Q-e Omaha Public PowerDistrict 444 South 16th Street Mall Omaha NE 68102-2247 May 15, 1997 LIC-97-088
. U. S. Nuclear Regulatory Conrnission Attn: Document Control Desk Mail Station P1-137 Washington, DC 20555
Reference:
Docket No. 50-285
SUBJECT:
Closure of NRC TAC Issues for Fort Calhoun Station Omaha Public Power District has implemented the necessary actions associated with the open TAC issues listed below. Subject to agreement by the NRC/NRR Project Manager, these items are considered ready to close.
TAC.#
Description / Status 96089 Use of ZIRLO Fuel Cladding Amendment 178 Implemented October 25, 1996 95552 Revised Trisodium Phosphate Requirements Amendment 179
/p Implemented: January 31, 1997 94814 Inverter LCO Requirements Amendment 180 Implemented: April 14. 1997
&)$/
97334 Administrative Control of Staff Working Hours Amendment 181 Implemented: April 24, 1997 970S190261 970515 PDR ADOCK 05000205 p
~ ~ ~ ~ ~ ~ ~
190020 45.5124 Employment wim Equal Opportunity
j a,
6 c4 U.S. Nuclear Regulatory Comission LIC-97-088 Page 2 Please contact me if you have any questions.
Sincerely, b $ms S. K. Gambhir Division Manager Engineering & Operations Support TCM/tcm c:
Winston & Strawn E. W. Merschoff, NRC Regional Administrator, Region IV L. R. Wharton, NRC Project Manager W. C. Walker, NRC Senior Resident Inspector 1