ML20205J730

From kanterella
Jump to navigation Jump to search
Insp Rept 50-219/88-26 on 880909 & 0912-15.No Violations Noted.Major Areas Inspected:Licensee Inservice Insp Program to Ascertain That Program Complies W/Applicable ASME Code & Regulatory Requirements & Response to Generic Ltr 88-01
ML20205J730
Person / Time
Site: Oyster Creek
Issue date: 10/11/1988
From: Mcbrearty R, Strosnider J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20205J724 List:
References
50-219-88-26, GL-88-01, GL-88-1, NUDOCS 8810310469
Download: ML20205J730 (9)


See also: IR 05000219/1988026

Text

-

,

.. .

..

-

.

,

y

U.S. NUCLEAR REGULATORY COMMISSION

,

REGION I

'

Report No.

50-219/88-26

i

Docket No.

50-219

i

'

i

License No. OPR-16

i

Licensee:

'O Nuclear Corporation

P.O. Box 388

i

Forked River, NJ 08731

[

Facility Name: Oyster Creek Generating Station

f

!

Inspection At:

Forked River, New Jersey

Inspection Conducted: September 9, and 12-15, 1988

/0///W

Inspectory

u

gr

A.~McBrearty, Reactor Engineer

date

/O/##

Approved by:

_

~

date

J. R. Strosnider, Chief, Materials and

Processes Section

Inspection Summary:

Inspection on September 9, 1988 and September 12-15,

'1T88 (Inspection Report No. 50-219/88-26)

Areas Inspected: A routine, unannounced inspection was conducted of the

licensee's inservice inspection (ISI) program to ascertain that the program

complies with applicable ASME Code and regulatory requirements.

Particular

emphasis was placed on the licensee's control of ISI activities such as ISI

vendor selection, control and tracking of nonconforming items, and the

incorporation of plant modifications into the ISI program.

In addition, the

licensee's respor.se to Generic Letter 98-01 was examined.

Ressly : The inspector concluded, based on the areas inspected, that the

licunsee's program complies with the mandated edition of the ASME Code and

maintains adequate control over the licensee's routine ISI activities.

The

licensee's response to GL 88-01 was timely and addressed the areas required by

the GL.

9

8810310469 681024

PDR

ADOCK 05000219

0

PDC

__

_ _ _

_ _

_ _ _ _ .

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ - _ _ . -.

..

..

-

,

s

DETAILS

1.0 Persons Contacted

General Public Utilities Nuclear Corporatior. (GPUN)

  • R. J. Blough, Manager Technical Support
  • G. W. Busch, Licensing

D. Covill, Materials Engineer - GPUN Technical Functions

  • E. E. FitzPatrick, Vice President / Director Oyster Creek
  • T. Gaffney, Plant Materials

0. Holland, Senior Project Engineer

  • 0. MacFarlane, Manager Quality Assurance Site Audits

0. Jerko, Licensing Engineer

  • R. Ostrowski, QA/SPP

T. Patterson, Manager, QA/SPP

  • G. Rhedrick, QA/ISI Engineer
  • A. H. Rone, Plant Engineering Director
  • M. J. Slobodien, Director, Rad Con
  • R. L. Sullivan, E. P. Manager

U.S. Nuclear Regulatory Commission

  • E. Collins, Resident Inspector
  • J. Wechselberger, Senior Resident Inspector
  • Denotes those present at the exit meeting.

2.0 Scope of Insgection

.

Section XI, Rules for Inservice Inspection of Nuclear Power Plant

Components, of the ASME Boiler and Presssure Vessel Code provides rules

for the examination, testing, and inspection of components and systems in

a nuclear power plant.

Section XI mandates that the plant owner develop

a program which will demonstrate conformance to Code requirements, and the

licensee performs inservice inspectio.1 to comply with those requirements

and with its inservice inspection program plan.

The following areas of the inservice inspection program were selected for

inspection:

ISI organization

ISI vendor selection and qualification

System for tracking reported flaws and deficiencies to assure proper

review and closeout

Process by which plant modifications are incorporated into the ISI

p rog ram

.

f

-

_ _ _ _ _ _ _ .

..

..

l

.

-

3

'

)

In addition to the above, the licensee's response to Generic Letter 88-01

,

I

was selected for inspection.

