ML20099H896

From kanterella
Jump to navigation Jump to search
Evaluation of Interim Measures & Procedures Re Redundant Alternate Shutdown Sys Fuses
ML20099H896
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 03/08/1985
From:
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
To:
Shared Package
ML20099H895 List:
References
JPN-85-21, NUDOCS 8503190524
Download: ML20099H896 (12)


Text

i e

i 1

ATTACHMENT NO. 1 TO JPN-85-21  ;

)

An Evaluation of Interim Measures and Procedures Recardina Redundant Alternate Shutdown System Fuses 4

New York Power Authority James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 March 8, 1985 e

8503190524 850315 PDR ADOCK 05000333 G PDR

J .

i' l.0 Introduction

' ~

! IE Information Notice No. 85-09 (Reference 3) describes a condition at Kansas Gas and Electric Company's Wolf Creek nuclear power plant

that could disable the plant's alternate shutdown system in the

! event of a fire in the control room. Fire damage could open fuses rendering the equipment inoperable if the fuse opens before control is transferred to the alternate shutdown circuit.

As a result of an independent, third party review of the fire protection programs and systems, the Authority has recently identified a similar condition at our FitzPatrick plant.

Specifically, the scheme used to transfer control of shutdown systems to the alternate shutdown system does not include redundant fuses.

The Authority has analyzed this condition. This analysis shows that the operators can successfully recover by manually replacing the blown fuse (s). As a result, we will implement both interim compensatory measures until long-term corrective actions are completed.

Section 2 of this report describes the existing alternate shutdown provisions. Section 3 describes the interim compensatory measures that will be implemented until the corrective modifications described in Section 4 can be completed. Section 5 is an analysis

~

to demonstrate that the interim procedures and measures are adequate to prevent the plant from reaching an.. unrecoverable condition.

2.0 Existina Alternative Shutdown Features This section describes the major features of the existing alternative shutdown capability at the James A. FitzPatrick Nuclear Power Plant. Included in this desc'ription are the locations and functions of the remote shutdown panels.

1 (A) Remote Shutdown Panel 25 RSP This remote shutdown panel is located on the south side of i the 300 ft. elevation of the Reactor Building. Process

! . parameters needed for safe shutdown using the alternate safe shutdown capability have been provided at 25 RSP.

These parameters are as follows:

o Suppression Pool Temperature j o Suppression Pool Level

^

o RHR Service Water Loop-B Flow 1 o RHR Loop-B Flow From Loop-B Injection ,

o RHR Pump-D Discharge Pressure >

E o Drywell Temperature  :

1 i  ;

I Other parameters, including reactor vessel pressure and

, reactor vessel level are monitored at instrument rack 25-6 f

located opposite panel 25 RSP. In addition to chese

' available indications, panel 25 RSP has isolation / control 1

i .

[  ;

4 o

i

  • switches and position indication for the following components:

o 02 SOV-17 o 27 SOV-126B 4

o 27 SOV-129B o 10 MOV-66B o 10 MOV-25B

! o 10 MOV-89B I o 23 MOV-16 o 600V bus 11600 (L16) incoming breaker 11602 i'

Also included on 25 RSP are control switches for RHR Pump

, D (10 P-3D) and RHR Service Water (RHRSW) Pump B I

(10P-1B). 25 RSP is provided with a dedicated, sound-powered, communications system which allows communication with other shutdown panels.

(B) Auxiliary Shutdown Panel 25 ASP-1 i Auxiliary Shutdown Panel 25 ASP-1 is located on the Reactor Building 272 ft. elevation. 25 ASP-1 provides isolation and control capability for the following valves:

o 10 MOV-149B (RHRSW to RHR Cross-tie)

, o 10 MOV-12B (RHR Heat Exchanger Outlet) o 10 MOV-70B (Steam Inlet Isolation Valve) 10 MOV-166B o (Heat Exchanger Vent to Torus)

o 10 MOV-148B (RHRSW to RHR Cross-tie) i .

Also included on 25 ASP-1 are position indicators for main steam isolation valves 29 AOV-86 A. B, C, and D and a dedicated communications system.

