ML20136C074
ML20136C074 | |
Person / Time | |
---|---|
Site: | Wolf Creek |
Issue date: | 10/19/1984 |
From: | Deyoung R NRC OFFICE OF INSPECTION & ENFORCEMENT (IE) |
To: | Denise R NRC - WOLF CREEK TASK FORCE |
Shared Package | |
ML20136C034 | List: |
References | |
FOIA-85-101 NUDOCS 8511210014 | |
Download: ML20136C074 (1) | |
Text
. - . - - -
- UNITED STATES
[ ," }, NUCLEAR REGULATORY COMMISSION U .S. KRC 3 -
.l wAsMasec70ee. o. c. roses
(- --
,/
oct 2S g DCT 23 Ag g 11 mmunis IELB CfITL ff5d W MEMORANDUM FOR: Richard P. Denise, Director Wolf Creek Task Force, Region IV FROM: Richard C. DeYoung. Director Office of Inspection and Enforcement
SUBJECT:
STATUS OF NRC/RIV PROCESSING OF ALLEGATIONS - WOLF CREEK
REFERENCE:
Memorandum Richard P. Denise to Richard C. DeYoung,
" Wolf Creek Allegation Program Assessment," dated September.44, 1984 Y
In item 3 of the referenced memorandum, you requested IE to perform an assess-mer.t of the NRC/RIV effort on allegation management and closecut related to the Wolf Creek plant. In further telephone discussions with W. Haass on October 9, 1984. ycu modified this request to provide only a complete identification of all allegations and a summary of the status of each open allegation. The infon::ation compiled was obtained from Region IV and O! personnel (Tom Westerman, Glen Madsen, and Dick Herr) and the Allegation Tracking System. The results are presented in the enclosure.
At the present time, a total of 38 allegations have been received by NRC with 20 resolved and 18 being processed. Within the latter grouping,3 all.egations involve needed Of action. Glen Madsen. the Wolf Creek Task Force member r'eslicMTble for processing allegations, estimates that the technical aspects of
, .all open allegations should be resolved by December 1, 1984. OI. however, due to the resource needs for Waterford and Comanche Peak, has not assigned per-sonnel to complete the Wolf Creek investigations and at the moment does not plan to do so until 1985.
With regard to the assessment of KG&E's Quality First program to which items 1 and 2 of the referenced memorandum are addressed. IE has assisted Region IV in completing the initial phase of your request; i.e., an inspection of the utility's program has been performed on September 25-27, 1984 and input for the inspection report has been forwarded to Larry Martin for finalization (IR50-482/84-37). It is our understanding that Region IV plans to conduct ;
additional evaluations of KG&E's processing of those allegations that are new ~
or were not closed at the time of our inspection in September as a followup. '
Should you require assistance from us for that effort, please let me know. '
Please contact W. Haass (FT5 492-9677) if you have any questions regarding the cnclosure.
8511210014 851107 PDR FOIA VARRIC H85-101 PDR Richard C. oung, ector Office of etion and Enforcement [
Enclosure:
Status of Wolf Creek .
Allegations Processed by NRC I"
)
__. ... . , h^d W-Fom %-Th WW }
- 3
-Q*
- ,' - t Y / /, y ;
[ ,
o v Er 11 ATE!
'i ,J ,, ,
fiUCL E AK RE GULO ORY COMMl!.5<'
l g RE GloN IV c;
[ PARKWAY CENTR AL PLAZ A BUILDING
' V.
611 RY AN PLAZA DRIVE. SUITE 1000
%'8 , , , , , j ARLINGTON, TEXAS 76011 OCT 2 6 B64 In Reply Refer To:
Docket: STN 50-482/84-22 Kansas Gas and Electric Company ATTN: Glenn L. Koester Vice President - Nuclear P.O. Box 208 Wichita, Kansas 67201 Gentlemen:
This refers to the inspection conducted by Mr. R. G. Taylor and other personnel, of this office during the period of June 11 through September 28, 1984, of activities authorized by NRC Construction Permit CPPR-147 for the Wolf Creek Generating Station, and to the discussion of our findings with Mr. F. J.
Duddy and other members of your staff at the conclusion of the inspection.
