ML20126F479
ML20126F479 | |
Person / Time | |
---|---|
Site: | Browns Ferry, Saint Lucie, Sequoyah, 05000000 |
Issue date: | 10/01/1982 |
From: | Dougan J OAK RIDGE NATIONAL LABORATORY |
To: | James O'Reilly NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
Shared Package | |
ML20126E434 | List: |
References | |
CON-FIN-B-0489, CON-FIN-B-489, FOIA-85-143 NUDOCS 8506170496 | |
Download: ML20126F479 (1) | |
Category:CORRESPONDENCE-LETTERS
MONTHYEARML17241A5001999-10-21021 October 1999
[Table view]Forwards Rev 3 to Emergency Response Data Sys (ERDS) Data Point Library for St Lucie Unit 1.Rev Provides Replacement Pages & Follows Format Recommended by NUREG 1394, ERDS Implementation, Rev 1,App C ML20217M4461999-10-20020 October 1999 Forwards Rev 8 to Sequoyah Nuclear Plant Physical Security/ Contingency Plan, IAW 10CFR50.54(p).Encl Withheld,Per 10CFR73.21 ML17309A9981999-10-19019 October 1999 Forwards Revised Epips,Including Rev 3 to EPIP-10 & Rev 25 to HP-202.EPIP-10 Added Onsite Monitoring Points,Made Administrative Changes & Incorporated New Attachments & HP-202 Added Red Team Survey Points 05000327/LER-1999-002, Forwards LER 99-002-00 Re Start of Units 1 & 2 EDGs as Result of Cable Being Damaged During Installation of Thermo- Lag for Kaowool Upgrade Project1999-10-15015 October 1999 Forwards LER 99-002-00 Re Start of Units 1 & 2 EDGs as Result of Cable Being Damaged During Installation of Thermo- Lag for Kaowool Upgrade Project ML20217J4151999-10-15015 October 1999 Forwards Request for Addl Info Re Util 990624 Application for Amend of TSs That Would Revise TS for Weighing of Ice Condenser Ice Baskets ML18039A9021999-10-15015 October 1999 Forwards LER 99-010-00 Re Occurrence of Plant Reactor Scram Due to Main Turbine Trip Which Resulted in Main Steam Moisture Separator.All Plant Safety Systems Operated as Designed in Response to Event ML18039A8961999-10-14014 October 1999 Forwards LER 99-009-00,re Manual Reactor Scram on Unit 2 from 54% Power,Iaw 10CFR50.73(a)(2)(iv).All Plant Safety Sys Operated as Designed in Response to Event ML20217E0711999-10-14014 October 1999 Grants Approval for Util to Submit Original,One Signed Paper Copy & Six CD-ROM Copies of Updates to FSAR as Listed,Per 10CFR50.4(c),in Response to ML20217D3261999-10-0808 October 1999 Responds to Re Event Concerning Spent Fuel Pool Water Temperature Being Undetected for Approx Two Days at Browns Ferry Unit 3 ML20217F7751999-10-0808 October 1999 Confirms 991006 Telcon Between T Abney of Licensee Staff & a Belisle of NRC Re Meeting to Be Conducted on 991109 in Atlanta,Ga to Discuss Various Maintenance Issues ML18039A8931999-10-0808 October 1999 Forwards LER 99-008-00,concerning HPCI Sys Being Declared Inoperable,Iaw 10CFR50.73(a)(2)(v).There Are No Commitments Contained in Ltr ML18039A8881999-10-0808 October 1999 Provides Licensee Supplemental Response to NRC 980713 RAI Re GL 87-02,Suppl 1, Verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors. ML20217F6171999-10-0808 October 1999 Forwards Insp Repts 50-335/99-11 & 50-389/99-11 on 990827 & 990907-09.No Violations Identified.Matl Encl Contained Safeguards Info as Defined by 10CFR73.21 & Disclosed to Unauthorized Individuals Prohibited by Section 147 of AEA ML20217G1141999-10-0707 October 1999 Responds to from P Salas,Providing Response to NRC Risk Determination Associated with 990630 Flooding Event at Sequoyah Facility.Meeting to Discuss Risk Determination Issues Scheduled for 991021 in Atlanta,Ga ML20217B2981999-10-0606 October 1999 Discusses Closeout of GL 92-01,rev 1,suppl 1, Reactor Vessel Integrity, for Sequoyah Nuclear Plant,Units 1 & 2. NRC Also Hereby Solicits Any Written Comments That TVA May Have on Current Rvid Data by 991101 ML20217B8431999-10-0505 October 1999 Requests NRC Review & Approval of ASME Code Relief Requests That Were Identified in Plant Second 10-yr ISI Interval for Both Units.Encl 3 Provides Util Procedure for Calculation of ASME Code Coverage for Section XI Nondestructive Exams ML20212J5981999-10-0101 October 1999 Forwards SE Accepting Request for Relief from ASME Boiler & Pressure