(C) Auxiliary Shutdown Panel 25 ASP-2

, Auxiliary Shutdown Panel 25 ASP-2 is located on the Reactor Building 242 ft. 8 in. elevation. Isolation and control for the following valves are provided there:

1 ,

o 10 MOV-13D (RNR Pump D Suction-Torus) o 10 MOV-16B (RHR Pump Minimum Flow Bypass) o 10 MOV-21B (Heat Exchanger Discharge to Torus) o 10 MOV-27B (LPCI Outboard Valve) o 10 MOV-15D (Torus Cooling Isolation Valve) o 10 MOV-39B (Torus Cooling Isolation Valve) o 23 MOV-25 (HPCI Minimum Flow to Suppression Pool) o 10 MOV-65B (RHR Heat Exchanger Inlet) o 23 MOV-60 (HPCI outboard Isolation Bypass) o 29.MOV-77 (Outside Main Steam Drain Isolation) o 12 MOV-18 (RNCU Supply Outboard Isolation) o 12 MOV-80 (RWCU Supply Outboard Isolation Bypass)

, Like the other alternate shutdown panels, 25 ASP-2 has been provided with'a dedicated communication system.

5

(D) Auxiliary Shutdown Panel 25 ASP-3 Emergency Diesel Generators B and D are provided with local control and isolation from the Main control Room.

The Control Panel is located in the Diesel Generator Switchgear Room B at the 272 ft. elevation. The control panel provides isolation along with local control, indication, and metering capabilities for the Emergency Diesel Generator and emergency bus breakers listed below:

1. Isolation For -

o Diesel-Generator Voltage Regulation o Diesel-Generator Metering o Diesel-Generator Synchronizing Permissive o Diesel-Generator Engine Speed o Diesel-Generator Output Breaker Operation o 10P-3D (RHR Pump D) o 10P-1B (RHR SW Pump B)

2. Isolation and Control For -

o Diesel-Generator Start /Stop o 46 MOV-102B (Emergency Service Water (ESW) minimum flow valve) o 46 MOV-101B (ESW supply to vital equipment)

~

o 46 P-2B (ESN pump 2B) o Breaker 10614 o Breaker 10604 o Breaker 10660 o Breaker 12602 o Breaker 10614 Synchronizing Circuit 25 ASP-3 has been provided with a dedicated communications system.

3.0 Interin Measures and Procedures The Authority will provide procedural measures to compensate for the lack of redundant fuses for alternate shutdown components. These

. interim measures will remain in effect until the long-term corrective modifications described in Section 4 are complete.

These interim procedures have been drafted based upon the new procedure for alternate shutdown. Operator actions within these procedures have been sequenced to assure that an unrecoverable condition will not occur. ,

' These procedures will require operators to check shutdown panels for e indications of open' fuses on alternate shutdown equipment. Open or-

. blown fuses are readily detectable by a loss of component indicating lights on the shutdown panel. After having detected an:open fuse, the operator is instructed to proceed to the location of the blown fuse. (An exception to this will be if another operator is significantly closer to the open fuse, an operator may ask the operator closer to the fuse's location to perform the replacement.)

]

f l

Replacement fuses will be located near their respective power sources. Replacement fuses will be clearly labeled to identify them. A fuse pullar will also be provided near each location where l

fuse replacement is required.

The procedure instructs the operator to identify and remove the blown fuse, replacing it with a spare replacement fuse. The operator will then return to the safe shutdown panel and continue the shutdown procedure.

4.0 Lonc-tern Modifications The Authority will install redundant fuses in alternate shutdown system circuits to correct this condition. Figure No. 1 illustrates this concept for a typical motor operated valve. Redundant fuses will not be in the circuit during normal plant operation.

5.0 Evaluation of Interim Measures This section will examine the feasibility of replacing blown fuses in hot shutdown systems to restore the equipment to operable. Using the procedure outlined in Section 3 of this report, an estimate of the amount of time required to initiate safe shutdown has been made.

The Authority will conduct a timed walk-through of this interim shutdown procedure to confirm that the required actions can be completed within the time available. This walk-through will be conducted prior to start-up from the (Reload 6/ Cycle 7) refueling outage now in progress.

Table No. 1 is a list of the components, fuse loca'tions and isolation switch locations associated with remote shutdown components. .

5.1 Assumptions The following conservative ascumptions were made for the purposes of this evaluation:

1. No more than twenty-percent of all fuses (approximately 10 fuses) associated with the control power circuits for alternate shutdown equipment require replacement as the result of a fire in the Control Room, Relay Room or Cable Spreading Room. This assumption is very conservative considering the level of fire protection present and the

- almost constant presence of plant personnel.

