ML20082L884

From kanterella
Jump to navigation Jump to search
Forwards IE Const Appraisal Team Insp Repts 50-440/83-31 & 50-441/83-30 on 830822-0923 & Executive Summary,Apps a & B. No Noncompliance Noted.Corrected Copy
ML20082L884
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 11/07/1983
From: Deyoung R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
To: Edelman M
CLEVELAND ELECTRIC ILLUMINATING CO.
Shared Package
ML20082L888 List:
References
NUDOCS 8312050607
Download: ML20082L884 (9)


See also: IR 05000440/1983031

Text

7

-

t

.

9

NOV 0 71983

Docket Nos. 50-440

50-441

The Clev' eland Electric Illuminating Company

ATTN: Mr. Murray R. Edelman

Vice President

Nuclear Group

P.O. Box 5000

Cleveland, OH 44101

Gen'lemen:

SUBJECT:

Construction Appraisal Team Inspection 50-440/83-31,50-441/83-30

This refers to the Construction Appraisal Inspection by the Offire of Inspec-

tion and Enforcement (IE) on August 22-September 2 and September 1z-23,1983, at

the Perry Nuclear Power Plant Units 1 and 2.

The Construction Appraisal Team

(CAT) was composed of members of IE, Region III, and a number of consultants.

The inspection covered construction activities authorized by NRC Construction

Permits CPPR-148 and CPPR-149.

This inspection is the fourth of a series of construction appraisal inspections

being planned by the Office of Inspection and Enforcement. The results of these

inspections will be used to evaluate implementation of management control of

construction activities and the quality of construction at nuclear plants.

The enclosed report identifies the areas examined during the inspection. Within

these areas, the effort consisted of deta11ed inspection of selected hardware

!

subsequent to Quality Control inspections, a comprehensive review of selected

l

portions of your Quality Assurance Program, examination of procedures and records,

observation of work activities and interviews with management and ov9r person-

i

(

nel.

Appendix A to this letter is an Executive Summary of the results of this inspec-

tion and of conclusions reached by this office. The NRC Construction Appraisal

Team noted no pervasive failure to meet construction requirements in the samples

,

'

of installed hardware inspected by the team.

However, management attention is

needed for the resolution of the detailed deficiencies identified during the

inspection.

t

_

_._

0312050607 831107

PDR ADOCK 05000440

_G

PDR

IE01

_

_

Cooy to RCPB, IE

5

_

t

e

O C 7 198 3

The Cleveland Electric Illuminating

-2-

Company

The NRC CAT inspectors identified a number of typical construction type defi-

ciencies which had been previously identified by the applicant's project organi-

zation. .They also perceived a quality conscious attitude throughout this project

organization.

It was noted that timely management attention was being given to

findings identified by both the NRC CAT and the project organization.

It is also our understanding that you plan to review welding of small bore piping

manufactured by Pullman Power Products at the Williamsport, Pennsylvania facility

as a result of problems identified during this inspection and by Georgia Power

Company at their Vogtle facility.

Appendix B to this letter contains a list of potential enforcement actions based

on the NRC CAT inspector observations. These have been referred to the NRC

Region III office for review and necessary actions.

In accordance with 10 CFR 2.790(a), a copy of this letter and the enclosures

will be placed in the NRC Public Document Room unless you notify this office,

by telephone, within 10 days of the date of this letter and submit written

application to withhold information contained herein within 30 days of the date

of this letter. Such applications must be consistent with the requirements of 10

CFR 2.790(b)(1).

No reply to this letter is required at this time. NRC Region III will address

the potential enforcement findings at a later date and any required response

will be addressed at that time.

Should you have any questions concerning this inspection, please contact us or

the Region III Office.

Sincerely,

ll

Richard C. DeYoung, Director

Office of Inspection and Enforcement

Enclosures:

1.

Appendix A - Executive Summary

2.

Appendix B - Potential Enforcement Findings

3.

Inspection Report 50-440/83-31, 50-441/83-30

'\\

s'

h

'

RCPB:DQASIP:

RCP8. ASIP:IE

ADIR:

IP:IE

DD:

y

DI :

"

RE u f ung

ABBeach/vj;

RFHeishman

JGPar ow

JTay

g

10/27/83 /

10/ /83

10h /s3

lb/q/83

itp/83

.

3

'

G

l

)

Minor editor.ial changes made on 11/03/83.

1

)

_

s

<

..

The Cleveland Electric Illuminating

-3-

Compacy

Dift,3ribution (w/Recort)

,

J. Naldron, Plant Manager

L. Beck, General Supervisor

,

Licensing and Fuels Management

DMB/ Document Control Desk

Sr. Resident Inspector, R-III

Harold W. Kohn, Ohio EPA

Terry J. Lodge, Esquire

James W. Harris, State of Ohio

,

Robert H. Quillin, Ohio Dept. of Health

SECY

OPE

OCA (3)

R. DeYoung, IE

J. Taylor, IE

E. Jordan, IE

J. Partlow, IE

Regional Administrators

RCPB R/F

J

.

I

l

!

.

-

-

!

, -

. _ _ _

-,_.. __.

.

, _ . . ,

.

, _ _ _ - . . - - _ _ _

_ . . - ,

. . _ . _

..

.-

-

,

.

APPENDIX A

EXECUTIVE SUMMARY

An announced Construction Appraisal Team (CAT) inspection was performed at the

Perry Nuclear Power plant site during the period August 22-September 2 and

September 12-23, 1983.

OVERALL CONCLUSIONS

The Construction Appraisal Team concludes that the results of this inspection

indicate several construction program weaknesses. NRC Region III has been made

aware of these weaknesses and is pursuing them with applicant management. The

applicant is initiating corrective action and/or continuing efforts to resolve

the identified concerns. An indication that prompt management attention is being

given to the identified deficiencies is that nonconformance reports or other

,

corrective action requests were immediately initiated by the applicant upon

identification of the deficiency. These are discussed in the details section of

the report. However, management attention is needed where some lack of resolu-

tion adequac, and timeliness were noted.

The NRC CAT inspectors noted that many of the typical problems experienced at

other facilities were experienced by the Perrj Nuclear Power Plant (PNPP) pro-

ject. However, an agressive attitude in the identification of problems was

demonstrated through the applicant's project organization, and was further

reflected by the amount of applicant's management involvement at the PNPP site.

The identified construction program weaknesses are as follows:

(1)

The current practice of installing concrete expansion anchor bolts in the

drywell wall is a concern to the NRC CAT inspectors. The number of

intended anchor bolt installations and the real potential for cracking

of the drywell wall as a result of normal, transient, and accident loadings

lead the NRC CAT to question the ability of the drywell to maintain the

specified leaktightness throughout its service lifetime. The preoperational

and periodic drywell bypass leakage tests are seen to be crucial tests to

assess and monitor drywell bypass leakage from all sources.

l

(2)

A number of examples were identified where the QC inspection program and

the "as-built" verification program for piping and pipe supports / restraints

did not ensure that installed items conformed to design requirements.

While many installations have progressed through the contractor's verifi-

cation programs, the applicants verification program is in the early

stages.

(3)

The welder qualification program for two contractors needs attention to

ensure welder qualifications are properly performed. Better controls

to ensure welder identification should also be utilized.

The NRC CAT

found few hardware deficiencies in the welding area, and in general, the

in-process and completed welds reviewed exhibited good workmanship. The

one exception was in the small bore piping area as discussed in the details

section of this report.

A-1

_. .

.__

__

e

.

(4)

A number of examples were found where corrective actions related to con-

tractor identified problems were not taken in a timely manner and where

nonconformances were closed out prior to completing all of the required

corrective actions. Examples wher'e timely corrective actions were not

taken include undersized welds on HVAC supports, "as-built" program defi-

ciencies, improper valve actuator installations, and reverifications for

required material traceability. Examples of improperly closed-out noncon-

formances include problems involving training for concrete placement crews

and a failure to submit a required FSAR amendment.

AREAS INSPECTED AND RESULTS

Electrical and Instrumentation Construction:

In general., the installation of

electrical and instrumentation components inspected was in accordance with

design documents and exhibited good workmanship. However, several program

deficiencies were identified.

Two problems were identified relative to electrical separation. One problem

involved documentation for Class 1E raceway installations that indicated

separation criteria to be satisfied when in fact a number of raceway instal-

lations examined did not conform to requirements. The other problem involved

the lack of adequate procedural controls to assure that the duct covers

(barriers) for the Power Generation Control Complex (PGCC) received the

appropriate quality inspections.

The NRC CAT also identified a problem where sketches were used to install'

conduit and conduit supports in the Unit 1 containment drywell area without

appropriate document controls such as issuance, revision, retrieval ar.d approval.

Mechanical Construction: HVAC and piping runs were found to be constructed in

accordance with the applicable requirements. However, a number of examples were

identified by the NRC CAT which indicate that some piping and pipe support /

restraint deficiencies have not been identified during QC construction accept-

ance inspections or during the "as-built" verification program. A weakness

in procedural adequacy and adherence was observed in these areas. The HVAC

inspection and "as-built" verification programs exhibited similar deficiencies

and procedural weaknesses.

In addition, two issues were identified regarding the lack of adequate corrective

actions taken by the applicant to identified deficiencies. One issue involved

HVAC support welding deficiencies which were not properly or promptly addressed.

