ML20137X293

From kanterella
Jump to navigation Jump to search
Insp Repts 50-424/85-37 & 50-425/85-29 on 850722-0830. Violation Noted:Failure to Prescribe Appropriate Procedures to Control Area & Pump Internal Cleanliness
ML20137X293
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 09/23/1985
From: Rogge J, Schepens R, Sinkule M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20137X266 List:
References
50-424-85-37, 50-425-85-29, NUDOCS 8510040498
Download: ML20137X293 (20)


See also: IR 05000424/1985037

Text

. _ _ .

_ _ _ _

_

__

._ _

t

>R Rec

UNITED STATES

jo

NUCLEAR HEGULATORY COMMISSION

,

  • \\

/

REGION ll

h pk N

I

j

101 MARIETTA STREET, N.W.

3

-

t

ATLANTA, GEORGI A 30323

'

yv /

.....

'

Report Nos.: 50-424/85-37 and 50-425/85-29

Licensee: Georgia Power Company

,

'

P.O. Box 4545

'

f.

i Atlanta, GA 30302

Docket Nos.: 50-424 and 50-425

License Nos.

CPPR-108 and CPPR-109

{

Facility Name: Vogtle 1 and 2

j

Inspection Conducted: July 22 - August 30, 1985

Inspectors: W . T h

9/28/85

g

J. F. Rogge, Senior Resident Inspector, Operations

Date Signed

@.M.

9/2.0/85

@

R. J. Schep9 s, Resident Inspector, Construction

Date Si ned

!

Approved By:

fcp

_ 4 Z.$ W

t

M. V. SinEufe, Section Chief

DWte Sligned

Division of Reactor Projects

SUMMARY

.

Scope:

This routine, unannounced inspection entailed 212 Resident inspector-

i

hou'rs on site (32 hours3.703704e-4 days <br />0.00889 hours <br />5.291005e-5 weeks <br />1.2176e-5 months <br /> were on backshifts) inspecting: containment and safety

related structures, piping systems and supports, safety related components,

i

auxiliary systems, : electrical equipment- and cables, quality programs and

j

administrative controls af fecting ouality, and follow-up on previous inspection

l

identified items.

The inspectors also participated in a corporate management

l

meeting and an ACRS hearing.

l

Results:

Two violations were identified

" Failure to Prescribe Appropriate

l

Procedures to Control Area Cleanliness" - Paragraph 15, and " Failure to Establish

Appropriate Acceptance Criteria to Verify Pump Internal Cleanliness" - Para-

j

graph 15.

!

j

<<

!

>

l

8510040498 850924

>PDR

ADOCK 05000424

G,

PDR

i

I '

1.

- ~ _ ._ _

- . . _-

. - _ _ _ _._. _

_

._ __ _

_ __ ._ . _ _ _

__. - . __

.

.

.

t

!

!

j

REPORT DETAILS

l

>

$

1.

Persons Contacted

j

Licensee Employees

1

i

D. O. Foster, Vice President and Project General Manager

I

P. D. Rice, Vice President and General Manager, Q.A.

'

W. T. Nickerson, Deputy Project General Manager

'

W. C. Ramsey, Readiness Review Manager

,

H. H. Gregory III, General Manager Nuclear Construction

j

,

M. H. Googe, Project Construction Manager

,

G. Bockhold, Jr., General Manager Nuclear Operations

0. Batum, General Manager Engineering and Licensing

  • C. W. Hayes, Vogtle Quality Assurance Manager

i

  • C. E. Belflower, Quality Assurance Site Manager - Construction
  • E. D. Groover, Quality Assurance Site Manager - Construction

'

S. D. Haltom, Quality Assurance Engineering Support Supervisor

4

W. E. Mundy, Quality Assurance Audit Supervisor

i

J. E. Sanders, Project Construction Manager - Unit 1

D. M. Fiquett, Project Construction Manager - Unit 2

  • B. C. Harbin, Manager Quality Control
  • C. R. Brewer, Assistant Quality Control Manager

T. L. Weatherspoon, Assistant Quality Control Manager

G. A. McCarley, Project Compliance Coordinator

W. C. Gabbard, Assistant Project Compliance Coordinator

i

J. O. Dorough, Administrative Manager

!

  • W. F. Kitchens, Operations Superintendent

!

  • J. L. Blocker, Mechanical Engineer Supervisor

"M. S. Hairston, Regulator Compliance Associate Engineer

!

  • A. L. Mosbaugh, Superintendent Engineering Liaison

'

  • C. H. Williams, Jr., Operations Supervisor

,

M. Stone, Engineering Supervisor

j

T. Dannemiller, Senior QA Engineer

J. Rowland, Coordinator

J. B. Beasley, Startup Support Superintendent

Other licensee employees contacted included craftsmen, technicians, super-

visors, engineers, inspectors, and office personnel.

Other Organizations

,

  • D. R. Ellsworth, Surveillance Specialist - Bechtel

!

  • R. K. Watson, Assistant QA Manager - Pullman Power

L. Fields, QA Manager - Chicago Bridge and Iron (CBI)

C. Petterson, Flushing Engineer - Westinghouse

M. L. Bagale, Surveillance Specialist - Bechtel

-

I. Jamison, NSSS Flushing Supervisor - Bechtel

'

J. Foley, Lead Engineer Startup Support Group - Bechtel

i

,

. - _ . _ .

-,y,

,

g,_

,., ,

_y-,__. _ _ -- .

__

m._,._

, , , .

-y,,y%.,.~,,,.,p,

m,

py.,y.,

,_.7,y_,w,y..

