OPERATLNG DATA REPORT DOCKET NO.
50-369 DATE 06-14-85 CO31PLETED BY J A - nonvis TELEPilONE 704-373-7567 OPERATING STATUS
- 1. Unit Name:
McGuire 1 Notes
- Nameplate Rating
- 2. Reporting Period:
May 1.
1985-May 31. 1985 (Gross MWe) calculated as
- 3. Licensed Thermal Power 151Wt):
3411 1450.000 MVA x.90 power
- 4. Nameplate Rating (Gross 31We):
1305*
factor per Page lii, 1180 NUREG-0020.
S. Design Electrical Rating (Net SIWE):
- 6. Staximum Dependable Capacity (Gross SIWE):
- 7. Slaximum Dependable Capacity (Net alWe):
11"O S. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report. Gise Reasons:
None
- 9. Power Lesel To Which Restricted,if Any (Net >!We):
None
- 10. Reasons For Restrictions,if Any:
This >!onth Yr. to Date Cumulative II. Hours in Reporting Period 744.0 3 623.0 10 671.0
- 12. Number Of Houn Reactor Was Critical 0.0 2 514.9 20 678.5
- 13. Reactor Reserve Shutdown Hours
- 14. Hours Generator On Line 0.0 2 494.3 20 456.8
- 15. Unit Resene Shutdown Hours
- 16. Gross Thermal Energy Generated (>lWH) 6 736 582 53 540 882
- 17. Gross Electrical Energy Generated (31WH) 221 2 295 297 18 524 522 IS. Net Electrical Energy Generated (51WH)
-3 317 2 188 829 17 564 084
- 19. Unit Senice Factor 0.0
'68.8 66.7
- 20. Unit Availability Factor 0.0 68.8 66.7
- 21. Unit Capacity Factor (Using.\\lDC Net) 0.0 51.2 48.5
- 22. Unit Capacity Factor (Using DER Net) 0.0 51 ?
48.5,
- 23. Unit Forced Outage Rate 0.0 4.2 14.9
- 24. Shutdowns Scheduled Oser Next 6 31onths(Type.Date,and Duration of Each1:
Currently Refueling
- 25. If Shur Down At End Of Report Period. Estimated Date of Startup: June 9, 1985
- 26. Units In Test Status tPrior to Commercial Operation):
Forecast Achiesed INITIA L CRITICA LITY INITIAL ELECTRICITY COilMERCIAL OPERATION 8506240048 850614 PDR ADOCK 05000369
- (9/77I R
AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.
50-369 UNIT Mer;uire 1 DATE 06/14/85 COMPLETED BY J.A. Reavis TELEPHONE 704-373-7567 MONTH May, 1985 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net)
(MWe-Net) 1 17 2
18 3
19 4
20 5
21 6
22 7
23 8
24 9
25 10 26 11 27 12 28 13 29 14 30 15 31
'16
~
INSTRUCTIONS On this format, list the average dally unit power level in MWe-Net for each day in the reporting month.
Compute to the nea est whole megawatt.
I
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET N0.
50-369 UNIT NAME Mccuire Unit 1 DATE 06-14-85 r
REPORT MONTH May 1985>
COMPLETED BY J. A. Reavis TELEPHONE 704-373-7567 "s
O t en$
License Cause & Corrective y
e32 "e
o.c u g
No.
'Date yb g
3g Event he, g
Action to 5E E
%Eb s,B BB H
o-a:
xmo Report #
mu vu Prevent Recurrence 4
85-05-01 S
44 00 C
RC FUELXX End of Cycle 2 Refueling Outage i
l i
i 4
t_.
J t
'l 2
3 4
Reason:
Method:
Exhibit G - Instructions S She A-Equipment Failure (Explain) 1-Manual for Preparation of Data led B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refueling 3-Automatic Scram Event Report (LER)
D-Regulatory Restriction 4-Other (Explain)
File (NUREG-0161)
E-Operator Training 4 License Examination F-Administrative 5
G-Operational Error (Explain)
Exhibit I - Same Source II-Other (Explain)
(4/77)
DOCKET NO:
50-369 UNIT:
McGuire Unit 1 DATE:
06-14-85 NARRATIVE
SUMMARY
Month:
May 1985 McGuire Unit I remained in refueling throughout May.
P M
MONTFLY REFUELING INFORMATION REQUEST t
'McGuire Unit 1 1.
Facility name:
2.
Scheduled next refueling shutdown:
currently Refueling 3.
Scheduled restart following refueling:
1 4.
Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?
Yes If yes, what will these be? _ Technical Specification Revision If no, has reload design and core configuration been reviewed by Safety Review Com=ittee regarding unreviewed safety questions?
N/A 5.
Scheduled date(s) for submitting proposed licensing action and supporting t
information:
N/A i
6.
