Rev 3 to Audit Plan for Independent Corrective Action Verification Program
ML20148N980
Person / Time
Site: Millstone Dominion icon.png
Issue date: 06/23/1997
From: Neri A, Querio R, Raheja R
SARGENT & LUNDY, INC.
To:
Shared Package
ML20148N977 List:
References
CON-9583-100 PROC-970623, NUDOCS 9707010090
Download: ML20148N980 (39)


Text

- - .. . - . .

i s c 4W 6A Siegare 4 Luncsyu e

)7 AUDIT PLAN FOR INDEPENDENT CORRECTIVE ACTION VERIFICATION PROGRAM (ICAVP) ,

REVISION 3 l NORTHEAST UTILITIES MILLSTONE UNIT 3 PROJECT NO. 9583-100 Prepared by:

R. D. Raheja l Date Accident Mitigation Review Group Lead

/. Wh N EDuerio Date Operations & Maintenance & Testing Review Group Lead m (,/z3/97 A. A. Neri / Date System Review Group Lead n d 7 T[Ryan[/ DMe /

Pfogramnsitic Review Group Lead Reviewed by: [ # <.ouc 2^ 2 h7 R. F. Czpjko (s'k) Da'te Quality' urafce Approved by: AC#

A. K. Singh

" c/23/97 Date IRC Chairman 1.T )+ -v MM3-f D. K. Schogr Verification Team Manager f Date 9707010090 970627 fI)

PDR ADOCK 05000423 >

P PDR ,

.. .. - - . - -- .. . ~ - - . - - - - - - - _ . - . - . - .. --

1 1  %

$st' p

i Northeast Utilities Millstone Unit 3

  • "7"* " ICAVP Audit Plan Revision 3 l

l 1.0 OBJECTIVE I i

The objective of this project is to implement an Independent Corrective Action Verification Program (ICAVP) at Northeast Utilities Millstone - Unit 3 in accordance with the Nuclear Regulatory Commission's (NRC) August 14,1996 l confirmatory order. The ICAVP will be an independent verification of the adequacy of results of the Configuration Management Plan (CMP) currently being

' implemented by Northeast Utilities which is directed at resolving existing design l

and configuration management deficiencies. The ICAVP will provide independent verification that, for selected systems, Northeast Utilities' CMP has identified and resolved existing problems, documented and utilized licensing and design bases, and established programs, processes and procedures for effective configuration 1 management in the future. The ICAVP will be comprehensive, incorporating all of the appropriate engineering disciplines, such that the NRC can be confident that Northeast Utilities has been thorough in identification and resolution ofproblems.

The ICAVP review will be conducted independently of Northeast Utilities and its i design contractors.

l 2.0 SCOPE OF WORK The scope of work for the ICAVP as described in the NRC's August 14,1996  ;

confirmatory order to Northeast Utilities includes: '

a.

A review of engineering and design control processes, b.

verification of current as modified plant conditions against design bases and licensing bases documentation.

c. verification that design and licensing bases requirements are translated into operating procedures and maintenance and testing procedures.
d. verification of system performance through review of specific test records and/or observation of selected testing of particular systems, and e.

review of proposed and implemented corrective actions for design deficiencies identified by Nonheast Utilities.

! The NRC's December 19,1996 oversight inspection plan provides further l

direction on the scope of the ICAVP. In addition to the above items, the oversight inspection further requires a review of accident mitigation systems that assesses the (2)

I t' 1 I

se Northeast Utilities Millstone Unit 3 2['*"' ICAVP Audit Plan Revision 3 critical design characteristics to ensure that these systems and components can perform their specified safety functions.

S&L will implement the above scope of work as follows:

ai The review of engineering and design control processes will consist of an assessment of the current Northeast Utilities change process procedures, a technical review of past changes other than modifications and technical review of all plant modifications to the systems selected for a vertical slice review by the ICAVP that were prepared after issuance of the operating license. The review of the plant modifications will include:

. - A technical review of the changes contained in the modification packages to system specific analysis and output documents and to topical engineering programs.

Verification that current design output documents have incorporated the changes identified in the modification packages.

Verification that current system operating, maintenance, testing and training procedures adequately reflect the modifications.

l e Verification that the physical installation conforms with the modification package.

Verification that the post modification test procedure and test results demonstrate the system is capable of performing its function. .

. Verification that no unreviewed safety question exists for the modification as documented in the 50.59 safety evaluation.

b. The verification of current as modified plant conditions against the design bases and licensing bases will include:

Review of calculations, analysis, specifications and design output documents for consistency and for conformance with the design and licensing bases.

. A physical walkdown of the system to verify conformance with the design output documents.

(3)

t 4 Northeast Utilities *""(: ""#"

Millstone Unit 3 /

ICAVP Audit Plan Revision 3 i I

c. I The verification that the design and licensing bases are translated into l

operating, maintenance and testing procedures will include a cross-check of l

functional and performance requirements identified in the licensing and l design bases versus those identified in the operating, maintenance, testing l and training procedures.

d.

The verification of system performance will be accomplished through a review of specific test records for recently completed surveillance and post modification functional tests.

e. The review of proposed and implemented corrective actions for I deficiencies identified by Northeast Utilities during the CMP will include a review of all corrective actions for systems selected for a venical slice review by the ICAVP and a review of randomly selected corrective actions for systems outside the scope of the vertical slice review.
f. The review of the accident mitigation systems will include an assessment of the critical design characteristics to ensure that the systems and components can perform their specified safety functions.

Successful completion ofitems b, c, d, e and the technical plant modification reviews of item a will ensure the systems selected for the vertical slice review (Tier 1) are capable of performing their functional requirements as specified in the design and licensing basis documentation. Successful completion of the reviews described in item a and the reviews described in item e will ensure the adequacy of the NU design control process (Tier 3).

The successful completion ofitem f will ensure the accident mitigation systems are capable of performing their specified functions (Tier 2).

3.0 PRO. LECT ORG AN17 ATION The organizational structure will facilitate both the internal and external interfaces of the Project Team. Exhibit i shows the project organization. This section describes how the organization will function and the expected interfaces. The roles and responsibilities of the different parts of the organization are provided.

3.1 Management Team The Sargent & Lundy management team for this project is comprised of the Project Director, Bryan Erler; the Verification Team (VT) Manager, Don Schopfer; and the Chairrnan of the Internal Review Committee, (4)

1 i i Northeast Utilities N "#

ICAVP Audit P;an 1

1 Millstone Unit 3 7 Revision 3 :

1 A. K. Singh. They are collectively responsible for ensuring that the project is properly planned and implemented, that it meets the requirements of the l

NRC Confirmatory Order, and that the process and the results are open and credible to the NRC and the public.

The Project Director will have the overall responsibility for Sargent &

Lundy's performance for the work. He will be responsible for facilitating '

the resolution of any differences between the VT Manager and the Internal Review Committee. The Project Director will be the primary external spokesman for the ICAVP Team and will meet with and report to the NRC, and Northeast Utilities as required and as allowed by the approved l protocol. He will be available to the press, the media, and the public when requested by the NRC and NU. The Project Director will also be signatory to the fmal report produced by the ICAVP Team.

The VT Manager will be responsible for directing the development of and approving the plans and procedures for implementing the review, including l recommended system selection criteria and the protocol covering communications between Sargent & Lundy project personnel and the other organizations. He will manage the work through the technical leads on the VT. He will be responsible for reviewing the fmdings produced by the VT, and, upon acceptance, submitting them to the Internal Review Committee.

He may also return them to the VT Leads for additional information or further review. The VT Manager will be responsible for distributing the findings, including posting them on the electronic bulletin board as established in the approved protocol after acceptance of the fmdings by IRC. Similany, the VT Manager will review, accept and distribute / post the VT's evaluation of the NU responses to the findings. He will be responsible for preparing the final report documenting the work of the VT.

The VT Manager will also serve as the backup for the Project Director with respect to communication with the NRC, and NU when necessary.