Areas examined during the inspection and our findings are discussed in the enclosed inspection report. Within these areas, the inspection consisted of selective examination of procedures and representative records, interviews with personnel, and observations by the inspectors.
As discussed with you and your staff on site, we have concluded that a significant violation of NRC regulations has occurred in the area of structtral steel welding in that the inspection program for safety-related structural steel welding was not executed in a manner to ensure conformance with the requirements of the Construction Procedures and the FSAR commitments. Details of the inspection findings which support this conclusion are discussed in the enclosed inspection report. A written comprehensive program for the reinspection of structural steel welding, along with appropriate corrective action is required to be ' :'itted to Region IV.
In accordance with our discussions, KG&E will c~. as their corrective action plans, and establish a date for submittal of the documented correction action plans, at a meeting with NRC on October 29, 1984.
The enforcement correspondence and Notice of Violation pertaining to the matter will be sent to you under separate cover. Certain aspects of these findings will be referred to the _ Office of Investigations for possible investigation. An enforcement meeting on this matter is scheduled for October 29, 1984.
J ,-
um m .
r,- R,
- i/
- .y.a .,n a 1
..x. . . . .
e, s' *
- Kansas Gas and Electric Company One new unresolved item is idei *ified in paragraph 4 of the enclosed report.
'In accordance with 10 CFR 2.790(a), a copy of this letter and the enclosure will be placed in the NRC Public Document Room unless you notify this office, by telephone, within 10 days of the date of this letter, and submit written application to withhold information contained therein within 30 days of the date of this letter. Such application must be consistent with the requirements of 2.790(b)(1).
Should you have any questions concerning this inspection, we will be pleased to discuss them with you.
Sincerely, ff R. P. Denise, Director Wolf Creek Task Force
Enclosure:
Appendix A - NRC Inspection Report 50-482/84-22 cc w/ enclosure:
Kansas Gas and Electric Company Forrest Rhodes, Plant Superintendent ATTN: Gene P. Rathbun, Manager Wolf Creek Generating Station of Licensing P.O. Box 309 P.O.. Box 208 Burlington, Kansas 66839 Wichita, Kansas 67201 k__.
.p.
I r,
// /: 'bs p.E. Bess,ReactorInspector,ProjectSectionB '
Reactor Project _ Branch.2 .
Approved: I?
Chief, Project Section A
/M/4/d/
Date /
L'.Reactor T. Martirj{
Pro ject Branch 2 Inspection Summary Inspection Conducted June 11 through September 28, 1984 (Report 50-482/84-22)
Areas Inspected: Routine, unannounced inspection of electrical separation, electrical cable tray and conduit as-built installations, structural steel as-built welding installations, electrical craftsman qualifications, procedures for penetration fire seals, and followup on previous NRC findings. The inspection involved 246 inspector-hours onsite by five NRC inspectors.
Results: Within the areas inspected, two violations were identified (failure to assure conformance of safety-related structural steel welds with requirements, paragraph 3, and failure to maintain adequate electrical sepa ration, paragraph 4). In addition, one new unresolved item is identified in paragraph 4.
.ta. , .1 , , /; n 6 7 (( ( UtM l l i #
--- -- - _- l
. .- i DETAILS
- 1. Persons Contacted Principal Licensee Employees
- F. J. Duddy, Construction Manager
- W. M. Lindsay, Supervisor - Quality Systems
- P. Dyson, Field Engineering Supervisor
- R. Grant, Director - Quality
- R. L. Stright, Licensing
- N. W. Hoodley, Nuclear Plant Engineer Daniel International Contruction, Inc. (DIC)
- J. Berra, Vice President
- J. Fletcher, Construction QC Bechtel Corporation
- C. M. Herbst, Assistant Project Engineer
- G. D. Brown, Engineer The NRC inspectors also interviewed other licensee, DIC and Bechtel personnel.
- Denotes those attending the exit interview.
- 2. Licensee Action on Previous Inspection Findings (Closed) Unresolved Item (50-482/77-05-01) This item involved the batchir.g of concrete for " mud mats" underlying the nuclear safety-related buildfr.p.