.y,yg.,.,.

_

.

.

2

2.

Exit Interview (30703C)

The inspection scope and findings were summarized on August 30, 1985, with

those persons indicated in paragraph 1 above. The inspector described the

areas inspected and discussed in detail the inspection findings listed

below. No dissenting comments were received from the licensee.

(0 pen) Violation,

50-424/85-37-01 " Failure to Prescribe Appropriate

Procedures to Control Area Cleanliness" - Paragraph 15.

(0 pen) Violation, 50-424/85-37-02 " Failure to Establish Appropriate

Acceptance Criteria to Verify Pump Internal Cleanliness" - Paragraph 15.

(0 pen) Inspector Followup Item, 50-424/85-37-03 " Review Licensee Action on

QA Surveillance Report Finding No. 85-016-BJ" - Paragraph 11.

(0 pen) TI 2500/14, " Location of Unit I and 2 Manual Reactor Trip Circuits" -

Paragraph 24.

(Closed) Inspector Followup Item, 50-424/82-09-01 and 50-425/82-09-01

"Embedment Plate Threaded Bolts" - Paragraph 23.

The licensee did not identify as proprietary any of the materials provided

to or reviewed by the inspector during this inspection.

The following NRC exit interviews were attended during this inspection by a

resident inspector:

DATE

INSPECTORS

August 9

- L. Jackson, R. Wright

August 15

- R. Latta, A. Belisle

August 16

- J. Harris

August 30

- R. Newsome

3.

Licensee Action on Previous Enforcement Matters (92702)

Not inspected.

4.

Unresolved Items (92701)

Unresolved items are matters about which more information is required to

determine whether they are acceptable or which may involve violations or

deviations. Unresolved items were not identified during this inspection.

d

_.

_

. __

_ - - - . _

_ _ _ .

-

.

.-_

. __

,

.

3

5.

Construction Inspection - Units 1 & 2

!

Periodic inspections were made throughout this reporting period in the form

of general type inspections in different areas of both facilities.

The

i

areas were selected on the basis of the scheduled activities and were varied

to provide wide coverage. Observations were made of activities in progress

to note defective items or items of noncompliance with the required codes

and regulatory requirements.

On these inspections, particular note was made of the presence of quality

control inspectors, supervisors, and quality control evidence in the form of

available process sheets, drawi ng s , material identification, material

protection, performanceof tests, and housekeeping.

Interviews were made with craft personnel, supervisors, coordinators,

quality control inspectors, and others as they were available in the work

areas.

,

Independent inspection effort encompassed but was not limited to the

following areas:

VSL platform installation and load testing on Unit 1.

Walkdown of the Unit 2 main steam line tunnel to observe in process

hanger welding, small bore piping prepping, fit-up, welding, and to

ensure appropriate protection from the outside environment was being

provided during inclement weather.

No violations or deviations were identified.

6.

Fire Prevention / Protection and Housekeeping Measures - Units 1 & 2

(42051C)

The inspector observed fire prevention / protection measures throughout the

inspection period. Welders are using a welding permit with a fire watch and

extinguisher.

Post indicator valves were being maintained in the open

,

position. Fire fighting equipment is in its designated areas throughout the

plant.

Periodic inspections conducted throughout the inspection period identified

weak housekeeping practices in the following areas.

The auxiliary

feed-water pump house containing the motor driven feedwater pumps was found

cluttered with tooling (such as welding cables, electrical cables, air

hoses, hand grinders, grinding shields, etc.), trash (such as wood cribbing,

paper cups, rags, etc.) and water on the floor creating a ccngested and

dirty work environment. Six cable trays, five in the Containment Building

and one in the cable spreading room, were found cluttered with tooling and

equipment (such as hand grinders, oxygen hoses, welding stingers and ground

cables, hanger tube steel, air hoses, grinding shields, wire brushes and

i

flashlights) and trash (such as cigarette butts, tape, cloth, wood, metal

shavings, dirt and paint chips, and light bulbs).

These items were

,

,-

,- - -

..

- - , - ,

_,,

---_..-_.,-n.-.---,.

-- _

_ . , , -

-_,n

. , _

. _-. .

_

--

--

.

. .

.

_

.

.

-

>

l

4

2

!

identified to the licensee and corrective action was taken.

The licensee

was informed that housekeeping will continue to be monitored closely

throughout the upcoming inspection period for evidence of improvement.

No violations or deviations were identified.

!

7.

Containment (Structural Concrete) - Unit 2 (47053C)

a.

Procedure and Document Review

The inspector reviewed and examined implementation portions of the

I

following procedures pertaining to the placement of concrete to

determine whether they comply with applicable codes, standards, NRC

Regulatory Guides and license commitments.

-CD-T-02, Rev. 15

Concrete Quality Control

-CD-T-06, Rev. 9

Rebar and Cadweld Quality Control

-CD-T-07, Rev 8

Embed Installation and Inspection

-CD-T-20, Rev. 6

Installation and Inspection of Trumpets,

Rigid Extensions, and Duct Sheathing

-2X2001A002, Rev. 11 Containment Concrete Forming and

Placing Plan and Section

-2X2007A001, Rev. 2

Diesel Generator Building Forming

Plan at El 220'-0"

-AX2008A121, Rev. 6

Auxiliary Buildirg Area 3 #2 Plan

at El . 240'-0" (Level 2)

.

b.

Installation Activities

The inspector witnessed portions of concrete placement indicated below

to verify the following:

,

(1) Forms, Embeds, and Reinforcing Steel Installation

- Forms were properly placed, secure, leak tight and clean.