The Chairman of the Internal Review Committee will be responsible for coordinating the activities of that group. The roles and responsibilite of the Internal Review Committee is provided later in this section of the audit plan. The IRC Chairman will also make himself available to the NRC, and NU when requested.

(5)

i . ,

c

./

Northeast Utilities * """

ICAVP Audit Plan

! Millstone Unit 3 #

Revision 3 l

l 3.2 Verification Team The VT is the core of the organization and is the group that does the actual review of the design and licensing bases and the effectiveness of the NU corrective actions. The VT is organized into four functional groups. Each subgroup will be headed by a Lead engineer and will be responsible for a portion of the overall verification program. There will be a System Review Group (SRG), a Programmatic Review Group (PRG), an Operations and Maintenance and Testing Review Group (ORG), and an Accident Mitigation Systems Group (ARG).

The VT has been organized functionally in accordance with the review processes instead of by traditional engineering disciplines. However, this is not to imply a strict compartmentalized group stmeture or review process.

It will function as a single project team with significant cross utilization of personnel among groups. It is expected that SRG and ORG personnel will perform review functions associated with the ARG and PRG. In addition, I there will be significant interfacing among the team members and the i

Review Group Leads. Periodic full project team meetings will be i conducted by the VT Manager in addition to periodic review group l meetings conducted by the Leads. During the review and discrepancy i resolution process, it is expected that the VT Manager will have daily briefmgs with the VT leads to discuss potential findings, share lessons learned, and discuss other project issues. Teamwork and frequent '

communications is a fundamental attribute for the conduct of the ICAVP and will be facilitated by the location of nearly all of the Chicago office project team members on the same floor of Sargent & Lundy's (S&L) orTices.

The SRG will perform the in-depth review of the selected systems. This group will review the current system output documents and analysis to verify conformance with the design and licensing bases. The SRG will also review design modifications to the selected systems made since receipt of the OL, focusing on the validity of the design process, identification of system interface requirements, potential synergistic effects of the modifications, and appropriate design document controls.

l The SRG will also be responsible for verifying that the current, as-built condition of the plant matches the current design output documents. This task includes physical and functional walkdowns of the selected systems (6)

  1. I Northeast Utilities $ 7 "' " ICAVP Audit Plan Millstone Unit 3 / Revision 3 and will be performed by the Physical Configuration Review subgroup (CRG) of the SRG.

The ORG will be responsible for reviewing system operating procedures, surveillance procedures, maintenance procedures, and training documents to confirm that the design bases and any changes made to the design bases have been translated correctly into these documents. This group will also confirm that current testing requir ments and post modification testing requirements are adequate to verify system performance.

i The ARG group will be responsible for reviewing the accident analysis contained in the FSAR to determine the accident mitigation systems and their critical design characteristics. The ARG will then review the accident mitigation systems and their critical characteristics to ensure the systems can perform their safety functions specified to mitigate the FSAR accident scenarios.

The PRG group will be responsible for the review of select NU processes for changing the facility design and for changing characteristics, procedures, or practices for maintaining, operating, testing, and training to ensure the adequacy of the change process. The PRG will also be responsible for the review of NU's corrective actions resulting from their configuration management plan review. This review will determine the adequacy of the corrective actions.

3.3 Role of the Internal Review Committee The Internal Review Committee will provide a S&L management technical oversight role. It will also help to provide consistency in the review results. It will be comprised of four very senior personnel within the organization that have specialized expenise in the areas being reviewed.

The IRC Chairman will be responsible for obtaining the IRC's review of the planning documents and procedures for performing the verification program. This includes the audit plan, the protocol, and the individual procedures required for the work. The IRC will review the findings of the VT for extent and for significance. They will also review the responses by NU after they have been accepted by the VT. The IRC may also make specific recommendations regarding the scope or methodology of the verification process as the work progresses. The IRC will also review the final report of the ICAVP.

(7)

.'s, Northeast Utilities Millstone Unit 3 9f'F I ICAVP Audit Plan Revision 3

! 4.0 METHODOLOGY This section of the audit plan describes the methodology S&L will use to d

implement the ICAVP. Exhibit 2 depicts the review process In general, the i

ICAVP will consist of the following tasks:  !

l

  • Defining System Boundaries 4
  • Document Gathering

.

  • System Review e Physical Walkdowns  !

e Operation, Maintenance and Testing Procedure Review I 4

  • Accident Mitigation System Review
  • Programmatic Reviews

, e Processing VT Findings e Review of NU Resolutions  !

  • Issuing Final Report Note: The intent of this review is to review only those systems for which NU's

' CMP process has been completed. Accordingly, if during the conduct of S&L's review, it becomes necessary to review items related to systems for

' which the NU CMP process has not been completed, a " place-holder" shall be utilized to discontinue that portion of S&L's review until such time that NU completes the CMP process for that system. Place-holders shall not be communicated outside of S&L.

4.1 Defining System Boundaries.

1 The systems to be included in the scope of the ICAVP program will be

' defined by the Nuclear Regulatory Commission. At the beginning of the system review process, a meeting will be held with the NRC, Nuclear Energy Advisory CouncilTNEAC) and NU to finalize the boundaries of the selected systems and interfacing systems. In general, the systems boundary will be limited to the safety related portion of the selected systems. S&L's review for the vertical slice system will address interfaces with the selected

systems as follows

I e

Mechanical Interfaces - S&L will review the interfacing system calculations to the extent needed to verify that the functions required to support the selected system were addressed in the design of the i

(8)

_.-__m.. _ _ . _ . _ _ _ . _ _ _ _ ~._ . _ _ . . _ . . . _ _ _ . _ . . . _ _ . . _ . _ . . _ _

[

- Northeast Utilities Millstone Unit 3

  • % #""' ICAVP Audit Plan 1

Revision 3 interfacing system. S&L will review the interfacing systems drawings

and procedures to the' extent needed to verify the support functions are addressed. This review will not include technical verification of the adequacy of the interfacing systems calculations, procedures or drawings. This review will address both direct interfaces (those which q l

interface with the selected systems pressure boundary) and indirect l mterfaces such as HVAC.

  • l I&C Interfaces I&C interfaces will be treated in'a slightly different i manner compared to mechanical interfaces section above. ' We will review input signals from interfacing systems through to their signal ~

l source to verify that the functions required to support the system under

]

' review were addressed in the design of the interfacing system. We will l

review the output I&C signals for the system under review through to j the input point of the interfacing system. The extent of this review is j

t ' described in detail in Attachment 6.3 of PI-MP3 02. l I

e. Electrical Interfaces - Electrical interfaces will be treated in a slightly j

'I different manner. A detailed review of the electrical distribution system from the motor control center or switchgear, as applicable, to the load is included as part of the selected system review. A load path review-L will be performed for the remainder of the electrical distribution system (diesel generator to switchgear or'MCC). The extent of this review is described in detailin Attachment 6.2 of PI-MP3-02.

4.2, Document Gathering l

The next step in the ICAVP review process will be to gather the licensing and design bases documents, procedures, design process documents and design output documents needed to perform the review. The following top level controlled documents have been obtained and are stored in both the S&L Chicago office and the local offsite office; e

Configuration Management Program

. Design Control Process Procedures e Current FSAR i e FSAR at O/L e SER and all revisions e 10 CFR 50.59 Safety Evaluation Procedure

Procedures for and System Specific Assessments L

(9) i

- - _ . - - . , , - - . _ _ _ . . _ - . _ _ ~ -- _- _ - . _ . - . - - - - - .

r 4

Northeast Utilities k# ""

ICAVP Audit Plan Millstone Unit 3 Revision 3

. Corrective Action Procedures

. List or database oflicensing commitments contained in docketed correspondence

. Description of document system and hierarchy system

. List of all modifications designed since receipt of O/L for Maintenance Rule Category I and 2 systems, sorted by primary affected system, including the organization responsible for the design

  • Complete index of the Unit 3 controlled documents, including calculations and drawings

. Complete index of the procedure system for Unit 3, including corporate / administrative procedures, engineering procedures, maintenance procedures, and operating procedures including emergency operating procedures

  • Complete listing of Adverse Condition Reports, sorted by system

. Documents describing specific engineering programs that may not be included in the above listing, such as MOV program, ISI/IST program etc.

