1RIELECTRIC NE 14716 December 15, 1987 S. L. Stamm Project Engineering Manager.
Stone and Webster Engineering Corporation CPSES COMANCHE PEAK STEAM ELECTRIC STATION ENGINEERINC ASSURANCE SURVEILIANCE REPORT: TSR 87 59' LEAD CONTRACTORS COMPLIANCE TO PROCEDURE ECE 1.01 A surveillance of SWEC CAP's Implementing Procedures (IPs) was conducted November 23 through November 25, 1987, by Comanche Peak Engineering -
Engineering Assurance (CPE-EA).
I.
PURPOSE i
The surveillance.was conduqted to verify on a limited basis SWEC CAPS
[
compliance with the requirements of procedure FCE 1.01, Revision 1, i
"Organization."
I II.
SCOPE The surveillance reviewed 62 SWEC CAP Implementing Procedures verifying procedural references were current and consistent with manual indexes as a basis for verification of procedural compliance. A listing of the procedures reviewed is provided in Attachment 1. is a listing of personnel contacted and those in attendance at the exit briefing.
III.
SUMMARY
The surveillance found that 19 of the SWEC-CAP's Implementing Procedures were not in full compliance with procedure ECE 1.01 requirements because they contain ECE and/or PP Procedures which were deleted or superseded.
IV.
FINDINGS DEFICIENCIES : None DISCREPANCIES:
DISCREPANCY NO. 1 PP-009, paragraph 6.2.5, page 10 of 13, bullet 4, states in part:
"Distribution shall be made utilizing SWEC transmittal form indicated on the Calculation Title Page and shall include, as a minimum the following:
8803040100 800223 PDR ADOCK 0500044S g
..A Bo.'.1002 Gen Roi*, Tetas it6434002
e I
NE 14116
-2 t
0 TU Electric Interim Calculation File (see Section 6.1.7.6)."
Section 6.1.7.6 does not exist in the current procedure.
DISCREPANCY NO. 2 PP 053, paragraph 3.0, "References", lists ECE 6.08-PE-I3; A review of the current Table of Contents for ECE procedures indicates no such procedure exists.
Action Responsibility : SWEC-CAP OBSERVATIONS: is a list of observations identifying inconsistencies with references cited in the SWEC-CAP IPs.
Action Responsibility : SWEC CAP V.
DISCUSSION / EVALUATION:
ES;ineering Assurance recommends SWEC CAP perform a complete review of IPs to assure compatibility to CPE - ECE procedures. Additionally, SWEC CAP needs to determine the impact, if any, of their activities being performed l
to procedures with inconsistencies identified as the result of the review and this surveillance.
A written response to the Discrepancies and Observations identified herein is to be submitted not later than January 15, 1988. The response should include the 7
cause of the findings reported, extent of condition, action to resolve the reported condition, action to prevent recurrence, and scheduled completion dates.
I u
l 3
J
g_.----
g, i
1 e
r
(
NE 14716
-3 If you have any. questions, please contact C. Morell at extension 6152.
I Prepared By:
),
k C.D. Morell EA Evaluations Comanche Peak Engineering
)
Approved By:
h A.H. Saunders EA Evaluations Manager Comanche Peak Engineering
[
CDM:jdb Attachments:
- 1) Listing of SWEC-CAP Drawings Reviewed - 4 pages
- 2) Listing of Observations 2 pages
- 3) Personnel Contacted and Exit Briefing Attendees 1 page cc: ARMS J. L, Barker E 10 M. D. Bever A 80 H. M. Carmicheal SW-1
- 0. W Love E-07 D.
McAfee Q 03 L. D. Nace E 01 D. M. Reynerson E-14 J. F. Streeter A 08 W. G. Westhoff T-09 I
a
O i.
NE 14716 ATTACHMENT 1 Page 1 of 4 LISTING OF SWEC CAP PROCEDURES REVIEWED PP REVISIONS CHANGE NOTICES No.
TITLE No.
Date No.