The condition included missing and undersized welds, improper configurations

and inadequate documentation. The other issue involved the lack of action where

known conflicts existed between installed pumps and valves and the design

criteria specified in the FSAR or in the purchase specifications. For example,

a number of valves containing actuator models which differed from tb original

design were identified by CEI, but no corrective actions had been initiated at

the time of this inspection.

Welding and Nondestructive Examination:

In general, welding and nondestruc-

tive examination (NDE) reviewed by the NRC CAT exhibited work performed in

accordance with requirements. However, several deficiencies were identified.

These included improper visual welding inspection of fillet welds made under the

rules of the AWS D1.1 Structural Welding Code; improper reinforcement on

A-2

.

.

.

weld-o-lets required by Section III of the ASME Boiler and Pressure Vessel Code;

and inadequate procedural controls of heat inputs for the welding of stainless

steel socket welds.

The welder qualification program for two contractors was found to be deficient in

that film quality of radiographs used for welder qualifications did not satisfy

ASME Code requirements. Additional controls should be applied to the welder

qualification program to further ensure proper welder identification during

qualification.

Civil and Structural Construction:

Current concreting activities and erected

structural steel appear adequate.

Past records of concrete placement, soils

backfill operations, and structural steel installations show conformance to

specification requirements. However, problems were found in the dispositioning

of some seismic clearance violations identified by the applicant's inspection

program. Examples of a lack of proper engineering consideration were also

identified. There is concern regarding drywell leaktightness due to the current

practice of installing numerous (8,000-10,000) expansion anchor bolts through the

drywell liner plate.

Material Traceability, Storage and Maintenance:

In general, the project material

traceability, storage and maintenance programs were found to be acceptable.

However, some deficiencies were found in the areas of fastener traceability and

material control of some small components, in-plant storage of safety-related

equipment and the control of maintenance in the central warehouses.

QC Inspector Effectiveness:

Interviews were held with inspectors randomly

selected from the applicant's organization and from contractors on the construc-

tion site. There were no instances of intimidation or threats reported.

In

one instance, issues were raised that could have an effect on the contractor

QC inspector effectiveness. This instance was referred to the NRC Region III

Office for resolution.

Quality Assurance: Selected portions of the QA audit program reviewed indicated

an adequate QA program was in-place to monitor construction activities by both

the applicant and his contractors. Audit personnel were found to be qualified in

,

l

accordance with the applicant's commitments. Nonconformances were sometimes

closed before the disposition was completed and two contractors were not taking

'

,

proper corrective action with regard to nonconforming conditions as required by

l

the co rective action program. Overall, the applicant's project organization was

l

found to be aggressive in identifying and resolving construction problems.

l

t

l

l

.

A-3

i

.

_

.-

.

.

APPENDIX B

POTENTIAL ENFORCEMENT FINDINGS

.

As a result of the CAT inspection of August 22-Septriber 2 and September 12-23,

1983, the following items have been referred to NRC Region III as potential

enforcement findings (section references are to the detailed portion of the

inspection report).

,

Electrical and Instrumentation Construction

1.

Contrary to 10 CFR 50 Criteria V, X and XVII, and the Perry Nuclear Power

Plant (PNPP) FSAR Section 8.3.1.4.1.4., separation requirements relative to

some raceway installations had not been properly inspected.

In one area,

inspection activities performed to determine the acceptability of Class 1E

raceway installations were not accomplished in accordance with applicable

procedures.

Inspection records ' indicated separation criteria to be accept-

able when in fact a number of installations examined did not conform to

requirements.

In another area, adequate procedural controls were not

established to assure that the installation of Power Generation Control

Complex (PGCC) duct covers (barriers) received appropriate inspections

'(Sections II.B.1 and II.B.2).

2.

Contrary to Appendix B, Criteria VI and XVII, and the PNPP Corporate

Nuclear Qua'lity Assurance Manual (CNQAM), Sections 0600 and 1700, raceway

sketches used to perform installation of conduit and conduit supports in

the Unit 1 containment drywell area lacked appropriate procedural control

for items such as issuance, revision, retrieval and approval.

Inspection

records generated for in-process inspections performed in accordance with

these sketches did not contain the applicable sketch revisions (Section

II.B.1).

Mechanical Construction

1.

Contrary to 10 CFR 50, Appendix B, Criteria V and X, and the PNPP CNQAM

Sections 0500 and 1000, seismic pipe supports / restraints have in some cases

not been constructed and inspected in accordance with design requirements.

In addition, the applicants "as-built" verification program for safety-

i

related valves, valve operators and pipe supports / restraints have in some

cases failed to identify discrepancies between installed items and design

drawings (Sections III.B.1 and III.B.2).

2.

Contrary to 10 CFR 50, Appendix B, Criteria XV ar.d XVI, and the PNPP CNQAM

Sections 1500 and 1600, the applicant's heating, ventilating and air

conditioning (HVAC) contractor's corrective action programs failed to

promptly and properly identify, evaluate and correct recurring deficiencies

in installed and QC accepted HVAC duct supports.

In addition, the appli-

cant has identified purchased equipment that does not meet FSAR ccmmitments

and has not initiated timely corrective action to resolve these identified

problems (Section III.B.5 and III.B.6).

B-1

. .

,

-

-

.

.

Welding and Nondestructive Examination

1.

Contrary to 10 CFR 50, Appendix B, Criteria V and X, and the PNPP CNQAM

-Sections 0500 and 1000, the performed welding inspection for AWS welds

in structurai steel and HVAC applications were found to be deficient with

respect to the requirements stated in the AWS D1.1 Structural Welding Code.

Fabrication requirements for field installed branch connection weld-o-lets

and measures to control the welding'of stainless steel socket welds were

found to be deficient with respect to the requirements contained in the

ASME Boiler and Presure Vessel Code (Sections IV.B.2, IV.B.5, and IV.B.7).

2.

Contrary to 10 CFR 50, Appendix B, Criteria IX and XVII, and the PNPP

CNQAM Sec tion 0900 and 1700, several examples were observed in the area

of welder qualification by radiography where the radiographs did not

conform to appropriate quality standards (Section IV.B.1 and IV.B.2).

Civil and Structural Construction

Contrary to 10 CFR 50, Appendix B, Criterion III, FSAR Section 1.8, and Regula-

tory Guide 1.29, Revision 3, Paragraphs C.2 and C.4, engineering dispositions of

seismic clearance violations have not in some cases been performed in a manner

which would ensure structural integrity.

Examples include: a lack of considera-

tion in some analyses for deficient hardware conditions and in lateral movement

of fire protection piping near Class 1E cable trays; improperly dispositioned

seismic clearance violations and several related calculation deficiencies

(Section V.B.1).

Material Traceability, Storage and Maintenance

Contrary to 10 CFR 50, Appendix B, Criteria VIII and XIII, and the PNPP CNQAM

Sections 0800 and 1300, the storage / issuance, application and installation of

fasteners and some components have not been adequately controlled to prevent the

use of incorrect parts (Section VI.B.1).

Quality Assurance

Contrary to 10 CFR 50, Appendix B, Criterion XVI, and the PNPP CNQAM Section

1600, nonconformances were closed prior to completion of the entire scope of work

proposed by the disposition of the nonconformance and the required corrective

actions completed (Section VIII.B.2.c).

i

!

'

B-2

._.

.__ _

_

_.

.

.

.

UNITED STATES NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

DIVISION OF QUALITY ASSURANCE, SAFEGUARDS, AND IMSPECTION PROGRAMS

REACTOR CONSTRUCTION PROGRAMS BRANCH

Report No.: 50-440/83-31,50-441/83-30

Docket Nos.: 50-440, 50-441

Applicant: Cleveland Electric Illuminating Company

Post Office Box 5000

Cleveland, Ohio 44101

Facility Name: Perry Nuclear Power Plant, Units 1 and 2

Inspection At: Perry Nuclear Power Plant, Units 1 and 2, Perry, Ohio

Inspection Conducted: August 22-September 2, 1983 and

[eptember 12-23, 1983

Inspectors:

1-

L U ') J.n c t.)

la/27/83

A. B. Beach, Sr. Reactor Construction

Dat'e Signed

Engin er TeamLesc>-)

M'

IO/27/A3

G. J. Georgiev, S(/ Reactor Construction

Dafe Signed

Eryjineer

N tSoulo

in/27/n3

[cu R. A. Rohrba'cher, Sr. Reactor Construction

Date S~igned

)

Engineer

b

0h.

ent

fal27/R3

m W.'A~. Hanson, inspection Specialist

Dat'e S'igned

.h

in/27/B3

.

D. B. Osborne, Reactor Construction Engineer

Date Signed

4[M

lo/27/g3

'H . W . P

lips,"ReactorfConstruction Engineer

Date Signed

M

10/27/A3

.

.

Hf J. Tong, React ~ Construction Engineer

Dat6 Sfgned

r i i bf u

in/27/R3

4 . E. Vandel, Reactor Inspector (Region III)

Dat6 Signed

)

Consultants:

R. M. Compton, D. C. Ford, E. Y. Martindale, and F. A. Pimentel

t

8@ M W

l0 /h7/f J

Approved By:

.-

'R. F. Heishman, Chief

Date Signed

Reactor Construction Programs Branch

C" 1 pn1

831107

m mv.24n wao

p

PDR

.

.

TABLE OF CONTENTS

TOPIC

SECTION

INSPECTION SCOPE AND OBJECTIVES....................................

I

ELECTRICAL AND INSTRUMENTATION CONSTRUCTION........................