. NRC inspection reports, QA audit repons and the NU responses to them The following system specific documents for the systems chosen for review will be requested in accordancc with the protocol outlined in PI-MP3-01.

Enginee6ng Calculations (Mech, Elect, Struct, I&C and Piping Analysis:

. Equipment Procurement Specifications

. Modification Packages

. System Descriptions

. Equipment List

. Environmental and Seismic Qualification Repons

  • P& ids

. Logic Drawings s Elec:rical Schematics

. I'ipmg Drawings

. Electrical Single Line Drawings

. Panel Wiring Drawings

. Cable Routing Drawings and Databases

. Pipe Support Drawings

. Structural Equipment Mounting Details General Arrangement / Equipment Location Drawings (10)

- . - . .- -- . - . - - . -- . . . .--.. - ~~

l Northeast Utilities F#

Millstone Unit 3 * ]/ ICAVP Audit Plan -

Revision 3 i  !

e Instmment Location Drawings

)

  • Zone Maps (Environment / Fire Protection, etc). '

e Operating Procedures including Emergency Operating Procedures

! Maintenance Procedures i e j Surveillance Test Procedures e Vendor Manuals l

  • System Training Procedures i

4.3 System Revieivs

[

The vertical slice system reviews will be performed by the SRG in accordance with PI-MP3-02 and 03. System reviews will focus on two objectives,1) to verify the system design elements being reviewed are technically adequate and consistent with the licensing and design bases (PI- 1 MP3-02) and 2) to verify the modifications implemented after receipt of the operating license are technically adequate and that configuration control of design documents was maintained (PI-MP3-03).

.I The first step of the process is to review the licensing and design bases documentation to identify the functional, design, performance, operational and testing requirements of the system. These requirements will be individually tabulated on a system requirements checklist. The system

' requirements checklist will be independently verified prior to its use by the j SRG and ORG as the bases for verifying design conformance to the design I and licensing bases. Discrepancies between the design and licensing bases documentation identified during the development of the system requirements checklist will be processed as discrepancy repons in accordance with Subsection 4.8.

Following the development of the system requirements checklists, the SRG will perform the four reviews described below. The purpose of these '

reviews is to verify the current system design is capable of the functional and performance requirements identified in the design and licensing basis documentation and to ensure consistency between the various design output documents and design process documents. Verification that current l system operating, maintenance and testing practices and that current l configuration is in accordance with the design and licensing basis

! documentation will be performed per sections 4.5 and 4.4, respectively.

These four reviews include:

i I

(11)

d Northeast Utilities * #""

Millstone Unit 3 ICAVP Audit Plan Revision 3

a. A review of design process documents to verify the technical adequacy of each document and its conformance to the design and licensing bases. This review will include mechanical, electrical, 1&C, and stmetural calculations, piping analysis and equipment -

EQ/SQ reports. The design process document conclusions and/or assumptions will be verified against actual operating data, where available.

Note: If a large population of repetitive standard type calculations are identified during the review process. S&L may request the NRC to approve an appropriate sampling in lieu of a 100% review of these repetitive calculations. The request shall be submitted with a sufficient technical basis for why a sample isjustified based on safety significance and the overall ICAVP process. Alternatively, for identical supports, S&L may perform a detailed review of the calculation for the suppon with the highest load. For the other identical supports, S&L will only verify the analyzed load is consistent with the stress analysis.

b. An upper tier drawing review including P&lDs, electrical schematics, electrical single line drawings, instrument loop diagrams and logic diagrams to verify the system design is capable of performing the functional requirements described in the design and licensing bases and to verify the drawings are consistent with -

, the design process documents.

c.

A component review to verify consistency between the licensing and design bases documents and the design output documents such as, component specifications, system calculations, and venoor component drawings.

d. A review of hazards resulting from postulated pipe breaks in the selected systems including pipe whip, jet impingement, missiles and flooding. Thi:: review will verify that the effects of these hazards on adjacent safety systems have been included in the hazards analysis.

In addition, the SRG will evaluate the components of the selected systems to verify they are capable of performing station blackout coping functions and Appendix R safe shutdown ftmetions, if required.

(12)

  • /

Northeast Utilities * " " "

Millstone Unit 3 # ICAVP Audit Plan Revision 3 1

The SRG will also assist the ORG with their review of procedures for the .

selected systems. The SRG will verify the technical adequacy of all parameters, including operating ranges and/or limitations contained in the 1 procedures. Additionally, the SRG will review all operating modes not explicitly identified in the system requirements checklist to verify the design i and analysis support operation in this mode. The ORG will defme the  !

parameters and modes to be reviewed by the SRG.

Once the reviews are completed, the SRG will enter on the systems requirements checklist how each of the design, functional and performance j requirements is satisfied. The ORG will complete the portion of the i checklist relative to operating and testing requirements.

The next step will be to review the plant modifications issued after receipt of the operating license. The scope of the modification review will include all major modifications (DCR's), Minor hiodifications (MMOD's) and all DCN's generated to support the DCR/MMOD processes. The modification review will include only the modifications to the selected systems. Modifications to systems which interface with the selected i systems are not included. DCN's generated to support like for like replacements, maintenance support engineering evaluations and NCR i disposition's are not included in the scope of this review. Each modification will first be screened to identify the lead discipline

)

j (mechanical, electrical or I&C). A lead verifier from the affected design discipline will then perform a modification screening process to identify which design elements are affected by the modification. The lead verifier will complete a checklist consisting ofgeneral questions to facilitate the  ;

determination of which design elements are affected by the modification.  !

The design elements that will be screened include:

I

a. Mechanical Design b.

{

Electrical Design i

c. I&C Design j
d. Structural Design  :
e. ALARA Design
f. Security
g. Appendix R Compliance
h. Electrical Equipment Qualification
i. Seismic Qualification
j. Radiological Environment
k. Non-Radiological Environment (13)

f .

Northeast Utilities *"&*7"" - ICAVP Audit Plan l

Millstone Unit 3 /

Revision 3

1. Station Blackout
m. Control Panel Design j
n. Piping Design i
o. Setpoint Database
p. Hazards /HELB Program j
q. Fire Protection
r. PRA
s. ' Training Procedures I
t. Plant Procedures (OPS, Maintenance, Surveillance)
u. Configuration Change Review
v. Quality Software Design Review For each design element that is affected, a VT member with the appropriate technical background will perform a detailed review to verify that the design element was adequately addressed in the modification. This review will verify the technical adequacy of the design inputs and of the calculations, specifications and design documents impacted by the modifications All reviews will be performed by the SRG with the exception ofItems s and t which will be performed by the ORG.

The SRG will then perform a detailed review of the changes to licensing documents that were generated for each modification to ensure the modification is adequately incorporated into the FSAR, Technical Specifications, Environmental Plan, Security Plan and Emergency Plan.

The SRG will also review the 10 CFR 50.59 safety evaluation prepared for each modification to ensure the unreviewed safety question determination was thorough and well documented.

Finally, the SRG will review the installation and testing requirements including acceptance test criteria to determine that appropriate installation and testing requirements were specified. The ORG will be responsible for verifying that satisfactory post- modification testing was implemented.

4.4 Physical Configuration Review The physical configuration review will be performed by the CRG in accordance with PI-MP3-05. This review will focus on verifying the current as built condition of the plant matches the current design documents. This group will perform a physical and functional walkdown of the systems in the scope vertical slice review. This group will also review plant modifications implemented after issuance of the OL to verify (14)

. . . . . - - - - . . - ~ . . . _

- . . ~ . . - - . . . - . . . . . . . . . . . . - - . - - . - - . - - -

u i.

I I

  • ?N Northeast Utilities * #~

Millstone Unit 3 ICAVP Audit Plan

/ Revision 3 l' ,

i 1 l

i l

i the as built condition conforms to the modification documents and to verify the modification documents have been accurately incorporated into the j affected design drawings or are posted against the affected design j l drawings. The walkdown of system modifications will be a more in-depth '

. walkdown than the system functional walkdown described above. Key

)

critical dimensions such as analysis / calculation bases and/or dimensional i restrictions identified on drawings will be verified during the modification walkdowns.  !