I=portant licensing considerations (new or different design or supplier,'
unreviewed design or performance analysis methods, significant changes in design or new operating procedures).
N/A i
L i-7.
Number of fuel assemblies (a) in the core:
193 i
(b) in the spent fuel pool:
'91 i
8.
Present licensed fuel pool capacity:
1463 t
Size of requested or planned increase:
~.
9.
Projected date of last refueling which can be accommodated by present L
licensed capacity:
August-1991 i-DUKE POWER COMPANY Date:
June 14, 1985 Name of
Contact:
J. A. Reavis Phone:
704-373-7567 i
0-er c
..-n
,,,-,,,,,n-
~,,. - -,, -. - -
~
i OPERATING DATA REPORT
\\
DOCKET NO. _50-370 DATE 06-14-85 COSIPLETED BY J. A. Reavis-TELEPilONE 7na-373-7567 l
t OPERATING STATUS I. Unit Name:
McGuire 2 Notes ~* Nameplate Rating i
- 2. Reporting Period:
May 1,
1985-Hay 31, 1985 (Gross MWe) calculated as
- 3. Licensed Thermal Power (MWt):
3411 1450.000 MVA x.90 power i
i
- 4. Nameplate Rating (Gross MWe):
1305 r per Page lii,
- 5. Design Electrical Rating (Net MWe):
1180
- 6. Maximum Dependable Capacity (Gross MWe):
- 7. Maximum Dependable Capacity (Net SIWE):
1180 S. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report. Give Reasons:
None i
- 9. Power Level To Which Restricted.lf Any(Net MWe):
None j
- 10. Reasons For Restrictions. If Any:
i i
i This Month Yr to.Date Cumulative
- 11. Hours in Reporting Period 744.0 3 623.0 10 967.0 i
- 12. Number Of Hours Reactor Was Critical 603.4 1 198.3 7 336.5
- 13. Reactor Reserve Shutdown Hours 1
- 14. Hours Generator On Line 530.8 1 125.7 7 216.7
- 15. Unit Resene Shutdown Hours
- 16. Gross Thermal Energy Generated (MWH) 1 613 921 3 562 167 22 932 838 i
. 17. Gross Electrical Energy Generated (MWH) 559 945 1 259 573 8 097 296 i
- 18. Net Electrical Energy Generated (MWH) 531 489 1 189 570 7 747 370
- 19. Unit Senice Factor 71.3 31.1 65.8
- 20. Unit Availability Factor 71.3 31.I 65.8
- 21. Unit Capacity Factor (Using MDC Net) 60.5 27.8 59.9
- 22. Unit Capacity Factor (Using DER Net) 60.5 27.8 59.9
- 23. Unit Forced Outage Rate 28.7 46.7 23.0
- 24. Shutdowns Sch'eduled Over Next 6 Months (Type. Date,and Duration of Eacht:
Maintertance Outage - June 28, 1985 - 2 Weeks l'
i 1
- 25. If Shut Down At End Of Report Period. Estimated Date of Startup:
- 26. Units in Test Status aPrior to Commercial Operation):
Forecast Achieved i
INITIA L CRITICALITY.
INITIAL ELECTRICITY
' COMMERCIAL OPERATION i-(9/77) 1-e,w-e
,,---,,1-
-.-------e,-~--
,~w,,,,
+e-.
-,~.m-,
e. m, a-+
--s,.u-,,w.
,.-rwe-
.n.
w--~
--,,e
AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.
50-370 UNIT _ McGuire 2 DATE 6/14/85 COMPLETED BY J.A. Reavis TELEPHONE 704-373-7567 MONTH May, 1985 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net)
(MWe-Net) 1 17 106 2
18 1 107 3
19 1 161 4
20 1 161 5
21 1 160 6
22 1 158 7
23 1 163 8
24 1 160 9
281 25 1 157 10 420 26 1 161 11 654 27 1 161 12 834 28 1 163 13 1 133 29 1 162 14 1 160 30 1 160 15 1 162 31 1 162 16 435 INSTRUCTIONS On this format, in the reporting month. list the average daily unit power level in MWe-Net for each day Compute to the nearest whole megawatt.
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.
50-370 UNIT NAME McGuire Unit 2 Page 1 of 2 DATE 06-14-85 REPORT MONTH May 1985 COMPLETED BY J. A. neavis TELEPHONE 704-373-7567 "s.
O tj License Cause & Corrective y
c.
32 v3E a
No.
Date
~.
