ML20135H305

From kanterella
Jump to navigation Jump to search
Final ASP Analysis - Perry (LER 440-93-010)
ML20135H305
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 05/14/2020
From: Christopher Hunter
NRC/RES/DRA/PRB
To:
Littlejohn J (301) 415-0428
References
LER 440-1993-011, LER 440/1993-010
Download: ML20135H305 (14)


Text

A. 13-1 A. 13 LER Nos. 440/93-011 and -010 Event

Description:

Clogged Suppression Pool Strainers and Service Water Flood Date of Event: March 26, 1993 Plant:

Perry A. 13.1 Summary During a maintenance outage in January 1993, the Perry residual heat removal (RHR) suppression pool suction strainers were found to be deformed because of excessive differential pressure caused by strainer fouling during normal RHR pump operation. The suppression pooi was partially inspected and cleaned, and the deformed strainers were replaced.

On March 26, 1993, the reactor was scrammed following a rupture in a 30-in, service water (SW) line.

Condenser vacuum was lost, the main steam isolation valves (MSIVs) were closed, and cavitation problems were experienced with a control-rod drive (CRD) pump. The reactor core isolation cooling (RCIC) system was used for pressure vessel makeup. Water from the break entered numerous plant buildings, accumulating in the lowest level of the auxiliary building and control complex, where safety-related equipment is located.

No safety-related equipment was impacted by the flood.

Three weeks later, the RHR suppression pool strainers were again inspected. One of the strainers was fouled and deformed. Excessive differential pressures across the RHR strainers from debris accumulation would have failed suppression pooi cooling (SPC) if this mode of RHR was required to operate for long periods of time. The conditional core damage probability estimated for this event is 1.2 x 10-. The relative significance of this event compared to other postulated events at Perry is shown in Fig. A. 13. 1.

LER 440/93-011 1 E-7 1 E-6 1 E-5 I E-4 I1E-3 1 E-2 LLOF~wwHPCS L

-30hE 360 h HPCS & RCIC LOOP

-"-Precursor Cutoff Fig. A. 13. 1 Relative event significance of LER 440/93-011 compared with other potential events at Perry A. 13.2 Event Description When the Perry suppression pool was inspected in May 1992, an accumulation of dirt and debris was noticed on the suction strainers for RHR trains A and B. strainer cleaning was scheduled for a later date, since RHR system performance was considered acceptable based on surveillance testing.

The suppression pool strainers were again inspected and cleaned during a maintenance outage in January 1993. RHR train A and B suction strainers were found to be deformed, with the area of the strainer surface between internal stiffeners partially collapsed inward, in the direction of system flow. It was LER Nos. 440/93-011 and -010

A. 13-2 determined that the strainers were deformed by excessive differential pressure caused by strainer fouling during normal pump operation. Review of a videotape taken during the May 1992 inspection revealed evidence of deformation that had not been noticed at the time of the taping. The containment side of the suppression pool was inspected and cleaned in February 1993, and the deformed strainers were replaced.

On March 26, 1993, the reactor was scrammed at 1526 hours0.0177 days <br />0.424 hours <br />0.00252 weeks <br />5.80643e-4 months <br /> in response to a rupture in a 30-in. SW line.

A leak of unknown origin had been detected at 1314 hours0.0152 days <br />0.365 hours <br />0.00217 weeks <br />4.99977e-4 months <br />, coming from under concrete slabs south of the water treatment building. At 1522 hours0.0176 days <br />0.423 hours <br />0.00252 weeks <br />5.79121e-4 months <br />, a low SW discharge pressure alarm annunciated in the control room and flow from the break increased substantially. An alert was declared at 1535 hours0.0178 days <br />0.426 hours <br />0.00254 weeks <br />5.840675e-4 months <br />, about 12 min after the trip and about 16 min after the rupture probably occurred. The total break volume was approximately 1.7 million gal. Approximately 5% of the total leakage entered the auxiliary, intermediate, diesel, turbine, radwaste, and offgas buildings, as well as the control complex, via electrical manway number I at the northwest corner of the radwaste building and by flowing under roll-up and access doors on the west side of the plant. Water levels reached during the flood did not impact safety-related equipment.

Flooded building areas included:

Auxiliary..Buildinig. A maximum of 5 in. of standing water was reported on elevation 568 ft (lowest level).

Water depths of less than 20 in. on this level will not compromise the operability of safety-related equipment.

Flooding on elevation 599 ft resulted in leakage into the high-pressure core spray (HPCS) room through the ceiling hatch plugs. The water dripped on the HPCS pump motor, but the motor was not damaged.

Intermediate Building. Water levels of up to 5 in. were reported on elevation 574 ft. Due to the heavy silt content of the flood water, the drains in this building backed up.

Co~ntrol Complex. Water levels up to 5 in. were reported on elevation 574 ft. Equipment required for safe shutdown and control room habitability is located at 22 in.

Emergency SW Pump House. The floor of this building was wet or covered with silt. Additionally, the motor-driven fire pump controller was wet but not damaged. Water was also found in an unused Unit 2 motor control center.

