Text
h l
I ENCLOSURE 1 NOTICE OF VIOLATION Duke Power Company Docket No. 50-413 Catawba Nuclear Station License No. NPF-35 The following violations were identified during an inspection conducted on June 24 - 28, 1985.
The Severity Levels were assigned in accordance with the NRC Enforcement Policy (10 CFR Part 2, Appendix C).
1.
10 CFR 50.54(q) requires that nuclear power reactor licensees follow and maintain in effect emergency plans which meet the requirements of Appendix E of 10 CFR Part 50 and the planning standards of 10 CFR 50.47(b).
Section 0 of the licensee's Emergency Plan delineated the training program for individuals assigned to the licensee's emergency organization.
Contrary to the above, the licensee in some cases assigned personnel to the onsite emergency organization prior to their receiving specified training.
By comparing training records against past and proposed revisions to Station Directive 3.8.4, the inspector identified 5 instances of this practice.
This is a Severity Level IV violation (Supplement VIII).
2.
Technical Specification 6.8.1.d specifies that written procedures covering Emergency Plan implementation shall be established, implemented, and main-tained.
Contrary to the above, the licensee did not implement procedure PT/0/B/4600/06 (Emergency Drills) which requires documentation of drill findings in that the results of the semiannual health physics drill held on August 29, 1984, were not documented.
This is a Severity Level V violation (Supplement VIII).
Pursuant to 10 CFR 2.201, you are required to submit to this office within 30 days of the date of this Notice, a written statement or explanation in reply, including:
(1) admission or denial of the ' alleged violations; (2) the reasons for the violations if admitted; (3) the corrective steps which have been taken and the results achieved; (4) corrective steps which will be taken to avoid further violations; and (5) the date when full compliance will be achieved.
Security or safeguards information should be submitted as an enclosure to facilitate withholding it from public disclosure as required by 10 CFR 2.790(d) or 10 CFR 73.21.