2. No credit has been taken for fire protection measures or systems currently installed in the Control Room, Relay Room or Cable Spreading Room. (A complete description of the existing area-wide carbon dioxide suppression system is in Reference 2.)

i.

d  :

3. Only five qualified persons are required to operate the j . . safe shutdown equipment subsequent to a fire. No credit i

is taken for any personnel not required to be on-site at I all times.  !

l 4. A period of ten minutes is available from the time that the operator manually scrans the reactor, trips the main turbine, verifies that all control rods are fully

! inserted, closes the Main Steam Isolation Valves (MSIVs),

i and leaves the Control Room. At this point, the reactor vessel is fully isolated. The only reactor coolant inventory loss is through the Safety / Relief Valves, which actuate intermittently to relieve pressure and provide core cooling. (The detailed basis for this is described in Attachment 1 to Reference 1, response to Question No.

l.) (The Authority considers the time actually available to be significantly greater than the ten minutes conservatively assumed. If ADS does not occur until 20 minutes after reactor scram and isolation, reactor water level will fall to approximately thirty-six inches below the top of active fuel (TAF) during depressurization and injection. Level will remain below TAF for approximately 120 seconds and then rise above the TAF and continue to l increase. This extremely conservative analysis showed I that, even after assuming loss of all high pressure makeup  ;

coincident with reactor scram and isolation (which is not ,

. considered credible), the core will not be uncovered if l ADS is actuated within ten minutes.) )

5. Control room operators (other than those mentioned in 3 above) who are also members of the plant's fire brigade may be utilized for fuse replacement before assuming their roles as fire brigade members.

l 6. The analysis assumes that the Shift Supervisor may dispatch one or more operators to the alternate shutdown panels in advance of scramming the' reactor and transferring control the shutdown panels. These operator (s) will use this time to familiarize themselves

!' with system lineups, check for and replace any open or blown fuses and establish communications. This is a

! realistic assumption considering the type of improbable L event required for a control room evacuation.

I 5.2 Operations Recuired to Achieve Safe Shutdown This section describes the operations requirod to achieve safe shutdown using the systems and components identified in previous

[ Authority submittals (Reference 2 and 4).

2

[

The post-fire scenario has been depicted on an operator-by-operator r basis. The actions required by each operator are depicted in a i chronological fashion to describe the integrated operation of the alternative shutdown system. The local control stations to be used, along with the functions to be performed at each, are specified.

+

1 .

l-Post-fire operational timeliness exemplify the sequence and duration of the required tasks for each operator. The actual sequence of

=

, post-fire activities will be determined by the Shift Supervisor.

These timelines are not intended to prescribe mandatory actions for fires of lesser magnitude.

! Shift Supervisor As the individual designated to be in charge of shift operations,  !

i the Shift Supervisor determines the appropriate response to a severe l l fire. Station Procedures require the Control Room to announce the l l receipt of a fire alarm over the station paging system and to notify j the fire brigade. If the Shift Supervisor decides that significant i potential exists for a situation developing that would require evacuation of the control room, the Shift Supervisor may preliminarily dispatch one or more operators to remote shutdown panels before evacuating the Control Room.

l The operators required for safe shutdown will be dispatched as follows:

1. Shift SuDervisor (SS). After the reactor has been scrammed, i

the turbine tripped, and safe shutdown personnel dispatched, the Shift Supervisor will proceed to the Remote Shutdown Panel 25 RSP.

, 2. Senior Nuclear Operator (SNO). The Senior Nuclear Operator will proceed to Auxiliary Shutdown Panel 25 ASP-3.

l 3. Nuclear Control ODerator (NCO). The Nuclear. Control Operator will proceed to Remote Shutdown Panel 25 RSP along with the j

Shift Supervisor to provide any necessary assistance.

l 4. Auxiliary Operator. An Auxiliary Operator will proceed to Auxiliary Shutdown Panel 25 ASP-1 after isolating one scram i header.

5. Auxiliary ODerator. An Auxiliary Operator will proceed to

! Auxiliary Shutdown Panel 25 ASP-2 after isolating one scram header.

Communications will be established between the operators and the Shift Supervisor through the use of the dedicated communications system at the safe shutdown panels. The Shift Supervisor will direct the actions of the operators controlling the safe shutdown panels.

Shift SuDervisor The Shift Supervisor will be with the NCO at panel 25 RSP. The NCO will be in communication with the other alternate shutdown panels.

The SS will use the indication available at panel 25 RSP and information supplied by the remaining operators to evaluate the plant status and coordinate the plant shutdown.

o Senior Nuclear Operator (SNO)

.The Senior' Nuclear Operator will proceed directly to panel 25 ASP-3. The SNO will verify the availability of electric power at the emergency buses. He will also take local control of B and D Emergency Diesel Generator by operating the control switches on 25 ASP-3. Any fuses that require replacement will be replaced to regain control. He will establish communications and report power system status to the NCO. He will then start the emergency diesel-generators, as required. The SS will then direct the SNO in any follow-up actions that are required.