II

MECHANICAL CONSTRUCTION............................................

III

WELDING AND NONDESTRUCTIVE EXAMINATION (NDE).......................

IV

'

CIVIL AND STRUCTURAL CONSTRUCTION..................................

V

MATERIAL TRACEABILITY, STORAGE, AND MAINTENANCE....................

VI

QC INSPECTOR EFFECTIVENESS.........................................

VII

QUALITY ASSURANCE..................................................

VIII

ATTACHMENT A - PERSONS CONTACTED AND DOCUMENTS REVIEWED

,

!

l

!

!

!

l

I

,

.

.

.

.

.-

_ _ _ , _ _ _ _ . .

- , . . - - - - _ _ - _ - , - , - - _ . _ _ _ _ _ - . . . - -

__

- _ _ _ _ _ _ _ _ _ _ - _ - _ - _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ ,

i

.

.

I.

INSPECTION SCOPE AND OBJECTIVES

The objective of this inspection was to evaluate the adequacy of construc-

tion at the Perry Nuclear Power Plant Units 1 and 2.

This objective was

accomplished through review of the construction program and selected portions

of the quality assurance program, with emphasis on the installed hardware

in the field.

Within the areas examined, the inspection consisted of a detailed examina-

tion of selected hardware subsequent to applicant quality control inspec-

tions, a selective examination of procedures and representative records,

and observation of in-process work.

Interviews were conducted with

designated site managers, quality control inspection personnel and craft

personnel .

For each of the areas inspected, the following was determined:

Is the hardware installed in accordance with the approved design?

Do individuals with assigned responsibilities in a specific area

understand their design.ated responsibilities?

Are quality verifications performed during the construction process

with applicable hold points and are quality verifications conducted

to adequate inspection acceptance criteria?

Do personnel involved with Quality Assurance / Quality Control have

the organizational freedom to perform their tasks without harassment

or intimidation?

Are management controls established and implemented to adequately

control activities in the subject area?

The areas in which a selected sampling inspection was conducted include:

Electrical and Instrumentation Construction

Mechanical Construction

Welding and Nondestructive Examination

Civil and Structural Construction

Material Traceability, Storage, and Maintenance

QC Inspector Effectiveness

Quality Assurance

!

I-l

.

.

II.

ELECTRICAL AND INSTRUMENTATION CONSTRUCTION

.

A. Objective

The primary objective of the appraisal of electrical and instrumentation

construction was to determine whether safety-related components and systems

were installed in accordance with regulatory requirements, SAR commitments

and approved construction specifications and drawings. Additional objec-

tives were to determine whether procedures, instructions and drawings used

to accomplish construction activities were adequate and whether quality-

related records accurately reflect the completed work.

B. Discussion

Within the broad categories of electrical and instrumentation construction,

attention was given to specific areas. These included electrical cable,

raceways, electrical equipment and instrumentation components. Addition-

ally, a review was made of a selected number of documents associated with

design change control and nonconformance reports.

1. Electrical Raceway Installation

a. Inspection Scope

The NRC CAT inspectors selected eight conduit runs, with a total

length of about 750 feet, from various plant areas for detailed

inspection. These runs were inspected for conformance to require-

ments relative to routing / location, separation, bend radii, supports,

support spacing, identification and attachments. An additional 200

feet of conduit, associated fittings and supports were inspected for

general workmanship, separation and identification.

Thirteen runs of installed cable tray, with an aggregate length

of about 1000 feet, were inspected relative to support location,

separation, mounting, protection and physical loading. Samples

were selected from plant areas which included the control complex,

radwaste, reactor and intermediate buildings.

Twenty raceway supports were examined in detail for such items as

,

l

location, material, anchor spacing, weld quality and installed

configuration.

b. Inspection Findings

!

(1) Cable Tray Separation

Relative to separation of cable tray, the PNPP FSAR Section

'

8.3.1.4.1.4 states in part "... cable trays of different divi-

sions have a minimum horizontal separation of three feet when

there is no physical barrier between trays. Where horizontal

separation of three feet is unattainable, the trays will be

separated by fire resistant materials...

In cases where trays

11-1

.

.

must be stacked one above another, a minimum separation of five

feet is maintained. Where vertical separation cannot be main-

tained, the trays will be separated by fire resistant materials."

Specific acceptance criteria for divisional separation between

cable trays and conduits are detailed on Gilbert Associates, Inc.

(GAI) Drawing D-214-004 Rev. K.

During inspection of the selected cable tray sample, the NRC CAT

inspectors observed the following tray segments (listed below)

which did not maintain the required separation between divisions.

The cable tray segments in the left column do not meet the

required separation relative to the tray segments listed in

the right column.

Division B 269

Division A 156

Division A 603

Non-Div. 2327

Non-Div. 1260

Division A 656

Non-Div. 1260

Division A 655

CDT. 1R33C-1040X

CDT. 1R33T-27X

CDT. 1R33R-407X

Non-Div. 425

Division A 665

%

CDT. 1E22H-201C

,

Division A 152

CDT. 1E22H-201C

CDT. 1E22H-204C

Division A 663

Non-Div. 1538

i

Non-Div. 1575

!

Non-Div. 3593

Non-Div. 083

Division A 150

Non-Div. 3593

Non-Div. 083

l.

l

Division B 274

CDT. 1R33C-3133C

Division B 273

CDT. 1R33C-3133C

Non-Div. 1649

Non-Div. 2238

Division B 272

CDT. 1R33C-2977C

'

CDT. 1R33R-1029C

!

Division B 1319

Non-Div. 595

Division 6 271

CDT. 1R33-2975C

Division A 601

CDT. 1R33C-2811D

CDT. 1R33C-315D

II-2

.

.

Division A 1680

CDT. 1017R-144C

Division B 1326

CDT. 1C71-136C

CDT. 1R33R-3020C

CDT. 1R33R-917C

CDT. 1R33C-2921C

CDT. 1R33C-3022C

Division A 153

CDT 2B42C-248

CDT. 1833C-3508B

CDT. 2R61A-1165B

Division A 3008

Non-Div. 4555

Division B 269

Division A 141

Division A 127

CDT. 1R33C-3301B

Division A 1657

CDT. 1R33C-3033

Division B 1846

CDT. 1R38C-3147C

CDT. 1R33F-142C

The NRC CAT inspectors reviewed the inspection records for these

installations. The records were in the form of an inspection

checklist issued as part of L. K. Comstock (LKC) Procedure 4.3.1,

" Cable Tray and Conduit Installation". Section 3.4 of this

procedure details the requirements for quality control inspection

of cable tray and conduit installations. With regard to separa-

tion, Section 3.4.4.11 states... " verify installed cable tray and

channel tray have not violated the separation criteria." In

reviewing the records of this inspection activity, the NRC CAT

inspectors noted that line item 11, separation criteria accept-

able, had been initialed by the QC inspector. This indicates an

acceptable installation when in fact the installed configuration

,

of the cable tray does not meet the specified separation

l

criteria.

I

The NRC CAT inspectors discussed this matter with representatives

of the quality organizations of both the applicant a1d the

electrical contractor. The results of these discussions indi-

cated that the initialed acceptance of the subject raceway

installations was intended to be contingent upon the installation

r

of approved barriers at some later date. The NRC CAT inspectors

,

observed that, although barriers were shown on the design draw-

'

ings, there were no procedures available for installation of

j

these barriers. Additionally, at the time of the CAT inspection,

material to be used for barrier applications had not been speci-

fied.

As a result of tnese observations, the licensee issued Action

Request (AR) 692 which details steps to be taken to correct these

discrepancies. The AR included:

II-3

-.

.

.

the stamping of all existing Form 17 and Form 82 (Cable

Tray and Conduit Inspection) Checklists with the words

" barrier installation not verified"

the revision of Procedure 4.3.1 to define the term "separa-

tion criteria"

the revision of Procedure 4.3.1 to procedurally address the

use of this stamp.

Further attention will be required by the applicant and elec-

trical contractor to assure that inspection records accurately

reflect the actual hardware installation and that work / inspection

procedures are developed to control activities associated with

barrier installation and inspection.

(2) Drywell Raceway Installation

During inspection of raceway installation within the drywell, NRC

CAT inspectors noted that construction activities were being

accomplished using sketches. A review of the program which

establishes use of these sketches indicated that initially the

installation of raceway in the drywell area was in accordance

with Gilbert-approved 500 Series drawings. However, as construc-

tion coordination problems in this area increased, a variance to

use sketches was requested via Field Variance Authorization (FVA)

4331-33-899. This FVA was approved on 8/19/82. Subsequently, a

review by the Site Quality organization indicated that the use of

an FVA to establish this program was not in accordance with

established procedures. Engineering Change Notice (ECN)

1327-33-2422 was then initiated to provide the appropriate

incorporation of the Reactor Building As-Built Drawing Program

into Electrical Construction Specification 33-4549-00.

The NRC CAT inspectors examined several sketches from areas

including the electrical contractor's QC file and the field stick

files. These sketches detailed conduit and conduit support

installations. Many sketches included specification variances.

Some variances were individually initialed, others were circled,

still others were apparently approved by initialing the sketch in

the icwer right hand corner. The sketches themselves did not

appear to be consistently approved. Some sketches reviewed

included sign-offs in the approval olock by electrical, struc-

tural, and civil engineers, others rectived only an initial

and date outside of the approval block. The NRC CAT inspectors

reviewed the program for issue and control of these sketches and

concluded that there was no formal, procedural control of this

activity. Discussions with the applicant and representatives

from the Coriduit Detail Group indicated that these documents are

controlled by the Conduit Detail Group and are not controlled or

handled by the Contractor's Document Control Section.