Vessel Code,Section Xi,Requirements for Certain Inservice Insp at Plnat,Unit 1 ML20217C7101999-10-0101 October 1999 Forwards Response to NRC 990910 RAI Re Sequoyah Nuclear Plant,Units 1 & 2 URI 50-327/98-04-02 & 50-328/98-04-02 Re Ice Weight Representative Sample IR 05000327/19990041999-10-0101 October 1999 Ack Receipt of Providing Comments on Insp Repts 50-327/99-04 & 50-328/99-04.NRC Considered Comments for Apparent Violation Involving 10CFR50.59 Issue ML20217B5481999-10-0101 October 1999 Requests Exception to 10CFR50.4(c) Requirement to Provide Total of Twelve Paper Copies When Submitting Revs to BFN UFSAR ML17241A4811999-10-0101 October 1999 Reports Number of Tubes Plugged During Unit 1 Refueling Outage SL1-16,per TS 4.4.5.5.a ML20212M1081999-09-29029 September 1999 Confirms Intent to Meet with Utils on 991025 in Atlanta,Ga to Discuss Pilot Plants,Shearon Harris & Sequoyah Any Observations & Lessons Learned & Recommendations Re Implementation of Pilot Program ML20212M1481999-09-28028 September 1999 Refers to Management Meeting Conducted on 990927 at Region II for Presentation of Recent Plant Performance.List of Attendees & Copy of Presentation Handout Encl ML20212M1601999-09-28028 September 1999 Refers to 990908 Engineering Meeting Conducted at NRC Region II to Discuss Engineering Issues at Lucie & Turkey Point Facilities.List of Attendees & Copy of Presentation Handout Encl ML20217A9451999-09-27027 September 1999 Forwards Insp Repts 50-327/99-05 & 50-328/99-05 on 990718- 0828.One Violation Identified & Being Treated as Non-Cited Violation ML20216J9351999-09-27027 September 1999 Responds to NRC Re Violations Noted in Insp Repts 50-327/99-04 & 50-328/99-04.Corrective Actions:Risk Determination Evaluation Was Performed & Licensee Concluded That Event Is in Green Regulatory Response Band ML17241A4701999-09-25025 September 1999 Forwards Info Requested by NRC Staff During 990916 Telcon to Complete Staff Review of Request for risk-informed Extension of Action Completion/Aot Specified for Inoperable Train of LPSI Sys at Plant ML17241A4721999-09-24024 September 1999 Forwards Rev 1 to Plant Change/Mod (PCM) 99016 to St Lucie Unit 1,Cycle 16 COLR, IAW TS 6.9.1.11.d.Refueling Overhaul Activities Are Currently in Progress & Reactor Operations for Cycle 16 Are Scheduled to Commence in Oct 1999 ML20212F0751999-09-23023 September 1999 Forwards SER Granting Util 981021 Request for Relief from ASME Code,Section XI Requirements from Certain Inservice Insp at Sequoyah Nuclear Power Plant,Units 1 & 2 Pursuant to 10CFR50.55a(a)(3)(ii) ML20212F4501999-09-23023 September 1999 Forwards Amends 246 & 237 to Licenses DPR-77 & DPR-79, Respectively & Ser.Amends Approve Request to Revise TSs to Allow Use of Fully Qualified & Tested Spare Inverter in Place of Any of Eight Required Inverters ML17241A4681999-09-22022 September 1999 Requests Restriction Be Added to Senior Operator License SOP-21093 for TE Bolander.Nrc Forms 369,encl.Encl Withheld Per 10CFR2.790(a)(6) ML20212F7751999-09-22022 September 1999 Requests Operator & Senior Operator License Renewals for Listed Individuals and Licenses ML20212M1911999-09-21021 September 1999 Discusses Exercise of Enforcement Discretion Re Apparent Violation Noted in Insp Repts 50-327/99-04 & 50-328/99-04 Associated with Implementation of Procedural Changes Which Resulted in Three Containment Penetrations Being Left Open ML17241A4671999-09-20020 September 1999 Forwards Completed NRC Form 536, Operator Licensing Exam Data, for St Lucie Units 1 & 2,as Requested in Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Exams. ML20212D3651999-09-20020 September 1999 Forwards SE Accepting Licensee 990430 Proposed Rev to Plant, Unit 3 Matl Surveillance Program ML17241A4581999-09-13013 September 1999 Forwards Info Requested by NRC Staff During 990630 & 0816 Telcons,To Complete Review of Proposed License Amend for Fuel Reload Process Improvement Program ML20211Q0311999-09-10010 September 1999 Requests Written Documentation from TVA to Provide Technical Assistance to Region II Re TS Compliance & Ice Condenser Maint