ML20150C940

From kanterella
Jump to navigation Jump to search
Safety Evaluation Re Employee Concern Element Rept EN 28303, Cable Tray-Wall & Floor Penetrations Overfill
ML20150C940
Person / Time
Site: Sequoyah  
Issue date: 03/11/1988
From:
NRC OFFICE OF SPECIAL PROJECTS
To:
Shared Package
ML20127A683 List: ... further results
References
NUDOCS 8803220436
Download: ML20150C940 (5)


Text

'

\\

>A Atog%

. UNITED STATES l

+

E i

NUCLEAR REGULATORY COMMISSION

'Ti -

p WASHING TON, 0, C, 20555

\\..../

+

SAFETY EVALUATION REPORT BY THE OFFICE OF SPECIAL PROJECTS EMPLOYEE CONCERN ELEMENT REPORT EN 28303

,"CABLE TRAY-WALL AND FLOOR PENETRATIONS OVERFILL"

, TENNESSEE VALLEY AUTHORITY SEQUOYAH NUCLEAR POWER PLANT, UNITS 1 AND 2

)

DOCKET NOS. 50-327 AND 50-328 1.0 SUBJECT Category:

Engineering (20000)

Subcategory:

Raceway Overfills and Cable Pulling (23000)

Element:

Cable Tray - Wall & Floor Penetrations Overfill (23803)

The basis for Element Report EN 23803, Revision 3, dated May 6,1987, was the generic applicability determination resulting from Watts Bar Nuclear Plant' (WBN) Employee Concerns.

Specific SON concerns have been identified by both the Employee Concern Task Group (ECTG) and the Generic Concern Task Force (GCTF) in Significant Condition Reports (SCR) and Nonconformance Reports (NCR).

Employee concerns:

The following cable tray overfill and wall-floor penetra-tion overfill are identified as follows:

0W-85-007-002 IN-85-186-003 WI-85-100-011 IN-85-798-004 l

IN-86-238-003 IN-86-232-002 IN-85-688-N05 IN-85-919-001 l

IN-85-432-002 IN-85-688-001 IN-85-856-003 PH-85-003-023 IN-86-028-002 IN-85-312-001 IN-85-734-001 IN-86-262-001 1

IN-85-832-001 IN-85-207-001 IN-85-519-001 WI-85-100-015 2.0 SUMF.ARY OF ISSUES The overfill of wall penetrations and floor penetrations ray cause cable danage when pulled through penetrations.

Plant orocedures have no reouirement prohibiting overfill of cable trays.

Overfill of cables through penetrations may cause inadequate pressure / fire barriers.

Cable tray fill criteria for cables violate the Natinral Electric Core (NEC) ard industry practices.

The overfill cf cable trays, wall penetrations and floor penetrations may cause overheating of cables.

The cable tray supports may be inadequate.

3.0 EVALUATION The licensee raviewed documents of employee concerns, NCR investigative interviews, FSAR cemitments, engineering and construction procedures for installation of cables in cable tray raceway systens.

The licensee also I

A g

O P

. conducted walkdowns and interviewed personnel asscciated with design and construction of the cable tray raceway system including cable installation.

Cable Tray Fill Requirements The FSAR commitments and the Design Criteria for cable tray fill are as follows:

6900 volt cable greater than 2/0 AWG:

3 phase grouped, spaced from other circuits by radius distance of larger cable.

6900 volt cable less than 2/0 AWG:

may be laid random but may not touch grouped cables.

600 volt or less power cable:

may be single layer or randem filled to 30" of the cable tray cross section area.

Control and instrument cables cross section area may be 60".,of the tray cross section area.

Power facilities used to generate electricity are exenpt frcm the provisions of the National Electrical Code INEC).

A GCTF report stated that there was no design require ent that cable could not extend abovo the side rails of the cable tray.

Maintenance and Action Item (MAAI-04) was revised to instruct maintenanc'e and construction personnel to install.iumper conduits to prevent cables frem being installed above the cable tray side rails.

Observations & Site Interviews The Nuclear Safety Review Staff (NSRS) observation and site interviews, regard-ing cable tray everfill, findings are as follows:

The disorderly arrangement of cables in trays was the primary reason for the appearance of overfilled trays, Cables in safety-related trays had been installed in a more orderly fashion than in non-safety-related trays.

Very few safety-related trays appeared to be full.

Cable tray covers were properly installed on safety-related trays in the auxiliary instrument room and the cable spreading room.

Other plant areas where tray covers could not be installed were either not required by divisional sep? ration or were non-safetv-related.

, Analysis The staff analysis is that a cable tray filled with either instrument or control cables with a total cross section area (CSA) not exceeding 60% of the tray cross sectional area could have cables extendina above the side rails.