Sketches

are issued to the field and to QC directly by the Conduit Detail

Group. The Conduit Detail Group is a rather unique part of the

II-4

_

_

.

.

PNPP project organization in the Nuclear Construction Engineering

Section. The detailers in the group work for the electrical

contractor (LKC), but the group technically reports to the

architect-engineer (GAI).

.

The NRC CAT inspectors asked about the control of revised or

superseded sketches without the use of a procedure. The appli-

cant was unclear as to whether revised or superseded sketches in

the field were retrieved or destroyed by the foreman.

Inspection of raceway installed in accordance with this program

is not accomplished until the "as-built" information from these

sketches is incorporated and approved on a Gilbert 500 Series

drawing. The exception to this is the inspection for placement

of Hilti bolts and welding of supports. These activities are

performed as an in-process inspection.

Inspection records

reviewed for this activity did not indicate the sketch revision

number. The NRC CAT inspectors were unable to discern to which

revision of a sketch these in-process inspections were performed.

Based upon these observations, the program for installation of

raceway in the drywell area appears to require additional proce-

dural controls.

(As a result of the NRC CAT review in this area,

the applicant has proposed changes to LKC Procedure 4.3.1, " Cable

Tray and Conduit Installation", and to Procedure 4.2.2, " Field

Engineering Changes", to clarify responsibility and control

of raceway sketches.)

(3) Raceway Separation

In the Unit 1 Auxiliary Building, the minimum separation distance

between redundant division conduit and pull boxes (PB) was not

,

met relative to conduit 1R33C4239B, PB-1-346 and PB-1-2925. [LKC

documented this condition on Nonconformance Report (NR) 2288.]

,

(4) Conduit Support

The water-tight flexible portion of conduit IP45H3B-3 in the

Emergency Service Water Pump House was supported by a piece of

tie-wire that was cutting into the outer covering.

(LKC initi-

ated NR 2292 to document this condition.)

(5)ConduitIdentification

Conduit identification was readily visible, properly located and

appropriately used where necessary,

c. Conclusions

(1) The separation status of numerous installed and inspected

cable trays was not accurately recorded on QC inspection

records. These records indicated " separation criteria

acceptable" when, in fact, this was not the case.

II-5

,

.

.

(2) Some drywell installation and inspection activities were being

accomplished without formal, procedural controls for the sketches

being used.

(3) Although a few minor deficiencies were noted, no major problems

were identified relative to the installed raceways.

2. Electrical Cable Installation

a. Inspection Scope

The NRC CAT inspectors selected a sample of installed electrical

cable runs that had been previously accepted by site quality control

inspectors. The sample included high voltage, power, control and

instrument cables. For each of these cable runs, physical inspection

was made to ascertain compliance with applicable design and installa-

tion criteria relative to size, type, location / routing, bend radii,

protection, separation, identification, physical loading and sup-

ports.

Additionally, the NRC CAT inspectors selected 56 cable ends (306

terminatedconductors). These were inspected relative to the appli-

cable design and installation documents for items such as termination

location, correct size and quantity of conductors and correct identi-

fication of cables and wires.

The following high voltage and power cables, totaling approximately

1,100 feet, were selected from different systems, electrical trains,

locations and sizes:

Cable No.

Type

IR23F-7A

3 1/c 500 MCM

1R23F-18B

3 1/c 500 MCM

1E12F-26A

3/c No. 12

1E12F-20B

3/c No. 12

The following control cables, totaling approximately 600 feet, were

selected from different systems electrical trains, locations and

sizes:

Cable No.

Type

1E12C-68B

1 3/c No. 14

1E12C-100B

1 7/c No. 14

1E420-37B

1 3/c No. 14

1E12C-238A

1 9/c No. 14

1E32C-82A

1 9/c No. 14

II-6

..

.

._

.

.

..

.

The following instrument cables, totaling approximately 600 feet,

were selected from different systems, electrical trains, locations

and sizes:

.

.

Cable No.

_ Type

IC51R-7800

C0AX

J

IC51R-782D

COAX

-

1E12R-29A

1-4/STP-20

1R61A-587C

1-STP-16

The NRC CAT inspectors also observed installation / pulling activities

associated with cable 1E22H2010. This is a 3/c 500 MCM cable to

HPCS pump motor 1E22-C001. Observations were made to determine

compliance with installation requirements, such as protection during

handling and pulling, use of cable lubricant, conduit condition prior

1

to pulling, use of a tension monitoring device and size and profi-

'

ciency of pulling crew.

b. Inspection Findings

(1) Routing

The LKC QA/QC Procedure 4.3.3, " Cable Pulling Procedure," Section

3.1.3, states "The cable size, type, and routing is as shown on

the pull slip or as modified by an approved RCIM (Routing Change

Modification). Obvious routing errors shall be brought to the

attention of the Project Organization by the Comstock Cable

,

,

Engineer. Routing of cable may be revised in the field by the

Project Organization. The authorized Engineer shall sign and

date all revisions to the original cable pull slip as well as the

'

work and QC copies in the field. QC shall have in his possession

an approved RCIM (document this RCIM on applicable form 105A)

stating revision to routing prior to final acceptance of cable

pull."

During inspection of the selected cable sample, the NRC CAT

inspectors observed the following cables with installed routings

-that did not match those indicated on the pull slip, and for

which an RCIM had not been initiated:

l

Cable 1R23F-7A was pulled from tray 128A through tray 688A

l

into equipment 1R23-S010. However, the pull slip does not

indicate vertical tray 688A as part of the routing.

'

Cable 1R42D-37B is pulled to equipment 1R23-5011. However,

the pull slip indicates the routing of this cable to equip-

ment 1R23-5012 instead of 1R23-S011.

i

II-7

j

'

._,

. .

._,

.

.

.

.

. _. . _ _ . _ _ . __

.

.

(As a result of these observations, the applicant has initiated

NR P033-2132 to rework and reinspect these discrepancies and to

revise procedures 4.3.6 and 4.3.17.for clarification to prevent

recurrence. Also, NR 0QC 302 was initiated to document the

discrepancy on circuit 1R2D-37B.)

Although several discrepancies were identified in this area, only

one instance was the result of poor construction / inspection

practices. A review of design information associated with the

remaining cables disclosed that routing discrepancies were a

result of errors in the pull slips. Although these errors should

have been identified by site QC personnel, there were only a

small number of discrepancies noted by the NRC CAT inspectors in

this area.

(2) Separation

The PNPP FSAR Section 8.3.1.4.1.1 states in part ... " electrical

equipment and wiring for Class 1E electrical systems are

segregated into separate independent divisions... such that no

single credible event is capable of disabling sufficient

equipment to prevent reactor shutdown, ... division separation

requirements apply to equipment and wiring systems concerned."

Separation of redundant divisions in general plant areas is

discussed in paragraph 1 of this section. For the purpose of

clarification, separation, as referred to in this section, deals

only with cable and wiring installed in the Power Generation

Control Complex (PGCC) ductways and panels.

LK Procedure 4.3.30, "PGCC Control Room Work / Inspection Procedure",

Section 3.3.1 states in part... "All cable routing in the PGCC

area will be accomplished using Cable Pulling Procedure 4.3.3."

LKC Procedure 4.3.3, Section 3.2.28.1, states in part, " pulled

through circuits will be routed as shown on wire list and drawing

to maintain the required separation within the duct work.

Separation shall be maintained both externally and in-panel."

Section 3.2.2.8.2 states... "QC shall inspect 100% of all pull

through circuits in Control Room only. Safety related circuits

shall be pulled in safety related raceways only."

Section 3.2.28.7 states... " divisional cables shall be separated

from cables of other divisions by six inches or metallic conduit

or barriers or as directed by Project Organization."

II-8

_

_.

_

_

- _

_

._ -_ __

_ _

.

.

,

During the inspection of cable installations in the PGCC ductway

of the Unit 2 Control Room, the NRC CAT inspectors observed that

many cable separation violations existed. Cables of one division

'

were installed in physical contact with those of another divi-

,

sion.

Discussions with the applicant, LKC and General Electric

(GE) indicated that approved barriers would be installed at a

.-

later date to correct this condition. LKC representatives

initiated an NR to document this situation.

Items indicated on

this report had been transferred to a master deficiency list by

'

the applicant.

The NRC CAT inspectors further reviewed installations in this

.

area and concluded that installation of barriers had yet to be

accomplished.

It was estimated that there are as many as 400

locations in which barriers will be required. Concurrently, the

installation of pull through circuits has progressed to the point

of 60-70 percent completion.

Examination of several potential barrier locations indicated

that the installed configuration of cable may significantly

impair the installation of barriers. Additionally, the NRC CAT

-

inspectors found no formal procedures for installation and

inspection of barriers.

Work currently being perfomed in Unit I ductways is accomplished

'

in accordance with a GE Field Design Deviation Request (FDDR).

During the inspection of this area, the NRC CAT inspector

observed the in-process installation of a separation barrier

(ductcover)inUnit1. The NRC CAT inspectors noted that there

were no QC personnel present during this activity and further

l

discussions with the applicant and LKC personnel disclosed that

QC had nct been notified of this installation activity.