Condenser vacuum was lost following the shutdown of the SW system. This required closure of the MSIVs and the use of the safety relief valves (SRVs) for reactor pressure control. The RCIC was placed in service for reactor makeup, and both trains of the RHR system were started at 1552 hours0.018 days <br />0.431 hours <br />0.00257 weeks <br />5.90536e-4 months <br /> for suppression pool cooling. At 2014 hours0.0233 days <br />0.559 hours <br />0.00333 weeks <br />7.66327e-4 months <br />, shutdown cooling (SDC) was established using RHR train A. RHR train B continued to provide SPC for an additional 5 h. RCIC was secured and the CRD system was used for level control.

The A CRD pump experienced minor cavitation due to loss of suction. The unit reached cold shutdown at 2210 hours0.0256 days <br />0.614 hours <br />0.00365 weeks <br />8.40905e-4 months <br />.

On April 14, 1993, all emergency core cooling systems (EGGS) strainers were inspected using a high-powered light and video camera. The RHR train B strainer was fouled and deformed in a manner similar to that observed during the January inspection. The remaining strainers showed no signs of fouling.

Without disturbing the debris on the strainer, a test run of RHR pump B was performed. The pump running suction pressure decreased to 0 psig after operating for 8 h, and the pump was secured.

The pump suction strainer was then inspected. The debris from the strainer was analyzed, and it was determined that the debris contained fibrous material and corrosion products. The predominant fibrous material was glass fiber from roughing filter material used in the drywell air cooler system. The RI-R LER Nos. 440/93-011 and -010

A. 13-3 strainer provided a structural framework for a uniform covering of the fibrous material, which in turn acted as a filter for suspended solids that would have otherwise passed through the strainer.

The licensee inspected and cleaned the containment following the discovery of the clogged strainers and did not identify large quantities of the fibrous material. Based on this, the licensee concluded that there was no chronic degradation of properly installed filter media. Instead, the licensee concluded that the fibrous material entered the suppression pool as intact pieces as a result of installation or maintenance activities (the roughing filters are normally replaced prior to startup 'from refueling outages). These pieces subsequently broke down to fibers once in the suppression pool. The actual time the material entered the suppression pool could not be determined.

The suppression pool was completely inspected and cleaned following the discovery of the clogged strainers.

This was the first thorough inspection and cleaning since initial criticality in 1986. Previous inspection and cleanup efforts were limited to easily visible and accessible pooi areas.

Additional information concerning this event are included in NRC Bulletin 93-02, Supplement 1, Debris Plugging of Emergency Core Cooling Suction Strainers, February 18, 1994, and Augmen ted Inspection, Team (AIT) report 50-440/93006(DRS), Perry Unit 1 Service Water Pipe Break, April 15, 1993.

A. 13.3 Additional Event-Related Information Systems available at Perry for reactor vessel high-pressure makeup include RGIG, HPGS, and the CRD pumps, as well as main feedwater (MFW). In the event that these systems are unavailable, the automatic depressurization system (ADS) is used to depressurize the reactor to the point where low-pressure systems can provide makeup. Low-pressure systems include low-pressure core spray (LPGS) and low-pressure coolant injection (LPCI).

Two of the three LPGI trains include heat exchangers and piping to remove he at from the suppression pool (suppression pool cooling mode of RHR [RHR/SPC]) and directly from the core (shutdown cooling mode of RHR [RHRISDC]). The strainers that were found clogged during this event were associated with the two LPGI trains that can be used for RHR.

In the event that RHR fails, the containment can be vented to remove decay heat *and prevent overpressurization. To achieve this, the operator manually vents the suppressio'n pool 'or the drywell. The steaming that will occur in the suppression pool may fail any injection source (such as 'LPCI) that draws from the suppression pool. Therefore, the feed operation associated with venting must come from an injection system that operates at low pressure and whose source of water is other than the suppression pool.

Flooding of the auxiliary building 568-ft basement level will not directly affect major ECCS compo Inents,.

as each of the RHR, HPCS, LPGS, and RGIG pumps are located in a separate room on the 574-ft level and protected by a watertight door. However, the local panels for all these pumps are mounted in the base ment corridor (20 in. above the floor, based on information in the ALT report) except for the HPGS panel, which is at the 574-ft level. Flooding of the corridor will fail the EGGS pumps once water reaches the local panels.

Flooding will also lead to loss of the ADS permissive; however, this can be bypassed by the operator in the control room.

Flooding of the control complex 574-ft elevation will result in loss of the instrument air compressors (12 in.,

above the floor), control complex chilled water pumps which provide ventilation cooling for the battery and switchgear rooms and control room (22 in. above the floor), and emergency closed cooling (EGG) system pumps (22 in. above the floor). The EGG system provides cooling water to the RGIG, LPGS, and RHR LER Nos. 440/93-011 and -010

A. 13-4 pump room coolers and to the RHR pump seals, as well as to the control complex chillers. Although flooding did not reach 12 in. above the 574-ft elevation, instrument air was lost during the event.

A. 13.4 Modeling Assumptions Excessive differential pressure across the RI-R strainers from debris accumulation would fail SPC and could fail LPCI if it was required to operate for long periods of time. The event was modeled as an unavailability of RHRISPC following (1) postulated initiators in the 1 -year period prior to discovery of the clogged strainers and (2) the reactor trip following the SW pipe rupture on March 26, 1993. The possibility of flooding damage to EGGS components was addressed in a sensitivity analysis.