If all cables were installed in a neat parallel configuration, the top layer of cables would be at the cable tray side rail height. However, during cable installation the neat parallel configuration appears not to be achieved and, therefore, the cable though acceptable by the percent fill criteria could extend above the side rails.

Beyond the percent fill criterion, cable tray fill limitation maybe required for any or all of the following conditions:

To limit maximum cable weight to meet requirerents of the cable tray manufacturer.

To meet total weight linits imposed upon the cable tray support system.

To allow the installation of tray covers.

To limit ampacity derating.

The observation that cables which extend above the side. rails of cable trays does not necessarily indicate that tha cabla tray fill criteria have been violated.

This determination can only be achieved by analysis.

The NEC Section 318.5(b) permits a 50% fill for ladder or ventilation through cable trays containing multi-conductor control and/or signal cables only.

TVA's Division of Nuclear Engineering, Sequoyah Engiraering Project Manual Procedure SQEP-06 Cable and Conduit Procedure approved December 1, 1987 indicates that the 60% (40.5 square inches) is reduced to 48% (32.4 square inches).

The staff reviewed the Detailed Design Criteria, SQN-DC-V-11.3, "Pcwer, Control, and Signal Cables for use in Category I Structures," Revision 6, dated June 25, 1987.

These criteria have not been revised in Section 5.2.2 Cable tray load to i

reduce the 605 fill requirecent to 50%; this is rot a restart item.

Cable Trav Supports The licensee has issued a SCR to provide corrective action concerning the cable tray overfill which may affect the cable tray supports.

This corrective action program is to identify 40 worst-case cable tray supports.

This review has been completed and the adequacy of the tray supports verified.

Additional analysis of cable tray supports is proposed, after restart, to provide a stat-istical bases for acceptability.

The staff will review this cable tray support analysis program for adequacy and agree with TVA, that given the adecuacy of i

the worst case reviews, this analysis program is not a restart iten, i

. Ampacity-Cable Overheating The employee concern relates to the overfill associated with instrurentation and control (I&C) cables.

These I&C rables do not have ampacity consideration causing overheating which requires darating to prevent overheating.

The staff concurs that overheeting is not a problem with I AC cables.

The licensee has addressed adequately ampacity for 480V power cables which were installed in trays to the 30", fill criteria.

In addition to overfill, the affect of coating compound (Flamemastic 77), and fire stop material at pene-trations is addressed in Employee Cnncern EN 24CC0.

Fire Stoo-Pressure Seal The concern is that cable overfill through a wall or floor penetration may preclude an adequate seal.

The evaluators indicated that the integrity of completed fire stops and pressure seals is not easily verifiable since they are covered with Ceroform boards and Flamemastic coating.

The evaluators had no evidence that the cable fire and pressure barriers which were type tested for SQN had the sare configuration presentad by overfilled cable trays.

The staff has reviewed the follcwing documents:

Mcdification and Addition Instructions MAI-13, Electrical Pressure Seal, Fire Stop Earrier, Therro-Leg 330, Fire Barrier Systen and Flame Retardant Cable Coating, Revision 8, dated July 24, 1987.

Conduit and Grounding Cable Trays drawing.

45 Ea-45 N880-23, Details-Sheet 1, Powerhouse Control Bay Units 1&2, Revision 11, dated July 30, 1982.

Conduit and Grounding Cable Trays Five Stop Penetrations Details, Sheet 13, drawing.

45E-45 N880-26, Revision 23, dated September 3,1987.

Telecopy from S. Mabie, Bechtel SCN to Accravotto/Igoa Bechtel SF0 dated December 1987.

Subject DNE EEE, list of overfilled tray, four worst case examples.

Calculation 84487 1211 002 cable tray through penetration fire stnp system analysis dated December 11, 1987.

The st3ff concludes from the review of the above documents and observations of selected cable fire stops at Sequoys.h Unit 2 that the cable firestops are adequately designed and installed to meet their intended function.

Cable Damage The concern about potential cable danage during cable installation is discussed in Employee Concern Elerents C010900-SCN, "Cable Installation," C019201-SQN, "Conduit Installation," and EN 23801, "Conduit Overfills and Cable Darage."

{

y i '

Although specific concerns about cable damage due to overfill of wall and ficor penetrations are not discussed in the above elements the concerns are the sare and the corrective actions are discussed.

4.0 CONCLUSION

The NRC staff concludes that the licensee's investigation of the concerns were l

adequate and their resolution of the corcerns described in Elerent Report EN 23803-SON, Revision 3, is acceptable.

i i

1 1

,