(LKCNR

,

2368 was initiated to document this condition.)

'

The NRC CAT inspectors concluded that the appropriate procedural

controls have not been established to assure that previously

inspected cables will not be damaged by the installation of

,

l

barriers, and that all required barriers will be installed. As a

-

result of this inspection, the applicant has initiated AR 720

l

which makes the following recommendations:

LKC QC to ensure that coverage is provided for the estab-

lished hold point on the installation of PGCC duct covers for

the balance of Unit 1,

.

!

No bulk installation of duct covers to proceed in Unit 2

l

without an approved installation / inspection procedure.

,

I

Initiate an NR to document the indeterminate status of the

!

cables in the ductways.

l

II-9

,

i

1

..


,-- , ,

,--.-,.m._

- - , . ,.

, , - , - , - - - , - . - . - -

- - . _ _ . - - _ , - . - -

, , ,

-

-

- - - -

. _ _ . _ _

e

l

Provide both craft and QC training pertaining to the above

mentioned requirements.

.

(3) Terminations

LKC Procedure 4.3.6 sets forth the criteria for cable

,

terminations. Contrary to this procedure, the NRC CAT inspectors

j

observed that the lug on the red conductor at terminal point T3

,

of cable #1E12F-53B exhibited a 1/4" gap between conductor

insulation and lug.

(NR LKC 2313 was initiated to rework this

'

connection.)

In general, the terminal blocks and lugs were of the specified

material, terminal lugs exhibited evidence of proper crimp tool

usage, conductors were free from jacket / insulation damage,

conductors were terminated as shown on applicable wiring

diagrams and conductors did not violate bend radii criteria,

c. Conclusions

With the exception of problems identified relative to separation of

i

cables and installation of duct covers in the PGCC dt:ctways, the

installation of the cable inspected is in accordance with design and

installation documents.

In general, cables, terminations and associ-

ated items exhibited proper configuration and good workmanship.

, Inspection records reflected the current status of the installed

components.

3. Electrical Equipment Installation

a. Inspection Scope

Over twenty pieces of installed electrical equtpment and associated

items were inspected. Samples were selected based on system function

and safety classification. Additional equipment samples are included

in paragraph 4 of this section.

The following specific electrical components were inspected:

' ) Motors

(1

The installation of two motors and associated hardware was

inspected for such items as location, anchoring, grounding,

identification and protection. The motors were the Emergency

Service Water Pump Motor IP45-C001B and the Emergency Closed

Cooling Pump Motor IP42-C001A.

(2) Electrical Penetration Assemblies

The following containment penetration assemblies were inspected:

1R22-5011, 1R22-5026 and 1R22-5004

The location, type, mounting

and identification were compared with the installation drawings.

II-10

. - .

-

- _ _ _

.

. - - - _ _ _

___

__

_

_ __

_

__

_ _ _ _ _ _

_

__ _ _ _ . . _ - _ _ _ . . _ .

_ _ . _ . _ _ _ _ _

_

e

>

,

.

3

(3) Circuit Breakers

i

i

The following Class 1E circuit breakers were examined to deter-

,

mine compliance with the design and installation documents for

size, type, mounting, system interface, and maintenance:

'

RHR Pump "A" Feeder Breaker EH-1110

HPCS Pump Feeder Breaker EH-1303

Emergency Service Water Pump "A" Feeder Breaker EH-1106

Diesel Generator Breakers EH-1201 and EH-1101

.

RPS Electrical Protection Assembly Breakers 1C71-S003 and

!

IC71-S003A

j

The use of circuit breakers with integral under voltage trip

attachments at the PNPP was investigated.

,

(4) Switchgear and Motor Control Centers

4

The following switchgear and motor control centers were

inspected: Emergency Service Water MCC 1R24-5030 and MCC EF1E2;

and 4.16 KV Switchgear 1R22-S006 and 1R22-S007.

'

The installations were compared with installation requirements

,

relative to location and mounting (welds, concrete anchors and

'

bolting).

Installation inspection records for the above equip-

ment also were reviewed.

,

(5) Station Batteries and Racks

The 125V battery rooms were inspected including the installed

batteries, battery racks and associated equipment. The location,

mounting, maintenance and environmental control for installation

of both Unit 1 and Unit 2 batteries were compared with applicable

requirements and QC records.

!

b. Inspection Findings

,

t

(1) Motors

!

The NRC CAT inspectors observed that the installed configuration

of these motors was in accordance with design drawings and that

installation activities were performed in accordance with proce-

dural requirements.

j

(2) Electrical Penetration Assemblies

Activities observed and documentation reviewed indicated that

the work performed was in accordance to requirements.

.

I

II-11

- _ _ _ - . . _ . _ _ _ _ ,.

-

_ _ - _ _ _ _ . _ ,

- _ _ , _ . . _

-.

.

.

_ _ - .

.

_ - . - - _ , _.

.

. _ .

- -

_.

e

.

One item which was identified related to the certification of

material used in the penetration sleeves. This matter had been

previously addressed by the applicant in a 10 CFR 50.55(e)

,

report.

(3) Circuit Breakers

The circuit breabrs inspected were installed in accordance with

-

design drawings and installation procedures.

An on-site review and discussions with the applicant indicated

that no circuit breakers with integral undervoltage trip

attachments, such as the W DB or GE AK-2 types, are planned for

use in safety-related appTications. Additionally, the applicant

,

has requested the NSSS and the AE to confirm that breakers of

.

the above type have not been specified or supplied for the Perry

Nuclear Power Plant (PNPP).

(4) Switchgear and Motor Control Centers

,

During the inspection of switchgear 1R22-5006, the NRC CAT

inspectors noted cabinet connection bolts of indeterminate

material had been used in cubicles EFH-1204 and EFH-1209. This

I

matter is discussed in Section VI.

(5) Station Batteries and Racks

4

The condition of the battery rooms was found to be in good order,

clean and free of debris. Ventilation systems were installed and

in operation. Access to these areas was controlled by keyed

entry, and the appropriate danger signs had been posted to

indicate no smoking or open flames.

'

i

!

The inspection of the 125V battery racks disclosed that indeter-

minate bolt material was used on the Unit 1 Division 1 and Unit 2

i

l

. Division 2 battery racks. This matter is discussed in Section

VI.

'

!

c. Conclusions

,

i

l

.Except for bolting material discrepancies relative to battery racks

and switchgear cabinet connections, the electrical equipment

inspected was installed in accordance with applicable requirements.

4. Systems Installation

a. Inspection Scope

In addition to the inspection of randomly selected plant components,

the NRC CAT inspectors. designated two plant systems for inspection of

electrical and instrumentation system integrity - the residual heat

removal and the reactor protection systems.

.

II-12

l

I

,

. . - _ _ . _ . .

- .. - - -

- - -

-

.

- -

-

-

.

__

_

_

__

,

.

Within these systems, electrical and instrument components,

cables, associated raceway, signal lines, and supports were

inspected relative to the applicable design documents and

,

construction drawings. The following samples were selected:

RHR System

RHR Pump Motors 1E12-C002B and 1E12-C002C

RHR Pump Motor Thermocouples

1E12-N486, IE12-N485, 1E12-N488 and 1E12-N489

Power Feed to 1E12-C0028 (Cable 1E12H-2B)

Power Feed to 1E12-C002C (Cable 1E12H-38)

Motor Operated Valve 1E12-F004B

,

M0V Control Cables IE12F-12B and 1E12C-40B

RHR Pump B Breaker EH-1208 and Pump C Breaker EH-1212

RPS System

RPS Power Distribution Panels 1C71-001 and IC71-P002

RPS Motor Generator Set IC71-S001B

b. Findings and Conclusions

During the inspection of these systems, the NRC CAT inspectors

observed that not all of the instrument components for these systems

have been installed. Additionally, several of the tubing runs

inspected, which appear to be essentially completed, have yet to

receive QC inspection.

The installation of electrical and instrument components inspected

in the RHR and RPS systems was in accordance with the applicable

requirements. Components reviewed were installed in accordance with

the latest construction drawings and exhibited good workmanship.

Documentation reviewed, including inspection and test records,

indicated acceptable installations and reflected the current

installed configuration.

5. I_nstrumentation

a. Scope

Six instrument panels and five instrument racks, including

associated instrument components and related items, were selec-

ted for inspection from various areas of the plant. The sample

included about 60 safety-related instrument components within

such systems as reactor protection, engineered safety features,

residual heat removal, high pressure core spray, some components

in the main steam line radiation monitor and reactor vessel instru-

mentation sub-systems. The racks ana panels were inspected for

compliance with installation requirements, including location,

protection, mounting / anchoring and separation of redundant components

and panels. Additionally, about 1000 feet of instrument tubing was

inspected against installation requirements relative to location /

II-13

O

e

routing, supports, support location, identification and protection.

The majority of the tubing runs inspected were from the process

connections to the sensors / transmitters installed on the above racks

and panels. Associated tubing penetration assemblies were also

inspected. The type, range, accuracy, material, and similar attri-

butes of 30 of the above installed instrument components were com-

pared with their specification requirements.

Instrument panels, and

associated instruments, inspected in detail included: H22-P001,

H22-P004, H22-P005, P22-P018, H22-P026 and H22-P027 in Unit 1.

b. Inspection Findings

Numerous installed components (mostly Rosemount transmitters) have

failed required qualification tests. The applicant is aware of this

situation'and has tagged the components that require replacement,

and some components have already been removed.

