ML20083E545

From kanterella
Jump to navigation Jump to search

Application for Amend to Licenses DPR-57 & NPF-5,revising Tech Specs to Clarify Operability Conditions for Drywell Hydrogen & Oxygen Analyzers to Meet NUREG-0737,Item II.F.1 Requirements
ML20083E545
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 12/21/1983
From: Head G
GEORGIA POWER CO.
To: Stolz J
Office of Nuclear Reactor Regulation
Shared Package
ML20083E546 List:
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-2.F.1, TASK-TM NED-83-074, NED-83-74, TAC-53454, TAC-53455, NUDOCS 8312290270
Download: ML20083E545 (2)


Text

,

Georga Poser Company 333 P;edmont Avenue AGmta Goug,a 30308 r TeMphum 404 52 & 7893 MAng Ad?ess Pcst Othee B.n 4M5

' AtLeta Gemma 30302 G. F. Head Spr':or V re Prr smo Power Gener 60n NED-83-074 December 21, 1983 Director of Nuclear Reactor Regulation Attention: Mr. John F. Stolz, Chief Operating Reactors Branch No. 4 Division of Licensing U. S. Nuclear Regulatory Commission Washington, D. C. 20555 NRC DOCKETS 50-321, 50-366 OPERATING LICENSES PPP-57, NPF-5 EDWIN I. HATCH NUCLEAR PLANT UNITS 1, 2 REQUEST TO CHANGE HYDROGEN AND OXYGEN POST-ACCIDENT MONI1DRING TECHNICAL SPFCIFICATIONS Gentlemen:

In accordance with the provisions of 10 CFR 50.90 as required by the provisions of 10 CFR 50.59(c)(1), Georgia Power Company (GPC) hereby proposes an amendment to the Fx! win I. Hatch Units 1 and 2 Technical Specifications (Appendix A to each Operating License). These changes would clarify the operability conditions for the drywell H2 and 02 analyzers to meet the requirements of NUREG-0737 Item II.F.1; which is, that continuous monitoring of these gases be available within 30 minutes of the initiation of a safety injection.

These changes would still maintain the present Limiting Conditions for Operation of this system for both units. Those limits allow reactor operation with an H2 and 02 analyzer inoperable for up to 7 days on Unit I and 30 days on Unit 2. However, these changes would alter the surveillance requirements for these analyzers, which were recently replaced with a different model, to conform with the new manufacturers recommendations for frequency of channel checks and calibrations for the new model.

Both the Plant Review Board and the Safety Review Board have evaluated these proposed Technical Specification changes and both have determined that the implementation of these proposed changes would in no way constitute on unreviewed safety question. The probability of occurrence or the consequences of an accident or malfunction of' safety-related equipment would not be increased above those analyzed in the FSAR, because the safety function of the drywell H2 and 02 analyzers as described in the FSAR 8 ,312290270 83 ,1221 9 ,

Georgia Powerkh Director of Nuclear Reactor Regulation Attention: Mr. John F. Stolz, Chief Operating Reactors Branch No. 4 December 21, 1983 Page Two would be maintained by this change. The possibility of an accident or malfunction of a different type than analyzed in .the FSAR would not result from this change because the allowed operational modes for these analyzers would be essentially unaltered and no new failure modes would be introduced. The margin of safety as defined in Technical Specifications would not be reduced by this change because the Limiting conditions for

( Operation of these analyzers remain intact.

Instructions for incorporation of these changes (Attachments 1 and 2),

along with copies of affected Technical Specifications pages are enclosed.

Included with this proposal is a detemination of amendment class (Attachment 3). We have detemined this to be one Class III amendment and one Class I amendment, and have enclosed the appropriate payment.

As required by 10 CFR 50.92, an analysis for each proposed Technical Specification change is enclosed with this submittal (Attachments 4 and 5).

Pursuant to the requirements of 10 CFR 50.92, J. L. Ledbetter of the Georgia Department of Natural Resources will be sent a copy of this letter and all applicable attachments.

G. F. Head states that he is Vice President of Georgia Power Company and is authorized to execute this oath on behalf of Georgia Power Company, and that to the best of his knowledge and belief the facts set forth in this letter are true.

GEORGIA POWER COMPANY By: k,S. b '

G. F. Head Sworn to and subscribed be ore mee this -- 21st nsy day ruuc,ofGwaa.

Decem b dett 53 My Commiss:en Expires Sept.18,1987 Notary Public CBS/mb Enclosure xc: H. C. Nix J. P. t.'Reilly (NRC Region II)

Senior Resident Inspector