Based on an interview with the reporting NRC inspector, this NRC inspect;r determined that the major issue involved was a lack of desire on the part of the applicant to utilize a certified batch plant for mixing the concrete. The NRC inspector was provided a Certificate of Conformance for Concrete Production Facilities" for the Penny Ready Mix plant in New Strawn, Kansas signed by a licensed professional engineer on May 9, 1977.
The certificate is sufficient to satisfy the requirements of the LWA-2, the NRC authorization for the work involved.
(Closed) Unresolved Item (50-482/78-04-05) Containment Base Mat Ninety-Day Cylinder Breaks. This item was superceded by Notice of Violation, Iten B of Appendix A to Inspection Report 50-482/78-13.
't
- _4 (Closed) Inf raction (50-482/78-04-8) Failure to Meet Concrete Acceptance Criteria for Containment Base Mat. This item was transferred to NRR for evaluation. The NRR evaluation.and. conclusion is contained in the Safety Evaluation Report for the Wolf Creek station (NUREG-0881) at paragraph '
3.8.4.
(Closed) Unresolved Itec (50-482/78-15) Pre-Planning For Concrete Placement. This unresolved item was superceded by Appendix B Notice of Deviation included with Inspection Report 79-03.
(Closed) Unresolved Itee (50-482/78-15) Placing Limitations for Concrete.
This unresolved item was superceded by Appendix A Notice of Violation included with Inspection Report 79-03.
(Closed) Unresolved Item (50-482/79-01) Concrete Practices. This unresolved item was superceded by Appendix A, Notice of Violation, included with Inspection Report 50-482/79-03.
(Closed) Unresolved Iter. (50-482/79-01) CFR Weld Deficiency of Unistrut Material. The 50.55(e) report was discussed in Inspection Report 79-07 which satisfied the unresolved item.
(Closed) Infraction (50-482/79-03) Failure to Adhere to Concrete Placement Limitations. This infraction was issued for record purposes with corrective action implicit within the licensee's response to Inspection Report 78-15. This conclusion is consistent with statements contained within paragraph 5, Report 50-482/79-03.
(Closed) Unresolved Ites (50-482/79-07) Observation of Concrete Testing Procedures. Although not specifically documented, the inspection ef fort described in Inspection Report 50-482/79-09, paragraph 11, by the inspector of record in report 79-07 is considered as resolving the matter.
(Closed) Unresolved Itee (50-482/80-13-01) Review of Work Hold Agreement Number 11. The work hold involved a conflict between the Daniel International Corporation procedure for coating application inspection and the applicable Bechtel specification. Bechtel letter BLKE 600 dated August 27, 1980, provides information on the resolution of the matter sufficient to warrant cancellation of the Work Hold Agreement in September 1980.
(Closed) Unresolved Item (482/8335-01) This item required the licensee to determine whether the Bechtel requirement that flexible. electrical conduit not be greater than 5 feet includes total length where the conduit is supported. There were five safety-related instrument transmitters found in this category. The licensee furnished the Bechtel design drawings for these transmitters which showed that a support was allowed for each. This item is considered closed.
- 3. Welding of Structural Steel
- During a review of QA/QC and Quality. First personnel' qualifications and subsequent interviews, the NRC inspector became aware of potential problens with corrective action reports CAR 29 and 31. The NRC inspector subsequently obtained copies of the two docunents. CAR 1-W-0029 (initiated on March 22,1983) states, in part, " Subsequently to the issuance of CAR 1-W-0019, quality has instituted a random reinspection of accessible structural steel fillet welds in all Q buildings. It has been detennined by the results of this reinspection that an una_cceptable_
percentage of_ these welds are deficient in the auxiliary, control, and
~
fuel buildings." Attached ~ documentation revealed that in the auxiliary building, 62 welds were inspected with 53 being rejected. In the control and fuel buildings, 50 welds were inspected with 43 rejected, and 53 inspected with 35 rejections, respectively. Revision 2 to CAR 1-W-0029 stated in the disposition that the defective welds would be transferred to a Nonconformance Report (NCR). The NRC inspector obtained a copy of NCR ISN 10381PW which was used as the vehicle to carry out the direction provided by CAR 1-W-0029. It appears that DIC Project Welding Engineering personnel again reinspected the welds to more clearly define the nature and extent of the defects on a weld-by-weld basis. A majority of the defective welds were categorized as having "cosnetic" defects. The DIC reconsnended disposition was use-as-is for welds identified containing
" cosmetic" defects. The NCR states that " cosmetic" defects include arc strikes, convexity, cold roll (understood to be synonymous with overlap),
porosity, and acceptable amounts of undercut. The NRC inspector noted with respect to these defects that overlap is prohibited by the governing AWS D1.1-75 Code and specific acceptance criteria for the other defects are also defined by this Code. The engineer accepted the Dit reconsnendation stating, "This disposition is based on the understanding that the cosmetic defects outlined . . . of this NCR do not constitute violations of AWS DI.1-75." A written-in note labeled "SNUPPS conraent" states that DIC had confinned the engineer's understanding. NCR ISN 10381PW was completed as indicated above on August 30, 1983.