I After retrieving the system design drawings and outstanding changes, the CRG will create a set of walkdown documents by redlining the open amendments onto the physical drawings. The CRG will then perform a review of the lower tier drawings such as piping drawings, wiring diagrams, electrical physical drawings and cable schedules etc., to verify conformance to the upper tier P& ids and schematics. This review is l

'- required to ensure the lower tier documents being used for configuration walkdowns are functionally in agreement with the upper tier documents that are checked for technical accuracy by the SRG. The SRG as part of their calculation reviews will also verify calculations such as stress reports and lower tier drawings such as piping isometrics are in conformance.

Discrepancies identified by the SRG in this area will be communicated to i the CRG. This review is not intended to be a line by line review of the lower tier documents, but only a functional check.

l 1

Prior to performing the walkdowns, the CRG will identify system boundaries on the walkdown drawings. These boundaries will be reviewed i

with the SRG to ensure consistency with the system boundaries previously

^

agreed to by the NRC, NEAC, NU and the VT.

The next step will be to perform physical plant walkdowns of the systems.

The walkdown will che k the following at:ributes:

a. System component location and identification are as indicated on the P& ids and other schematic type documents.
b. Component nameplate data is consistent with component specifications and drawings.
c. System components are not physically damaged.

(15)

1 l

~

f Northeast Utilities "~

ICAVP Audit Plan Millstone Unit 3 #

Revision 3

d. System configuration is functionally consistent with design output documents by verifying:

. Line size e

Configuration of piping including number and location of bends, location of valves, supports and other in-line components e

Valve orientation and flow direction e

Pipe support type and configuration

. l Equipment and instrumentation mounting details e

l Configuration ofconduit and tray routing i e

Cable "To and From" routings Conduit and cable size Conduit and tray support type and configuration

. Tubing / electrical configuration to instruments e

HVAC ductwork size and routing

e. Divisional trains of the system are physically separated by barriers and or distance. Electrical separation will be checked by verifying  !

cable is routed through applicable divisional raceway.

f. Based on NRC Approval Letter dated 4-7-97, S&L is precluded from performing reviews of seismic II/I related issues due to prior S&L involvement. This review if required must be performed outside the S&L scope for the ICAVP, As stated previously, this walkdown is not intended to check all dimensions, but is merely intended to be a functional verification. '

The CRG will also perform a review of the modifications identified by the SRG as impacting system configuration drawings. The SRG will provide / identify drawing changes resulting from system modifications. The SRG will also clearly identify which portions of the modification packages are presently installed. Upon receipt of this data, the CRG shall first review the drawing changes to ensure they are either incorporated into the current drawings or are identified as open amendments against the drawings. The CRG will then perform a detailed walkdown of the modifications which have been installed. This walkdown will include a check of critical dimensions and a review of seismic II/I attributes in (16)

-f Northeast Utilities ""

ICAVP Audit Plan Millstone Unit 3 / Revision 3 2

addition to the other walkdown attributes described above for the functional walkdown.

4.5 Operation & Maintenance and Testina Review The operating & maintenance and testing review will be performed by the ORG in accordance with PI-MP3-06. This review will focus on verifying that the system operating procedures, maintenance procedures, surveillance procedures and training documents conform to the systems design and licensing bases. This group will also review the post modification tests performed following the installation of plant modifications to the system to verify the testing was adequate to maintain the design and licensing bases.

Upon receipt of the system requirements checklists from the SRG, the ORG will perform a review to verify the following:

a. The operating procedures are in conformance with the systems functional requirements described in the Licensing and Design ,

Bases. This review will include di modes of system operation including normal, abnormal and emergency system operations. This review willinclude:

a.1 Review of the operating procedures against the system P& ids.

a.2 Verification that instrumentation and controls described in the procedure are consistent with the installed condition.

a.3 Verification that procedures for support systems are adequate to support the operation of the system.

a.4 Verification that manual operator actions can be performed under accident conditions.

b. The maintenance procedures are in conformance with the maintenance requirements described in the Licensing and Design Bases. The review will:

b.1 Verify that maintenance procedures and vendor manuals exist for key system components.

(17)

_ . - _ . _ _ _ . _ _ . _ _ . . _ _ . . _ . - . - .._ _ . _ _-~ _ . _ _ . _. _ .. _ ._ .

,o i

.af r$%

Northeast Utilities *MP*" ICAVP Audit Plan

[ Millstone Unit 3 '

Revision 3 i  !

b.2 Check the maintenance procedures for technical adequacy.

b.3 Review vendor manuals, generic communications (i.e.,

Bulletin, Information Notices, Generic Letters, NSSS  !

! Technical Bulletins) and verify applicable items have been j- implemented into the maintenance program.

4 i ' b.4 '

Review component history files to identify recurring E

equipment problems and determine if any trends exist.

t t

.' b.5 Review past maintenance activities and verify technical i

adequacy, performance of the appropriate post maintenance i testing, and satisfactory demonstration of equipment -

!- operability. '

c. The review will verify that test procedures and surveillance -

3 procedures are in conformance with the Design and Licensing

[

' .. Bases. The review will focus on the following:

I c.I Review the technical adequacy of Technical Specification Surveillance Test Procedures and verification of the i adequacy of test results completed during the last operating

' 'l cycle.

c.2 Verify the system tests adequately ensure the system will l

operate as intended under postulated conditions.  !

c.3 Determine if surveillance test procedures comprehensively address system responses addressed in the licensing l'ases.

Upon completion of the above reviews, the ORG will complete the system requirements checklist to document how the Licensing and Design Bases requirements related to Operation & Maintenance and Testing are satisfied.

l The ORG will also review plant modifications implemented after issuance ,

of the Operating Licensing. As stated in Section 4.2 of this audit plan, the  !

SRG screening process will determine if plant modifications'may affect the i operation, maintenance or inspection requirements of a system. The ORG will independently evaluate the modifications to identify the required changes. The ORG will then review the operating, maintenance and testing procedures to verify the changes due to the modification have been .

(18)

g

' Northeast Utilities  ?"

ICAVP Audit Plan Millstone Unit 3 7 Revision 3 i

i-reflected in the procedures. Additionally, the ORG will review the post modification test results for each modification to verify the adequacy of the

test results.

y

~

i 1

i 4.6 ' Accident Mitigation Systems Review

' The process discussed in this section will be used by the ARG to develop l

the critical characteristics or parameters for the accident mitigation i systems. This process shall be implemented in accordance with PI-MP3- 1 4

07.

The ARG Lead and Verifiers will review the initiating events in the FSAR, i

as they apply to Millstone Unit 3 and identify the accident mitigating systems and components within the system. The reload analysis and the i..

FS AR shall be used to identify the specific critical parameters which are required to mitigate the event. As a result of this review, the ARG Lead will create a database consisting of the following items: a) Analyzed Accidents, b) Mitigating Systems, c) Components, d) Critical Parameters and e) References to the accidents and associated documents contained in j the SAR. The list of systems and associated critical characteristics shall be j submitted to the NRC for approval prior to ARG verification of the

parameters. {

i The portion of the database consisting of the accident mitigation systems in i

" the scope of the vertical slice system reviews (Subsection 4.3) will be given  !

to the ORG and SRG for their review of the Critical Parameters.

The ARG Verifiers will verify the Critical Characteristics (Parameters) j using a documented System / Component test, and or Surveillance test from 3 the Millstone Unit 3 Technical Specification or Post Maintenance Tests.

For example, Technical Specifications Surveillance Tests results shall be

used to verify the instrument setpoint pressures and associated delay times for initiation of the Safety Injection signal assumed in the analysis.

In addition, the Critical Characteristics (Parameters) will be verified using the design calculations, specifications, and vendor documents for acceptability. For example, the maximum heat removal rate of the containment fan coil units shall be verified by reviewing vendor tests / calculations to assure the functional capability of the units following a postulated LOCA.