Date 000 Project Organization 1
02/02/87 1
001 Management Plan for Project Quality 1
02/19/87 1 05/19/87 002 Preparation, Issuance, and Control of 2
10/15/87 1 11/16/87 Project Procedures 003 Preparation, Review and Approval of 0
11/21/86 2 05/14/87 Generic Issue Reports (GIRs) 005 Procedure for the Evaluation and 0
10/10/87 Processing of (TDDRs) 006 Procedute for processing Corrective 1
11/08/87 Action Requests (CARS) 007 Preparation, Review and Approval of 0
03/23/87 1 04/21/87 Package Process Forms (PPFs) 008 Preparation and Approval of Task 2
09/16/87 Descriptions 009 Preparation and Control of Manual and 2
08/13/87 5 11/03/87 Computerized Calculations 010 Preparation, Issuance, and Control of 2
11/16/87 Project Correspondence 011 SWEC-CAP /TU Electric Interface 1
08/25/87 1 10/07/87 012 Westinghouse Interface 1
02/27/87 014 SWEC-CAP /Ebasco Interface 2
08/24/87 1 10/22/87 015 SWEC CAP /Impell Interface 2
08/24/87 1 10/07/87 017 Lrinneli Interface 1
02/27/87 019 Change controls for Licensing 1
02/12/87 Documents 020 Control of Design Re.ated Project 2
09/21/87 021
)ocument Control 1
09/21/87 022 ferforming Project Surveillances 1
11/10/87
t..
NE-14716 ATTACHMENT 1 Page 2 of 4 f
LISTING OF SWEC CAP PROCEDURES REVIEWED'
~PP REVISIONS CRANCE NOTICES No.
TITLE No.
Date No.
Date 023 ' Processing of Design Change 4
04/17/87 7 11/13/87 Authorizations (DCAs) and Change Verifications 024 Review of Construction, Quality 1
04/02/87 Control, Startup and Pre-Operational Procedures i
025 Record Corrections, Changes and 0
04/02/87 Supplements 026 Processing of Nonconforming Reports 5
10 05 87 2 11 06 87 (NCRs) Conditional Releases Requests and Tests Deficiency Reports (TDRs) 027 Systems for Processing Items of 0
11 03 86 2 08 27 87 Reportability 028 Project Records Management Program 2
11 10 87 029 Administration of the Problem Report System 1
04-22 87 030 Preparation, Review, and Approval of 1
10-14-87 1 10 26 87 Design Engineering Packages (DEPs) 031 Preparation and Issue of Design 0
05-19-87 1 09-29 87 l
Modifications (DMs) 032 Preparation, Review, and Approval 3
07-20 87 of SWEC Project Drawings 033 Review of Contractor Specifications 1
06 03 87 034 Processing of Procurement Documents 2
06 03 87 3 11 06 87 035 Project Training Program 2
10 08 86 2 05 07 87 036 Procedure for Computer Aided Design 1
07-20 87 (CAD) Drawing Conversion 037 Definition of Design Document Classif-0 10 08 86
[
ication and Marking of Design Documents 039 Procedure and Maintenance of Project 3
11-13 87 1
10 23 87 J
.___,_c..
7. __ _. _
l
?
- a r NE 14716 ATTACHMENT 1 Page_ 3 of 4 LISTING OF SWEC CAP PROCEDURES REVIEWED PP-REVISIONS CHANGE NOTICES No.
TITLE No.
Date No.
Date 040 Procedure for Review of Wiring 0
10 29 87 t
Diagrams 041 Nenconformances Evaluation Procedure 2
10-it-27 042 _SWEC-CAP /PSAS Interface 1
08 24-87 1 10-23 87 045 Time Charging 0
12 01-86 C46 Engineering Activities to Support 0
05/21/87 1 07/02/87 i
SWEC Certification of ASME III, i
Class 2 and 3 System N 5 Data Reports as Piping System Designer I
047 ProcessinS Work Package Change Notices 1-
'06/09/87 (WPCNs) f 048 Maintenance of the Til Electric 1
09/11/87 l
Calculation File I
049 Control of Engineering Sketches 0
10/08/87 i
050 Preparation of Field Verification 2
09/03/87 3 11/03/87 Method (TVM) Procedures 05:
Control of Safeguards Information 1
03/23/87 r
2 10/22/87 055 The Qualification of Embedments in 0
06/10/87 f
Concrete 056 Preparation, Approval and Issue of 3
11/13/87
(
Specific Technical Issue Reports (STIRS) 057 Guidelines for Planning and Scheduling 0
02/12/87 058 Processing of Licensing Correspondence 1
07/07/87 t
I h
n
i, t-e 4.