'

A compression fitting was installed in a completed welded-joint

tubing run near valve 1E12F0530A and related to panel P22-P018.

This run was modified by the addition of a compression fitting tee by

Johnson Controls, Inc. (JCI), the instrument contractor, at the

request of the Nuclear Test Section (NTS) of the PNPP project organi-

zation.

It was not clear to the NRC CAT inspectors that this modifi-

cation was appropriately recorded, scheduled for rework and subse-

quent re-inspection. Additionally, the installed tubing clamps were

removed from this tubing and not properly controlled. About 20 feet

was left unsupported and unprotected.

(Procedures pertaining to

modifications requested by NTS and performed by JCI are to be revised

to correct this type of problem.)

In several locations, safety-related instrument tubing ,;as, at best,

marginally protected from damage from adjacent construction activi-

ties and from inadvertant damage which may occur during plant opera-

tion.

It was observed that some non-safety-related instrument tubing

was more suitably protected from damage than some safety-related

tubing.

A choker used for rigging to relocate instrument panel 1H22-026 was

attached to internal panel members and across a section of tubing

rather than attached to the panel frame.

(An NR is to be initiated

to document this condition.)

Although much of the safety-related instrument tubing has been

installed in Unit 1, the tubing is not color-coded as specified. The

applicant indicated that color-coded tape will be applied after

tubing hydro tests.

c. Conclusions

Although some minor discrepancies were noted,' no items of major

safety significance were identified.

In general, the racks, panels,

components, tubing and associated items inspected were installed in

accordance with applicable requirements - or appropriately tagged

and/or recorded as nonconforming.

II-14

-

,

.

6. Design Change Control and Nonconformance Reports

a. Inspection Scope

The design change program and related procedures used at the Perry

site were reviewed.

In regard to electrical and instrumentation

installation activities, 70 LKC ECNs and 50 LKC FVAs were reviewed;

35 JCI ECNs and 25 JCI FVAs were reviewed; and 10 GE Field Design

Instructions and 10 GE Field Design Deviation Requests were reviewed.

The NRC CAT inspectors also reviewed a sample of NRs issued by the

electrical and instrumentation contractors. These reports were

reviewed for items such as content, completeness, timel'iness of

review, proper approval, technical justification, and document

processing. Approximately 45 NRs initiated by the electrical

contractor and 20 NRs initiated by the instrumentation contractor

were examined. Additionally, several reports initiated by GE and

the PNPP Project Quality Organization were reviewed.

b. Inspection Findings

GAI approves design and engineering changes either at their home

office in Reading, PA. or by the GAI assistant project manager at the

Perry site. Processing and control of these changes are in accord-

ance with GAI Interface Procedure, Appendix N.

GAI initiates ECNs,

indicates whether the change is specification or drawing-related and

transmits the ECN package to the project Nuclear Construction Engi-

neeringSection(NCES). ECNs can also be written to accomplish

construction work under the direction of the Nuclear Test Section

(NTS). This work is to be controlled by the Corporate Nuclear

Quality Assurance Program.

For drawing-related ECNs only, GAI may issue the ECN to the affected

contractor prior to transmittal to the project NCES, but only for

minor modifications to electrical conduit routings, conduit and tray

supports, cable terminations and piping supports including

instrument piping supports.

For minor changes only, FVAs may be used. They are generally used

for drawing changes, but may be used for specification changes if no

design change is involved. FVAs can be initiated by either the

applicant or the AE (GAI), but FVAs require GAI approval.

In accordance with site procedures, contractors utilize a nonconform-

ing reporting system to document discrepancies which render the

quality of an item indeterminate or unacceptable. Of the noncon-

forming reports reviewed, it was noted that they had been initiated,

reviewed and processed in accordance with the applicable procedures.

II-15

L

_.

..

_

. _ _

.

_ . - - _ _ _ _ .

--

.

.

t

c. Conclusions

The general program and procedures established to control

design and engineering changes were, in general, considered adequate.

.

However, two problems were identified that indirectly relate to

design change controls. One problem, as discussed in paragraph 1

.

of this section, pertains to the lack of formal, procedural controls

'

of sketches used for conduit installation activities. The other

-

problem relates to the weakness in the control of changes under the

direction of NTS - as mentioned in paragraph 5 of this section.

Nonconformance reports reviewed were initiated, reviewed and

processed in accordance with the applicaole procedures.

.

i

l

l

II-16

'I

. , ~ .

___

. .

. _ _ _ . _ . _ _ _ __ . . _ _ _ _ _ _ . . _ _ . _ _ _ _ . . , _ . . . . _ _ . _ _ . . _ _ _

,_

_

.-

-

..

.

.

.

.

III. MECHANICAL CONSTRUCTION

A. Cbjective

The objective of the appraisal of mechanical construction was to determine

if installed and Quality Control (QC) accepted safety-related mechanical

items conformed to engineering design, regulatory requirements and licensee

commitments.

B. Discussion

The specific areas of mechanical construction that were evaluated were:

piping, pipe supports / restraints, the piping "as-built" program, c.oncrete

expansion anchors for pipe supports / restraints, mechanical equipment and

heating, ventilating and air conditioning (HVAC) systems. To accomplish

the objective, a detailed field inspection of a sample of, QC accepted

hardware was performed in each area.

In addition, certain programs,

procedures and documentation were reviewed as required to support or

clarify hardware inspection findings.

1. Piping

a. Inspection Scope

Ten piping isometric drawings were selected and the installed piping

inspected for conformance to design and procedural requirements.

The installed piping was examined for pipe identification (via ASME

Code Data Plates), proper configuration, valve identification, valve

and valve operator orientation, bolted flange makeup, interference

and support / restraint location (partial). As a result of a problem

identified during the inspection with valve / valve operator orienta-

tion, an additional 10 valves were selected to verify conformance of

their orientation to that shown on the isometrics. Approximately

eight flanged joints were inspected for proper gasket and bolting

material and proper makeup.

See Table III-1 for a listing of the

piping inspection samples and observations.

The following documents provided the basic acceptance criteria for

the inspections:

Pullman Power Products Procedure IX-3, Rev 4/5/83,

" Fabrication and Field Installation Specifications for

,

Nuclear Power Plant Components, Piping Systems and Appur-

tenances ASME-Section III"

Pullman Procedure IX-5, Rev 1/31/83, " Torquing of Flanged

Joints in Piping Systems"

Pullman Procedure VI-5, Rev 8/12/82, " Control of Process

Sheets and Weld Rod Stores Requisitions"

Pullman Procedure X-4, Rev 6/8/81, " Final Inspection

(Field)"

Applicable piping isometric drawings

III-1

.

.

.

,

-.

. - _

- - _ . .

.

. - - - - -

.

- _ . .

,

.

b. Inspection Findings

In general, the piping runs inspected were found to conform to

requirements for the attributes verified. Hcwever, one bolted valve

and two valve operators were not oriented as shcwn on the iscmetric

drawings. As a result of these observations the NRC CAT inspectors

selected 10 additional valves for inspection of proper orientation

(See Table III-1). Three of these valves and one of the valve

I

-

operators were oriented in conflict with the isometric drawing. It

should be noted that three of the seven valves oriented in conflict

with the isometric drawings had been "as-built certified."

Even though some of the valve installations had been "as-built",

Pullman, the responsible contractor, does not inspect piping for

configuration, valve orientation, flow arrows, and other similar

attributes until the final turnover walkdown inspection per their

Procedure X-4.

Also, none of the valves in question had been

inspected for joint makeup per Procedure IX-5.

However, joint makeup

process sheets do not specify or require verification of proper

orientation. The NRC CAT inspectors do not consider the current

scheduie of piping / equipment configuration (construction acceptance)

inspection tc be timely, nor prudent from a potential rework / repair

standpoint.

ln addition, the NRC CAT inspectors do not consider the

Pullman final walkdown procedure, Procedure X-4, to be specific with

regard to the detailed inspections required, the applicable inspec-

tion / acceptance criteria and the methods of dispositioning unsatis-

factory conditions; i.e., punchlists, deficiency reports, or noncon-

formances.

c. Conclusions

(1) With the exception of valve and valve operator orientation,

no major hardware deficiencies were identified in the

piping runs inspected.

(2) Valves and valve operators are being improperly installed

by the crafts and the "as-built" program has failed to

identify the discrepancies.

(3) The construction acceptance inspections for certain piping

features are not being performed in a timely manner and the

final piping turnover walkdown procedure lacks specificity

regarding responsibilities, inspection / acceptance criteria

and discrepancy processing.

2. Pipe Suoports/ Restraints

a. Inspection Scope

Twenty-eight QC accepted safety-related supports / restraints were

selected for inspection which provided a variety of types, sizes,

systems and locations. These supports / restraints were inspected for

configuration, identification, location, fastener / expansion anchor

III-2

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

_

__

__

_

.

.

installation, clearances, member size and damage.

In addition,

approximately 50 unidentified safety- related supports / restraints

were observed in the field for obvious deficiencies such as loose or

missing fasteners, improper clearances or angularity, damage and

improper concrete expansion anchor spacing.

The NRC CAT inspectors also selected and inspected eight Class 4

supports / restraints. These supports / restraints are installed on

fire protection systems or, although not installed on safety-

related piping, have a safety function due to their proximity to

safety-related items. They are designed to seismic Category I

requirements and must not fail during seisn! c/ accident condi-

i

tions. See Table III-2 for all of the pipe supports / restraints

inspection samples.