4

- Rebar and other embedment installation was installed in

accordance with construction specifications and drawings,

,

secured, free of concrete and excessive rust, specified

distance from forms, proper on-site rebar bending (where

applicable) and clearances consistent with aggregate size.

(2) Delivery, Placement and Curing

- Preplacement inspection was completed and approved prior

'to placement utilizing a Pour Card (Exhibit CD-T-02*18).

,

l

- Construction joints were prepared as specified.

-

'

- Proper mix was specified and delivered.

--Temperature control of the mix, mating surfaces, and

ambient were monitored.

,

i)

,

,

-

,

a

, , , , - -

,

--,

- ..

~.

-

-

. . _ .

.

. _ .

.

.

-

-

._ -

-

.

>

.

!

5

i

J

- Testing at placement location was properly performed in

i

accordance with the acceptance criteria and recorded on a

Concrete Placement Pour Log (Exhibit CD-T-02*20).

- Adequate crew, equipment and techniques were utilized.

- Inspections during the placement were conducted by quali-

,

fied personnel.

,

l

- Curing temperature was monitored.

j

(3)

Installation of Trumpets, Tendon Sheaths and Anchorage

Components for Containment Pours Only

!

-Trumpets, sheaths and anchorage components were oriented

i

properly, installed within specified tolerances, clear and

j

free of damage.

Pour No.

Location

Inspection Activity

,

l

2-071-001C

Diesel Generator Building

Preplacement, Placement

Base Slab

and Curing

2-010-039

Containment Dome El 356'

Preplacement and Curing

!

5-5/8" to 363' 1-1/4"

A-082-059, 064

Auxiliary Building Wall

Placement

No violations or deviations were identified.

8.

Containment (Prestressing) - Observation of Work Activities - Unit 1

(47063C)

.

!

Procedure and Document Review

4

The inspector reviewed the following VSL Procedures which were developed in

response to GPC QA AFR No's. 802-II, 803-II, 804-II, 806-II, 808-III to

'

determine whether they comply with applicable codes, standards, NRC

!

Regulatory Guides and licensee commitments.

VSL Procedure No.

Titles

In Response to AFR#

!

PT-01, Rev. O

VSL Field Procedure

804-II

Development and Control

PT-02, Rev. O

Control of Measuring and

806-II

Test Equipment

'

PT-03, Rev. O

Review & Control of QA

808-III

Documentation

PT-04, Rev. O

Document Control

804-II

.

. -

. .

.

..

- .-

- . . - - -

-

-

,

. .

.

. _ , . . . - . .

. . ,

-- - . - . . - . .

-

- -

..~

.

-

.

_.

-

.

-

.- .

j

.

.

6

,

PT-05, Rev. O

Receipt Inspection Storage

803-11

and Handling

PT-06, Rev. O

Nonconformance Control

802-II

.,

No violations or deviations were identified.

9.

Containment (Steel Structures and. Supports) - Units 1 & 2 (48053C)

Periodic inspections were conducted to observe containment steel and support

installation activities in progress to verify the following:

!

-

Components were being

properly

handled (included bending

or

straightening).

!

,

-

Specified clearances were being maintained.

,

-

Edge finishes and hole sizes were within tolerances.

Control, marking, protection and segregation were maintained during

-

storage.

I

-

Fit-uo/ alignment meets the tolerances in the specifications and

drawings.

,

Welding Activity (Unit 2)

a.

Observation of Work

j

The inspector observed in process welding activities of the personnel

airlock weld (No.100-A2) to the containment penetration as described

below to determine whether applicable code and procedure requirements

were being met.

l

b.

Welding Procedure Specifications and Quality Assurance Procedures

(1) The following Welding Procedure Specification (WPS) applicable to

the weld joint noted above was reviewed along with a sample of the

.

i

Procedure Qualification Records (PQR) which supported the WPS and

compared with the ASME Code.

The WPSs and their supporting PQRs

'

were reviewed to ascertain whether essential, supplementary and/or

nonessential

variables,

including

thermal

treatment,

were

consistent with Code requirements; whether the WPSs was properly

!

qualified and their supporting PQRs were accurate and retrievable;

whether the PQRs had been reviewed and certified by appropriate

,

personnel.

-

WPS E7018/74-2195/6, Rev. 2; 2-140'0 X 228'-9 Containment

Liner ASME Code Section III Summer 1975.

,

i

---

- - ,

,-r

, - - . , -

- ~ ,

-g

,.~p

-

v- m - n

,e

,--re-

-< , - - , -

m

--

- _ _

_

. _

. -

.__

-

.

,

4

7

a

.

-

PQR 3659, Rev. 0; PQR 2631, Rev. 0 (PWHT); and PQR 3638,

Rev. O.

The Penetration Assembly, material SA516 GR70, was being welded to

the Containment Liner, caterial SA516 GR70. The inspector noted

'

that the procedure was qualified for welding P-1 G-1 to P-1 G-2,

<

therefore any combination of P-1 to P-1 material could be welded

with this WPS. The WPS thickness range is 3/16" to 2-1/2" and the

actual material thickness was 1-3/8".

(2) The following Quality Assurance Procedures / Documents were reviewed

to determine whether they comply with with applicable codes,

standards, NRC Regulatory Guides and licensee commitments.

-

General Welding Procedure Specification for the Shielded

Metal ARC Process; GWPS-SMAWX, Rev. 1

-

Nuclear QA Manual for ASME Section III Products Section 8.0

Welding, Rev. 8 and Section 7.0 Process Control, Rev. 7

Personnel Airlock Weld No. 100-A2 Record Drawing Table and

-

As-Built Drawing

Containment Liner Detailed Checklist

-

Bechtel Dwg. No. 2X2001J018

-

,

'

,

c.