Practices at Plant ML18039A8721999-09-10010 September 1999 Informs of Licensee Decision to Withdraw Proposed Plant risk-informed Inservice Insp Program,Originally Transmitted in Util 981023 Ltr.Licensee Expects to Resubmit Revised Program within Approx 6 Wks ML20211Q5731999-09-0909 September 1999 Submits Response to Administrative Ltr 99-03 Re Preparation & Scheduling of Operator Licensing Exams.Completed NRC Form 536,operator Licensing Exam Data,Which Provides Plant Current Schedules for Specific Info Requested Encl ML20216F5441999-09-0707 September 1999 Provides Results of Risk Evaluation of 990630,flooding Event at Sequoyah 1 & 2 Reactor Facilities.Event Was Documented in Insp Rept 50-327/99-04 & 50-328/99-04 & Transmitted in Ltr, ML20211N5681999-09-0101 September 1999 Submits Clarification of Two Issues Raised in Insp Repts 50-327/99-04 & 50-328/99-04,dtd 990813,which Was First Insp Rept Issued for Plant Under NRC Power Reactor Oversight Process Pilot Plant Study ML17241A4521999-08-31031 August 1999 Withdraws Relief Request 16 & Suppl Relief Request 15 with Info Requested During 990526 Telephone Conference Re ISI Insp Plan,Third 10-yr Interval ML17241A4531999-08-31031 August 1999 Informs That No Candidates from St Lucie Plant Will Be Participating in PWR Gfes Being Administered on 991006 ML20211G5881999-08-27027 August 1999 Submits Summary of 990820 Management Meeting Re Plant Performance.List of Attendees & Matl Used in Presentation Enclosed ML17241A4501999-08-26026 August 1999 Informs That FPL Has Reviewed Reactor Vessel Integrity Database,Called RVID2,re Closure of GL 92-01,rev 1,suppl 1. Requested Corrections & Marked Up Pages from Rvid 2 Database Summary Repts That Correspond to Comments,Attached ML20211G6491999-08-26026 August 1999 Confirms Telcon with T Abney on 990824 Re Mgt Meeting Which Has Been re-scheduled from 990830-0927.Purpose of Meeting to Discuss BFN Status & Performance ML20211F8891999-08-25025 August 1999 Forwards Sequoyah Nuclear Plant Unit 1 Cycle 9 Refueling Outage, Re Completed SG Activities,Per TSs 4.4.5.5.b & 4.4.5.5.c ML20211A1851999-08-16016 August 1999 Forwards Proprietary TR WCAP-15128 & non-proprietary Rept WCAP-15129 for NRC Review.Repts Are Provided in Advance of TS Change That Is Being Prepared to Support Cycle 10 Rfo. Proprietary TR Withheld,Per 10CFR2.790 ML20210V1471999-08-13013 August 1999 Forwards Insp Repts 50-327/99-04 & 50-328/99-04 on 990601- 0717.One Potentially Safety Significant Issue Identified.On 990630,inadequate Performance of Storm Drain Sys Caused Water from Heavy Rainfall to Backup & Flood Turbine Bldg ML17241A4371999-08-13013 August 1999 Forwards fitness-for-duty Program Performance Data for six- Month Period Ending 990630,per 10CFR26.71(d) 1999-09-09 Category:INCOMING CORRESPONDENCE MONTHYEARML17241A5001999-10-21021 October 1999
[Table view]Forwards Rev 3 to Emergency Response Data Sys (ERDS) Data Point Library for St Lucie Unit 1.Rev Provides Replacement Pages & Follows Format Recommended by NUREG 1394, ERDS Implementation, Rev 1,App C ML20217M4461999-10-20020 October 1999 Forwards Rev 8 to Sequoyah Nuclear Plant Physical Security/ Contingency Plan, IAW 10CFR50.54(p).Encl Withheld,Per 10CFR73.21 ML17309A9981999-10-19019 October 1999 Forwards Revised Epips,Including Rev 3 to EPIP-10 & Rev 25 to HP-202.EPIP-10 Added Onsite Monitoring Points,Made Administrative Changes & Incorporated New Attachments & HP-202 Added Red Team Survey Points 05000327/LER-1999-002, Forwards LER 99-002-00 Re Start of Units 1 & 2 EDGs as Result of Cable Being Damaged During Installation of Thermo- Lag for Kaowool Upgrade Project1999-10-15015 October 1999 Forwards LER 99-002-00 Re Start of Units 1 & 2 EDGs as Result of Cable Being Damaged During Installation of Thermo- Lag for Kaowool Upgrade Project ML18039A9021999-10-15015 October 1999 Forwards LER 99-010-00 Re Occurrence of Plant Reactor Scram Due to Main Turbine Trip Which Resulted in Main Steam Moisture Separator.All Plant Safety Systems Operated as Designed in Response to Event ML18039A8961999-10-14014 October 1999 Forwards LER 99-009-00,re