Nuclear Control Operator (NCO)

The Nuclear Control Operator will man the Remote Shutdown Panel 25 RSP with the SS. The NCO will isolate the components controlled on 25 RSP. The NCO will identify any open fuses that may exist, replace them in accordance with the interim alternative shutdown procedure and. establish communications with the other operators.

The NCO will verify the system lineup at 25 RSP. The SS will direct the NCO to operate the safe shutdown systems as required. This will involve opening blowdown valves after starting the RHR pumps and then injecting water into the vessel.

Auxiliary ODerator

'~

One AO will proceed to panel 25 ASP-1 and operate isolation switches to prevent spurious operations. Any fuses which may be open will be replaced by the AO. The AO will establish communications with the NCO, verify the component lineup on 25 ASP-1 and report to the NCO.

Auxiliary Operator

. He will proceed to 25 ASP-2 and isolate components, replace open fuses with assistance from NOA, verify system lineup at 25 ASP-2, and report to the NCO.

5.3 Summary In no situation did the time required to manually actuate the ADS valves exceed ten minutes. This analysis, using conservative assumption, has shown that safe shutdown can be accomplished assuming that a fire in the control room, relay room or cable spreading room blows twenty percent of the fuses associated with alternate shutdown circuits.

6.0 References

~

1) PASNY letter, J.P. Bayne to D.B. Vassallo, (J PN-8,2-87 )

dated November 22, 1982 regarding reassessment of fire protection features for conformance to Appendix R to 10CFR50.

t

2) PASNY letter, J.P. Bayne to D.B. Vassallo. (JPN-82-61) dated July 13, 1982 "A Reassessment of the James A.

FitzPatrick Nuclear Power Plant for Conformance to the Requirements of Appendix R to 10CFR50", as amended.

3. IE Information Notice No. 85-09, " Isolation transfer Switches and Post-Fire Shutdown Capability," dated January 31, 1985.
4. PASNY letter, J.P. Bayne to T.A. Ippolito. (JPN-80-53) dated November 20, 1980, transmits revised " Safe Shutdown Analysis" dated October 1980.
5. NRC memorandum, L.S. Rubenstein to R.J. Mattson, dated December 3, 1982 regarding use of the Automatic Depressurization System (ADS) and Low Pressure Coolant Injection (LPCI) to meet Appendix R shutdown goals.

I 4

5

m

~

($, a, 'filYl$c'a?['N Wirne. cwa"r soa .arsss.s 6/ 2foun k e<sJ { -

_v v -- - --

1- y x

, . .~

i

~ ' I)g _

+ '

53 11 Tp , 33

55 c e , ,,

o ' g',3,,

7 -420 pg.gg

',,, 'T 33- ity15 =  ;

l'esrau, ar * ' s 1

stafLT 5 en s., o y m8es%.vtsatsy 4 688*' ) sw 73 p.

! ereJ eu e -

j aree<u ses s- a e g.cg) a93-(L***L) i , -9., m to M C 1-1 9 sd ! g,g, g i

srgrat ss a n as e t) ..esA 59s g ,j ge O, Z

..:dtr

$ct d

" 'w 'A

< t.e i'a-10A

<e

' '-' ) 5d,t->  ;.3  :- ..A-rus

=5d (st 5

(c)g,,,. gg

,, y f 4-wses y o

,,...,. e o .s.,

g g

.2 =: ...- s,. c , ,,

99t W MS) 1 p

> 0 ii T_ - ggga ' .

g.si E fe Il%- I 08 0-U s . .-J!g.33 99-I '"

teseest st!'47 M g atsee'C Srtfst e .e g t.c a t , 3! 1 I *** f te**L P i j$ gggggg, m o 5ftrcy o, o, a 41  ; b 42 C H*

at c e sy (st f ale N- #5e 2 d2 g ggggL ) g, .

    • ,,,, g,
  • n

/sn $ u u i b 43 [.