On August 16, 1983, DIC personnel issued CAR 1-C-0031 which indic6tt.d that approximately 16.4 percent of the miscellaneous structural steel wcidino
. records for "Q" weldino couta not be located. After corresponding back and fortn, va and the engineer concluded that it was acceptable for some amount of these records to be missing, provided that the quality inspection prograr,was acceptable. Senior ifcensee QA management expressed to the NRC inspector that the program had obviously been fully successful since very few welds had been found to require repair'af ter a substantial reinspection effort associated with CAR 29. The NRC inspector expressed concern wi'th this approach to resolution and suggested that the licensee reevaluate their position.
6-On September 11, 1984, the licensee, in conjunction with senior DIC managment personnel, made a presentation to the NRC Task Force Director and oth'er NRC staff personnel, including-the NRC inspector. The.,
presentation was aimed at the DIC effort to provide adequate records of inspection of the structural welds. This effort involved the inspection at that point in time of 319 weld joints in the reactor building for which there appeared to be no records. Of these, 48 were found to not meet code / design original requirements. Several had been reanalyzed by the engineer and found to provide adequate structural strength and were deemed to be "use-as-is."
The NRC Task Force Director and the NRC inspector met with the KG&E Project Director on September 14, 1984. The NRC personnel informed the project director that the NRC position was that NCR ISN 10381PW had not been properly dispositione_d and that, therefore, the underlying premise
'for the closure of CARS G9.and(Il3was faulty. The NRC personnel stated that it appeared that the quality status of the majority of all structural steel welds was at best indeterminate. The project director proposed to have the engineer identify a group of structural members with the highest design loads or the lowest design strengtt safety margin and to have these joints inspected. The NRC personnel ind' oted that might be one possible approach to resolution of the matter.
During the week of September 17, 1984, a reinspection of the identified structural members with the highest design loads or the lowest design strength safety margin was initiated. The reinspection identified a number of welds which do not meet drawing requirements. This information was presented to the NRC staff during a meeting conducted on September 25, 1984. In an effort to confirm certain of the identified conditions, the NRC inspector accompanied DIC welding inspectors into the reactor building to observe specific, identified weld joints. This observation confirmed the welding inspectors' findings; e.g., welds that are undersized and of insufficient length, lack of fusion, and missing welds.
The sissina welds are from the same location in each of six pressurizer support connections. Certain of the other welds in the pressurizer support connections were undersized and of insufficient length. Drawing No. C-05 2904 shows that various length 5/8-inch welds are required in 14 specific locations. Four locations required a 5/8-inch fillet weld of 8 inches in length. The actual welds in two of the locations measured between 3/8-inch and 1/2-inch by 5 inches in length, and 1/2-inch by 3 inches in length. The missing welds and the undersized, insufficient length welds are_ clear 1y not in compliance with the requirements of the drawing or AWS D1.1-75.F The initial weld inspection records for these connections could not be located.
The NRC inspector accompanied two 01C welding inspectors for reinspection of nine structural steel connections in the auxiliary building. Drawing
F .