(19)

._ _ . _ . _ _ ._..-.___.__._._..._._._._.m .-. _ . _ . . _ . _ _ _ _ _ _ . _ _

l j . - . 1

f Northeast Utilities " " "

Millstone Unit 3 ICAVP Audit Plan 4

Revision 3 I

! 4.7 Prourammatic Reviews The programmatic reviews will be conducted by the PRG on a horizontal bases (across systems) for the purpose of determining if the actions taken by Northeast Utilities (NU) to correct previously identified problems have 1

' been effective and if the NU change processes are elTective. The programmatic reviews will be performed in accordance with PI-MP3-04.

I 4

Licensee Initiated Corrective Action._s 4

As part ofits Configuration Management Program (CMP), NU has performed a vertical slice review of safety-significant systems and has identified degraded or non-conforming conditions: For each of these degraded or non-conforming conditions NU is initiating corrective actions. I Additionally, NU has implemented corrective actions for design deficiencies identified by the architect engineer before initial operation (E&DCR's). The programmatic review will assess the adequacy of these corrective actions. This review will be conducted for all corrective actions associated with the systems included in the scope of the ICAVP vertical slice system reviews, and for a representative sample of corrective actions associated with the other NU completed CMP vertical slice systems.-

.The NU CMP findings / corrective action documents will be obtained both for the systems in the scope of the ICAVP vertical slice system review and for systems outside the ICAVP vertical slice system review.

A checklist will be prepared for the review of corrective actions. Using the checklist, the PRG Verifier will assess the corrective actions for adequacy of the follow'mg:

a. Root cause determination - the extent to which plant processes 2

and procedures are affected.

b.

Extent of condition determination - the extent to which other systems, structures or components are affected.

c. Plant restart -is the corrective action required prior to restart?
d. Content - is the corrective action adequate in resolving the issue?

Chance Processes (20)

4

, /

Northeast Utilities #"*"

Millstone Unit 3 '# ICAVP Audit Plan Revision 3 NU's current plant change processes will be reviewed for both their j

adequacy with respect to industry standards and for the effectiveness by  !

which they are being implemented. Both design change processes and i

procedure change processes will be included in this review.

l As part of the ICAVP system reviews, the SRG and the ORG will assess the plant modifications made on the selected systems. This review will i

evaluate the effectiveness of the change processes involved in these j

modifications (i.e. if the resulting modification is found to be acceptable, it i can be inferred that the process used in performing the modification is acceptable). In addition to this system review, specific process related '

reviews will also be performed by the PRG. The various change processes reviewed will include the following:

Process Correspondine MP3 Procedure drawings NUC DCM Chapter 7 i

specificaticns ~

NUC DCM Chapter 6 '

calculations NUC DCM Chapter 5 procedures DCl, DC2, DC3, DC4 temporary alterations NGP 8.05 minor modifications NUC DCM Chapter 3 modifications NUC DCM Chapter 3 licensing documents NGP-4.03 vendor manuals NUC DCM Chapter 8 like for like replacements NUC DCM Chapter 1 setpoint changes NGP 3.16 The current MP3 procedure for the processes listed above will be evaluated for its content and completeness. This evaluation will determine if the procedure exercises adequate controls on the change process and invokes (21)

i 1

Northeast Utilities **"'$.1 .. "*""

Millstone Unit 3 # ICAVP Audit Plan i Revision 3 )

appropriate interface reviews to assure the plant design bases and configuration is maintained consistent with the licensing bases. The evaluation will be based on guidance provided in the following:

Reg Guide 1.33, Quality Assurance Program Requirements (Operation) l NRC Inspection Manual INPO guidelines i 1

INPO 87-006, Report on Configuration Management in the Nuclear Industry '

NEI guidelines t

l The adequacy ofNU's implementation of the change process procedure ,

will also be evaluated. Since the system review will assess the technical adequacy of the change, the programmatic review is intended to evaluate only the procedural adequacy of the change. The evaluation will determine if the current procedure is being followed, that the required checklists are being accurately and completely filled in, and that all other documentation is complete and accurate. This evaluation shall be performed for the changes made to the selected systems using the current procedures. If a suitable sample of these changes for a particular process is not captured in I the system reviews, a suitable sample outside the ICAVP systems will be l

reviewed for both process implementation and technical adequacy.  ;

In addition to the process and implementation reviews noted above, a review of select past changes on a plant-wide basis will also be made. For each of the change processes not generally associated with modifications, a random sample of changes made during each five-year interval following receipt of OL will be reviewed for their technical adequacy. The changes will be selected from various systems other than the selected systems in i order to maximize plant coverage. This review will assure that these past changes did not compromise the unit's design or licensing basis. The

" process specific questions" in checklist CK-MP3-04-02 in conjunction with applicable checklists from the SRG and ORG will be used to evaluate the technical adequacy of the changes.

4.8 Processing Verification Team Findinus When a member of the VT identifies a discrepancy which does not appear to meet the requirements, he shall initiate a discrepancy report (DR) per PI-MP3-11. Exhibit 3 of this Audit Plan depicts the DR process. A discrepancy is a condition, such as an error, omission or oversight which (22)

l 0 t

.f Northeast Utilities ICAVP Audit Plan Millstone Unit 3 Revision 3 prevents consistency among the physical configuration and information sources (e.g. documentation and databases), design basis and/or regulatory I requirements. Examples of discrepant conditions are a disagreement between the system design bases and the FSAR, the as-built configuration of a piping system and the piping analysis, or a change to maintenance l

procedures, which should have been made due to a plant modification, but was not. The DR will document the discrepant condition and the documents or walkdown reports that were reviewed to arrive at that conclusion. Other technical and administrative items will be included on the DR form to help track, trend and analyze the results of the verification I program. The DR will be signed by the VT member and forwarded to the VT Group Lead.

The VT Group Lead will review each DR with the VT member for technical adequacy, completeness, and whether that specific issue has already been addressed by another DR or by an existing NU corrective l action document. The DR could be returned to the VT member for additional information or investigation; or it could be accepted and signed i

by the VT Group Lead; or it could be determined to be not valid. For any DR's determined to be not valid, thejustification for this decision will be documented on the DR and the DR will be signed by the VT member and the VT Group Lead. If valid the VT Group Lead will forward the DR to the VT Manager.

1 The VT Manager will review each DR with the Group Leads for technical adequacy, completeness, and whether that specific issue has already been l

addressed by another DR or by an existing NU corrective action document.

The DR could be returned to the VT member for additional information or investigation; or it could be accepted and signed by the VT Manager; or it could be determined to be not valid. For any DR's determined to be not valid, thejustification for this decision will be documented on the DR and the DR wi!! be signed by the VT member, VT Group Lead and VT Manager.

The VT Manager will submit accepted DR's to the IRC for their review.

They will review the DR's for extent of the condition to confirm that the VT looked deep enough into the issue to ensure that the problem is fully l scoped; they may make recommendations to the VT to look for similar j

conditions in other areas or systems. The IRC may request that the VT l member obtain additional information; they could accept the DR as written, whereupon the IRC Chairman would sign the DR and return it to the VT l

(23)

._ _ . . _ . . . _ _ - . _ . - . _ . _ _ _ . _ _ - - . _ ~ - _ . _. _ .. .

l

, i' '

1 i l

! Northeast Utilities * *b$i"~

Millstone Unit 3 ICAVP Audit Plan

! /

Revision 3 i

Manager, or the IRC may conclude the DR is not valid. If the VT member, I VT Group Lead, and the VT Manager agree with the conclusion that the

l DR is not valid based on additional information, thosejustifications shall be L l documented on the DR and signed by the VT member, VT Group Lead,

! and the VT Manager.

- All DR's will be transmitted to the NRC, NEAC, and NU when the above

(

process is completed. The DR's will be transmitted in accordance with the I approved protocol. Since an important part of this project is to keep the public informed of the status and results, in addition to expected monthly meetings with the public, all DR's which are sent to NU and the NRC will be posted on the Internet World Wide Web 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> after their submittal j

to the NRC/NEAC/NU.