Manual Reactor Scram on Unit 2 from 54% Power,Iaw 10CFR50.73(a)(2)(iv).All Plant Safety Sys Operated as Designed in Response to Event ML18039A8931999-10-0808 October 1999 Forwards LER 99-008-00,concerning HPCI Sys Being Declared Inoperable,Iaw 10CFR50.73(a)(2)(v).There Are No Commitments Contained in Ltr ML18039A8881999-10-0808 October 1999 Provides Licensee Supplemental Response to NRC 980713 RAI Re GL 87-02,Suppl 1, Verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors. ML20217B8431999-10-0505 October 1999 Requests NRC Review & Approval of ASME Code Relief Requests That Were Identified in Plant Second 10-yr ISI Interval for Both Units.Encl 3 Provides Util Procedure for Calculation of ASME Code Coverage for Section XI Nondestructive Exams ML20217C7101999-10-0101 October 1999 Forwards Response to NRC 990910 RAI Re Sequoyah Nuclear Plant,Units 1 & 2 URI 50-327/98-04-02 & 50-328/98-04-02 Re Ice Weight Representative Sample ML20217B5481999-10-0101 October 1999 Requests Exception to 10CFR50.4(c) Requirement to Provide Total of Twelve Paper Copies When Submitting Revs to BFN UFSAR ML17241A4811999-10-0101 October 1999 Reports Number of Tubes Plugged During Unit 1 Refueling Outage SL1-16,per TS 4.4.5.5.a ML20216J9351999-09-27027 September 1999 Responds to NRC Re Violations Noted in Insp Repts 50-327/99-04 & 50-328/99-04.Corrective Actions:Risk Determination Evaluation Was Performed & Licensee Concluded That Event Is in Green Regulatory Response Band ML17241A4701999-09-25025 September 1999 Forwards Info Requested by NRC Staff During 990916 Telcon to Complete Staff Review of Request for risk-informed Extension of Action Completion/Aot Specified for Inoperable Train of LPSI Sys at Plant ML17241A4721999-09-24024 September 1999 Forwards Rev 1 to Plant Change/Mod (PCM) 99016 to St Lucie Unit 1,Cycle 16 COLR, IAW TS 6.9.1.11.d.Refueling Overhaul Activities Are Currently in Progress & Reactor Operations for Cycle 16 Are Scheduled to Commence in Oct 1999 ML17241A4681999-09-22022 September 1999 Requests Restriction Be Added to Senior Operator License SOP-21093 for TE Bolander.Nrc Forms 369,encl.Encl Withheld Per 10CFR2.790(a)(6) ML20212F7751999-09-22022 September 1999 Requests Operator & Senior Operator License Renewals for Listed Individuals and Licenses ML17241A4671999-09-20020 September 1999 Forwards Completed NRC Form 536, Operator Licensing Exam Data, for St Lucie Units 1 & 2,as Requested in Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Exams. ML17241A4581999-09-13013 September 1999 Forwards Info Requested by NRC Staff During 990630 & 0816 Telcons,To Complete Review of Proposed License Amend for Fuel Reload Process Improvement Program ML18039A8721999-09-10010 September 1999 Informs of Licensee Decision to Withdraw Proposed Plant risk-informed Inservice Insp Program,Originally Transmitted in Util 981023 Ltr.Licensee Expects to Resubmit Revised Program within Approx 6 Wks ML20211Q5731999-09-0909 September 1999 Submits Response to Administrative Ltr 99-03 Re Preparation & Scheduling of Operator Licensing Exams.Completed NRC Form 536,operator Licensing Exam Data,Which Provides Plant Current Schedules for Specific Info Requested Encl ML20211N5681999-09-0101 September 1999 Submits Clarification of Two Issues Raised in Insp Repts 50-327/99-04 & 50-328/99-04,dtd 990813,which Was First Insp Rept Issued for Plant Under NRC Power Reactor Oversight Process Pilot Plant Study ML17241A4521999-08-31031 August 1999 Withdraws Relief Request 16 & Suppl Relief Request 15 with Info Requested During 990526 Telephone Conference Re ISI Insp Plan,Third 10-yr Interval ML17241A4531999-08-31031 August 1999 Informs That No Candidates from St Lucie Plant Will Be Participating in PWR Gfes Being Administered on 991006 ML17241A4501999-08-26026 August 1999 Informs That FPL Has Reviewed Reactor Vessel Integrity Database,Called RVID2,re Closure of GL 92-01,rev 1,suppl 1. Requested Corrections & Marked Up Pages from Rvid 2 Database Summary Repts That Correspond to Comments,Attached ML20211F8891999-08-25025 August 1999 Forwards Sequoyah Nuclear Plant Unit 1 