Welding Filler Material Control

The inspector reviewed the CBI program for control of welding materials

to determine whether materials were being purchased, accepted, stored

and handled in accordance with QA procedures and applicable code

requirements.

The following specific areas were examined:

-

Purchasing, receiving, storing, and distributing and handling

procedures, material identification; and inspection of welding

material issuing stations.

-

Weld Material Authorization & Release Reports - Weld Filler Metal

Certification and Receipt Inspection Report Nos.:

26 - E7018 3/32" 500#

23 - Linde #81 WireFlux 3/32" 1300#

21 - E6010 1/8" 750#

16 - E309 - 15 1/8" 90#

No violations or deviations were identified.

.

.

-

-

_

__.

. .-

__

._- ._ ._ ,,

-

. - - - .

-

. .

. .

_ _

. - - .

--

.

.

1

j

.

8

,

10. Safety-Related Structures (Structural Steel and Supports) - Units 1 & 2

(48063C)

Periodic inspections were conducted to observe construction activities of

4

safety-related structures / equipment supports for major equipment outside the

.,

j

containment to verify that:

'

-

Materials and components were being properly handled to prevent damage.

!

-

Fit-up/ alignment were within tolerances in specifications and drawing

requirements.

-

Specified clearances from adjacent components were being met.

!

No violations or deviations were identified.

11.

Safety Related Piping - Observation of Work and Work Activities - Unit 1

(49063C)

During the inspection period, pipe run walkdowns were performed where piping

installation is near completion to determine whether the piping run is

installed as shown on current, approved drawings and in accordance with

applicable construction specifications. Specific pipe run walkdowns of ASME

{

B&PVC,Section III, Class II piping are listed below:

j

ISO NO./ REVISION

PIPE RUN INSPECTED

1K5-1204-006-01, Rev. 8

RWST Safety Injection Suction

i

Header Piping (1204-006-24") - Spool

l

Nos. 006-S-20 and 006-S-24

IK3-1204-006-01, Rev. 12

RWST Safety Injection Suction Header

Piping

(1204-006-24")

-

Spool

Nos.

006-S10, 11, 12, 13, 14, 15, 16, 17, 18,

22, & 19.

l

l

IK3-1204-038-01, Rev. 13

RWST .. Safety Injection Suction Header

'

Piping (1204-006-24")

Spool

Nos.

!

-

{

006-S-09, 08, 07, 06, 05, 02 & 01.

j

Specific areas examined during the pipe run walkdown for compliance with the

l

applicable isometric drawings and the Plant Design and Instrumentation

Construction Specification No. X4AZ01, Revision 19 were as follows:

j

Vent and Drain Connections and Locations

Instrumentation Connections and Locations

Valve Installation and Orientation

-

Line Size and Location

'

Fittings Type and Size

i

Pipe / Valve / Fitting /End Connections

Hanger Locations and Types

!

, . _ _ _

. .

. .

_ _ _ _ _ _ _ _ _ _ . _ _ _ . _ _ _ _ _ _ . ,

.

_ . _ , _ . _

_

._

, _ _ _ - , , _ _ , . . , , , _ , _ , _ , . .

. . . . ,

-

_

--

.-

-.

.. -

-

.

.

.

_ .

.

.

-

1

9

1

l

t

!

During the inspection period, a review of the following flush procedures was

[

conducted:

i

i

1-1B8-02, Rev. O

Reactor Coolant System Pressurizer Spray Line

'

Flush

1-18B-09, Rev. O

Boron Injection and Hot Leg to Loops

'

1-1BJ-01, Rev. O

Safety Injection (with CVCS and RHR (crosstie)

Chr Nos. 1,2,&3

Flush

1-1BJ-02, Rev. O

Safety Injection Pump Discharge Piping Flush

Chg No. 1

e

]

1-1EF-02, Rev. O

Nuclear Service Cooling Water System Flush

i

1-1EF-05, Rev. O

Nuclear Service Cooling Water Train B Flush

Chg Nos. 1,2,3,&4

1-1EG-01, Rev. O

Component Cooling Water Flush

Chg No. 1

The following flushes were observed during the inspection period:

1-1BJ-02, Flow Path 2.10 -

Flush of the Miniflow Recirc Line No. 003 -

1 1/2"

I

i

  • 1-1BJ-02, Flow Path 2.13 -

Flush of the WPS Reactor Coolant Drain Tank

Pump Line 005 2" to waste

NSCW Train B operation of circulating water from the basin thru the NSCW

tunnel supply header piping bypassing the ACCW and CCW heat exchangers back

4

thru the NSCW tunnel return header piping and discharging out into the top

of the basin via a temporary strainer. The purpose of this flow path is to

-

circulate the water in the basin thereby cleaning it and the supply and

!

return header piping prior to starting the NSCW flush.

During the observation of the flush for flow path 2.13, a review of the

official flush procedure package was conducted. A representative of Georgia

Power Company's Quality Assurance Audit Organization was present performing

a surveillance and documented the below discrepancies on surveillance report

,

finding number 85-016-BJ:

On page 6 of the procedure the sign-offs for steps 6.1.1 (temporary

a.

modifications complete) and 6.1.2 (temporary hoses flushed) relating to

flow path 2.13 were not initialed and dated as being complete and step

6.2 (valve lineup) was initialed and dated as being complete along with

the flush being in progress. A review of Attachment 10.3 Temporary

Flushing Modifications required for flow path 2.13 revealed that these

activities had been completed prior to starting the flusn anu were

signed-off as such but had not been signed-off on the spread sheet for

,

,

, - . ,

1-..