4.9 Review NU Resolution to Verification Team Findings i As shown in Exhibit 3 the handling of NU's proposed resolution of the VT  !

findings will follow a similar process as the generation of the findings. The i

resolution will be submitted to the VT member who initiated the DR the VT Group Lead and the VT Manager. If the proposed resolution is determined acceptable, it is forwarded to the IRC for their review. If both the VT Team and the IRC find the NU resolution of the DR to be adequate, NU, the NEAC and the NRC will be notified by the method established in the protocol. At this point we.will post the accepted resolutions to the findings on the Internet bulletin board established for public access. If NU's resolution to the finding is not considered adequate by the VT member, VT management, or the IRC, it will be returned to NU with a written explanation and bases for why the team did not consider it to be adequate. The resolution and explanation will be sent in parallel to the NRC and NEAC and will be posted on the Internet Bulletin Board. It is expected that NU would reconsider the information and resubmit it to the VT. Meetings between NU and the VT may be required to reach an understanding and resolution of particular issues. These meetings would be requested and held in accordance with the established protocol.

5.0 SYSTEM SELECTION CRITERIA At the public meetings on September 24,1996, the NRC indicated that they would select the systems for review rather than S&L. They also stated at those meetings 1.

l (24)

s > i e i Northeast Utilities "" " " * "

ICAVP Audit Plan Millstone Unit 3 Revision 3 l

that the NRC would decide on the number of systems to be selected for review.

As input to the NRC staff, S&L recommendations on the number and selection of j

the systems for review are provided below. i Sargent & Lundy's system selection criteria are based on NRC Inspection Manual Chapter 2535, Design Verification Program, modified to be appropriate to this situation of an operating unit. These criteria would be applied to the list of approximately 20 systems for which the NU line organization and the NU oversight organization will have completed their review also.

l

1) The systems should be in the top quartile of risk significant or safety related j systems.
2) The systems should involve a full cross section of engineering disciplines I with internal and external organizational interfaces, such as NSSS supplier, component vendor, and engineering service organization.
3) The concept and implementation of the design should not be limited to the NSSS supplier or another single component supplier. )
4) The systems should be generally representative of the safety related features of other systems.
5) The systems should be reasonably complex, regi . iring multiple operating modes.
6) The systems should have multiple, non-trivial modifications performed on it since initial licensing, preferable by different design organizations.

1 With the likely selection of four systems. it is not necessary that every system meet i

all of the above criteria. However, each system should meet as many of the criteria j as possible and each of the criteria should be met by at least two of the selected l

systems. The system selection may of course also be weighed more heavily to concentrate on specific known problem issues at Millstone Unit 3.

6.0 PROJECT DELIVERABLES i Deliverables for this project will include a final report which describes the scope of the ICAVP, the methodology used, the results of the review and the conclusions regarding the adequacy of the configuration management program and the corrective action program at Millstone Unit 3. Exhibit 4 of this audit plan presents an outline of the final report.

(25) 4

l

.6,Y dhbr .

! Northeast Utilities "Y""" ICAVP Audit Plan l Millstone Unit 3 ' #

l Revision 3 i l

7.0 PROJECT TEAM The current project team members are identified on the project roster included  !

herein as Exhibit 5. The project organization chart is included herein as Exhibit 1.  !

Changes or additions to the project team will be communicated to the NRC in i accordance with PI-MP3-08, when applicable, and will not require a revision to l

the audit plan. The compilation of Project Team position descriptions, personnel  !

resumes, and conflict ofinterest statements is provided in Appendix A to this Audit Plan.

The selection of personnel for the ICAVP was based on their qualifications to  !

perform the assigned reviews, their financial and technical independence from the l

Unit being reviewed, and NRC acceptance of the personnel. Substitution of existing personnel on the team may be required to add expertise or manpower to fully investigate issues which are identified during the course of the program. A specific procedure (PI-MP3-08) has been written to govern the substitution and addition of personnel to the project team. NRC notification and approval is required.

l 8.0 GOVERNING PROCEDURES AND TRAINING The work for this project is classified as Nuclear Safety Related and shall be i performed in accordance with this audit plan, S&L's Quality Assurance Program and the following project instructions.

Project Instruction No. Title PI-MP3-01 ICAVP Communications Protocol PI-MP3-02 Review of System Design for Compliance with Design and Licensing Bases PI-MP3-03 Review of Plant Modifications Prepared After Receipt of Operating License for Technical Adequacy and for Configuration Control PI-MP3 04 Programmatic Reviews PI-MP3-05 Physical Plant Configuration Walkdowns PI-MP3-06 Operations and Maintenance and Testing Procedures and Training Documentation

Reviews PI-MP3-07 Review of Accident Mitigation Systems (26)

, o i ,

Northeast Utilities "" """

ICAVP Audit Plan Millstone Unit 3 '

Revision 3 PI-MP3-08 ICAVP Team Personnel Substitution and/or Addition PI-MP3-09 Preparation and Approval of Checklists PI-MP3-10 Differing Professional Opinions PI-MP3-11 Discrepancy Report Submittal and Closure PI-MP3-12 Project File Index The project team members will be trained on the applicable S&L QA procedures and on the ICAVP project instructions. The project team members will also be trained on any revisions to the applicable project instructions. Training will also include background information about NU's activities over the recent years that led up to issuance of the NRC order requiring the ICAVP to be conducted. This portion of the training will include a review of the order itself, and the subsequent documents that have provided details and supporting information about the order.

Project team members will be trained in the fundamentals ofinspection processes and techniques. New personnel added to the project team will be trained in the applicable items prior to beginning their review activities. Training records will be maintained in accordance with S&L QA procedures.

The project team members are expected to conduct their evaluations with a questioning attitude about the adequacy ofitems that are being reviewed and evaluated. Additionally, they are expected to use a conservative threshold for data interpretation and decision about adequacy ofitems reviewed.

The Manager of the S&L Quality Assurance Division will select an audit team to monitor the activities of the project as it progresses. Their review will be to ensure that the process used by the project team is in accordance with the NRC Confirmatory Order and the procedures developed to implement those requirements. The QA auditors will review selected DR's identified by the VT and will pay particular attention to any DR's that are determined to be not valid. A summan of the QA activities related to the ICAVP and their conclusions will be included as part of the ICAVP final report.

9.0 EXTERNAL PROJECT INTERFACES The purpose of this project is to obtain an unbiased assessment of the Millstone -

Unit 3 configuration management and corrective action programs. Therefore, evey reasonable effort must be made to assure that the observations and l conclusions made are the result of our Project Team's own independent i assessment and not influenced or biased by outside organizations. To maintain this i

I (27)

, e gl[ -

Northeast Utilities "*$""*" ICAVP Audit Plan l Millstone Unit 3 7 Revision 3 assurance ofindependence, communications with outside organizations will be in j accordance with PI-MP3-01, "ICAVP Communication Protocol." l J

(

10.0 LOCATION OF WORK l 1

1 The S&L VT with the exception of the CRG subgroup of the SRG will be stationed in S&L's Chicago offices. The CRG will be stationed at an offsite office l i

located near the Millstone station.

{

The project team members stationed in the Chicago offices may make periodic trips to the S&L offsite office and to the station as needed to gather i

documentation, interview NU personnel, or to attend meetings to discuss NU i proposed resolutions to S&L discrepancy reports. I i

11.0 PROJECT SCliEDULE The current project schedule is illustrated in the bar chart included herein as Exhibit 6 for information only. Schedule changes will be communicated with NU, NRC and NEAC directly, when appropriate, and will not require a revision to this audit plan.

i 12.0 BUDGET DATA Applicable project number and task codes for this project are listed in Exhibit 7.

(28)

\ '.

1 ICA P Project """

Organization Chart l l Northeast l Utilities System NRC 4E Al i

B. A. Erler Project Director Quality l Assurance I

A. K. Singh D. K. Schopfer 1R Committee Verification Chairman Team Manager IR Committee System O&M and Accident Programmatic

. . Green Review' Lead Testing Mitigation Review Lead A. A. Neri Review Lead Review Lead

  • * # T. J. Ftyan R. E. Querio R. D. Raheja D. P. Galle l Physical l Configuration l Review Lead R. E. Kropp i

i kk l

l I

l

f!