Acceptance criteria for the field inspections are contained in

the following documents:

Pullman Procedure VII-2, Rev 12/2/82, " Material Control"

Pullman Procedure VIII-1, Rev 9/8/82, " Procedure for

Identification of Materials, Parts and Components"

Pullman Procedure IX-6, Rev 7/21/83, " Installation and

Inspection of Pipe Supports"

Gilbert Drawing, 4549-5-322-002, Rev C, " Pipe Support

Dimensions and Tolerances"

Gilbert Drawing, 4549-5-322-004 Rev C, " Pipe Support Erection

Standards"

Power Piping standard drawings and catalogues

l

Applicable support / restraint detail drawings

ITT Grinnel Special Installation Instructions (GE

Supports / Restraints)

b. Inspection Findings

General Electric Company (GE) is responsible for the installa-

tion and inspection of approximately 154 Unit 1 safety-related

supports / restraints for two systems, Reactor Recirculation

and Main Steam (MS), in accordance with Cleveland Electric Illumi-

nating (CEI) Specification 38. As none of these ITT Grinnel Fabri-

cated supports / restraints were in a final, QC accepted condition,

only one support was inspected in the field for proper configuration.

No problems were identified. The NRC CAT inspectors reviewed in

detail the partially completed travelers gov aning the installation

of GE supports 1 B33-H355A and 1 B33-H301A. No problems were identi-

fied. The final assembly and adjustment travelers were still in

preparation.

III-3

- ______________________ ____________

.

.

.

Pullman Power Products (PPP) is responsible for the installation and

inspection of the remainder of the safety re-lated and balance of

plant pipe supports / restraints. Gilbert Associates, Inc. provides

the detailed support / restraint design draw;ngs which are redrawn by

the hardware fabricator, Power Piping. Pullman adds field weld

numbers and any applicable change documents such as Engineering

Change Notices (ECN's) or Field Variance Authorizations (FVA's) and

issues the drawing to the field for installation.

Pullman performs QC inspection of safety related supports / restraints

in three phases as follows:

Phase I - Verification of primary attachment to the building

structure.

Phase II - Verification of installation details of completely

installed assembly.

Phase III - Verification of final settings, clearances, tight

fasteners, completeness and freedom from damage just prior to

system turnover.

Of the approximately 13,200 large bore and 4,600 small bore safety

related supports / restraints in Unit I and common areas, approximately

2,900 had been Phase II inspected at the time of the NRC CAT inspec-

tion. Class 4 (nonsafety-seismic) support / restraints are also QC

inspected for proper installation.

Inspections are documented on

detailed checklists.

Discrepancies identified on QC accepted supports / restraints by

the NRC CAT inspectors are listed in Table III-3.

In summary,

three out of 28 safety related supports / restraints, six adjacent

supports / restraints and two of eight Class 4 supports / restraints

were found not to conform to design requirements. In addition,

one Class 4 installation had been QC accepted with an inadequate

weld size and wide flange shape size specified on the drawing

(1P11-H098).

The following miscellaneous discrepancies were also identified

during the NRC CAT inspection activities:

Restraint 1E32-H100 had been disconnected from the pipe,

but had a Phase II tag attached contrary to the require-

ments of Procedure IX-6.

It was later determined that no

Phase II inspection checklist existed for this restraint.

The travel stop had been removed from spring hanger IP42-H225

prior to the Phase III inspection.

Clamp bolt threads were not staked on support 1G36-H062.

This item would have been verified again during the Phase

III inspection.

III-4

.

-

_ - _ - _ _

-

.

.

The Phase II checklist for restraint 1E12-H748 was signed, dated

and on file but none of the checklist items had been marked as to

whether the iteins were acceptable, unacceptable or not appli-

cable.

The welding process sheets for supports 1P42-H1043, IP45-H360,

"

IE12-H178 and IC11-H516 (four of 12 examined during the observa-

tion of in-process welding activities) did not indicate the

latest Pullman issue number of the installation drawing; some as

many as five issues behind.

However, each work package did

contain a copy of the latest issued drawing.

Three supports / restraints (1821-H006,1E12-H010 and 1E12-H614)

were found to have potential clearance problems with other

structures. There were no seismic clearance violation (SCV)

stickers in these areas indicating prior identification by the

SCV inspection group.

Even though overall " area" inspection

effort by the SCV group may at some point identify these clear-

ance problems, the NRC CAT inspectors consider that clearance

criteria should be clearly specified for hardware installation

and that each contractor should verify proper clearance for their

hardware prior to and during acceptance inspections. This will

provide greater assurance that all clearance problems will be

identified and resolved and minimize rework / reanalysis efforts.

See Section V of this report for more details on the SCV inspec-

tion group activities.

During this review, controls that Pullman exercises to maintain

required traceability of supports /restaints were evaluated,

This is

discussed in detail in Section VI.

,

Several Pullman QC inspectors and field engineers and CEI QC Surveil-

lance personnel were informally observed and interviewed in the field

by the NRC CAT inspectors. These personnel appeared to be know-

ledgeable of their responsibilities and of the requirements of the

activities they were performing.

c. Conclusions

(1) No extensive or gross structural integrity problems were

identified on installed supports / restraints.

(2) Some ASME Section NF (safety related) and Class 4 supports /

restraints that had been QC accepted were found by the NRC

CAT inspectors to be nonconforming with design drawing and

procedural requirements.

III-5

_

_

_ _ _ - - -

.-

.-

_ _ - _ _

.

.

3. As-Built Program (Pullman)

.

a. Inspection Scope

The NRC CAT inspectors reviewed approximately 10 redlined drawings

from the as-built field files. Also reviewed were the as-built

procedures and program activities of Pullman field engineering,

drafting and QC personnel, as well as the CEI Nuclear Construction

Engineering Section.

Three of the piping runs and eight of the pipe supports / restraints

inspected as detailed in Sections III.B.1 and III.B.2 had been

"as-built certified" by Pullman Power Products,

b. Inspection Findings

Discrepancies between installed hardware and drawings were noted

on six cut of 11 " certified as-built" drawings included in the

NRC CAT piping and pipe support / restraint samples. See Tables

III-1 and III-3 for listings of identified discrepancies.

The review of "as-built" documentation and program activities

indicated several additional deficiencies and weaknesses. For

restraint IP11-H059, the field redlining was performed and the

certified "as-built" issued against ECN 12198-45-890 Rev. A, but

ECH 12198-45-890 Rev. C was the current revision listed on the

Pullman issued installation drawing.

Procedure X-24, " Procedure

for As-Building Piping Systems and Components," is not being

followed in that QC is not involved in all walkdown inspections,

walkdown teams are not signing and dating redlined drawings in

all cases (IP45-H529,1P45-H485) and the field engineering group

is not determining conformance of hardware to erection toler-

ances.

It should be noted that PulIman personnel were aware

that this procedure was not being followed, but had not taken

corrective action.

The NRC CAT inspectors consider that Procedure X-24 needs to more

clearly define who determines when redlined dimensions are out of

tolerance and, if so, what specific action is to be taken. The

Pullman drafting group has issued at least four "as-builts"

(IP45-H590, 1P45-1176, 1E12-H2002, IP45-H1277) and has numerous

others in the final stage of preparation that had been identified

informally to Pullman QC as having conditions requiring determination

,

of acceptability (conflicts between redlined information and the

latest design drawing) but, for which no response had been given.

Procedure X-24 is also unclear and is inconsistently being applied

regarding the determination of elevation, location and concrete

expansion anchor diameter and length for supports / restraints.

A review of the CEI program to review "as-builts" as detailed in

Site Project Administration Procedure 0303, Rev. 1, "As-Built

Drawings" indicated a thorough engineering review.

In fact, this

review has been resulting in rejection of a high percentage of

Pullman "as-built" drawing submittals since April 1983.

From April

III-6

.

.

- _ _ _ _ _ _ _ _ _ .

- -

.

-

-

-

-

_ . _

.

.

through July, 1017 of 4164 support / restraint "i Nuilts" (24%) and

645 of 1667 piping "as-builts" (39%) had beer

ted by CEI.

Most of the submitted "as-builts" have been

safety related

hardware. However, the same people and proces, re "-M

for safety

related work. CEI QC involvement in the "as-built" t.rfort appears to

be limited and CEI's program has not effectively identified and

rectified significant deficiencies in the Pullman "as-built" program.

The NRC CAT inspectors reviewed the Gilbert Associates, Inc. site

procedure " General Procedure for IE Bulletin 79-14", Rev. 3, detail-

ing actions to meet the requirements of IE Bulletin 79-14, " Seismic

Analyses for As-Built Safety-Related Piping Systems". Related

program activities were discussed with the Gilbert Site IEB 79-14

Coordinator. This review revealed that the 79-14 program is essen-

tially a separate Gilbert executed program, involving walkdown

redlining of piping and valve data verification. However, as Pullman

support / restraint "as-builts" are utilized as input to the 79-14

~

evaluation, inaccuracy in Pullman's program may affect the safety

system analysis,

c. Conclusion

The review of procedures and the "as-built" program implementation

reflected by hardware and documentation deficiencies, indicate a

number of discrepancies and weaknesses in the Pullman "as-built"

program. Pullman and CEI have not taken prompt action to correct

previously identified deficiencies in the 'as-built" program.

