Further Response to FOIA Request for Documents Re NRC Consideration of Effects of External Events Upon Emergency Response Planning.App B Documents 1-12 & 15-20 Encl & in Pdr.App B Documents 13 & 14 Withheld (Ref FOIA Exemption 5)
ML20117B786
Person / Time
Site: Beaver Valley, Turkey Point, Diablo Canyon, 05000000
Issue date: 12/04/1984
From: Felton J
NRC OFFICE OF ADMINISTRATION (ADM)
To: Bell N
NUCLEAR INFORMATION & RESOURCE SERVICE
Shared Package
ML20114F973 List:
References
FOIA-84-661, REF-10CFR9.7 NUDOCS 8505090242
Download: ML20117B786 (4)


Text

l 00 L - Dl y

~ [

.g'o,,

UNITED STATES NUCLEAR REGULATORY COMMISSION l

e o

g

.E WASHINGTON, D. C. 20555

/

yn Ms. Nina Bell Assistant Director Nuclear Information and Resource Service 1346 Connecticut Avenue, NW, 4th Floor IN RESPONSE REFER Washington, DC 20036 TO F01A-84-661

Dear Ms. Bell:

This is in further response to your letter dated August 6,1984, in which you requested, pursuant to the Freedom of Information Act (FOIA), documents relating to NRC's staff and Commission consideration of the potential complicating effects of external events such as earthquakes upon emergency response planning.

The documents listed on Appendix B are responsive to your request.

Documents 4, 5, 6, and 19 have previously been made available at the NRC Public Document Room (PDR) for inspection and copying. Access to these documents may be acquired by referring to the accession number listed by each of these documents. With the exception of documents 13 and 14, which are discussed below, the remaining documents are being placed at the PDR in the file folder F01A-84-661.

Documents 13 and 14 contain information which is being withheld pursuant to Exemption 5 of the FOIA (5 U.S.C. 552(b)(5)) and 10 CFR 9.5(a)(5) of the Commission's regulations.

Document 13 is a 13-page memorandum to S. Trubatch from C. W. Reamer regarding the Diablo Canyon Order on Earthquakes and Emergency Planning. This memo contains predecisional advice and recommendations regarding the licensing of Diablo Canyon.

Release of this memorandum would tend to inhibit the open and frank exchange of ideas essential to the deliberative process. This document is being withheld in its entirety. There are no reasonably segregable factual portions.

Document 14 is a one-page memo to H. Plaine from S. Chilk regarding the requirements for and discussion of earthquakes and emergency planning for Diablo Canyon.

This memo also contains predecisional advice and recommendations regarding the licensing of Diablo Canyon.

Releasing this memo would tend to inhibit the open and frank exchange of ideas essential to the deliberative process. The nonexempt portions of this memo are being placed in the PDR in file folder F0IA-84-661.

8505090242 841204 PDR FDIA BELL 84-661 PDR f

y

s '.

?

4 i

Other documents relating to earthquake activities in emergency planning have been previously addressed in response to your request F01A-84-795.

Pursuant to 10 CFR 9.15 of the Commission' regulations, it has been determined that the information withheld is exempt from production or disclosure, and that its production or disclosure is contrary to the public interest. The person responsible for this denial is Mr. John C. Hoyle, Assistant Secretary of the Commission.

This denial may be appealed to the Commission within 30 days from the receipt of this letter. Any such appeal must be in writing, addressed to the Secretary of the Comission, U.S. Nuclear Regulatory Commission, Washington, DC 20555, and should clearly state on the envelope and in the letter that it is an " Appeal from an Initial F0IA Decision."

This completes NRC's action on this F0IA request.

Sin rely, r

/ f' g

J. M. Felton, Director Division of Rules and Records Office of Administration

Enclosure:

As stated h

Re: P01404-661 APPEE!X 1'

Undated Section 13 - Dominant Contributors to Seismic Risk - An Appraisal (53 pays) 2.

Undated Memo to J. Davis, DeYoung. Denton, Cunningham, Felton, Foucharti and Regional Administrators fron Frank Gillespie re: Proposed knhents to 10 CFR Part 50. Appendix E; Consideration of Earthquakes in the Context of Emergency Pmpamdness w/ enclosure Proposed Ru)amaking Packaoe (17 Pages) 3.

Undated Memo to tne Counission from William J. Dircks, subject:

f

" Emergency Planning.

(8pages) 4.

3/16/81 Memo to W. Dircks from J. Mark re: Emergency Planning at Nuclear Facilities During and.Following Natural Events PDR No. 8103230326 (1 page) 5.

5/13/81 Letter to Robert Dietch from' Robert Tedesco re: Clarification of Staff Letter of Deceder 17, 1980 Regarding Effect of Earthquakes on Emergnecy Responses at San Dnofre Generating Station PDR No. 8107090552 (2 pages) 6.

5/13/81 Memo to J. Mark from William Dircks re: Emergency Planning at

}

Nuclear Facilities During and Following Natural Events PDR No. 8111050489 (2 pages)

{

7.

8/4/81 Before the ASLB - EC Staff Coments with Respect to the Board's Drder of July 29, 1981 Raising an Issue Concerning Earthquakes l

and Eergency Planning (3 pages) 8.

2/21/83 Memo for Chaiman Palladino from William J. Dircks, subject:

" Emergency Planning and Seismic Hazards."

(6pages) 9.

10/22/84 Uses of Probabilistic Estimates of Seismic Hazard and Nuclear Power Plants in the U.S. by Leon Reiter (14 pages) 10.

1/18/84 Memo to Harold Denton from Themis Speis re:

Earthquakes and Emergency Planning.

(1 page) 11.

4/4/84 Memo to Edward Jordan from Richard Vollmer re:

Comments on-the FEMA Draft National Plan for Federal Response to a Catastrophic Earthquake.

(1 page) 12.

4/30/84 Memo to P. Williams from Robert Jackson re:

Geosciences Branch Review of Draft Comission Paper on Emergency Preparedness.

(1 page) 13.

7/30/84 Memorandum from C.W. Reamer to S. Trubatch re:

Diablo Canyon Order on Earthquakes and Emergency Planning.

14.

7/31/84 Memorandum from S. Chilk to H. Plaine re:

Requirements -

Discussion of Earthquakes and Emergency Planning for Diablo Canyon.

(1 page)

I

Re: F01A-84-44 /

15. 8/1/84 Memo to Herzel Plaine from Samuel Chilk re: Staff Requirements -

Discussion of Earthquakes and Dnergency Planning for Diablo Canyon and Discussion of Stay Motion (1 page) 16. 8/7/84 Memo to Herzel Plaine from Samuel Chilk re:

Staff Requirements -

Discussion /Possible Vote on Order on Earthquake and Emergency Planning for Diablo Canyon (1 page) 17. 9/25/84 Memo to Ray Fraley from Frank Gillespie re: ACRS Review of Proposed Rule Change to 10 CFR Part 50, 50.47 and Appendix E; Consideration of Earthquakes on Emergency Preparedness (2 pages) 18.

10/4/84 Memo to William Dircks from Robert Minogue re:

Proposed Amendments to 10 CFR Part 50, Section 50.47 and Appendix E; Consideration of Earth Preparedness (3 pages) quakes in the Context of Emergency 13.

10/10/84 SECY-84-394 - Proposed Amendments to 10 CFR Part 50, Section 50.47 and Appendix E; Consideration of Earthquakes in the Context of Emergency Preparedness (SECY Paper File) 20.

10/18/84 Memo to Connissioners from John Zerbe re:

on Earthquake Effects on Emergency Planning (2 pages) Proposed R b

1 M

_