4 i t - m o Yeo ' x 1- 8 Com!T Al >lMra87 S PA AY. 00T Deptp WAlvE 80MoV-168 CAT Nf. sauts.') Mcc, all ( ater) $ @

M

? fret 4sAPee% DesPt AF cs prva'L su c e ms.rm sv r. =,

'ng;s OL! D.S2 o seASSs Src r z sw619tr468 sier. i .. " * ' 5 ,,' 5'

  • 3 *- 8'l o-M

" n ~'J3-74 _ gwngjwge) f 3 _

db II C IRCusT IT FLP5E.

i -

sak

'" 3 To A>Ju 9 3 Afo7:

GE pwG 791E46l SH 13 CANueT 8E Postfp -

i -

.cy. -

-iRiftte$ I A -IA'fE8'S to csL Rf"'Tr c,gegr of/*J TYPICAL Con 3TiteL CIRCO 7 - CoMTReL Room llELAT ReeM _ caste .smsAss47r. AasA local valve 15eLATsoe3 SlvsTCHES

  • P*g3 1 ef 2 NEW YORK POWER AUTHORITY James A. FitzPatrick Nuclear Power Plant TABLE 1 Remote Shutdown System Components FUSES AND ISOLATION SWITCH LOCATIONS SHUTDOWN FUSE LOCATION ISOL SW LOCATION COMPONENT MCC/SWGR ELEVATION PANEL NO. ELEVATION Rmam ID NO.

H06SWCR 10P-3D 10640 DGB-272' 25 ASP-3 DGB-272' H06SWGR 10P-1B 10620 L26SWGR ELEC BAY 46P-28 BKR12610 272' MOTRS:

MCC 165 10 NOV-66B COMP B1 RB-243' 25 RSP RB-300' 1. Distance between fuse MCC 165 located in MCC C163, 10 NOV-25B COMP A4

" 25 RSP RS-300' C 165, BMCC 2 & BMCC MCC 165 4 and 25 ASP-2, is 10 NOV-27B COMP B2 " 25 ASP-2 RB-243' about 30'.

MCC 163 i 10 MOV-39B COMP F1 " 25 ASP-2 RB-243' 2. Distance Between fuse l MCC 163 located in MCC C161 &

10 MOV-13D COMP J5 " " " 25 ASP-1 is about 20' I

MCC 163 i 10 MOV-15D COMP G4 " " " 3. Distance between fuse I MCC 163 located in H06 l 10 MOV-65B COMP F2 " " " breakers and 25 ASP-3 l MCC 163 is about 10' and 10 MOV-16B COMP H3

" " " distance between fuse MCC 163 located in diesel

" " " generator panels and 10 MOV-21B COMP He BMCC-2 25 ASP-3 is about 75' 23 MOV-60 COMP OE2 BMCC-2 4. Distance between- fuse 29 MOV-77 COMP OA1 " " " located in L26 SWGR &

BMCC-4 MCC C262 and 25 ASP-3

" " " is about 250'.

12 MOV-18 COMP 082 BMCC-4 12 MOV-80 COMP ODI " " " 5. Distance between fuse BMCC-4 located in L16 SWGR 23 MOV-25 COMP 081 " " " and 25 RSP is about MCC C161 100'.

10 MOV-1488 COMP-83 RB-272' 25 ASP-1 RB 272' ,

MCC C161 10 MOV-1498 COMP A3 e

1 l

. p nn 2 et 2 d

e .

TABLE - 1 (cont'd) l SHUTDOWN FUSE LOCATION ISOL SW LOCATION COMPONENT MCC/SWGR ELEVATION PANEL NO. ELEVATION REMARKS ID No.

MCC C161 10 MOV-12B COMP B1 RB-272' 25 ASP-1 RB-272' MCC C161 10 MOV-70B COMP A2 " " "

MCC C161 10 MOV-1668 COMP C1 " " " l MCC C161  ;

10 MVO-89B "

COMP B2 25 RSP RB-300'

' 29 SOV-86A 25 ASP-1 "

25 ASP-1 RB-272" 29 SOV-86B " " " "

29 SOV-86C "

29 SOV-86D " " " "

MCC C262 ELEC. BAY 46MOV-101B COMP D1 272' 25 ASP-3 DGB-272' MCC C262 46MOV-1028 COMP D2 " " "

93-EDGB(cont) ECPB DGB-272' " "

93-EDGD(cont) ECPD 93-EDGB(inst) ECPB " " "

t

. 93-EDCD(inst) ECPD " " "

H06 BKR 93-EDGB 10602 * " "

H06 BKR 93-EDGD 10612 " " "

H06 BKR TIE BKR 10604 " " "

H06 BKR TIE BKR 10614 " " "

H06 BKR BKR 10660 10660 " " "

BMCC 6 -

23 MOV-16 COMP-0A1 RB-272' 25 RSP RB-300' L26 SWGR ELEC. BAY BKR 12602 COMP 28 -272' 25 ASP-3 DGR-272' L16 SWGR BKR 11602 COMP IB RB-300' 25 RSP RB-300' 27 SOV-126B 25 RSP " " "

27 SOV-129B 25 RSP " " "

02 SOV-17 25 RSP " " "

-. . _ _ _ -.