Forwards Conformance to Reg Guide 1.97,Davis-Besse Nuclear Power Station,Unit 1, Reviewing Util 840628 Submittal. Response to Open Items Requested within 70 Days of Ltr Date
ML20133P866
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 10/16/1985
From: Stolz J
Office of Nuclear Reactor Regulation
To: Williams J
TOLEDO EDISON CO.
Shared Package
ML20133P869 List:
References
RTR-REGGD-01.097, RTR-REGGD-1.097 TAC-51084, NUDOCS 8511010236
Download: ML20133P866 (2)


Text

- - - - _ - - . . .

, October 16, 1985 g (){ h

. Docket No. 50-346 ESTMBUTER r ra Mr. Joe Williams, Jr. L PDR GDick Vice President, Nuclear ORB #4 Rdg ADe Agazio Toledo Edison Company HThompson Gray File Edison Plaza - Stop 712 OELD EBrach 300 Madison Avenue EJordan H0rnstein Toledo, Ohio 43652 BGrimes WPaulson ,

JPartlow GEdison

Dear Mr. Williams:

JJoyce

SUBJECT:

CONFORMANCE TO REGULATORY GUIDE 1.97 - DAVIS-BESSE NUCLEAR POWER STATION, UNIT N0. 1 By letter dated June 28, 1984 (Serial No. 1059), Toledo Edison Company (TED) submitted a report describing how Davis-Besse meets the requirements of Regulatory Guide 1.97 (R.G.1.97).

The TED report has been reviewed 0y the NRC staff and contractor, EG&G Idaho, Inc. A copy of the contractor's int (rim report, documenting the review to date, is enclosed. Generally it is concluded that TED has provided an

explicit comitment on conformance to R.G.1.97 with the exception of those items identified. However, in some instances, there was insufficient 4

information provided to permit a determination to be made regarding whether or not an exception was justified.

Please review the enclosed interim report and provide responses to the open items within 70 days of the date of this letter. You may also wish to inform

-; us if the report includes any incorrect assumptions or reflects a commitment which is beyond that which you intended. This request for information '

affects fewer than ten respondents; therefore, OMB clearance is not required

. under P.L.96-511.

Sincerely, l

mmmae John F. Stolz, Chief i

Operating Reactors Branch #4

! Division of Licensing i

Enclosure:

As Stated l cc w/ enclosure:

See next page J:DL ORB '

  • Oh DL k;cf ADe azio JSt 0//0/85 10/pg/85 10/ 4/8 8511010236((PDRh46 PDR ADOCK F

> l

. Mr. J. Williams Davis-Besse Nuclear Power Station Toledo Edison Company Unit No. I cc:

Donald H. Hauser, Esq. Ohio Department of Health The Cleveland Electric ATTN: Radiological Health Illuminating Company Program Director P. O. Box 5000 P. 0, Box 118 Cleveland, Ohio 44101 Columbus, Ohio 43216 Mr. Robert F. Peters Attorney General Manager, Nuclear Licensing Department of Attorney Toledo Edison Company General Edison Plaza 30 East Broad Street 300 Madison Avenue Columbus, Ohio 43215 Toledo, Oh-io 43652 Mr. James W. Harris, Director Gerald Charnoff, Esq. Division of Power Generation l Shaw, Pittman, Potts Ohio Department of Industrial Relations and Trowbridge 2323 West 5th Avenue 1800 M Street, N.W. P. O. Box 825 Washington, D.C. 20036 Columbus, Ohio 43216 Paul M. Smart, Esq. Mr. Harold Kohn, Staff Scientist Fuller & Henry Power Siting Commission 300 Madison Avenue 361 East Broad Street P. O. Box 2088 Columbus, Ohio 43216 Toledo, Ohio 43603 Mr. Robert B. Borsum President, Board of Babcock & Wilcox Ottawa County Nuclear Power Generation Port Clinton, Ohio 43452 Division Suite 200, 7910 Woodmont Avenue Bethesda, Maryland 20814

! Resident Inspector U.S. Nuclear Regulatory Commission 5503 N. State Route 2 Oak Harbor, Ohio 43449 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 50137 4

. .,._ -.