Case 1. Unavailability of RHR/SPC cooling following postulated initiating events. The potential for plugging the suppression pool strainers existed prior to the May 1992 refueling outage. To estimate the relative significance of the event within a 1 -year observation period (the interval between precursor reports), a 1-year observation period was used in the analysis (6132 hours0.071 days <br />1.703 hours <br />0.0101 weeks <br />0.00233 months <br />, assuming the plant was critical or at hot shutdown 70% of the time). Based on the strainer deformation and clogging observed in 1992 and 1993, both trains of RHRISPC were assumed to be failed and not recoverable for long-term decay heat removal.

LPCI injection and short-term SPC prior to initiation of RHRJSDC were assumed to be operable (RIIR train B suction pressure decreased to 0 psig after 17 h of operation following the SW flood). The unavailability of RHRISPC affected sequences on each of the three ASP models: transient, Ioss-of-offsite power, and small-break loss of coolant accident. The reactor trip frequency utilized in the transient model was not reduced to reflect the trip following the SW pipe rupture analyzed in Case 2. A nominal reactor trip frequency was used in the analysis.

The existing ASP model was modified to include the potential use of containment venting for decay heat removal in the event that both RH-R/SPC and RI-RISDC fail. This was done by revising the dominant sequences involving failure of both RHR cooling modes to also include failure to vent the containment. The probability of failing to vent was assumed to be dominated by human error. A probability of 0. 01 was utilized for sequen ces in which the source of water for injection is separate from the suppression pool.

For sequences in which the injection source takes suction from the suppression pool (such as LPCS or LPCI), an alternate injection source, the CRD pumps or essential SW (RHRSW in the ASP models), must be aligned for injection following venting. Venting is considered much less reliable in such cases; an operator error probability of 0.5 was utilized (see NRR Daily Events Evaluation Manual, 1-275-03-336-01, January 31, 1992).

The current ASP models do not address the potential use of RCIC for reactor vessel (RV) injection in the event of a failed-open SRV. Thermal-hydraulic analyses performed in support of a number of contemporary probabilistic risk assessments indicate that RCIC can provide injection success provided only one SRV fails open. The conditional probabilities for sequences involving failed-open relief valves were revised to reflect the probability that RCIC must also fail or two or more SRVs must fail open before high-pressure RPV makeup fails. This probability was estimated as:

p(RCIC) + p(2 or more SRVs fail open I 1 or more SRVs fail open).

This approximation assumes that sequences involving RCIC success avoid core damage if RHR is also successful. Since the probability of RHR failure is very small relative to the probability of failing RCIC, this approximation is valid. The failure probability for RCIC during this event was estimated at 0.042. A value of 0.024 was estimated for p(2 or more SRVs fail open I 1 or more SRVs fail open), based on an estimated probability for two or more SRVs failing open of 0.0015 (see NUREG/CR-4550, Vol. 1, Rev. 1, LER Nos. 440/93-011 and -010

A. 13-5 Analysis of Core Damage Frequency: Internal Events Methodology, January 1990, pp. 6-10) and an estimated probability of one or more SRVs failing open of 0.0627 (this is developed in Appendix C of NUREG/CR-4674, Vol 1, Precursors to Potential Severe Core Damage Accidents: 1985, A Status Report, December 1986). The estimated probability of one or more SRVs failing open is dependent on the number of valves at a given plant and the probability of an SRV failing to close per demand. The probability of RCIC failure or more than one SRV failed open is then 0.042 + 0.024 = 0.066. RCIC can also provide makeup following a steam-side, small-break, los's-of-coolant accident (LOCA). Consistent with other ASP analyses, the probabilIity of a steam-side LOCA was assumed to be 0. 6. The probability of RCIC failing to provide RPV makeup following a small break LOCA is, therefore, (1-0.6) + 0.042 =0.442.

Case 2. Reactor trip, effective loss of MFW, CRD pump problems, and unavailability of RHRISPC.

Following the reactor trip and SW system shutdown, condenser vacuum was lost and the MSIVs were closed.

This resulted in unavailability of the power conversion system (PCS) for decay heat removal and the MFW and condensate systems for RV makeup. The CRD system was used for makeup after RCIC was secured; CRD pump A cavitated due to loss of suction. Because of the cavitation problems with the A pump, the CRD system was assumed to be unavailable for RV makeup in the short term (two-of-two CRD pumps are required for success) had it been needed in the event of failure of HPCS and RCIC. In addition, long-term RHR/SPC was also unavailable, as described in Case 1.

Analysis assumptions concerning the potential use of RCIC following a failed open SRV and containment venting were the same as for Case 1. Although C RD flow for short-term RV makeup was assumed unavailable because of cavitation problems with the pump A, CRD was assumed available for makeup following venting.ý One-of-two pumps provides success in this situation, since the decay heat load is lower.

If SW had not been secured, continued flooding of the auxiliary building and control complex could have resulted in damage to ECCS components. As described in Additional Event-Related Information, the LPCS, RHR, RCIC, and ECC system pumps would have been impacted had the water level reached 20-22 in. in these buildings (flood levels reached 5 in. during the actual event). The lack of detailed information concerning equipment locations and flood pathways prevents consideration of potential flooding effects in this analysis (operational events involving flooding are normally considered impractical to analyze in the ASP program because there is a lack of detailed information). However, a sensitivity analysis was performed to bound the potential effects of the flood.

The sensitivity analysis considered, in addition to the system unavailabilities described in -Case 2, the unavailability of the RHR (LPCI and RHRISDC as well as SPC already lost because of the suction strainer problems) and RCIC pumps if flooding reached 20-22 in. in the auxiliary building and control complex.