,-,

,

,.------------e--

-

,-,_s._.

- .

. - .

. -

e.,

..,

r

r

- - . . - . . - -,-.

-- s

r-w

r--w - -

.

_

__ _ _ _

.

.

10

paragraph 6.3 on page 6. The flushing engineer initialed and dated

,

steps 6.1.1 and 6.1.2 as .being completed for flow path 2.13 once this

"

was brought to his attention and after confirming that they had been

previously completed and signed-off in Attachment 10.3. An entry was

noted in the log to document the late entry and the above action taken

to correct the discrepancy.

b.

Attachment 10.7 " Test Equipment Calibration sign-off sheet" was not

properly completed

i.e., the test equipment number was the only item

'

filled in.

The instrumentation location, equipment description and

verification initial and date columns had not been completed. The

question of why only one entry when more than one flow paths had been

flushed was raised in addition to why the required blanks had not been

filled out. and,

c.

Sum 16, Rev. 4 references Regulatory Guide 1.37 which endorses ANSI

N.45.2.1 - 1973 " Cleaning of Fluid Systems and Associated Components

During Construction Phase of Nuclear Power Plants".

All of these

documents require that the system (or in this case piping subsystems)

be flushed at its normal design velocity (or other velocity if

specified by procurement documents).

During the observation of flow

path 2.13, it was noted that the procedure did not specify a quantita-

tive value for the minimum design velocity of that flow path presently

being flushed nor did it for any of the other flow paths contained in

the flush procedure package. The inspector observed the GPC quality

,

control inspector inquire of the flushing engineer what exactly was the

design velocity for flow path 2.13.

The flushing engineer performing

the flush did not know the design velocity value for flow path 2.13.

'

However, it was noted that the procedure did require that the obtained

j

velocity during the flush be recorded.

The question was raised how

does one know if the minimum design velocity is being met or obtained

since a quantitative value is not specified for each flow path

<

contained in the procedure.

'

The inspector advised the licensee that, pending review of the licensee

action to resolve surveillance report finding number 85-016-BJ, this matter

will be identified as Inspector Followup Item 50-424/85-37-03, Review

Licensee Action on QA Surveillance Report Finding Number 85-016-BJ.

No violations or deviations were identified.

12.

Reactor Vessel Protection - Unit 1 & 2 (50053C)

The Unit No. 1 inspection consisted of examination of the Reactor Vessel

installed in Containment to determine that proper storage protection

practices were in place and that entry of foreign objects and debris was

prevented.

During the inspection period, the inspector noted that adequate

measures were established and maintained during the removal of flushing

equipment from the vessel, the filling of the Reactor Vessel with water, and

the installation of Combustion Engineering's ISI-2 positioning device, into

the vessel for performing the Reactor Vessel Pre-service Inspection.

-

u

,

_

. . _ . _

. _ . _

. -

- .

_ . _

.

_ . _ .

.

. ..

.-

. - _ _

_

. - - _ _

. -

-

.

.

11

The Unit No. 2 inspection consisted of examination of the Reactor Vessel

,

installed in containment to determine that proper storage protection

,

,

practices were in place and that entry of foreign objects and debris was

!

prevented.

No violations or deviations were identified.

4

!

13.

Reactor Vessel Integrated Head Package - Unit 1 & 2 (50053C)

3

'

The Unit No. 1 inspection consisted of examination of the integrated head

package stored on the refueling floor in its designated laydown area to

determine that proper storage protection practices were in place, entry of

i

foreign objects and debris was prevented, and that access was controlled.

The Unit No. 2 inspection consisted of examination of the Reactor Vessel

head with the installed control rod drive mechanisms as it was being

relocated and stored initially on the refueling floor and finally to its

,

designated laydown area on the refueling floor.

Proper storage protection

practices were observed to be in place and maintained during these critical

evolutions.

No violations or deviations were identified.

.

~

14.

Reactor Vessel Internals - Unit 1 (50063C)

1.

Periodic inspections were conducted during the inspection period when the

'

t

upper and lower internals were stored in the cavity in their designated

storage area to determine that proper storage protection practices were in

l

place, entry of foreign objects and debris was prevented and that access was

controlled.

No violations or deviations were identified.

15. Safety Related Components - Unit 1 (50073C)

!

The inspection consisted of plant tours to observe protection of installed

>

'

components to determine that adequate protection from dirt, dust, debris,

'

water, or adjacent construction activities were in place.

Unit 1 Equipment examined included:

,

j

- Residual Heat Removal (RHR) Pumps

- Diesel Generator Train B

l

- CVCS Centrifugal Charging Pumps and Positive Displacement

Pump

- Containment Spray (CS) Pumps

- Containment Penetration Encapsulation Vessel for

.

Train A & B RHR and CS

!

- Auxiliary Feedwater Motor Driven Pumps & 1-1817-U3-008 A&B

F

- NSCW Train B Pumps Including the Transfer and Spare

,

-

-.w

- _ , . ,

. . . .

, , - . . . - - . ,

,

,,

, , . - _ .

_m.,

,,.._..-em-.

-,c.

,

,.__.,,e

. - , . - . - - , . , - - - - , , . . . , . , . , ,

-

-

--.

-

_

. - .

__

_.

-.

.

8

.