3.0 Inservice Inspection (ISI) program (73051)

The inspector determined that the Oyster Creek facility is in the second

ten year inspection interval which commenced on December 8,1979, and

will continue until December 7, 1989. The applicable code, as specified

by 10 CFR 50.55a(g)(4)(ii), is the 1974 Edition of Section XI through

Summer 1975 Addenda.

Inservice Inspection Organization Staffing

The Special Process and Programs Division includes Nondestructive

Examination (NDE), Welding Engineering and Inservice Inspection groups,

and in addition, Materials Support to Quality Assurance.

The onsite ISI staff includes the following:

Manager ISI/NDE

Lead ISI Engineer

ISI Engineer

NDE Engineer

The staff is aided by the NDE group which includes Level II and Level III

personnel.

During refueling outages the onsite staff is enhanced bv the

e

addition of Magnaflux Quelity Services personnel, the licensee's ISI

vendor, and by corporate staff members.

In addition General Electric

Company will perform augmented examinations for the detection of

intergranular stress corrosion crweking in austenitic stainless steel

piping welds.

The licensee's staff was found to be technically capable of performing

their assigned duties, and staff size is adequate to meet the scheduled

work load.

ISI Vendor Selection

The licensee perforns periodic surveys of its ISI vendor to initially

place the vendor on its Supplier Quality Classification List (SQCL) and

to retain the vendor on the list after the initial finding.

These

surveys are performed at the vendor's facility. Additionally, onsite

dudits of the ISI program and of vendor activities are performed during

refueling outages when these activities are in progress, and serve, in

part, to ascertain that the vendor maintains its qualification.

_

_. ..

_ _ _ _ _ _ _ _ _ _

..

..

%

4

The inspector reviewed Survey Report No. 8701009 which was performed by

the licensee on February 12, 1987 at the Magnaflux Quality Services

(MQS), Inc. facility at Trevose, Pennsylvania. The purpose of the survey

was to review and verify implementation of the MQS, Inc. QA program as

it relates to 10 CFR 50, Appendix B, and ANSI N45.2 in providing QA and

NDE personnel services for possible placement of MQS on the licensee's

SQCL.

In addition to the above, licensee QA Audit No. S-0C-87-03 was

selected for inspection.

This was the latest audit of the ISI program

and ISI vendor onsite activities during the last refueling outage.

The

audit was performed by the licensee's onsite audit group to assess the

definition and implementation of the 151 program at Oyster Creek.

The inspector found that Survey 87010v9 resulted in one finding regarding

the certification of visual inspectors using practical test specimens

that did not contain known defects.

The survey team, which included a

level III member, recommended that MQS procure hanger, snubber and

restraint practical test specimens that contain known defects.

Audit S-0C-87-03 focused its attention on various ISI elements including

the following:

ISI organization

Personnel qualification / certification

Records management

Inspection standards

Control of recordable indications

The audit resulted in no findings which required a response by the

audited organization.

The licensee transmitted the report of Survey 8701009, including the

l

finding arid recommendation, to MQS by letter dated March 2,1987.

l

Licensee acceptance of MQS as a vendor was withheld pending the MQS

'

response to the survey finding,

The inspector determined that the MQS

response to the survey finding was provided in a timely manner, and was

acceptable to the licensee.

The recommendation to procure test samples

was implemented by MQS, and evidence of this was provided to the

licensee.

Based on the MQS response, the licensee closed out the survey

finding and pieced MQS on its SOCL,

The check lists associated with Survey 8701009 and Audit S7-03 were

examined by the inspector with respect to the appropriateness of each for

the licensee's purpose.

The inspector determined that survey and audit

elements provided sufficient variety to allow the licensee to intelli-

gently assess the ISI program implement-* ion, and its IST vendor's

capability to provide the necessary services.

No violations were identified.

-- .

____

. _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ -

.

.

5

Control of Nonconforming Items

The licensee's system for tracking inservice inspection items which do

not clearly meet the applicable acceptance criteria includes the use of a

"Request for Evaluation" (ER), and a "Material Noncoriformance Report"

(MNCR).