To simplify the sensitivity analysis, these pumps were assumed unavailable and not recoverable if flooding reached this height. Based on information from the licensee, the LPCS pump was assumed to remain operable, although its room cooling would have been unavailable following the loss of the ECC pumps (this assumption has little affect on the sensitivity analysis results).

The probability of failing to secure SW prior to release of sufficient water to impact the RHR and RCIC pumps was estimated using the following assumptions:

  • The rate of auxiliary building and control complex flooding was constant and therefore the time required before sufficient SW was released to reach 20-22 in. was approximately four times the actual flood duration. This assumption is subject to large uncertainties since details of the flooding pathways are not known.
  • The compelling cue for SW shutdown was the observation of significant flooding of plant buildings at 1535 h, 14 min after the increase in break flowrate. The SW system was shut down 5 min later. Based on these times and the fact that water levels reached one-quarter of the height LER Nos. 440/93-011 and -010

A. 13-6

  • required for damage, break flow must be terminated -62 min following the cue to prevent damage to EGGS pump control panels in the auxiliary building basement corridor. Control panel flooding would fail WGC. Djamage to the EGG pumps in the control complex, which would impact RHR pump seal: cooling and EGGS pump room cooling, would shortly follow.
  • The observed time to secure SW (5 min) was Assumed to be the median of a lognormal distr-ibution with an error factor of 3. 2 (see Dougherty and Fragola, Human Reliability Analysis, John Wiley And Sons, New York, 19,88, Chapter 10). This is the error factor for time-reliability correlatiohs (TRCs) for actions without hesitancy, which is considered appropriate based on the nature of the flood and the fact that the SW system is not safety-related at Perry. The resulting probability of failing to sec~ure SW before RHR and RCIC pump impact is 1.9 x 10 -4 During the Actual event, the HPCS pump motor was wetted by Water dripping from a ceiling hatch plug; how~ever the pump was not dainaged. A separate sensitivity analysis was performed assuming the HPGS p-u Imp.w -as. unavailable and,not recoverable during the actual event and during postulated flooding to understand the impact of such potential damage'ý VFiV core damage probability calculation sheets document the analysis. Case I addresses unavailability of kiU-k/SPC for a 1 -year period. Case 2 addresses the reactor trip, loss of condenser vacuum, and GRD Pro;bletns following the SW pipe rupture.,The conditional core damage probability for the event was estimalted by modifying the sequence conditional probabilities to reflect the potential use of RCIC in the event of A single faifled-open SRV and the use of containment venting for long-term decay heat removal (indicated iiwithd notes At the end of eac~h calculation sheet) and summing the conditional probabilities for the two, cases. The three calculation sheets for the potential flooding-inipacts and HPG S-unavailtable sensitivity Analyses are also inicluded.

A.. 0. 5 Analysis Results The condit.ional core damage probability estimated for this event is 1.2 x 10-4 The donfinant core damage sequence, highlighted on the event tree shown in Fig. A. 13.2, 'involves a scram with PCS and FW unavailable followihg the SW pipe rupture, HPCS success, failure of long-term decay heat removal via the RPR system, and failure to vent the containment.

The results of the sensitivi Ity analysis to address potentialI flooding effects indicates a core damage probability of 2. 5 X ý 010 given the rupture. This is small compared to the overall core damage probability for the event, indicatintg that potential flooding effects do not significantly contribute to the overall event, based on inoraiont available in the LER and AlTiniiit report. The flood is interesting, however, since it impacted multiple, buildings that would typically be considered independent structures in an internal flooding risk Analysis.

if the H4PC'S pump motor had been damaged by the water that dripped from the ceiling hatch, the estimated 4

core damage probability would be 8.5 x 10- (including the suppression pool strainer unavailability), a much more significant event.

ILER Nos. 440/93-011 and 1-010

A. 13-7 OK Ok 12 Co OK OK.

Cý o

OK OF Is Co OK le Co OK 17 C

OK OK OK OK 22 CO 9x ON 91i OK

24.

Co OK F5 CO RK 2K CO 27 CO 25 CD OK 210 CI) ox OiK 39 O

OK OK SI Co OK OK 22 CO OK OK 33

  • CO OK C K 44 CID OK.

35 go Ox 30 CO Fig. A. 13.2 Dominant core damnage sequence for LER I*

LER Nos. 440/93-011 and -010

A. 13-8 CONDITIONAL CORE DAMAGE PROBABILITY CALCULATIONS Event Identifier:

Event

Description:

Event Date:

Pt ant:

440/93-011 UnavaiLabiLity of RHR suppression poot cooLing (case 1) 03/26/93 Perry 1 UNAVAILABILITY, DURATION= 6132 NONRECOVERABLE INITIATING EVENT PROBABILITIES TRANS LOOP LOCA SEQUENCE CONDITIONAL PROBABILITY SUMS

7.

4E+00 5.3E-02 1.OE-02 End State/Initiator CD TRANS LOOP LOCA TotaL ATWS Probabi Li ty 2.OE-03(l) 4.4E-04(1) 8.8E-05(1) 2.6E-03(l)

TRANS LOOP LOCA TotaL

0.

OE+OO

0.

OE+OO

0.