  • p tl  ; , ' ;t!s ih L5 !;r tL tI* (t tI47 ri'b6 tI!* sI f,* g!i

- . ,j!

9 _

O -

t.-..

- u.-

o- _

S.-

e e.o 4 _

f _

F S n.- _

ee s

su -

e. i [ ,

o e _

- m e , _

e ,

e me es S,

m s )e p3 n _

2 w

e

~

s%a n

s a 5 c

@a. .

ti ss ne ae

.i 3. p a Gh o c. .

es e

, e a _

m

%.e d ,,

m a

e' e g

q i I i 1I1 iIl _

- 1!l i _

- - .e ==e G -

- a.  %

o- e _

s e e As _ . i N T -  :

I 3 a,

s eo se e t O

e 3 ms oe

- 3.m

- o _- e e n .e m n h go m 9e$

o o.

- s o ia o 9 e w h 8e e s.,

  • l III i l w
  • e *
  • e s-l III
e. =

e fIl i1l e I I i e w

. e 4

3= n, e

m

~

s 3i _

m i ,

ein

. see s

~

, i s a

e e

\ e e i e

g-g 4

m s

X.

es e b.

3m e g

- gs0 i

~

o ,

n639 rge 3e I i i eI

)e

- e " n eg - 3 a es

. s as

  • C ,,*e

, E e. '* .

m )ameg #sS_

  • s ->

A 8'8 e -

  • i m wemet a

- {

- ( mg ses a

  • , ,, d n ga nu, n .e

< eer ee_

' / e w

i i ,.

i sns ee

-eee rses

.e iem e

a. ass e

i 5

3 Il iiI ii i mc3st 1 se i

p n . Io) st) o e I I ,hI se e'

M e me eee e

ss 5

o s tes

. , s ;j sg aoe n

e S 8

1 e e m =e

- i-e no eo t- t s

s a

s o

mN; m.

eim y

.& aw

. - e ee s- m

. 3 b

r -

e 3

wg s, , ea i n.

e mes m

.-af eu _

e .

i se= -

e e. ss A m e-

_ sa i

s-. _

-i

- oSi. p e ..

p .mt

. ge s

.e

, ag

.m9 e l

  • =l m e

- e ea ,.

eDiO

  • t- - ,l a i 3

m s i m w*e Mm s=

i a88 s s o ,

n s sm

,_. [s.

r i s n8 . e t8 w* n .

i i.

e a o 3 e e ,

n t e.

8 n m s$u e .. s s _

G .

= e n

ee .* e o

=e e. m.

e i s ne e e 'n

  • m a EE

. a. *a.

e i e

s IIl e

1lI aI lII M caWs s

e o s

em m

3 s.

sa m

~ j iI il1 i1 i m e, t a

~ e s

x e

~ ,s -- -. e e

r e .

e w

=0 r

-en0 e8 e

I

, > _f

.e e

m e 3, e e e r o e m -

sn

.e - 2

=-

a 3

e sr, -1ei.

- 2em t I e 1.eg. .' _'

tmi

.

  • b %Qae e t

- 3sm B btm e e t

' iIi I

- e eee s e .e e

en . e

' m -

a o .

e ) .

p ee s a - _

" i 8 ~3 m " L s -

  • i, e m -

he  :-

e.

e s

m .e _

r

- f

- i

- I l i s e e

.e

-e *r e m*e n .e e.

g i

e e.,

s bg e e.

2m e

nAI ee o

-m

=

=,

=

c. e*

n e

e e

- ,em )att M=+

es ore m e - st n

eep sm

- se

.e m

I O'1 3

t n

e m

e e 1l e 8 e

eeAp se u.

a%

= VO AM i m ~

m'

+

e e 3 e

me i

I f

m eet gm d3

, e s

em e i ee ms dH

.osas i

)'u 5a HV t,

OH e e , e 3

, I!

ew- 31

~ne

_ i i 4,

A k

r a

en emE1 eo

)n. & ,s i

u e.

  • M.+ e 31 SO 4_

4 a

e n

a e SH m

4 J 1 De m *L 5

S D

es e

s e

e s .

e

_ a n

  • ** s e a 4m. / e* e m

%m a_ e m

f~ ._ *m* **L

  • . ~

ne w ' ".t e*5

  • L em # *e4 t o

4

" te - 8 d

  • $w r e e e te 1
  • s e i
  • *u as o

p a

w A

l ie -

o l .

l l

l PROCESSING FINDINGS inmate % Exhibit 3. Rev. 3 i AND RESOLUTIONS  : Report (DR)

VT 4

tu Mais Rev6ew DR m R.p.d vr Mgma

. DR Vaud & m nd m vand Y,es 74 More Rev6ew DR 2 Reped IRC e DR Veild & m not u Adequate? Vaid v

Document Beeie for Yee Not Diecrecent E W sut-i DR i.

NRC/NEAC/NU & Poet ,'

en Flar*nnie BB VT Mgmt J

t i Prtude DR Reepones to VT Menecement NU ,

Review NU Response for Adeousey VTNT Mgmt Document Reseone for Regoction/ Submit to {

NU/NRC/NEAC & Poet Review NU Response on Electrore, BB & VT Acceptance /

VT Mgmt RajarHari IRC a

NU No Response to DR M d*

1 Yes Document Acceptance

& Submit to l NRC/NEAC/NU &

i Poet on Electronic BB j VT Mgmt

, - F- -

.Am 17.1807. 224 53 pu ,

f a

4 Exhibit 4

. Outline ICAVP Final Report Executive Summary ICAVP Oversight Team Report Sargent & Lundy Quality Assurance Division Report 4

i I. Introduction A. Background B. Objective C. Scope D. Methodolagy E. Project Organization

2. Conclusions A. Overall Conclusion B. Design Control Process C. Design Basis / Licensing Basis Consistency i D. Design Adequacy E. As-built Plant Configuration F. Translation of design into plant maintenance and operation G. Adequacy of Testing Programs H. Applicability of selected sample to all Millstone 3 systems I. Corrective Action Program III. Review Results A. System 1 B. System 2 C. System 3 D. System 4 E. Accident Migitation Systems F. Corrective Action Program G. Change Processes Appendices
1. Project Team
2. Objectivity Questionnaires
3. Review Records
4. Discrepancy Reports
5. NU Resolutions
6. Project Manual
7. List ofChecklists

!.. e l

l Millet na Unit 3 ICAVP Pcrsgnn:1 EMS Revision 3 I Page 1 of 2 l NRC C-O-1 l lCAVP Project Team Position Interview Statement Resume l Management Team l B. A. Erier Project Director X X X j D. K. Schopfer Verification Team Manager X X X l Internal Review Committee A. K. Singh IRC Chairman X X X D. P. Galle IRC Member X X X K. J. Green IRC Member X X X l W. G. Schwartz IRC Member X X X l Verification Team l SRG A. A. Neri SRG Lead X X X '

R. Hameetman Lead Verifier (Mechanical) X X X D. J. Feingold Lead Verifier (Mechanical) X X X D. A. Schroeder Lead Verifier (Electrical) X X X

l. Wamer Lead Verifier (Electrical) X X X J. DeMarco Lead Verifier (l&C) X X X N. Klaic Lead Verifier (Structural) X X X J. L TenWnkel Verifier X X X i R. Hindia Verifier X X X C. M. Launi Verifier X X X J. M. Rich Verifier X X X J. W. Johnson Verifier X X X P. R. Olson Verifier X X X M. D. Stout Verifier X X X l S. Yassin Verifier X X X A. Prakash Verifier X X X l A. Patel Verifier X X X l B. J. Dionne Verifier X X X 1 J. F. Wakeland Verifier X X X D. J. Kendall Verifier X X X R. Morton Verifier X X X CRG R. E. Kropp CRG Lead X X X T. L. Sarver Lead Verifier X X X I J. W. Read Lead Verifier X X X l R. M. Tamera Verifier X X X R. Lukes Verifier X X X A. Serrano Verifier X X X F. Gallegos Verifier X X X S. Gruike Verifier X X _

ARG R. O. Raheja ARG Lead X X X W. R. Peebles Mech. Discipline Verifier X X X l

l W. J. Johnson Radiological Discipline Verifier X X X l T.J.Kane System Verifier X X X L. A. Bennett .