5

12

4

f

4

- CVCS Volume Control Tank

'

- CVCS Letdown Heat Exchanger

- NSCW Pumps Train B

- Safety Injection Pumps

- Auxiliary Component Cooling Water (ACCW) Heat

Exchangers

- Component Cooling Water (CCW) Heat Exchangers

- ACCW & CCW Pumps

- Reactor Makeup Pumps

- Boron Injection Tank

- Cable Spreading Room Train A & B

,

- 18816 480 VAC Switchgear

i

- 1AAB MCC Train A, 120 VAC Vital Power, & Vital AC

Inverter

l

- Nuclear Grade Piping, Valves, & Fittings

- Spent Fuel Pool Heat Exchangers

- Pressurizer Relief Tank

4

- Accumulators Tanks

- Reactor Coolant Drain Tank Pumps

- CVCS Letdown Heat Exchanger

- Excess Letdown Heat Exchanger

4

- Reactor Coolant Drain Tank and Heat Exch' anger

,

!

- Reactor Cavity Sump Pumps

!

- Battery and Charger Rooms Train A, B, C, & D

I

During an inspection of the safety injection train B pump room on August 17,

1935, the inspector noted that the safety injection pump was completely

disassembled and that zone cleanliness requirements for the safety injection

train B pump room had not been established as required by ANSI N45.2.3 -

1973Property "ANSI code" (as page type) with input value "ANSI N45.2.3 -</br></br>1973" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process., Housekeeping During the Construction Phase of Nuclear Power Plants. At

the time of this inspection GPC's Field Manual Procedure No. GD-T-17, Rev. 2

did not address the criteria for establishment of zone 1,2,3,4,& 5 areas.

The licensee was informed of this matter and the inspector observed the

,

licensee take immediate corrective action. A revision to the Field Manual

Procedure No. GD-T-17 was in managements review cycle at the time of this

finding and was subsequently issued on August 22, 1985.

The inspector

subsequently observed that the licensee had established the safety injection

train 8 pump room as a zone 2 cleanliness area for the remaining work on the

safety injection pump until it was reassembled.

The above cordition is an example of failure to prescribe appropriate

procedural to control area cleanliness when performing work where foreign

matter may have detrimental effects. This is considered to be in violation

of 10 CFR Part 50, Appendix B, Criterion V and will be identified as

violation 50-424/85-37-01 " Failure to Prescribe Appropriate Procedures to

'

Control ~ Area Cleanliness".

!

'

i

,

_,

.

...m..

_ , _

..#.

_

. _ , - . , . , ,

..r_-,_,,r.,

,__

--.. .7

.

.

13

The inspector conducted an inspection of the safety injection train B pump

disassembly, cleaning, and reassembly process on August 17, 1985. This work

was being performed by Pullman Power under their construction QA/QC program

to resolve deficiency report number PP-11317.

This deficiency report

addressed the concern of foreign matter being in the pump as a result of a

leaking pump isolation valve during the performance of the safety injection

discharge line flush. The inspector reviewed the following documents which

controlled the work being performed to resolve the deficiency report.

,

- Field Process Sheet No.1X6AG02-16 for Train B pump 1-1204-P6-004

- Piping Material Requisition No. 113753; Replacement Parts -

Gaskets "0" Rings.

- 1X6AG02-16-2; Safety Injection Pump Operation and Maintenance

Manual

- Document No. IX-48, Dated 3/25/85; Procedure for Equipment

Installation

- Document No. XIII-4, Dated 10/18/84; Cleaning Procedure (Field)

- Westinghouse Process Specification No. 292722, Rev.9; Cleaning and

Cleanliness Requirements of Equipment for use in Nuclear Steam

Supply System and Associated Components.

The Pullman Power field process sheet detailed the steps to disassemble,

verify pump cleanliness, and reassemble the pump. Each step referenced the

appropriate document which was to give the necessary instructions to the

individual performing the step. The step for verifying pump cleanliness

referenced the Pullman Power Field Cleaning Procedure Document No. XIII-4,

Dated 10/18/84. The cleanliness acceptance criteria contained in Document

No. XIII-4, dated 10/18/84 was reviewed against the criterion established in

Westinghouse Process Specification No. 292722, Rev. 9.

The inspector noted

that the Pullman Power Document No. XIII-4, dated 10/18/85 failed to specify

the appropriate acceptance criteria for the inspector to veri fy pump

internal cleanliness prior to reassembly.

The Westinghouse Process

Specification No. 292722, Rev.9 states that when the surfaces are

accessible, a wipe test of a representative area in accordance with ASTM

A-380 shall be used to evaluate tF3 cleanliness of the surface. The surface

shall not exceed the limits for chloride and flouride contamination as

specified for the cleanliness classification which you are trying to

achieve. 1his acceptance criteria was not contained in the Pullman Power

Document No. XIII-4, dated 10/18/84.

The above condition is an example of failure to establish appropriate

acceptance criteria for the quality control inspector to use in verifying

pump internal cleanliness. This is considered to be in violation of 10 CFR Part 50, Appendix B,

Criterion V and will be identified as violation

50-424/85-37-02 " Failure to Establish Appropriate Acceptance Criteria to

Verify Pump Internal Cleanliness".

During an inspection of the Train A,B,C,& D battery and charger rooms on

August 27, 1985, the inspector noted that access control was being defeated

in the following manner:

_ . - - . . - -_. - . - _ -

. - - - -- ..

-_


_.-

-.

_ - ..

_ - -

l

.

i

,

l

14

i

- Train A battery room door was found to be unlocked

- Train C battery room door was found opened

- Train C charger room door was found wedged opened

,

i

Workers in the general area were questioned to determine if they were

working in the above rooms and no one acknowledged that they had been or

were going to be doing any work in the above noted rooms.

