ML20134E449

From kanterella
Jump to navigation Jump to search
Discusses Millstone 3 Concrete Problem
ML20134E449
Person / Time
Site: Millstone Dominion icon.png
Issue date: 06/22/1996
From: Blanch P
AFFILIATION NOT ASSIGNED
To: Zwolinski J
NRC
Shared Package
ML20134D719 List:
References
NUDOCS 9611010170
Download: ML20134E449 (1)


Text

- . . _ . . _ _ _ -_-__ - - - . . . _ - .

From: <VMBLANCH9aol.com>

To: WND2.WNP3(jaz),udl.internet3("JAZWOL9aol.com")

Date: 6/22/96 8:12am

Subject:

Millstone 3  !

JZ This is with respect to Millstone 3 and the concrete problem.

Paul Did you watch TV tonight? The question of repeating the SIT was floating. We must not trust allegations that chemical reactions have no effect on integrity. B.S.! Also, we should demand a new Leak Rate test (after an SIT, as is common). If you want me to review the previous ILRT and the SIT, I can do this as a courtesy. Yours l CC: WND2.WNP3(jnh),TWDI.TWP4(wjs,1jnl),WNDl.WNP2(dcd),... )

i i

i 1

1 i

l l

i 9611010170 961024 i PDR ORG NRRA l PDR

! From: <VMBLANCH9aol.com>  !

To: WND2.WNP3(jnh,jaz),TWD1.TWP4(wjs,1jn1),WND1.WNP2(d...

Date: 6/22/96 8:13am l

Subject:

MORE MILLSTONE Regulators criticize handling of Millstone By MICHAEL REMEZ and SUSAN E. KINSMAN This ran in The Courant June 5, 1996  ;

WASHINGTON -- Federal regulators responsible for overseeing Northeast Utilities' nuclear power operations now say the Millstone Point complex in Connecticut should have been put on the watch list of troubled plants much sooner than 1996 -- most likely after a serious valve leak in 1993.

The candid assessments were included in a report released Tuesday by the ,

Nuclear Regulatory Commission's independent inspector general. The report looked into whether highly critical self-analyses done by the company in 1991 were kept secret, while other, more flattering reports were made public.

NU also learned Tuesday that it faces a $100,000 fine based on accusations it discriminated against Adam P. McNiece of East Lyme, who raised nuclear safety questions at Millstone in 1994, while employed by Bartlett Nuclear Inc., an 4 NU contractor.

It was the third fine levied by the NRC against NU since 1993 for harassment and intimidation of employees who raised nuclear safety issues. NU says it did not discriminate against McNiece, who was laid off from Millstone in December 1994 and rehired in March 1996.

The federal agency's inspector general found no violation of NRC rules in keeping the 1991 documents secret. But interviews with NRC officials at the local and national levels indicate the problem-plagued plants in Waterford were given chance after chance until being put on the watch list earlier this year.

The inspector general's office investigated a complaint from Ernest Hadley, the Massachusetts lawyer who has represented several Millstone

whistle-blowers Hadley complained that the agency and the utility conspired in 1991 to keep damaging self-assessments done by NU out of the agency's public records.

But the inspector general found that the company has wide latitude under NRC regulations to determine what should or should not be made public. The company must, however, make a formal request to keep the documents secret.

Hadley said that was "the stupidest" regulation he had ever heard of. "But,"

he said, "it's entirely consistent with the NRC's history of turning over of its regulatory role to the licensees, not only with regard to public safety l

but also with the public's right to know."

Anthony Castagno, an NU spokesman, said the company wanted the 1991 reports kept confidential because they included specific names and personal information.

Castagno said NU made the findings public and announced a course of actions to respond to recurring operational problems. Part of that was creation of what was known as the Performance Enhancement Program in 1992.

"In hindsight, it is clear the enhancement program wasn't sufficient to

. resolve our problems," Castagno said.

Q(t{)0 lib 0)] f~

The inspector general's analysis shows that NRC officials repeatedly gave the company the benefit of the doubt that improvement programs would turn Millstone operations around.

They did not, however. All three units are now shut down and the NRC says they cannot be restarted until NU demonstrates each can operate in compliance .

with its license. The shutdowns are costing the company millions of dollars  !

each week in replacement power costs alone.

The report describes how the agency's senior managers discussed operating and safety problems at the Millstone plants at regular meetings from 1991 until the watch list designation this year. During those years, they noted "a '

historic emphasis on cost savings versus performance."

The investigators concluded that periodic company initiatives and management restructurings repeatedly delayed actions by the regulators. "Moreover, NU's sporadic improvements in some areas of NRC concern neutralized the staff's willingness to take prompt aggressive action," they wrote.