Cycle 9 Refueling Outage, Re Completed SG Activities,Per TSs 4.4.5.5.b & 4.4.5.5.c ML20211A1851999-08-16016 August 1999 Forwards Proprietary TR WCAP-15128 & non-proprietary Rept WCAP-15129 for NRC Review.Repts Are Provided in Advance of TS Change That Is Being Prepared to Support Cycle 10 Rfo. Proprietary TR Withheld,Per 10CFR2.790 ML17241A4371999-08-13013 August 1999 Forwards fitness-for-duty Program Performance Data for six- Month Period Ending 990630,per 10CFR26.71(d) ML20211A1921999-08-12012 August 1999 Requests Proprietary TR WCAP-15128, Depth-Based SG Tube Repair Criteria for Axial PWSCC at Dented TSP Intersections, Be Withheld from Public Disclosure Per 10CFR2.790 ML17241A4461999-08-11011 August 1999 Requests That W Rept Entitled, Evaluation of Turbine Missile Ejection Probability Resulting from Extending Test Interval of Interceptor & Reheat Stop Valves at St Lucie Units 1 & 2, Be Withheld from Public Disclosure ML20210Q6931999-08-0909 August 1999 Forwards Updated Changes to Distribution Lists for Browns Ferry & Bellefonte Nuclear Plants ML18039A8371999-08-0606 August 1999 Forwards BFN Unit 2 Cycle 10 ASME Section XI NIS-1 & NIS-2 Data Repts, for NRC Review.Corrected Inservice Insp Summary Rept for Unit 3 Cycle 8 Operation,Included in Rept ML20210L4291999-08-0202 August 1999 Forwards Sequoyah Nuclear Plant Unit 2 Cycle 9 12-Month SG Insp Rept & SG-99-07-009, Sequoyah Unit-2 Cycle 10 Voltage-Based Repair Criteria 90-Day Rept. Repts Submitted IAW TS 4.4.5.5.b & TS 4.4.5.5.c ML20210L1611999-07-30030 July 1999 Forwards Request for Relief RV-4 Re ASME Class 1,2 & 3 Prvs, Per First ten-year Inservice Test Time Interval.Review & Approval of RV-4 Is Requested to Support Unit 1 Cycle 10 Refueling Outage,Scheduled to Start 000213 L-99-171, Forwards Rev 56 to Physical Security Plan.Summary of Changes & Marked Up Copy of Revised Pages Also Encl.Encls Withheld from Public Disclosure Per 10CFR2.790(a)(3)1999-07-29029 July 1999 Forwards Rev 56 to Physical Security Plan.Summary of Changes & Marked Up Copy of Revised Pages Also Encl.Encls Withheld from Public Disclosure Per 10CFR2.790(a)(3) ML20210G5301999-07-28028 July 1999 Forwards Sequoyah Nuclear Plant Unit 2 ISI Summary Rept That Contains Historical Record of Repairs,Replacement & ISI & Augmented Examinations That Were Performed on ASME Code Class 1 & 2 Components from 971104-990511 ML17309A9911999-07-26026 July 1999 Forwards Revised EPIPs & Revised Procedures That Implement Emergency Plan as Listed.Procedures Provides Instruction for Operational Support Ctr (OSC) Chemistry Supervisor to Establish Remote Labs at Locations Specified ML18039A8181999-07-26026 July 1999 Forwards LER 99-004-00 Re Inoperability of Two Divisions of Plant CSS Due to Personnel Error During Surveillance Testing.Event Reported Per 10CFR50.73(a)(2)(i)(B) ML20210F3031999-07-22022 July 1999 Submits Rept Re Impact of Changes or Errors in Methodology Used to Demonstrate Compliance with ECCS Requirements of 10CFR50.46.One Reportable non-significant Error Was Found During Time Period of 980601-990630 ML17241A4221999-07-22022 July 1999 Forwards List of Proposed Licensing Actions for St Lucie Units 1 & 2,planned During Fys 2000 & 2001,in Response to Administrative Ltr 99-02, Operating Reactor Licensing Action Estimates. ML17241A4471999-07-22022 July 1999 Requests That Rev 1 to WCAP-14732 & Rev 1,Add 1 to WCAP-14732 Be Withheld from Public Disclosure ML17241A4151999-07-22022 July 1999 Forwards Revised Relief Request 25 for Second 10-yr ISI Interval for Unit 2 ML17241A4101999-07-16016 July 1999 Forwards FP&L Supplemental Response to NRC Request for Info Re Y2K Readiness at Nuclear Power Plants ML20210J1091999-07-10010 July 1999 Submits Suggestions & Concerns Re Y2K & Nuclear Power Plants ML17309A9881999-07-0707 July 1999 Forwards Rev 5 to EPIP-03, Emergency Response Organization Notification/Staff Augmentation. Rev 5 to EPIP-03 Was Revised to Transfer EP Responsibilities from Training Manager to Protection Svcs Manager ML17355A3661999-06-30030 June 1999 Forwards Florida Power & Light Topical QA Rept, Dtd June 1999.Encl