Informs That Util Completed Const Work on 840706 Re Joint Reinforcement in Masonry Walls Per IE Bulletin 80-11.No Structural Credit Taken for Dur-O-Wall in Masonry Block Walls Near safety-related Equipment
ML20093G129
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 07/06/1984
From: Brey H
PUBLIC SERVICE CO. OF COLORADO
To: Johnson E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
IEB-80-11, P-84195, TAC-42925, NUDOCS 8407230333
Download: ML20093G129 (1)


Text

. - . _ ..

1 public Service Company *P Odwado P.O. BOX 840 DENVE R. COLORADO 80201 2420 W. 26th Avenue, Suite 100-D Denver, Co 80211 July 6, 1984 Fort St. Vrain Unit No. I P-84195 S

  1. h'h]

Mr. E. H. Johnson, Chief Reactor Project Branch 1 Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive Suite 1000 Arlington, Texas 76012 DOCKET NO. 50-267

SUBJECT:

I&E Bulletin 80-11 Joint Reinforcement in Masonry Walls

REFERENCE:

PSC Letter to E.H. Johnson from 0.R. Lee Dated November 8, 1983 (P-83364)

Dear Mr. Johnson:

This letter is to inform you that on July 6,1984 Public Service Company of Colorado has completed the construction work for rein-forcing those masonry block walls in which credit had been previously taken for the Dur-0-Wall joint reinforcement. No structural credit is now taken for the Dur-0-Wall in the masonry block walls located near safety related equipment at FSV.

Mr. Wagner of the NRC was advised on July 3, 1984 that the completion date for this project would be delayed a few days from the original July 2,1984 date as stated in the referenced letter. Mr. Wagner agreed that this would be acceptable and requested that the NRC be notified as soon as the project is complete.

If you have any questions concerning this project, please contact Mr. M. H. Holmes at (303) 571-8409.

Very truly yours, DO$fo on@f., .

PDR H. L. Brey, Manager '

Nuclear Engineering Division HLB / RAG:pa -