OE+ 00 O.OE+00 SEQUENCE CONDITIONAL PROBABILITIES (PROBABILITY ORDER)

Sequence End State Prob N Rec**

11 trans -rx.shutdown pcs/trans srv.chatt/trans.-scram -srv.ctose

-fw/pcs.trans rhr(sdc) RHR(SPCOOL)/RHR(SDC) 40 Loop -emerg.power -rx.shutdown srv.chatt/toop.-scram -srv.ctose

-hpci rhr(sdc) RHR(SPCOOL)/RHR(SDC) 12 trans -rx.shutdown pcs/trans srv.chatt/trans.-scram -srv.ctose fw/pcs.trans -hpci rhr(sdc) RHR(SPCOOL)/RHR(SDC) 21 trans -rx.shutdown pcs/trans srv.chaLl/trans.-scram srv.ctose

-fw/pcs.trans rhr(sdc) RHR(SPCOOL)/RHR(SDC) 71 Loca -rx.shutdown -hpci rhr(sdc) RHR(SPCOOL)/RHR(SDC) 49 Loop -emerg.power -rx.shutdown srv.chaLL/Loop.-scram srv.ciose

-hpci rhr(sdc) RHR(SPCOOL)/RHRCSDC) 22 trans -rx.shutdown pcs/trans srv.chatL/trans.-scram srv.ctose fw/pcs.trans -hpci rhr(sdc) RHR(SPCOOL)/RHR(SDC) 41 Loop -emerg.power -rx.shutdown srv.chatt/Loop.-scram -srv.cLose hpci -rcic rhr(sdc)

RI4R(SPCOOL)/RHR(SDC) 13 trans -rx.shutdown pcs/trans srv.chaLL/trans.-scram -srv.cLose fw/pcs.trans hpci -rcic rhr(sdc) RHR(SPCOOL)/RHR(SDC) 65 Loop emerg.power -rx.shutdown/ep -ep.rec srv.chaLL/Loop.-scram

-srv.cLose -hpci rhr(sdc)/-Lpci RHR(SPCOOL)/-LPCI.RHR(SDC) 72 Loca -rx.shutdown hpci -srv.ads -Lpcs rhr(sdc) RHR(SPCOOL)/RFI R (SDC) 50 Loop -emerg.power -rx.shutdown srv.chaLL/Loop.-scram srv.cLose hpci -srv.ads -Lpcs rhr(sdc) RHR(SPCOOL)/RHR(SDC)

    • nonrecovery credit for edited case SEQUENCE CONDITIONAL PROBABILITIES (SEQUENCE ORDER)

CD CD CD CD CD CD CD CD CD CD CD CD 1.7E-03(1) 3.2E-01 4.1E-0401) 1.8E-01 1.8E-04(1) 1-2E-01 1.1E-0401) 3.2E-01 8.7E-0501) 1.7E-01 2.8E-05(1) 1.8E-01 1.2E-05(1) 1.2E-01 2.7E-0601) 6.OE-02 1.2E-06(l) 3.9E-02 6.9E-0701) 5.9E-07(l )

1.4E-01 5.7E-02 1.8E-07(1) 6.1E-02 LER Nos. 440/93-011 and -010

A. 13-9 Sequence End State Prob N Rec**

11 trans -rx.shutdown pcs/trans srv.chall/trans.-scram -srv.cLose

-fw/pcs.trans rhr(sdc) RHR(SPCOOL)/RHR(SDC) 12 trans -rx.shutdown pcs/trans srv.chatl/trans.-scram -srv.cLose fwlpcs.trans -hpci rhr(sdc) RHR(SPCODL)/RHR(SDC) 13 trans -rx.shutdown pcs/trans srv.chaLL/trans.-scram -srv.close fw/pcs.trans hpci -rcic rhr(sdc) RHR(SPCOOL)/RHR(SDC) 21 trans -rx.shutdown pcs/trans srv.chall/trans.-scram srv~close

-fw/pcs.trans rhr(sdc) RHR(SPCOOL)/RHR(SDC) 22 trans -rx.shutdown pcs/trans srv.chall/trans.-scram srv.close fw/pcs.trans -hpci rhr(sdc) RHR(SPCOOL)/RHR(SDC) 40 loop -emerg.power -rx~shutdown srv.chall/loop.-scram -srv.close

-hpci rhr(sdc) RHR(SPCOOL)/RHR(SDC) 41 loop -emerg.power -rx.shutdown srv.chaLL/Loop.-scram -srv.close hpci -rcic rhr(sdc) RHR(SPCOOL)/RHR(SDC) 49 Loop -emerg.power -rx.shutdown srv.chaLL/Loop.-scram srv.close

-hpci rhr(sdc) RHR(SPCOOL)/RHR(SDC) 50 loop -emerg.power -rx.shutdown srv.chaLL/Loop.-scram srv.cLose hpci -srv.ads -Lpcs rhr(sdc) RHR(SPCOOL)/RHR(SDC) 65 Loop emerg.power -rx.shutdown/ep -ep.rec srv.chaLL/loop.-scram

-srv.close -hpci rhr(sdc)/-lpci RHR(SPCODL)/-LPCI.RHR(SDC) 71 loca -rx.shutdown -hpci rhr(sdc) RHR(SPCOOL)/RHR(SDC) 72 loca -rx.shutdown hpci -srv.ads -Lpcs rhr(sdc) RHR(SPCOOL)/RH R(SDC)

CD CD CD CD CD CD CD CD CD CD CD CD 1.7E-03(1) 3.2E-01 1.8E-04(1) 1.2E-01 1.2E-06(1) 1.1E-04(1) 3.9E-02 3.2E-01 1.2E-0501) 1.2E-01 4.1E-0401) 1.8E-01 2.7E-060I) 6.OE-O2 2.8E-0501) 1.8E-01 1.8E-07(l) 6.9E-0701

8.