System Verifier X X X V. E. Balodis ISystem Verifier X X X I

'
  • A Millatcna Unit 3 ICAVP Personnel E42it 5 Revision 3 Page 2 of 2 l NRC C-O-l ICAVP Project Team Position Interview Statement Resume J. Kish System Verifier X X X PRG T.J.Ryan PRG Lead X X X A. S. Caruso Verifier X X X R. P. Sheppard Verifier X X X S.P.Wrona l Verifier X X X J. E. Dombrowski Verifier X X X l ORG R. E. Querio ORG Lead X X X )

T. Tamlyn Lead Verifier / Verifier X X X l R. Spear Lead Verifier / Verifier X X X R. J. Ungeran Lead Verifier / Verifier X X X J. A. Kleam Lead Verifier / Verifier X X X W. Pinner Lead Verifier / Verifier X X X I

l l

1 J

Northeast Utilities - Millstone Unit 3 Sargant a tonby ICAVP Implementation Schedule rch l April l May J ID Task Name Start Finlah 3/16 l 3/23 l 3r30 l 4/6 I 4/13 l 4t20 l 4/27 l 5/4 l 5/11 15/18 l 5/25 6t1 l GIB 1 Submt Unt 3 Audt Plan to NRC for approval 3/17S7 3/17S7 m i a

2 NRC finalize approval of NU seledian 4/7S7 4/7S7 A m y --

3 Develop unt 3 Checidists 3/20/97 4/4S7 4 NRC rewew Unit 3 Audt Plan & Pts and provide comments 3/2007 4/11 S 7 _

5 S&L resoNe / tncorporate NRC comments & resubmt 4f14S7 4f28S7 g 6 Obtain non-system specific Unt 3 documerts 4/17S7 5/14S7 7 NRC Approw Unt 3 Audt Plan 42907 5/16S7 8 Mobilize and Train Projed Team 5/12S7 5/Z3S7 '

9 NU completes CMP on Wave 1 systems for Unt 3 5/27S 7 5/27S 7 4 5/27 to NRC Seied first 2 Und 3 systems 5/27S 7 5/28 S 7 m 11 Ottain Unt 3 system specific docunwlts for first 2 systems 5/2997 7/2G7 g

12 Meeting w/ NU, NRC, NEAC to agree on 1st 2 system boundaries 6/19 S7 6/19S7 13 Begin ARG rewew (Tier 2) / seled Unt 3 crtical charaderistics 5/27S 7 6/27S 7 '

14 NRC review and accept Unt 3 crtical characteristics 6f30G7 7/21 S 7 15 PRG perform Unt 3 process rewew 5f27B7 6/25 S7 2 16 PRG prepare unt 3 implementatm review checklist 6/12/97 6/25S7 17 PRG submt Unt 3 implementation checidist to NRC for approval 6/27S 7 6/27S 7 18 NRC approve PRG Unt 3 process implemertation checidist 6f30S7 7/21 S 7 19 Complete Unt 3 ARG review 6/30G7 8/18S7 20 Begin SRG, CRG, ORG rewews on first 2 Unt 3 systems (Tier 1) 6f12S7 8/14S7 2 6 r BJ 21 NRC ICAVP implementabon Inspectm of S&L 7721 S 7 8/15/97 m

22 NU completes CMP on Waw 2 & 3 systems for Unt 3 7/14S7 7n4S7 :r cr 23 NRC / NEAC Select remaining Unt 3 systems 7/1747 7/17S7

  • em 24 Obtain Unt 3 system specific documents for remaining systems 7/18S7 8/7S7 2 en 25 Meeting w/ NU, NRC, NEAC to agree on rem. sptem boundaries 7730/97 7/30G7 t 2.

CVilAICAVP\SCHEDVCAVP_3 MPP Page1 &

-,-.---,m , - - - - , . - - - - - -. - - .--. - -.- - , - . --

7 m - - . - - - - , - - - - - . - - - . . - - - - - - - - - , - - - - - - - - - - - - , - - - - - - - - - - - , - - - ,

JP Northeast UZlities - Mill 2 tone Unit 3 sn9ma m errns7 ICAVP Implementation Schedule rch l April l May J G Task Name Start Finish 3/16 l 3/23 l 3/30 I e l 4/13 l 4/20 l 4/27 l 5/4 -l 5/11 l 5/18 l 5/25 6/1 l 66-26 PRG perform Unt 3 aiW e. review 7/24/97 8/2D97 27 PRG perform Unt 3 correctre action review 6126/97 95/97 .

I 28 FRG revtew Unt 3 past design changes 7/t497 W29/97 29 SRG, CRG ORG review remaining Unt 3 systems (Tier 1) 7f25/97 9/12/97 i 30 Process and Report Unt 3 Findings &26/97 9/19197 31 NU Provide Proposed Resokton to Unt 3 findengs 7/3/97 9/26/97 32 Rewew NU Proposed Resohtion to Unt 3 findings 7/1187 10G97 33 Prepare Unt 3 Final Report 9/15/97 10f10/97 N

z E

1  !

ha k

Page 2 * "

C:WU\lCAVP\SCHED\lCAVP_3 MPP

-a ,

Northeast Utilities - Millstone Unit 3 sargent agg ICAVP Irnplementation Schedule ne l July l August I September l October l November ID 6/15 l &22 l 6/29 l 7M l 7M3 l 7/20 l 7/27 l 8/3 l 8/10 l 8/17 l 8/24 f8rJ1 l 9/7 l M4 l 9/21 l Of28 l 105 l 10/12 l 10/19 l 10/26 l 11/2 l 11/9 l 11h6 l 11/23 1

2 3

4  !

5 6

7 i

8 9

10 .

11 -

i2 'j '

13 14 l

15 16 p 17 i 18 g

19

i 21 -

m ,

x

  • 22 4p,g94 g  ;

cr .

23 E E ,

24 '{

gi l

  • i

, y[

5 1 I EI a

C.WU\lCAVP\SCHEDilCAVP_3.MPP Page 3

e

=

l l .v Northeast Utilities - Millstone Unit 3 s=g a a tu5y ICAVP Implementation Schedule ne l July j August September October l l l Novenbar so sris I er22 I er291 7/8 l 7/13 i 7/20 l 7G7 l 8/3 l 8/10 l 8/17 l 8G4 i 8/31 l 9/7 l 9/14 l Of21 l Of2B l 106 l 10t12 l 10/19 l 10f26 l 11Q j 11/9 l 11/16 l 11/23 28

- i 1mmmmmmmmmmmmmmmmmmm. t

--m W

32 33 m

l

}

m:

5-l wi 7

?!

%l C:1NUVCAVP\SCHEDVCAVP_3 MPP Page 4

_ . . . _ . - . _ _ . - . . _ . ~ . . . . _ . . _ _ _ _ _. _ -_ _. _ . _ . . _ _ . . .

ty = u 4

Exhibit 7 1

.(

ICAVP Budget Data Project No.: 9583-100  :

Task Codes: As follows:

l l Task Code bacription A00311 Development ofProject Manual A30020 Project Administration A30022 IRC Review ofDRs and Disposition )

1 A30027 Development ofCommunications 1

A30028 Development ofWeb Site 2:

A30055 Training & Mobilization  !

A30056ARG ARG - Perform Reviews / Report Findings A30056CRG CRG - Perform Reviews / Report Findings l

A300560RG ORG - Perform Reviews / Report Findings A30056PRG PRG - Perform Reviews / Report Findings  !

A30056SRG SRG - Perform Reviews / Report Findings A30057 Evaluate Resolution ofFindings A30058 Final Report A30420 Document Receipt & Maintenance