To ascertain that the licensee's system for tracking ISI nonconforming

items provides for adequate liceasee review and resolution of these items

the folicwing procedures were selected for inspection:

Procedure No. GPUN 6150-ADM-3272.03, Revision 0, Entitled "Recording

and Distribution of Non-destructive Examination Data for Inservice

Inspection"

Procedure No. GPUN 9850-ADM-3272.01, Entitled "Evaluation of

Recordable Indications"

Procedure No. 1000-ADM-7215.01, Revision 2, Entitled "GPUN Material

Nonconformance Reports and Receipt Deficiency Notices"

The inspector determined that a request for evaluation is issued by the

SPP/ISI group when an ISI report identifies a condition or an indication

that requires evaluation to ascertain its acceptability.

The evaluation

is performed by a Level II or Level III Examiner, and if additional

examinations are required they are performed by the QC NDE/ Welding

group.

Indications which are determined to be non-relevant or geometric

in nature must be documented on the ER and justification for the

evaluation provided.

Additionai evaluation, when required, is provided

by the appropriate engineering organization at the request of the ISI

group.

If the engineering group finds that the condition or indication

is unacceptable a MNCR is generated by the ISI group.

A Material Nonconformanca Report may be initiated by anyone, but Quality

Control is responsible for assigning a sequential number and for tracking

the MNCR.

The originator must deliver the MNCR to the QC Manager or his

designee during normal work hours, or to the appropriate Shift Supervisor

or Senior Plant Reactor Operator during backshifts or weekends. QC is

additionally responsible for taking measures to preclude use of the

nonconforming item and for assigning and notifying the responsible

department who evaluates the condition and proposes a disposition.

The

final disposition is provided by the cognizant engineering group.

Material Nonconformance Reports are reviewed by various levels of

management and are closed out by the QC dopartment when the disposition

is completed and verified by QC, and when the QC Manager ascer'ains that

all required reviews and sign offs are completed.

Sign off by L'e QC

Manager indicates the closecut of the MNCR.

,

_ _ _ _ - _ _ - _ _

_

_

. _ _ _

_ _ - _

. _ _ _ _ _ _ _ _ _ _ _ _

_

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

..

..

%

6

In addition to the above, the follosing MNCRs were selected for inspection

to ascertain whether closecut was properly done and was based on the

documented engineering disposition:

MNCR #86-498 - opened to track nonconforming conditions documented

by a visual inspection report.

MNCR #86-632 - opened to track an unacceptable ultrasonic

indication.

MNCR #86-432 - opened to track nonconforming conditions documented

by a visual examination report.

MNCR #86-426 - opened to track a nonconforming condition documented

by a visual examination report.

MNCR #86-605 - opened to track unacceptable ultrasonic indications.

The MNCRs resulted from evaluation requests which addressed conditions

which were found to be unacceptable and required rework or repair to

become acceptable.

The inspector determined that initiation, processing,

review and closecut of the MNCRs was in accordance with the licensee's

,

i

established system.

No violations were identified.

Incorporating Plant Modifications into the Inservice Inspection Program

Plant modifications and design changos are controlled by the licensee

with the following Technical Cunc'.lons Division and Quality Assurance

Engineering procedures:

Procedure No. 5000-ADM-7315.01, Revision 2-00, entitled

"Specifications"

Procedure No. 5000-ADM-7313.11, Revision 3-01, entitled

"Modification and System Design Descriptions"

Procedure No. 9800-QAP-7203.01, Revision 1, entitled "GPUN QA Review

of Engineering Specifications, Installation Specifications,

Modification and System Design Descriptions"

The inspector reviewed the above procedures and found that Quality

Assurance Engineering is required to review modifications and design

change packages with respect to inservice inspection requirements

including preservice inspection of new welds.

.

The procedures required that conditions shall be identified for

performing ISI during operation or shutdown and, in addition, access

requirements to accommodate ISI must be identified.

-

,

.

.

-

s

,

7

In addition to the above, the inspector reviewed the fol' lowing modifica-

tion package which was completed during the last refueling outage:

Reactoi Head Vent Valve Modification

The inspector found that all required reviews were performed as evidenced

by the completed sign offs. Additionally, the applicable edition of ASME

Section XI was referenced, and the requirements for preservice inspection

of new welds was identified.

The appropriate welding records and NDE

reports were included in the package and in addition, the Code required,

properly completed NIS-2 Form was included.

