengthening and surface finishing prior to the UT examination. Ten of the

repairs on Brunswick-1 were applied in 1983 and 1984 and have been in

service for two fuel cycles. The remaining 22 repairs were applied during

the 1985 Reload 4 outage and, as such, will have been in service for only

one cycle.

CP&L plans to upgrade the ten repairs applied in 1983 and 1984 such that

inspections can be accomplished using the EPRI qualified UT technique.

Upgrading these weld overlay repairs consists of adding length and

thickness to the overlay, as required, and performing surface finishing.

CP&L has endorsed a NUTECH analysis which justifies continued operation of

Brunswick-1 for an additional 18-month fuel cycle without upgrade or

inspection of 21 of the 22 weld overlay repairs applied in 1985. As

recommended by the report, the licensee will upgrade and inspect weld

12"-B32-BR-J-3.

In addition, the licensee plans to upgrade and inspect as

many of the remaining 21 repairs applied in 1985 as possible without

impacting the outage critical path.

.

8

.

The inspector reviewed the licensee's welding program, procedure, procure-

ment, qualifications activities, filler material control and storage and

in process welding activities to determine whether the licensee quality

control systems met the applicable procedure, regulatory requirements

and a licensee commitments. The applicable code for the overlay repair

welding is ASME,Section IX, the mandatory edition and addenda in effect

on the date of the welding procedure qualification.

New procedures,

evaluation procedures and acceptance criteria for austenitic piping is

ASME Code Section XI paragraph IWB-3640 and Section IX, 1983 Edition with

Addenda thru Winter 1983.

a.

Review of Procedures

The inspector reviewed the procedure indicated below to determine

whether the procedures were consistent with regulatory requirements

and licensee commitments.

The procedures were also reviewed in the

areas of procedure approval, and compilation of required records:

Procedure ID

Title

Plant Model 86-068

Existing Weld Overlay Repairs

WP-502 Revision 9

Welding Procedure Control

WP-503 Revision 11

Welder Qualification

WP-510 Revision 4

Qualification of Welding Procedure

Specification

WP-511 Revision 2

Welding Equipment Control

WP-501 Revision 5

Procurement of Welding Materials

b.

Base Materials & Filler Metal Compatibility

The inspector reviewed purchasing and receiving records for the

filler material used to repair the weld overlays (P.O. B-31925, Heat

No. S8t'530, ER-308L(.035)) and verified that the filler material was

_

properly identified, storage and controlled in weld shack B.

c.

Welding Procedure Specifications

The inspector verified the licensee's welding specifications were in

accordance with Section IX and XI of the ASME Code, supported by

acceptable Procedure Qualification Reports (PQR's) that had received

the required mechanical test.

The following welding specifications

and their applicable PQR are listed below:

-

.

-

.

,-

9

Welding Procedure Specification / Effective Code

PQR

WPS-8BU7 Revision 0 - ASME (77579)

68

WPS-88U12 Revision 5 - AMSE (80W81)

33

WPS-43BU1 Revision 3 - AMSE (83584)

147

d.

Welder Performance Qualification

The inspector reviewed the qualification status for the weld

operators listed below and observed in process qualification efforts

for the overlay repair welding in the weld test shop.

Welder

WPS 8BV7

88V12

43BV1

P15

/

/

/

P29

/

/

/

P20

/

/

/

P38

/

/

/

YD8

/

/

/

P16

/

/

/

Y7G

/

/

/

P10

/

/

/

P18

/

/

/

P12

/

/

/

P34

/

/

/

P5

/

/

/

V1N

/

/

/

e.

Production Welding

The inspe. tor observed in process repair welding activities on weld

overlays for weld numbers 28" B32-B-4 and 28" B32-A-4.

During this

observation, the inspector reviewed the plant modification require-

ments for these welds, welding filler material control records and

welding procedure parameters used by the welders to make the repair

welds. The inspector noted that the welder on weld 28" -1832-A-4 was

operating in the sync pulse mode and had his machine set at .05 for

the oscillation amplitude. The required welding procedure WPS-88U12

for this repair required that the oscillation amplitude ' be -set

between .06 and .200 when operating in the sync pulse mode.

Failure

to follow the qualified parameters of the welding procedure is a

violation of regulatory requirements and was reported to the licensee

as Violation 325/87-04-01, Failure to Follow Welding Procedure

Specification Parameters.

Within the area examined, no violations or deviations were identified,

except as noted in 7.e. above.