-7 No. K6720, applicable to these connections, shows 12 weld locations per connection with certain of the welds requiring returns. Reinspection of the welds and returns involved provided the following sumarized data':
Missing welds 2 Welds with insufficient length 9 Undersized welds 6 Undersize welds with insufficient length 2 Overlength returns 44 Undersize returns 25 Undersize returns with insufficient length I The NRC inspector requested the initial weld inspection records for these welds and returns in the 9 reinspected connections. As of September 28, 1984, the only inspectiun records that were located pertained to 10 welds and 6 returns in one connection, and 6 welds and 4 returns in each of 3 other connections. These records did not indicate that the welds were anything other than acceptable. The licensee informed the NRC inspector of a situation where one inspection record for connection 524B2, clearly indicated by an attached sketch, the existence of the a weld that reinspection found not to exist. This problem will be followed up in conjunction with the other structural steel problems.
The NRC inspector made a comparison between the existing initial inspection records and the results of the reinspection effort in order to determine the validity of the initial records. The initial records show that the 10 welds with 6 returns in one connection were inspected and accepted on December ?l,1978. The reir.spection id(ntified one undersized weld, other undersized and overlength returns, and three overlength re turns . The initial records for thc other thret connections show that eight welds with four returns per connection were inspected and accepted on Septer.ber 8, 1979. The reinspection of these welds and returns identified two returns which were overlength and undersized and two -
returns which were overlength per connection. 4;.
The failure to execute the required welding inspection program is a g]y '
violation of Criterion X of Appendix B to 10 CFR part 50. (482/8422-01)
- 4. Observation of Electrical Separation (Class IE Cables)
The NRC inspectors observed the completed electrical cable work for confomance to the separation criteria specified ir, the FSAR, IEEE l standards and site procedures. The specific areas inspected were the physical separation between redundant safety groups and between safety and non-safety groups. The plant areas inspected were the following:
.e.
- North Electrical Penetration Room
- South Electrical Penetration Room -
- Control Room
- Centrifugal Charging Pump Rooms A and B
- Safety injection Pump Rooms A and B
- Lower Cable Spread Room
- Upper Cable Spread Room o Standby Diesel Generator Room B
- Main Steam Isolation Valve Room The following documents were examined during this inspection:
- Bechtti Drawing E-IR8900, Revision 1, dated July 11, 1984, " Raceway Notes, Symbols & Details"
- Bechtel Drawing E-01013(Q), Revision ll, dated December 20, 1983,
" Installation, Inspection, and Testing Details for Electrical Equipment and Cable"
- Bechtel Specification 10466-E-0(Q), Revision 11, dated June 25, 1981,
" Electrical Design Criteria for the Standardized Nuclear Unit Power Plan' System (SNUPPS)"
- Bechtel Drawing E-01006, Revision 8, dated December 7, 1982, " Single Line and Schematic Diagram Standards, Notes and Symbols"
- Daniel Procedure WP-X-303, Revision 9, dated September 22, 1982,
" Installation of Cable"
- Daniel Procedure WP-X-304, Revision 14, dated February 9, 1984,
" Termination of Cable" Bechtel Drawing E-IR8900, Revision 1, states in paragraph 3.36.4 that:
" Minimum separation between different Class IE conduit systems and minimum separation between Class IE conduit systems & non-!E conduit systems shall be 1"." Separation shall be measured between the outside edges of the conduit."
Contrary to the above, the following observations were noted where the required minimum separation was less than 1":
- Tiex conduit 4J1039 (Class IE) crosses within 1 inch of flex conduit 6J1175 (Non-Class IE) in the Centrifugal Charging Pump Room B.
- Flex conduit 4U3 FIT (Class IE) crosses within 1 inch of junction box IU1201 (redundant Class IE group) in Safety Injection Pump Room B.
- Flex conduit 403E7A (Class IE) crosses within 1 inch of flex conduit IU3K4B (redundant Class IE group) in the North Electrical Penetration Room.
- Flex conduit 1U1288 (Class IE) crosses within 1 inch of flex conduit 5J1124 (Non-Class IE) in the Main Steam Isolation Valve Room.
- Flex conduit 1U1281 (Class IE) crosses within 1 inch of flex conduit 5J1125 (Non-Class IE) in the Main Steam Isolation Valve Room.
- Rigid conduit 3C3009 (Class IE) crosses within 1 inch of rigid conduit SC851A (Non-Class IE) in the Lower Cable Spread Room.