The NDE reports contained

all the required QC, ISI and ANI signatures.

The inspector determined that the modification was initiated, reviewed

and performed in accordance with the licensee's established system.

No violations were identified.

4.

Licensee Response to Generic Letter (GL) 83-01 "NRC Position on

WSCC in SW Austenitic Stainless Steel PipIF(~9270T)

--

Intergranular stress corrosion cracking (IGSCC) near weldments in BWR

piping has been occurring for almost 20 years.

Early cases were in

relatively small diameter p! ping.

In early 1982, cracking was identified

in large-diameter piping in a recirculation system of an operating BWR

plant in this country.

Since then, extensive inspection programs have

been conducted in BWR piping systems.

These inspections have resulted in

the detection of significant numbers of cracked weldments in almost all

operating BWRs.

Substantial efforts in research and development have been sponsored by

the BWR Owners Group for IGSCC Research.

The results of this program

along with other related work by vendors, consulting firms, and

confirmatory research sponsored by the NRC, have permitted the

development of revised Staff Positions regarding the IGSCC nroblems.

The technical bases for these positions are detailed in NUREG-0313,

Revision 2. "Technical Report on Material Selection and Guidelines for

BWR Coolant Pressure Boundary Piping",

NUREG-0313 Revision 2 describes

the technical bases for the staff positions on materials, processes, and

primary coolant chemistry to minimi:e and control IGSCC problems.

Inspection schedules and inspection sample sizes are based on the

susceptibility of weldments to initiation and propagation of IGSCC.

Inspection schedules are comparable to those specified in Section XI of

the ASME B&OV Code in cases where the piping material is IGSCC

resistant.

,

%

..

..

,

s

8

This Generic Letter applies to all BWR piping made of austentitic

stainless steel that is four inches or larger in nominal diameter and

contains reactor coolant at a temperature above 200 F during power

operation regardless of Code classification.

It also applies to reactor

vessel attachments and appurtenances such as jet pump instrumentation

penetration assemblies and head spray and vent components.

Licensees are

requested to respond to the GL within 180 days of the receipt of the

letter.

The GL provides a list of specific items which should be

included by Itcensees to constitute an acceptable response to the GL.

The licensee's response to the GL dated August 12, 1988 was reviewed by

the inspector to ascertain that applicable systems were identified, welds

were categorized and inspection schedules were established in ac:ordance

with Table 1 of NUREG-0313, Revision 2.

The inspector found that the licensee responded to the GL within the

allotted time and that the response addressed the five areas listed by

the Generic Letter.

The licensee has developed an inspection schedule based upon the

categories defined by the NUREG and the GL.

The weld categories in this

plan are predicated upon stress improvement plans which will be performed

during the upcoming 12 R outage, and Hydrogen Water Chemistry which will

be implemented upon the plant returning to power operation after the 12 R

outage.

The licensee plans to conduct inservice inspections during the

12 R outage in accordance with the existing plan based on Generic Letter 84-11.

The licensee met with the NRC (NRR) on May 26, 1988 and again on June 28,

1988 to discuss the licensee's plans for outage 12 R and its plans regarding

1GSCC inspection / stress improvement.

These meetings were the subject of

NRC correspondence to the licensee dated 6/16/88 and 7/6/88.

Correspondence from the licensee to the NRC dated 2/16/88 and 4/5/88

provided information regarding the licensee's plans for outage 12 R.

The S/16/88 NRC letter advised the licensee that the information

presented in its correspondence of 2/16/38 and 4/5/88 and during the

meeting of 5/26/88 would be reviewed by the staff and that the licensee

would be advised of the staff's position regarding the matter.

The NRC

letter of 7/6/88 discussed items presented by the licensee during the

6/28/83 meeting and requested additional, specific information from the

licensee.

The licensee response was contained in its letter of 8/1/88.

At the tirne of this inspection the licensee had not yet been advised of

the staff's position.

1

- - _ _ _

.

..

~,

..

9

5.

Exit Meeting

The inspector met with licensee representatives (denoted in paragraph 1)

at the conclusion of the inspection on September 15, 1988.

The inspector

summarized the scope and findings of the inspection.

At no time during the inspection was written material provided by the

inspector to the licensee.

The licensee did not indicate that

proprietary information was involved within the scope of this inspection.

.