%h g
jg Event h
g Action to usE a
'o e
mm y
N 56 E
$5S Report #
NO
$8 Prevent Recurrence IK 85-05-01
[
136.92 A SF VALVEX Repair Seat Leak on Safety Injection Isolation Valve (NI-9)
IL 85-05-06 F
24.0C A
CH PUMPXX Feedwater Pump Tripped During Startup 1M 85-05-07
.F 24.0C A
2 CH TURBIN Feedwater Pump Tripped During Transfer from Auxiliary to Main Steam
.4-p 85-05-08 F
F ZZ ZZZZZZ Secondary Chemistry Hold 5-p 85-05-09 S
.B IB INSTRU Flux Mapping 6-p-85-05-09 F-A ZZ ZZZZZZ Turbine Runback During Load Reduction to Perform Core Power Distribution Test 7-p u5-05-10 F
A HA INSTRU Load Swing Due te Turbine Control Problems 8-p 85-05-10 F
D RC FUELXX Quadrant Power Tilt Ratio Out-of-Limit 9-p 85-05-11 S
B j IB INSTRU Fold for Nuclear Instrumentation Calibrations 10-p
'85-05-11 F
A CH PUMPXX Feedwater Pump Control Oil Repairs 1
2 3
4 Reason:
Method:
Exhibit G - Instructions
[
A-Equipment Failure (Explain) 1-Manual for Preparation of Data 1ed B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refuelinj;;
3-Autmatic Scram Event Report (LER)
D-Regulatory Restriction 4-Other (Explain)
File (NLREG-0161)
E-Operator Training 6 License Examination F-Administrat ive 5
G-Operational Error (Explain)
Exhibit I - Same Source II-Other (Explain)
(Q /'71
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-370 UNIT NAME McGuire Unit 2 Page 2 of 2 DATE 06-14-85 REPORT MONTH May 1985 COMPLETED BY J. A. Reavis i
TELEPHONE 704-373-7567 O
O o,$
. License Cause & Corrective y
cM "c
v.!E s g
a No.
Date
%h yy Event
,&r, g
o Action to R
YE 8
%Eb QE 82 H
o~
a:
xmo Report #
mu uu Prevent Recurrence 2
85-05-16 F
28.33 H
2 HJ XXXXXX Lost Generator hydrogen While Attempting to Correct Unacceptable Hydrogen Purity 11-p' 85-05-17 F
F ZZ ZZZZZZ Secondary Chemistry Hold 12-p 85-05-18 S
F ZZ ZZZZZZ Hold at Reduced Load for Dispatcher 1
1 2
3 4
Reason:
Method:
Exhibit G - Instructions
[F A-Equipment Failure (Explain) 1-Manual for Preparation of Data e
B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refueling 3-Automatic Scram Event Report (LER)
D-Regulatory Restriction 4-Other (Explain)
File (NUREG-0161)
E-Operator Training 6 License Examination F-Administrative 5
G-Operational Error (Explain)
Exhibit I - Same Source H-Other (Explain)
- (9/77)
DOCKET No: 50-370 UNIT: McGuire Unit 2 06-14-85 DATE:
NARRATIVE
SUMMARY
Month:
May 1985 McGuire Unit 2 was prevented from restart from their end of cycle 1 refueling outage due to valve repairs on May 1.
Also during startup on May 5 and 6, the feedpumps tripped. The unit returned to service on May 8, and operated at 100% until May 16 when Generator Hydrogen was lost forcing a manual trip. The unit returned to service on May 17, and operated at 100% for the balance of the month.
m.
m MONTHLY REFUELING INFORMATION RE01iEST 1.
Facility name:
McGuire Unit 2 2.
Scheduled next refueling shutdown:
April 1986 3.
Scheduled restart following refueling:
June 1986 4.
Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?
Yes If yes, what will these be?
Technical Specification Revision l
T If no, has reload design and core configuration been reviewed by Safety Review Co==ittee regarding unreviewed safety questions?
N/A 5.
Scheduled date(s) for subsitting proposed licensing action and supporting j
information:
N/A 6.
I=portant licensing considerations (new or different design or supplier, 1
unreviewed design or performance analysis methods, significant changes in design or new operating procedures).
N/A 1
7.
Number of fuel assemblies (a) in the core:
193 (b) in the spent fuel pool:
60 8.
Prasent licensed fuel pool capacity:
1463
~
Size of requested or planned increase:
9.
Projected date of last refueling which can be accommodated by present
- licensed' capacity:
August 1991 DUKE POWER COMPANY Date:
June 14, 1985 Name of
Contact:
.J.'A. Reavis Phone: 704-373-7567
4 McGUIRE NUCLEAR STATION Monthly Operating Status Report 1.
Personnel Exposure For the month of April, no individual (s) exceeded 10 percent of their allowable annual radiation dose limit.
2.
The total station liquid release for April has been compared with the Technical Specifications maximum annual dose commitment and was less than 10 percent of this limit.
The total station gaseous release for April has been compared with the Technical Specifications maximum annual dose commitment and was less than 10 percent of this limit, i