NRC records depict declining trends in Millstone operations starting in 1989.

The problems -- most often stemming from too little attention to license requirements and ineffective management -- crop up repeatedly.

Several officials interviewed by the inspector general's office said the extended efforts to repair a leaky steam valve in the summer of 1993 should have been the last straw. In that case, the company spent three months making repairs to a valve in Millstone 2. They hoped to avoid a costly shutdown to replace the defective parts.

Then, on Aug. 5,1993, as the repairs continued. one of four bolts holding the valve in place broke, the leak intensified ana h. agers were forced to make an emergency shutdown. If the valve had ruptured, Mdegree water would have burst out at 1,000 gallons a minute. If the reactor "usel started to drain, NU faced the possibility of a meltdown in the radioactive core.

That incident, an unnamed plant inspector told investigators, should have pushed the agency to add Millstone to its troubled plant list.

"He noted that this event was not only safety significant, but it provided the NRC with meaningful insight into NU management's performance," the report says. "He added that NU management's approach allowed the [ incident] to occur, and the event was an example of NU's disregard for safety."

Other officials, up the line to the executive director for operations who reports directly to the commissioners, offered similar assessments. Unnamed but identified by his title, James M. Taylor, the executive director, said the agency did take the unusual step of meeting with the NU board of directors in

, early 1995 about problems at the Millstone plants.

Thomas T. Martin, the regional administrator who is being moved to a desk job in headquarters in August, also agreed in hindsight that the plants should have been put on the watch list earlier. Also unnamed, but identifiable by his title, Martin said that senior managers thought until January that NU was making improvements.

Nonsense, said Hadley, who noted that the study shows senior managers were well-informed of the problems at the Waterford complex.

"This isn't asleep at the switch anymore. We've got them conscious behind l the wheel. They've moved from an agency that is neglectful to an agency knowingly condoning what is going on," Hadley said.

Commenting on speculation that Martin was being transferred because of his role in NU's troubles, Hadley said, "If someone wants to effect some change, it's going to take more than giving Tim Martin a lateral transfer. Some people should be standing in the unemployment line right now."

t l

Connecticut lawmakers said they were troubled by the findings.

Rep. Sam Gejdenson, D-2nd District, said the study raises questions of "whether the NRC can develop operating systems that tranform them from nuclear boosters to regulatorr."

Sen. Joseph I. Liebe.+'n, D-Conn., said the study shows fundamental problems in the agency's handling J its mission. He said he earlier asked the General '

Accounting Office, the investigative arm of Congress, to review the agency's '

" entire approach to inspections and performance evalution." '

In the McNiece case, the NRC also cited Bartlett Nuclear for discriminating against an employee engaged in an activity protected by federal law, but no fine was imposed because the contractor is not a nuclear licensee regulated by the agency.

In a complaint filed with the Department of Labor in May 1995, McNiece said that NU and Bartlett had " acted in concert" to keep him from working as a senior health physics technician in radiation protection after he asked questions about the day-to-day operations of the nuclear power facilities. ,

"I became a persona non grata by simply asking such things as, 'What's up i with this primary coolant in the environmental sump? Could this be a release  ;

pathway?' " McNiece said. I "The response to these questions was a growing pattern of harassment and intimidation by both management and my peers, culminating in early layoff in ,

December 1994, ostensibly for lack of work," McNiece said in his complaint to '

Labor Secretary Robert B. Reich.

McNiece said he had worked at Millstone 2 for four years straight. "My work effort kept me on board through outage and non-outage periods, even when there were very few contractors on site. Now, after questioning business as usual, I was the first to be laid off," he said.

After an investigation, the Department of Labor found in McNiece's favor in July 1995.

It ordered the utility to reinstate McNiece to his former position, to pay him wages back to December 1994, revise his performance evaluation, issue him a public apology and pay attorneys' fees and punitive damages of $100,000.

After a formal hearing, a labor department administrative law judge found in December 1995 that NU and Bartlett had discriminated against McNiece. The company denied the accusation and filed a motion for reconsideration. The judge's recommended decision is being reviewed by the secretary of labor.

"We did ask the Department of Labor for another hearing before another ,

administrative law judge because we disagreed with the original administrative  !

law judge. But we will pay the fine if it is ordered after final review," said Deborah Beauchamp, an NU spokeswoman.

McNicce was rehired at Millstone in March 1996.

Tuesday, the NRC said it adopted the findings of the law judge and concluded the utility violated federal law.

l

{

.