The inspector

1

advised the licensee of this matter and the licensee took immediate action

to correct the situation and documented their findings on a QA Surveillance

Report. The licensee's policy in this area is to maintain these doors

!

locked for personnel safety reasons.

Since there is no requirement that

'

these doors be maintained locked no further action will be taken at this

.

l

time by the resident.

'

16. Safety Related Components - Unit 2-(50073C)

'

The inspection consisted of plant tours to observe protection of installed

components to determine that adequate protection from dirt, dust, debris,

water, or adjacent activities were in place.

Unit 2 Equipment Examined Included:

- Residual Heat Removal (RHR) Pumps

4

- Containment Spray (CS) Pumps

,

- CVCS Centrifugal Charging Pumps & Positive Displacement Pump

1

- Steam Generators

i

- Safety Injection Pumps

- Auxiliary Component Cooling Water (ACCW) Heat Exchangers

- Component Cooling Water (CCW) Heat Exchangers

l

- ACCW Surge Tanks

'

l

- CCW Surge Tank

- CCW Drain Tank

j

- ACCW & CCW Pumps

- Reactor Coolant Pump Casings

- Accumulator Tanks

- Pressurizer Relief Tank

- Diesel Generator Fuel Oil Tanks

During the inspection period, the inspector observed preventive maintenance

being performed to the CVCS centrifugal charging pumps in accordance with

the storage requirements specified on the EMSL card. This work was governed

"

by the EMSL program which is administered under the field procedure manual

number GD-T-09, Rev. 8 " Inspection and Maintenance of Items in Storage".

.

No viclations or deviations were identified.

.

l

l

i

i

_ . , .

_ _ , , , , _ , -

-

, _.,

,,____

. .

. . . - . -

.

-- .

.. _ . . _ , _ . _ _

.

.

.

15

17.

Electrical (Components and Systems) - Units 1 & 2 (51053C)

Periodic inspections were conducted during the inspection period to observe

safety-related electrical equipment to verify that the installation and

storage were accomplished in accordance with applicable requirements. The

following areas were examined at during the inspections:

- Location and alignment

- Type and size of anchor bolts

- Identification

- Segregation and identification of nonconforming items

- Equipment space heating

- Rotation of motor shafts

- Lubrication and fluid levels

- Protective coatings, preservations, descicants, inert gas

blanket, etc.

No violations or deviations were identified.

18.

Electrical (Cables and Terminations) - Unit 1 (51063C)

Periodic inspections were conducted during the inspection period to

cetermine whether the raceway installation and protection of installed cable

is in accordance with applicable codes, standards, and NRC Regulatory

Guides.

In reference to the raceway installation, the following areas were inspected

to verify compliance with the applicable requirements:

- Identification

- Alignment

- Bushings (Conduit)

- Grounding

- Supports and Anchorages

In reference to the installed cable, the following areas were inspected to

verify compliance with the applicable requirements:

- Protection from adjacent construction activities (welding, etc.)

- Coiled cable ends properly secured

- Unterminated cable ends taped

- Cable trays, junction boxes, etc., reasonably free of debris

- Conduit capped, if no cable installed

- Cable supported

,

No violations or deviations were identified.

.

.

16

19. Reactor Coolant Pressure Boundary (Welding) - Unit 2 (55073C)

Periodic inspections were conducted on Reactor Coolant System Primary Loop

pipe welds at various stages of weld completion.

The purpose of the

inspection was to determine whether the requirements of applicable

specifications, codes, standards, work performance procedures and (QC)

procedures were being met as follows:

-

Work was conducted in accordance with a process sheet which

identifies the weld and its location by system, references

procedures or instructions, and provides for production and QC

signoffs.

-

Welding procedures, detailed drawings and instructions, were

readily available and technically adequate for the welds being

made.

-

Welding procedure specification (WPS) were in accordance with the

applicable ASME Code requirements and that a Procedure Qualifica-

tion Record (PQR) is referenced and exists for the type of weld

being made.

-

That the base metals, welding filler materials, fluxes, gases, and

insert materials were of the specified type and grade, have been

properly inspected, tested and were traceable to test reports or

certifications.

-

That the purge and/or shielding gas flow and composition were as

specified in the welding procedure specification and that

protection was provided to shield the welding operation from

adverse environmental conditions.

-

That the weld joint geometry including pipe wall thickness was

specified and that surfaces to be welded have been prepared,

cleaned and inspected in accordance with applicable procedures or

instructions.

-

That the pipe to be welded to the component was assembled and held

in place within specified s,ap and alignment tolerances allowed by

the ASME Code.

-

That a sufficient number of adequately qualified QA and QC

inspection personnel were present at the work site, commensurate

with the work in progress.

-

That disbursement of welding materials was controlled in

accordance with approved procedures.

No violations or deviations were identified.

,

- -

_

.

.-

. -

-_

._

.

---

.

- -

--

. _

-

.

.

17

20.

Safety Related Piping (Welding) - Unit 1 (55083C)

Periodic inspections were conducted on safety-related pipe welding at

various stages of weld completion.

The purpose of the inspection was to

,

determine whether the requirements of applicable specifications, codes,

standards, work performance procedures and QC procedures are being met as

follows:

-

That the weld area cleanliness was maintained and that pipe

alignment and fit-up tolerances were within specified units.

.

-

That weld filler material being used was in accordance with

welding specifications, that unused filler material was separated

from other types of material and was stored in heated cans, and

stubs properly removed from the work location.