- Flex conduit 4J1CSB (Class IE) crosses within 1 inch of non-safety 120voJ}_ACoutletQA1530inStandbyDieselGeneratorRoomB.
,/ -
Bechtel Drawing E- 1013(Q), Revision 11, requires the following:
k
- a. Paragraph'5.8.1.b "Within the control boards and other panels associated with protection systems, circuits and instruments of different separation groups shall be independent and physically separated horizontally and vertically by a distance of 6 inches."
- b. Paragraph 5.8.3 "Non-safety related circuits shall be separated fror. Class IE circuits by the same distances applicable to Class IE circuits of different groups."
Contrary to the above, the follosing cables within cabinets or panels in the control room were found to have less than the required 6-inch minimum spacing:
- Cables 458508AD and 45B50800 (Class IE) are within 6 inches of cable 5SCIO1AE (Non-Class IE) at the floor penetration of cabinet RLO25/026.
- Cables 1EJG09CD and IEMG13AD (Class IE) are within 6 inches of separation group 4 vendor wiring at the base of cabinet RLO17/018.
$5BS508CC, 55FR16BB, SSFS11BG, SSFS11BF, SSFR16BA, and SSFY11AC in the main control board panel.
I
1 - , - .
! 10 i
i I
- Cable 4SB508AC (Class IE) is within 6 inches of several bundled
- separation group 5 non-class IE cables in the main control board panel. Two examples are. cables 558207AJ and 5SBZO7AA.
- Cables 4SBS08AB, 45B50888, and 4EM117BA (Class IE) are within 2 6 inches of cables 15850848, 158508CB, and IEM117AA (redundant Class IE group) in the main control board panel, i Bechtel sent to the NRC inspector, Startup Field Report (SFR) 1-RL-31 which details additional separation violations in the control room. This
' SFR, along with the examples noted by the NRC, show a widespread problem '
in internal panel and cabinet electrical separation.
The above examples are a violation of Criterion V of Appendix 8 to l 10 CFR Part 50. (482/8422-02)
The NRC inspector also observed several installations of flexible
- electrical conduit which had the required 1 inch separation, but due to j certain postulated events could violate the separation criteria. The installations noted were those where the flexible conduit dropped in air j; from rigid conduit to safety-related equipment. During events such as
{ equipment vibration, transmitted hydrodynamic loads, or seismic events, the flexible conduits could come within 1 inch of redundant conduit. The
- following cases were observed
!
- Flex conduit IJ1033 (Class IE) crosses flex conduit 5U1378 (Non-Class l IE) at pumps OP-EM-01A in Centrifugal Charging Pump Room A.
.
- Flex conduit IJ1035 (Class IE) crosses flex conduit 5J1258 (Non-Class j IE) at pump DP-EM-01A in Centrifugal Charging Pump Room A.
- Flex conduit IUCIU (Class IE) crosses flex conduit 4U1228 (Non-Class
! IE) at pump DP-EM-01A in Centrifugal Charging Pump Room A.
- Flex conduit 4U1297 (Class IE) crosses flex conduit 6J1139 (Non-Class
- IE) at MSIV AB-HV-011 in the main steam isolation valve room.
- Flex conduit 4U1295 (Class IE) crosses rigid conduit 1U1113 (redundant Class IE group) at MSIV AB-HV-014 in the main steam isolation valve room. .
- computer cabinet RJ159A and flex conduit 6J1055 (Non-Class IE) at top entry to cabinet RJ159A in the north electrical penetration room.
1 l These examples' need to be evaluated by the licensee for safety significance and generic implications. Pending this evaluation, this item is considered unresolved. (482/8422-03) 4 e
, ,. m. - __,- , _ _ _ . . , _ . _ .,. - . _ . . . - _.--_.,_~,,,.w.,____-..._._, m, . . _ _ _ , . - .. . . - - . . . , , , _ . _ .
- 5. As-Built verification of Electrical Raceways The NRC inspectors selected several Class IE conduit and cable tray runs located in the reactor building, control building, 'a nd auxiliary building for verification of actual installation against the latest approved design drawings. The inspection was limited to an examination of the following:
- Location and routing
- Supports
- Separation
- Loading (cables physical and thermal)
- Identification (conduit and tray)
Additional inspections will be performed by other NRC inspectors at a later time. A total of 765 feet of cable tray and 335 feet of conduit were inspected.