I Includes Summary of Changes Made to Topical QA Rept Since 1998 ML17241A3971999-06-30030 June 1999 Forwards Suppl Response to GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs, as Requested in 990317 Ltr ML17241A4011999-06-30030 June 1999 Forwards Info Copy of Florida Wastewater Permit (FL0002208) (Formerly NPDES Permit) Mod,Which Was Issued by Florida Dept of Environ Protection on 990604 ML20196K0381999-06-30030 June 1999 Provides Written Confirmation of Completed Commitment for Final Implementation of Thermo-Lag 330-1 Fire Barrier Corrective Actions at Snp,Per GL 92-08 ML17241A3951999-06-29029 June 1999 Provides Response to NRC Request for Info Re Y2K Readiness at Nuclear Power Plants.Gl 98-01, Y2K Readiness of Computer Sys at Nuclear Power Plants, Requested Response on Status of Facility Y2K Readiness by 990701.Disclosure Encl 1999-09-09 Category:RESEARCH INSTITUTION/LABORATORY TO NRC MONTHYEARML17261A8541989-01-13013 January 1989
[Table view]Discusses 890110-11 Meetings Re Nozzle Sizing Study.Most Accurate Sizing Obtained by Collecting Data of Edge Diffracted Waves from Geometric Extremities of Flaw ML19324A1111988-05-19019 May 1988 Forwards Memo Describing Results of Testing of Plant Bolting Matls Under FIN A-3866,Task Assignment 12 ML19324B2701988-03-0202 March 1988 Forwards Rept on Metallurgical Evaluation of Five Bolts Obtained from Farley Plant.Bolts Found Acceptable ML20207R7571987-03-10010 March 1987 Forwards Technical Evaluation Rept Input for South Texas Initial Plant Test Program Through FSAR Amend 56,Feb 1987 Sser & & Beaver Valley Unit 2 Initial Plant Test Program Through FSAR Amend 15 & Nov 1986 Sser ML20207S5001987-03-0606 March 1987 Forwards Technical Evaluation Repts for Domestic Mark III Plants (Grand Gulf,Clinton,River Bend & Perry) & Gessar Ii. Inserts to Be Included in Section 6.2.1.8 of Draft Sser 2 for Clinton,River Bend & Perry Plants Also Encl ML20195F8651986-10-31031 October 1986 Forwards Request for Addl Info Re MSIV Operability at Facility,Based on Initial Review of Util Rept Entitled, Final Rept 10CFR50.55(e) MSIV Actuators, Forwarded by Util ML20206H3211986-09-10010 September 1986 Forwards Summary Repts from 860811-14 Visit to Kewaunee Nuclear Station & 851002-03 Visit to Cooper Nuclear Station Re Generic Issue 83 on Control Room Habitability ML20206J6001986-08-0808 August 1986 Advises That NUREG-0956 Support Calculations Using ORNL Trends Code to Evaluate Influence of Containment Chemistry or Retention of Hi Can Also Provide Useful Info for General NUREG-1150 Issue Paper,Per Telcon Discussion ML20206H1131986-06-23023 June 1986 Submits DHEAT2 Parametric Calculations for Plant,Per 860620 Discussions.Calculations Run Assuming Any Steam Spike Would Develop Too Slowly to Contribute to DCH Peak Pressure ML20215N4371986-04-25025 April 1986 Submits Trip Rept of 860414-16 Site Visit W/Util & NRC for FIN A-3839 Re Welding Concerns.List of Attendees Encl ML20215N4331986-03-18018 March 1986 Submits Trip Rept of 860226-28 Visit to Facilities in Conjuction W/Duties as Expert Welding Team Members on FIN A-3839, Evaluation of Welding Concerns at TVA Operating Reactors ML20214E1721986-02-25025 February 1986 Ack Receipt of 860210 & 21 Ltrs Accepting Task Orders 3 & 4 Under FIN A-3552 & Task Order 5,respectively.Orders Include Work at Palisades & LaSalle Stations & Mod Review at Davis-Besse.Modified Task Order 4 Under FIN A-3550 Encl ML20206J2521986-01-24024 January 1986 Forwards Early Draft of Executive Summary from Analysis of Station Blackout Accidents for Bellefonte PWR, Per Request. Initial Draft of Rept Scheduled to Be Completed by 860315 ML20206J3681986-01-15015 January 1986 Discusses Latest Calculations of Molecular Iodine (I2) & Organic Iodide (CH3I) Scrubbing During TC1 Sequence from Draft Plant Rept ML20141J4811986-01-14014 January 1986 Provides Possible Mods to Five Internal & Three External Event Failure Modes for Facility.Discussion of Analysis W/Plant Personnel & Three Engineers from United Engineers & Constructors Suggested W/Listed Reasons ML20141M9511986-01-0606 January 1986 Informs