P NE 14716 ATTACHMENT 1 Page 4 of 4 LISTIriG OF SWEC CAP PROCEDURES REVIEWED PP REVISIONS CHANGE NOTICES No.
TITLE No.
Date No.
Date 059 Procedure for Processing of Deficiency 0
02/24/87 5 10/20/87 Reports (DRs) 060 - Control of Concrete Attachments Spacing 1
11/11/87 Violations 062 Processing Temporary Software and Data 0
08/18/87 Base Modifications to In Plant Computers 063-Specification, Procedure and Drawing-0 07/20/87 Update (SPADU) Program 064 Preparing and Documenting Safety 1
10/14/87 Evaluations on Preoperating License Design Modifications 065 Control of Computerized Equipment List 0
04/08/87
x r
NE 14716
~ ATTACHMENT 2 Page 1 of 2 LISTING OF OBSERVATIONS REFERENCE TSR 87-59 1)
PP-000 Revision 1, paragraph 3.0 "References" lists TNE AD 1; this precedure has been deleted and superseded by ECE 1.01 accordiag to TU Electric CPE ECE Manual Table of Contents, Revision
- 174, 2)
PP 001c Revisioa 1,~page 1 of 7 Criterion 3, lists PP 004 as a current procedur s; this procedure has been canceled since May 21, 1987.
3)
PP-005 Revision 0, paragraph 3.0 "References" lists TUCCO TNE AD5; this procedure has been deleted and superseded by ECE 9.01.
6)
PP 012 Paragraph 3.0, "References" and 4.0 "Definitions" lists ECE AD 1; this procedure has been deleted and superseded by ECE 1.01, Revision 1 (08/13/87).
7)
PP 017 Paragraph 1.0 "Purpose", 3.0 "References", and 4.0 "Definitions" lists TNE AD 1; this procedure has been deleted and superseded by FCE 1.01, Revision' 1 (08/13/87).
8)
PP 020 Attachment PP 02 A, lists.ECE DC-21; this procedure has been deleted and superseded by ECE 5.01 13, 9)
PP-021 Paragraph 3.0, "References" lists ECE 2.13 12; this procedure has been replaced by ECE 2.13 02.
- 10) PP-023 Paragraph 3.0, "References" lists ECE 5.01 13; this procedure has been superseded by ECE 5,09-01.
- 11) PP 024 Paragraph 3.0, "References" lists ECE AD-1-1; this procedure has been deleted and superseded by ECE 1.01 11; ECE-DC 14 has been deleted and superseded by ECE 9.08 03.
s.. g-e.,
- 1, NE 14716-ATTACHMENT 2 Page 2 of 2 LISTING OF OBSERVAT' IONS REFERENCE TSR 87-59
- 12) PP 032 Paragraph 3.0, "References" lists ECE 2.11; this procedure has been deleted and superseded by ECE 2.11 I1; ECE AD 4 has been deleted and superseded by ECE 2.13 11.
- 13) PP 033 Paragraph 3.6 and 4.1 lists TNE-AD-1; this procedure has been deleted and superseded by_ECE 1.01.
- 14) PP 034 Paragraph 3.0 lists the following: ECE-PR4, this procedure has been deleted (6/01/87) and superseded by ECE 6.08-11: TNE PRI has been deleted (11/12/87) and superseded by ECE 6.02; ECE PR 5 2 has been deleted (10/28/87) and superseded by ECE 6.08-02.
- 15) PP 036 Paragraph 3,4, lists TNE AD 4; this procedure has been deleted (5/18/87) and superseded by ECE 2.13.
16)
PP 041 Paragraph 2.0, "Applicability" lists TNE AD-5; this procedure has been deleted (9/20'87) and superseded by ECE 9.01.
/
- 17) PP 059 Paragraph 3.0, "References" lists ECE AD-5 6; this procedure has been deleted (9/24/87) and superseded by ECE 3.06, d
.., i a
I
.i
- i g...
I i
-NE 14716 ATTACHMENT 3
. PERSONNEL CONTACTED e
~
D. Nelson SWEC-QA A. H. Saunders
- CPE EA EXIT BRIEFING An Exit _ Briefing was conducted on December 2, 1987 with the following attendees:
[