The following is a list of documents examined:
- Bechtel Drawing E-1R1411, Revision 0, dated Apr11 16, 1984,
" Raceway Plan - Auxiliary Building - Area 1. E1. 2026'-0" "
- Bechtel Drawing E-1R1421. Revision 2, dated June 15, 1984, " Raceway Plan - Auxiliary Building - Area 2, E1. 2026'-0" "
- Bechtel Drawing E-1R1441. Revision 2, dated April 26, 1984, " Raceway Plan - Auxiliary Building - Area 4. E1. 2026'-0" "
- Bechtel Drawing E-1R1431 Revision 0, dated June 15, 1984, " Raceway Plan - Auxiliary Building - Area 3 E1. 2026'-0" "
- Bechtel Drawing E-IR1433A, Revision 2, dated June 23, 1984, " Exposed Conduit - Auxiliary Building - Area 3 E1. 2026'-0" "
e Bechtel Drawing C-1R1443C, Revision 2, dated July 11, 1984, " Exposed Conduit - Auxiliary Building - Area 4. El. 2026'-0" "
- Bechtel Drawing E-1R3711. Revision 1, dated June 28, 1984, " Raceway Plan - Control Building - Area 1. E1. 2073'-6" "
- Bechtel Drawing E-1R3512., Revision 3, dated June 23, 1984, " Raceway Plan - Control BuildinD - Area 1 El. 2032'-0" "
- Bechtel Drawing E-OR3714, Revision 6, dated October 18, 1902,
" Exposed Conduit - Control Butiding - Area 1. E1. 2073'-6" "
~12-
^
- 8echtel Orawing E-1R3514, Revision 4, dated October 4,1984, " Exposed Conduit - Control Building - Area 1. E1. 2032'-0" "
- 8echtel Orawing E-IR2423, Revision 0, dated May 31, 1984, " Raceway Partial Plan - Reactor Building - Area 2, E1. 2026'-0" "
- 8echtel Drawing E-IR2421. Revision 2, dated August 4, 1984, " Raceway Plan - Reactor Building - Area 2, E1. 2026'-0" "
- Bechtel Drawing E-1R2411, Revision 1, dated May 3,1984, " Raceway Plan - Reactor Building - Area 2 E1. 2026'-0" "
- Bechtel Drawing E-1R8900, Revision 1, dated July 11, 1984, " Raceway Notes, Symbols and Details" The following Bechtel typical cable tray support details were reviewed:
- C-0401, Revision 14, dated January 13, 1984
- C-0402, Revision 15, dated March 6,1984
- C-0403, Revision 19, dated February 22, 1984
- C-0404, Revision 18, dated April 26, 1984
- C-0405, Revision 9, dated April 24, 1984
- C-0408. Revision 0, dated June 28, 1984
- C-0409, Revision 13, dated April 26, 1984
- C-0411, Revision 8, dated November 4,1983
- C-0434, Revision 9, dated April 20, 1983
- C-0420 Revision 4, dated October 13, 1983 In addition, the following 8echtel typical conduit support details were examined:
- C-0601, Revision 18, dated February 22, 1984
- C-0602, Revision 19, dated April 16, 1984
- C-0603, Revision 13, dated February 7, 1984
- C-0604 Revision 17, dated May 14, 1984
- C-0605, Revision 17, dated March 6, 1984
= 's ;
The NRC inspectors noted the following discrepancies during the inspection of cable trays and conduit:
- A loose bolt where'the P1068 angle clip attaches the P1001 horizontal brace to the P1001 vertical brace at tray support 142-0058 at elevation 2026'-0" in the auxiliary building.
- The angle clips for trays 4U3852 and 4J3852 on support 143-0026 are 3\ inches in length versus the required 4 inches. These are located at elevation 2026'0" in the auxiliary building.
- Tray 4C8F87 has three out of four P-1068 angle clips missing on its two supports at elevation 2073'-6" in the control building.
- Cable IRPY10AA is unterminated, coiled, and supported by cable ties instead of required supporting material. This cable is located above tray IC8F58 at elevation 2032'-0" in the control building.