of 860123-24 Site Visit W/United Engineers & Constructors to Discuss Questions Re Crossties to Sys & Operator Recovery Actions & Explore Preliminary Analysis Vulnerabilities.Specific Questions Listed ML20136F4771985-12-31031 December 1985 Forwards PNL-5718, Review of Tdi Diesel Generator Owners Group Engine Requalification Program,Final Rept, Technical Evaluation Rept ML20206J4031985-12-13013 December 1985 Summarizes Preliminary Scoping Calculations for Molecular Iodine (I2) Scrubbing in BWR Pressure Suppression Pools. Calculations Made for Most Recent TC1 Sequence in Draft Plant Rept ML20133A3141985-09-27027 September 1985 Forwards Review of Section 4.7 of Technical Evaluation Rept PNL-5600, Review of Resolution of Known Problems in Engine Components for Tdi Emergency Diesel Generators, Reflecting Views Re Crankshafts for 16-cylinder Engines ML20128H7371985-06-27027 June 1985 Forwards Rev 1 to Review of Engine Base & Bearing Caps for Tdi DSRV-12,DSRV-16 & DSRV-20 Diesel Engines, Technical Evaluation Rept ML20141N2981985-05-29029 May 1985 Requests Listed Addl Info Re S&W 1982 Rept, Ultimate Pressure Capacity of Shoreham Primary Containment ML20126E8721985-05-24024 May 1985 Forwards PNL-5200-3, Review of Emergency Diesel Generator Engine & Auxiliary Module Wiring & Terminations, Dtd May 1985 ML20133N7721985-03-27027 March 1985 Forwards Info Telecopied on 850325 Re Locational Distribution of Three Fission Product Species for Surry V Sequence & Time Dependent Release for Fission Product Groups for Peach Bottom ML20214F5101985-03-13013 March 1985 Forwards List of Questions Re Plant Pra,Per 850512 Telcon. Statement of Work, Review of PRA for Seabrook Nuclear Power Plant, Encl ML20134A1011985-02-20020 February 1985 Submits Results of Noble Gas Release Sequences Using March Code for Facilities ML20133N3461985-02-20020 February 1985 Discusses Review of March Results for Surry & Peach Bottom Sequences,In Order to Quantify Expected Noble Gas Releases. March Model Appropriate for Behavior of Noble Gases ML20128P3401984-12-0505 December 1984 Submits Rept for Task 1 Per M Silberberg 841116 Memo Re Concerns Re Lanthanum Releases in BMI-2104.Discusses Discrepancies in Corcon Calculations,Presents Revised Tables 6.14 & 7.16 & Recommends Reanalyses ML20138N6971984-09-18018 September 1984 Forwards Repts Re Irradiation,Decontamination & DBA Testing, Per Request of Y Korobov of Carboline Co ML20134E1591984-08-0202 August 1984 Forwards Brief Summary Rept on Leakage Characteristics of Nuclear Containment Hatches During Severe Accident. Draft of Complete Rept Will Be Mailed Later in Aug ML20127B9221984-07-20020 July 1984 Forwards PNL-5201, Review & Evaluation of Tdi Diesel Engine Reliability & Operability - Grand Gulf Nuclear Station, Unit 1 ML20127B8881984-05-21021 May 1984 Comments on May 1984 Draft Tdi Diesel Generator Owners Group Program Plan.Full Insp of One Engine to Owners Group Spec Recommended ML20093G4821984-05-0202 May 1984 Provides Summary of Battelle Subcontract W/Tdi to Evaluate Special Silicon carbide-impregnated Cylinder Liners & Piston Rings.Task Does Not Involve Dependability Tests of Tdi Engines.No Apparent Conflict Found ML20113A0201984-04-0404 April 1984 Forwards Requests for Addl Info Developed During Review of FSAR Chapter 14 Re Initial Plant Test Program.Review Conducted Through Amend 4.Listing of Items Requiring Resolution Encl ML20117C9421984-04-0303 April 1984 Forwards Proposed Radiological Source Term Input for Facility.Encl Amended to Reflect NRC Suggested Changes ML20093C5281984-03-30030 March 1984 Forwards Audit of Susquehanna Unit 2 Tech Specs, Technical Evaluation Rept ML17320A9711984-03-0606 March 1984 Forwards First Round Questions Following Evaluation of Exxon Rept, Steam Tube Rupture Incident at Prairie Island Unit 1, PTSPWR2 Vs Data,Preliminary Benchmark Analysis. ML17320A9741984-03-0505 March 1984 Forwards First Round Questions on Exxon Methodology Rept for PTSPWR2.Rept Lacks Specific Details Re Biases in Initial Conditions & Boundary Conditions ML20128N6571984-02-22022 February 1984 Comments on Draft