-

That there were no evident signs of cracks, excessive heat input,

sugaring, or excessive crown.

Installation Activities

,

l

During the inspection period, welds at various stages were observed in the

following systems:

-

Residual Heat Removal System

,

-

Component Cooling Water System

'

-

Chemical & Volume Control System

-

Nuclear Service Cooling Water System

No violations or deviations were identified.

21.

Participation in ACRS Meeting - Units 1 & 2 (94700)

On August 9, 1985, the ACRS held a meeting in Washington, D. C. pursuant to

the operating license review.

Regional representation at this meeting was

i

performed by J. F. Rogge and M. V. Sinkule.

i

22. Second Corporate Management Meeting - Units 1 & 2 (30301B)

,

On August 27, 1985, a meeting was held onsite with the persons listed below

to discuss the change in emphasis from construction to the operations

phases. Topics discussed at the meeting included the status and handling of

construction and preoperational problems prior to unit licensing, the

regulatory process steps in obtaining a license recommendation from Region

II, the Regional Inspection activity with emphasis on the preoperational

program and special team inspections.

It is anticipated that subsequent

meetings may be held as necessary to discuss the Startup Test, Health

'

i

Physics and other NRC programs as appropriate.

i

4

0

!

---

.~-r-,

-c-

-

~

r-w---.

m

v.

,

, ,

- - - .

,-

---<---r

9

. . , -

-r,,-

y,

--,>

..

_ _ . _ - .

.

-

-

-

_.

O

.

1

18

i

I

Attendees

GPC/SCS

D. O. Foster, Vice President and General Manager

1

!

G. Bockhold, Jr., General Manager, Nuclear Operations

R. M. Bellamy, Initial Test Manager

J. F. D' Amico, Superintendent, Regulatory Compliance

C. W. Hayes, Vogtle Quality Assurance Manager

C. E. Belflower, QA Site Manager, Operations

P. A. Herrmann, Senior Engineer-Nuclear Safety, Southern Company

Services (SCS)

J. A. Bailey, Project Licensing Manager, SCS

,

i

b

1

V. L. Brownlee, Branch Chief, Division of Reactor Projects (DRP)

M. V. Sinkule, Section Chief, Projects Section 2D, DRP

F. Jape, Section Chief, Test Programs Section (TPS)

}

J. F. Rogge, Senior Resident Inspector

R. J. Schepens, Resident Inspector

G. A. Schnebli, Reactor Inspector, TPS

W. H. Rankin, Project Engineer, DRP

23.

Inspector Follow-up Items (IFI)-Units 1 & 2 (927018)

'

'

(Closed) IFI 50-424/82-09-01 and 50-425/82-09-01, Embed Plate Threaded

Bolts. This item was reviewed and found to be duplicative of a Constructive

Deficiency Report (COR).

CDR 82-21 was inspected and closed in reports

50-424/85-08 and 50-425/85-08.

I

24.

Follow-up On Headquarters Requests (25014) Units 1 & 2

TI2500/14 (0 pen) Solid State Protection System (SSPS) Manual Trip Circuit.

This inspection was perfermed to determine the electrical location of the

'

manual trip circuit in relation to output transistors Q3 and Q4.

A

'

short-circuit failure of the output transistors would prevent the automatic

tripping of the associated reactor trip breaker.

In this case, the manual trip would have to be utilized to trip the breaker. By design the manual

trip switches should be located between the transistors output and the

undervoltage trip device in the breaker. A recent NRC review indicated that

!

erroneous controlled schematics showing the manual trip switches before the

,

transistors could lead to possible wiring errors.

,

l

The inspector verified with Document Control the number and location of each

I

controlled document for the SSPS System (1X6AX01-466-1).

Each document

contains Figure 10-9 SSPS Schematic Diagram (1296H01) Sheet 13 showing the

correct location for the Manual Trip switch.

In order to determine that

4

field construction was being constructed properly, the inspector requested

the licensee to arrange a panel walkdown. This item will receive continued

follow-up.

4

. . .

_ _ ~ _ , _ , . -

- _ _

_ , , _ , _ _ , _ , , . _ . _ _ , _ _ , , , _ _ , . , .... , ,

_

.

.

. . .

-

C

-

4

19

25. Management Meetings (307028)

On August 15, 1985, the resident inspector attended a meeting with the

Georgia Power Company Startup Support Superintendent to discuss the function

and role of the newly formed Startup Support organization at plant Vogtle.

The inspector was informed that the primary responsibility of this organiza-

tion is to provide craf t support to the flushing group for performing

flushing modifications and system restorations and to complete punchlist

items on ANSI B31.1 Power Piping Systems. In addition this group will be

perforn:Ing ASME Section XI work. This group will not be doing any ASME

Section III work on Pullman Power ASME Section III N-Stamp piping systems.

The administrative procedure detailing how this group is to function is

presently being - developed and will be issued as SUM 36.

Other key

procedures which this group will be utilizing are SUM 22, Maintenance Work

Orders and Administrative Procedure No. 00351-C ASME Section XI Repair /

Replacement Program. This group is starting with a work force of 80-90

crafts and is expected to peak at 200-250 crafts. Support functions such as

planning, coordination, engineering, and quality control will be provided by

within this organization.

On August 20, 1985, the resident inspectors attended a meeting with Georgia

Power Company in Region II. Georgia Power Company outlined for the staff the

progress they have made to date in implementing numerous action plans to

improve the electrical construction area.

!

!

!

d

- . - . . _ _ . . . , .

-,.- ____

- , -

_,__,.,,_-m

. , . _ _