The discrepancies were shown to Daniel QC personnel who confirmed the first two discrepancies. A work order is being issued to correct them.
Daniel showed the NRC inspector that tray 4C8F87 was connected to the vertical support by direct bolting as allowed by an alternate support detail. Cable IRPY10AA was found to be a deleted cable. These discrepancies represent isolated cases considering the large number of supports inspected. No further action is required.
- 6. As-Built Verification of Electrical Cables The NRC inspectors selected thirteen Class 1E electrical cables to verify that routing and separation conformed to design documents. The following cables were inspected:
Cable Tray System 1AL103AA Instrumentation Aux. Feedwate r IALG02C8 Control Aux. Feedwater IALG04CB Control Aux. Feedwater IB8G39AC Control Reactor Coolant 18B538AA Instrumentation Reactor Coolant IGNG02CC Power Containment Cooling 1GNG02CG Power Containment Cooling 3GNG02AC Power Containment Cooling 1GNG02AG Power Containment Cooling l INGG01AJ Power 480V Syster INGG018F Power 480V Systes 4585010A Instrumentation Reactor Protection 4585048A Control Reactor Protection There were no violations or deviations identifiedi
l
\ 7. Review of Procedures (Penetration Fire Seals)
The NRC inspector reviewed the B&B Insulation, Inc., procedures for the installation of Radfiex (flexible fire-radiation barrier) and High Density l
Lead Elastomer (solid fire and radiation barrier). These documents were examined to assure compliance with NRC requirements and licensee comitner.ts.
The following B&B procedures were examined:
1030.112 " Installation Procedures - B&B Insulation. Inc. -
~
Radflex Seal", Issue F, dated February 16, 1984
~
1030.114. " Installation of B&B Insulation Radfiex Sealant Material Using a Mono-Pump Dispensing System". Issue 0, dated May 2, 1984 1030.212. " Proprietary - Proportioning, Pre-Batching and Blending B&B
- Radflex Components A&B for Mono-Pump Application" 1700.101, " Installation of Hi-Density Leaded Matrix", B. Issue, dated February 16, 1984 1703.102, " Repair, of High Density Leaded Elastomer Penetration",
D !ssue, dated February 16, 1984 1700.121 " Installation of Hi-Density Leaded liatrix Annulus Reducing Seal s" 17C3.201, " Proportioning & Pre-Blending of B&B Hi-Density Leaded Matrix Components AAB", B Issue, dated February 27, 1984 No violttions or deviations were identified.
l C. Revient c' Nonconformance Reports, Design Change Notices arid Field Change Requests (Safety-Related Conduits and Cable Trays)
The NRC inspector reviewed eight Daniel Construction Inc., Field Change Requests, three nonconfomance reports and five design change notices relative to the installation.of safety-related conduits and cable trays.
The documents were reviewed to detemine whether the records were legible, complete, reviewed by QC personnel, readily retrievable and reflect "as-built" conditions of safety-related conduit and cable trays. In addition, the records were examined to detemine whether nonconformances and changes were adquately described and included in the status of the corrective action or resolution.
t _ _ _ _ . _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ -
. > (
The following records were examined:
NCR's DCN's FCR's 15N17957E C-0404(Q)15 1-5187-E ISN17323E C-0404(Q)14 1-5246-E ISN4986E C-0404(Q)10 1-5133-E C-0404(Q)9 1-5261-E C-0404(Q)8 1-5370-E 1-5236-E 1-5466-E 1-5441-E No violations or deviations were identified.
- 9. Interviews with Electrical Termination Personnel The NRC inspectors interviewed two DIC personnel who performed actual terminations of Class IE electrical cable. The two employees' training records were reviewed also. Both exhibited adequate technical knowledge as well as the understanding of procedure requirements.
No violations or deviations were identified.
- 10. Unresolved Items Unresolved items are matters which require more information to ascertain whether they are acceptable items, violations, or deviations. One unresolved item is identified in paragraph 4.
- 11. Management Interview The NRC personnel met with licensee and DIC management persannel as noted in earlier paragraphs of this report. The NRC personnel met with the licensee personnel noted in pagraph 1 to express the full results and conclusions pertaining to this inspection.
.