7E -05 (1 5.9E-0701

6.

1E-02 1A.E-O1 1.7E-01 5.7E-02 nonrecovery credit for edited case Note:

For unavailabiLities, conditional probability values are differential values which reflect the added risk due to failures associated with an event. Parenthetical values indicate a reduction in risk compared to a similar period without the existing failures.

SEQUENCE MODEL:

BRANCH MODEL:

PROBABILITY FILE:

No Recovery Limit s: \\asp\\prog\\mode Is\\bwrcsea I.

cmp s: \\asp\\prog\\models\\perry.s 11 s: \\asp\\prog\\mode Is\\bwr cs 11.

pro BRANCH FREQUENCIES/PROBABILITIES Branch trans loop loca rx.shutdown rx.shutdown/ep pcs/trans srv.chaLl/trans. -scram srv.chaIL/Loop.-scram srv.c lose emerg.power ep. rec fw/pcs~trans fw/pcs. Loca hpc i rcic crd srv. ads I

pcs Lpci(rhr)/Lpcs rhr(sdc) rhr(sdc)/- Lpci rhr(sdc)/Lpci RHR(SPCOOL)/RHR(SDC)

Branch Model:

1.OF.1 Train 1 Cond Prob:

RHR(SPCOOL)/-LPCI.RHR(SDC)

Branch Model:

1.OF.1 Train 1 Cond Prob:

RHR(SPCOOL)/LPCI *RHR(SDC)

System 1.2E-03 1.6E-05 3.3E-06 3.OE-05 3.5 E-04 2.3E-01 1

.DOE+OO 1 O0E+00 6.3E-02 2.9E-03 1.7E-01 2.8E-01 1.OE+OO

2.

OE-02 6.OE-02 1.OE-02

3.

7E-03 2.OE-02 6.DE-04 2.3E-02

2.

OE-02 1.OE+OO 2.OE-03 > 1.OE+OO 20OE-03 > FaiLed(2) 20OE-03 > 1.OE+OO 2.OE-03 > FaiLed(2) 9.3E-02 > 1.OE+O0 Non-Recov 1.OE+OD 5.3E-01 50OE-01 1.OE+OO 1.OE+OO 1.OE+OO 1.OE+O0 1.OE+OO 1.OE+OO 8.OE-01 1.OE+00 3.4E-01 3.4E-01 3.4E-01 70OE-01 1.OE+OO 7.1E-01 3.4E-01 7.1E-01 3.4E-O1 3.4E-01 1.OE+OO 3.4E-01 > 1.OE+OO(2) 3.4E-01 > 1.OE+OO(2) 1.OE+0O Opr Fai l 1 OE-02 1 OE-02 1.OE-03 1 OE-03 1 OE-03 LER Nos. 440/93-011 and -010

A. 13-10

  • Branch Model; 1.0F.1 Train 1 Cond Prob:

rhrsw

  • branch miodel file
    • forced 9.3E-02 > FaiLed(2) 2.OE-02 3.4E-01 2.OE-03 Notes
1. Revised core damaga probabilities reflecting the potential use of RCIC in the event of a single failed-open relief valve and containment venting for tong-term decay heat removal.

Sequence 40 12 21 71 49

.2?

41 13 65 50 p(RCIC) n/a n/a n/a n/a n/a n/a n/a n/a n/a 0.46 0.066 p(

vent) 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.5 0.5 Total p(sequence) 1J.E-05 4.1E -06 1.8E-06 1.1 E-06 8.7E-07 2.8E-07 1

.2E-07 2.7E-08 1.2E-08

6.

9E-09 1.4E-07

5.

9E-09 2.5E-05

2. Nonrecoverable failure of Long-term suppression pool cooling.

LER Nos. 440/93-011 and -010

A. 13-11 CONDITIONAL CORE DAMAGE PROBABILITY CALCULATIONS Event

Description:

SW break with effective LOFW and CRD problems (case 2)

Event Date:

03/26/93 Plant:

Perry 1 INITIATING EVENT NONRECOVERABLE INITIATING EVENT PROBABILITIES TRANS 1.0E+0O SEQUENCE CONDITIONAL PROBABILITY SUMS End State/Initiator CD Probability 8.8E-03(l) 8.8E -03(1)

TRANS Total ATWS TRANS Total 3.E-05 3.OE-05 SEQUENCE CONDITIONAL PROBABILITIES (PROBABILITY ORDER)

Sequence End State Prob 12 trans -rx.shutdown FW/PCS.TRANS -hpci 22 trans -rx.shutdown FW/PCS.TRANS -hpci 13 trans -rx.shutdown FW/PCS.TRANS hpci 28 trans -rx.shutdown FW/PCS.TRANS hpci 23 trans -rx.shutdown FW/PCS.TRANS hpci 20 trans -rx.shutdown FW/PCS.TRANS hpci 15 trans -rx.shutdown FW/PCS.TRANS hpci OL)/RHR(SDC) 99 trans rx.shutdown PCS/TRANS srv.chaLL/trans.-scram -srv.cLose rhr(sdc) RHR(SPCOOL)/RHR(SDC)