Vols IV-VI of BMI-2104,presented at Peer Review 840126 & 27 Meetings.Comments Concern Completed Calculations for Sequoyah Ice Condenser Plant,Recalculated Surry Results & Completed Calculations for Zion Plant ML19306A0151984-02-10010 February 1984 Summarizes 840206-07 Visit to Nevada Test Site Hydrogen Burn Facility to Inspect Condition of Equipment & Cable/Splice Samples After Series of Hydrogen Burn Tests Conducted by Epri.No Indication of External Damage to Equipment Noted ML17320A9731983-11-22022 November 1983 Forwards First Round Questions on Mods to Exxon Draft Repts, PTSPWR2 Mods for St Lucie Unit 1 & Description of Exxon Plant Transient Simulation Model for Pwrs. ML17320A9721983-09-30030 September 1983 Forwards First Round Questions on Exxon Plant Transient Code,Based on Review of Proprietary Rept, Description of Exxon Nuclear Plant Transient Simulation Model for Pwrs. ML20080B5631983-08-12012 August 1983 Forwards Draft Preliminary Review of Limerick Generating Station Severe Accident Risk Assessment,Vol I:Core Melt Frequency. Rept Satisfies Milestone for Task 1 of Project 3 Under FIN A-3393 ML20211D5971983-04-11011 April 1983 Forwards Summary of Independent Development of Finite Element Models & Determination of Natural Frequencies for Piping Problems in Containment Spray Discharge Line & Accumulator Loop 4 ML20132B4961983-02-11011 February 1983 Forwards Evaluation of Generic Key Indicators for Project Engineering/Design Activities at Facilities ML20072L7101982-12-20020 December 1982 Forwards BNL 821213 Memeo Re Degraded Core Accidents at Facilities,Per Task III.3 Defined in Design Basis for Hydrogen Control Sys in CP & OL Applications. No-cost Extension to Contract Requested ML20079J5641982-12-16016 December 1982 Summarizes Findings of 821207-08 Plant Tour Re Use of PORVs or Depressurization Scheme for Removing Decay Heat.Addl Info Requested Includes General Arrangement & Isometric Drawings of Piping Near San Onofre Pressurizer ML20027D1751982-10-18018 October 1982 Responds to 820806 Request to Evaluate Rapid Depressurization & DHR Sys for C-E Plants W/O Porvs, Discussing Role of Task Action Plan A-45, Shutdown Heat Removal Requirements, in Supporting Evaluation of Facility ML20126F4791982-10-0101 October 1982 Requests Permission to Observe Upcoming Types A,B & C Tests at Listed Facilities,Per FIN B-0489, Containment Leak Rate Testing ML20072L6851982-09-21021 September 1982 Forwards Analysis of Full Core Meltdown Accidents in Grand Gulf Reactor Plant, Draft Informal Rept.Rept Satisfies Preliminary Rept Milestone for Task I Defined in Safety Evaluation of Core Melt Accidents:Cp,Ml & OL Applicants ML17276B0731982-02-10010 February 1982 Comments on Const of Two Power Reactors by Skagit/Hanford Nuclear Project at Hanford.Purchasing & Finishing Terminated Wppss Plants at Hanford & Satsop Should Be Considered as One Alternative to Proposed Action 1989-01-13 |
Text
.
}
/
OAK RIDGE NATIONAL LABORATORY
'
- OPERATED BY
' union CARB1DE CORPORATION NUCLEAR DIVISION O
PO5T OFFICE BOX Y OAK RIDGE, TENNESSEE 37830 October 1,1982 Mr. J. P. O'Reilly Regional Administrator, Region II U. S. Nuclear Regulatory Commission 101 Marietta Street, NW -
Suite 3100 .
Atlanta, GA 30303
Dear Mr. O'Reilly:
I am working on the NRC sponsored project " Containment Leak Rate Testing" (Fin. No. B0489). The NRC project manager is E. G. Arndt (FTS 443-5860).
One aspect of the work description requires the witnessing of at least one test each of Type A, B, and C tests. I have been informed of three St. Lucie upcoming)
(October ; Sequoyah tests in your region (November); which Ferry and Browns I would like to witness:
(December). If possible, I would like to arrive at least one day prior to the tests in order to observe the pre-test procedures. I have discussed this matter with Frank Jape and Herbert Whitener is also aware of my request. Also, I have sent Form 277 to the regional security office. This letter is a written request that the NRC obtain the appropriate clearances for me so that I may 6bserve these tests.
Sincerely, e ~S. .
.~2 James R. Dougan