PCS/TRANS srv.chaLL/trans.-scram srv.close rhr(sdc)

RHR(SPCOOL)/RHR(SDC)

PCS/TRANS srv.chall/trans.-scram -srv.cLose

-rcic rhr(sdc)

RHR(SPCOOL)/RHR(SDC)

PCS/TRANS srv.chall/trans.-scram srv.cLose s rv. ads PCS/TRANS srv.chaLL/trans.-scram srv.close

-srv.ads -Lpcs rhr(sdc)

RHR(SPCOOL)/RHR(SDC)

PCS/TRANS srv.chall/trans.-scram -srv.cLose rcic CR0 srv.ads PCS/TRANS srv.chalL/trans.-scram -srv.close rcic CR0 -srv.ads -Lpcs rhr(sdc) RHR(SPCO CD CD CD CD CD CD CD 8.2E-0301) 5.5E-040 )

5.4E-05(1) 5.4E-06(1) 3.7E-0601) 3.4E-06(1) 2.3E-0601)

N Rec**

3.4E-01 3.4E-01 1.1E-01 2.4E-01 1.1E-01 1.7E-01 8.OE-02 ATWS 3.OE-05 1.OE+00 nonrecovery credit for edited case SEQUENCE CONDITIONAL PROBABILITIES (SEQUENCE ORDER)

Sequence End State Prob 12 trans -rx.shutdown FW/PCS.TRANS -hpci 13 trans -rx.shutdown FW/PCS.TRANS hpci 15 trans -rx.shutdown FW/PCS.TRANS hpci OL)/RHR(SDC) 20 trans -rx.shutdown FW/PCS.TRANS hpci 22 trans -rx.shutdown FW/PCS.TRANS -hpci PCS/TRANS srv.chati/trans.-scram -srv.close rhr(sdc)

RHR(SPCOOL)/RHR(SDC)

PCS/TRANS srv.chall/trans.-scram -srv.close

-rcic rhr(sdc)

RHR(SPCOOL)/RHR(SDC)

PCS/TRANS srv.chall/trans.-scram -srv.close rcic CR0 -srv.ads -Lpcs rhr(sdc)

RHR(SPCO PCS/TRANS srv.chaLL/trans.-scram -srv.cLose rcic CR0 srv.ads PCS/TRANS srv.chaLL/trans.-scram sr'v.close rhr(sdc)

RHR(SPCOOL)/RHR(SDC)

CD CD CD CD CD 8.2E-0301) 5.4E-05(1 )

2.3E-0601) 3.4E-0601) 5.5E-0401)

N Rec**

3.4E-01 1.1E-01 8.0E-02 1.7E-01 3.4E-01 LER Nos. 440/93-011 and -010

A. 13-12 23 trans -rx.shutdown PCS/TRANS srv.chall/trans.-scram srv.close FW/PCS.TRANS hpci *srv.ads -Lpcs rhr(sdc) RHR(SPCOOL)/RHR(SDC 28 trans -rx.shutdown PCS/TRANS srv.chaLL/trans.-scram srv.cLose FW/PCS.TRANS hpci srv.ads 99 trans rx.shutdown CD 3.7E-06(l) 1.1E-01 CD ATWS 5.4E-060l 3.OE-05 2.4E-01 1.OE+00

    • nonrecovery credit for edited case SEQUENCE MODEL:

BRANCH MODEL:

PROBABILITY FILE:

s :\\asp\\prog\\modelIs\\bwrcseaLI. cmp s:\\asp\\prog\\modeLs\\perry.s~l1 s :\\asp\\prog\\model s\\bwr cs 11.

pro No Recovery Limit BRANCH FREQUENC IES/PROBABILITIES Branch trans Loop I

oca rx. shutdown rx. shutdown/ep PCS/TRANS Branch Model:

1.OF.1 Train 1 Cond Prob:

srv.chaLL/trans.-scram srv.chaLL/Loop.-scram srv.c lose emerg.power ep. rec FW/PCS.TRANS Branch Model:

1.OF.1 Train 1 Cond Prob:

FW/PCS. LOCA Branch Model:

1.OF.1 Train 1 Cond Prob:

hpci rcic CRD Branch ModeL:

1.OF.1+opr Train 1 Cond Prob:

s rv. ads I

pcs Lpci(rhr)/Lpcs rhr(sdc) rhr(sdc)/- Lpci rhr(sdc)/Lpci RHR(SPCOOL )/RHR(SDC)

Branch Model:

1.OF.1 Train 1 Cond Prob:

RHR(SPCOOL)/-LPCI.RHR(SDC)

Branch Modlel:

1.OF.1 Train 1 Cond Prob:

RHR(SPCOOL)/LPCI.RHR(SDC)

Branch Modlel:

1.OF.1 Train 1 Cond Prob:

rhrsw System Non-Recov Opr Fai L 1.2E-03 1.6E-05 3.3E-06 3.OE-05 3.5E-04 2.3E-01 > 1.OE+00 2.3E-01 > UnavailabLe(3) 1.OE+OO 1.OE+OO

6.

3E-02 2.9E-03 1.7E-01 2.8E-01 > 1.OE+OO 2.8E-01 > Unavailable(3) 1.OE+OO > 1.OE+OO 1.OE+OO 2.OE-02 6.OE-02 1.OE-02 > 1.OE+OO 1.OE-02 > Failed(4) 3.7E-03 2.OE-02 6.OE-04 2.3E-02 2.OE-02 1.OE+OO 2.OE-03 > 1.OE+OO 2.OE-03 > Failed(2) 2.OE-03 > 1.OE+OO 2.OE-03 > Failed(2) 9.3E-02 > 1.OE+OO 9.3E-02 > Failed(2) 2.OE-02 1.OE+00 5.3E-01 5.OE-01 1.OE+0O 1.OE+00 1 MO+00 1.OE+OO 1.OE+0O 1.OE+00 8.OE-01 1.OE+OO 3.4E-01 > 1.OE+OO(3) 3.4E-01 > 1.OE+OO(3) 3.4E-01 7.OE-01 1.OE+OO 7.1E-01 3.4E-01 7.1E-01 3.4E-01 3.4E-01 1.OE+OO 3.4E-01 > 1.OE+OO(2) 3.4E-01 > 1.OE+OO(2) 1.OE+OO 3.4E-01 1

.OE-02 1.OE-02 1.OE-03 1.OE-03 1.OE-03

2.

OE-03

  • branch model file
    • forced LER Nos. 440/93-011 and -010

A. 13-13 Notes

1. Revised core damage probabilities reflecting the potential use of RCIC in the event of a single failed-open relief valve and containment venting for Long-term decay heat removal.

Sequence 12 22 13 28 23 20 15 p(RCIC) n/a n/a n/a 0.066 0.066 n/a n/a p(vent) 0.01 0.01 0.01 1.0 0.5 1.0 0.5 Total pC sequence) 8.2E-05 5.5E-06 5.4E-07 3.6E -07 1.2E-07 3A.E -06 1.2E-06 9.3E-05

2. Nonrecoverable failure of Long-term suppression pool cooling.
3. These unavailabilities result from the Loss of condenser vacuum and MSIV closure.
4. CRD pump "All cavitation.

LER Nos. 440/93-011 and -010

A. 13-14 CONDITIONAL CORE DAMAGE PROBABILITY CALCULATIONS Event Identifier:

Event

Description:

Event Date:

Plant:

440/93-011 SW break with LOFW, CRD problems and flood impacts (sensitivity) 03/26/93 Perry 1 INITIATING EVENT NONRECOVERABLE INITIATING EVENT PROBABILITIES TRANS 1.9E-04 SEQUENCE CONDITIONAL PROBABILITY SUMS End State/Initiator CD Probability 1.9E -04(1) 1.9E-04(1)

TRANS Total ATWS TRANS Total 5.7E-09

5.

7E-09 SEQUENCE CONDITIONAL PROBABILITIES (PROBABILITY ORDER)

Sequence End State Prob 12 TRANS -rx.shutdown PCS/TRANS srv.chall/trans.-scram -srv.close FW/PCS.TRANS -hpci RHR(SDC) RHR(SPCOOL)/RHR(SDC) 22 TRANS -rx.shutdown PCS/TRANS srv.chall/trans.-scram srv.cLose FW/PCS.TRANS -hpci RHR(SDC)

RHR(SPCOOL)/RHR(SDC) 15 TRANS -rx.shutdown PCS/TRANS srv.chall/trans.-scram -srv.close FW/PCS.TRANS hpci RCIC CRD -srv.ads -lpcs RHR(SDC)

RHR(SPCO OL)/RHR(SDC) 23 TRANS -rx.shutdown PCS/TRANS srv.chaLL/trans.-scram srv.close FW/PCS.TRANS hpci -srv.ads - lpcs RHR(SDC)

RHR(SPCOOL)/RHR(SDC 99 TRANS rx.shutdown CD CD CD CD 1

.8E -04(1) 1.2E-0501) 1.2E-06(1 )

N Rec**

1.9E-04 1.9E-04 6.4E-05 7.9E-0801) 6.4E-05 5.7E-09 1.9E-04 ATWS

    • nonrecovery credit for edited case SEQUENCE CONDITIONAL PROBABILITIES (SEQUENCE ORDER) 12 TRANS -rx.shutdown FW/PCS.TRANS -hpci 15 TRANS -rx.shutdown FW/PCS.TRANS hpci OL)/RHR(SDC) 22 TRANS -rx.shutdown FW/PCS.TRANS -hpci 23 TRANS -rx.shutdown FW/PCS.TRANS hpci 99 TRANS rx.shutdown Sequence PCS/T RAN S RHR ( SC)

PCS/TRANS RCIC CRD srv.cha[L/trans.-scram -srv.close RHR(SPCOOL )/RHR(SDC) srv.chaLL/trans.-scram -srv.close

-srv.ads -lpcs RHR(SDC)

RIIR(SPCO CD CD CD CD End State Prob 1.8E-0401) 1.2E-060 )

N Rec**

1.9E-04 6.4E-05 PCS/TRANS srv.chall/trans.-scram srv.close RHR(SDC) RHR(SPCOOL)/RHR(SDr)

PCS/TRANS srv.chall/trans.-scram srv.close

-srv.ads -lpcs RHR(SDC)

RHR(SPCOOL)/RHR(SDC 1.2E-05(1) 1.9,E-04 7.9E-08(1) 6.4E-05 5.7E-09 1.9E-04 ATWS

    • nonrecovery credit for edited case SEQUENCE MODEL:

SEQUECE MOEL:

\\asp\\prog\\mode Is\\bwrcseatI. cmp