'

4. Concrete Expansion Anchors for Pipe Supports

a. Inspection Scope

Twenty eight pipe supports / restraints containing 108 concrete anchors

were inspected for proper torque. Table III-4 provides a listing of

supports and torqueing results. The supports were installed in eight

different safety related systems and contained anchors ranging in size

from 5/8" to 1-1/4" diameter . Additional examinations performed by

the NRC CAT inspectors included verification of the proper length

,

marking on the anchor, installation of washers, proper engagement of

nut, and measurement of the length of anchor extending from the

concrete (only for those anchors that appeared excessive). The

Pullman Power Procedure IX-6 " Installation and Inspection of Pipe

Supports" dated 7/21/83 was reviewed as part of this activity,

b. Inspection Findings

(1) Torqueing

The vast majority of nuts exhibited no rotation when the

minimum specified torque (per ECN 10493-44-1641 Rev. C) was

applied. The maximum rotation was 3/16 of a turn for one

nut.

III-7

-

_ _ - _ .

.

..

..

-

.--_

_

-

-_-

.

.

(2) Nut Engagement

All anchors were at least flush with the top of the nut per

the procedurtI requirements.

(3) Anchor Embe hent

To verify proper anchor embedment, the anchors that had 2 inches

or more of standout from the concrete were noted and the embed-

ment for these anchors was calculated and compared to drawing

requirements. A :otal of five anchors on four supports equaled

or exceeded 2" of standout. Four of the five (three supports)

had less than the specified minimum embedment, ranging from 1/4

to 1/2 inch. See Table III-5 for a comparison of data on these

anchors.

(4) Miscellaneous Discrecancies

One anchor on support (1G41-H253) did not contain a marking.

An ultrasonic examination (UT) performed on both anchors on

this support verified that they were the specified length of

10 inches.

On support 1G36-H1024, there were no washers ir. stalled on the 2

anchor bolts as required. Nonconformance Report (NR) CQC 2880

was issued for this condition.

c. Conclus'ons

i

(1) The Field Process Sheet for the concrete expansion anchors do not

contain a signoff for verifying bolt diameter. The bolt identifi-

cation marking relates to length only. Although not a hardware

problem for the sample selected, it is conceivable that without

this verification, improper torques could be applied in addition

to installing improper sized bolts.

'

(2) With the exceptions of missing washers and the anchor embedment

on three hangers no hardware problem was identified. The appli-

cant should provide justification that expansion anchor embed-

ments are adequate and are being properly inspected.

5. Mechanical Eouipment FSAR Comparisens

a. Inspection Scope

A sample of mechanical equipment was reviewed to determine that

purchase specification requirements conform with FSAR commitments

and whether installed hardware conforms with supplier documentation,

purchase specification requirements and FSAR commitments. To accom-

plish this task, equipment from the RCIC and RHR systems were chosen

because of preponderance of operational data given in the FSAR for

these systems. Nine components were reviewed including an RHR pump,

an RCIC pump, an RCIC turbine, and several RCIC valves. Table III-6

III-8

._.

.

.

provides a listing of the inspected equipment along with the opera-

tional parameters reviewed. Table III-7 provides a listing of

documentation reviewed.

b. Inspection Findings

A summary of discrepancies is provided in Table III-8. Of the five

discrepancies noted, three require revision to the FSAR. The other

two require follow-up action by CEI to assure that acceptable

material is installed.

It should be noted that CEI had previously

uncovered the problem or problems of a similar nature for the dis-

crepancies identified by the NRC CAT inspectors. The more signifi-

cant discrepancies are discussed below.

(1) RCIC Isolation Valve (F063) Not Meeting FSAR Requirements

The NRC CAT inspector discovered that a discrepancy (non-

conservative) exists between the purchased RCIC Isolation Valve

(F063) and the FSAR commitment (see Table III-8).

In 1979,

Gilbert suggested changing this valve from being normally open to

normally closed (along with other modifications) so as to reduce

the energy release from a rupture in the 4" RCIC steam supply

line. Because of the logic change, less stringent requirements

for the valve from that shown in the FSAR were apparently pos-

sible. The NRC CAT inspector did not verify the adequacy of

these requirements since these requirements will be reflected in

a FSAR revision and will receive appropriate review at that time.

CEI was aware of problems between the FSAR and system design

descriptions prior to the NRC CAT review as evidenced by their

1982 audit of Gilbert which identified two discrepancies between

system design and FSAR commitments. Action Requests (ARs) were

issued requiring complete FSAR review by Gilbert against system

design descriptions. As a result of the NRC CAT inspection,

the appl b nt has commited to include procurement specification

requirements > the FSAR review. Additional programs include a

CEI FSAR VerificaMon Program and a future audit of GE's procure-

ment program.

Proctdures have not yet been developed for the

CEI FSAR Verificatio i Program, so that its adequacy cannot be

determined.

A Gilbert Procedure entitled Technical Document Revision (#QAP

3.1) dated 2/14/83, requires that the procurement document be

reviewed to verify that the design criteria are consistent with

SAR commitments. There is no evidence that this procedure was

followed or if another program / procedure was applicable to the

valves and pumps in question. The NRC CAT inspectors do not

consider FSAR verification after all equipment is in place to be

either prudent or timely from a potential equipment replacement

standpoint or from a re-analysis standpoint.

III-9

.

-- -.

_

_

-

- . _

.-

,_.

.

.._

.

-__

-

-

. =

.-

_

-

..

_ .. _

.

.

(2) Incorrect Actuator Model # on RCIC Suction Valve (F031):

This discrepancy was initially identified by CEI in the summer of

1982 after the valves and actuators had been installed in the

field.

In addition to identifying valve F031, CEI identified

over 100 valves containing actuator models which differed from

the design. The identification of these valves by CEI was part

of an inventory program (no procedure identified) for ordering

spare parts. A fornal procedure existed which, if followed,

should have identified the problem prior to the arrival of valves

and actuators on site. Section C.1.K of Gilbert's Manufactur-

ing Surveillance Plan 043, Rev. O dated 2/6/78 requires final

inspection of 50% of each type of valve for the correct specif.ied

motor operator (actuator). With over 100 valves not in compli-

ance with the design, there was an obvious breakdown in this

procedure. Gilbert has contacted the valve manufacturers (Borg

Warner and Contromatics) to assure that the installed actuators

are suitable for the specified conditions. The NRC CAT inspec-

tors observed no documented evidence that the valve manufacturers

had responded.

c. Conclusions

(1) The depth and importance of the FSAR verification effort should

be emphasi::ed, since there is an obvious conflict between pur-

t

chased equipment and what the designer intended as reflected in

the FSAR. These efforts should be adequately administered so

that the equipment in the field satisfies the FSAR commitments.

Furthermore, effective programs should be in place to verify

that equipment currently being purchased satisfy FSAR

requirements.

(2) While the discrepancies involving over 100 valves containing

a

actuator models which differed from design were identified by

CEI, the identification was part of an inventory program for

spare parts. The Gilbert manufacturing surveillance procedure

that should have been followed to identify discrepancies of this

type was apparently not followed and corrective action to prevent

re-occurrence was not initiated.

6. Heating, Ventilating and Air Conditioning (HVAC)

a. Inspection Scope

HVAC systems installation work is essentially complete in Unit 1

and common areas. The contractor for HVAC is the Robert Irsay,

Co. (RIC0) who fabricates, installs, inspects and leak tests

systems in accordance with Gilbert design drawings and specifi-

cations.

System M40 and portions of M15, M36 and M30 have been

turned over to CEI.

The NRC CAT inspectors selected samples of 10 supports / restraints, 15

pieces of equipment and 22 duct segments for field verification of

conformance to design and procedural requirements. Duct joint makeup

III-10

.

'm,iwen-e

e

-iw

o- - - .

-w

w-=,

?i.-..-

-

.v.e.y-.,_

rwa

m

.9-

-e--e

---.--s

--..-----.-ppg

= _ = -

. - . -- .

. _ - - - .

.- - --

.

a

.

i

was examined on numerous other unidentified duct segments during

other NRC CAT inspection activities. Features verified were config-

uration, member size, identification, weld size, fastener / expansion

anchor installation, duct gasketing and bolting. See Table III-9 for

a listing of inspected items.

The following documents provide the acceptance criteria for HVAC

hardware installations:

-

The Robert Irasy Company (RICO) Quality Assurance Manual

RICO procedure QCP-6-4/707, Rev 2, " Installation Inspection of

Safety Related Drilled in Concrete Expansion Anchors"

RICO Procedure QCP-11-5/707, Rev 4 " Inspection of Seismic

Supports"

RICO Procedure QCP-11-6/707, Rev 2, "HVAC System Walkdown

Inspection"

RIC0 Seismic Duct Brochure

j

RICO Drawings 0-937-901, 902, 903, 905, 906, 907, 908, sad 909,

" Duct Support Standard Connections" and D-937-920, "At-

ment

Schedule"

1

l

Applicable construction drawings and fab tickets

b. Inspection Findings

Two of the 10 supports / restraints inspected had significantly

undersized member to building structure attachment welds. Three

adjacent supports also were observed to have undersized attach-

ment welds and similar findings by the NRC CAT welding inspec-

tors are detailed in Section IV.

RICO QC stated that they

believed these inadequate welds could be traced to inspections

performed by one individual who was on site from May 1979

,

through June 1980 and who is no longer employed on-site. A

reinspection of the suspect supports and a sampling of supports

inspected and accepted by the previously employed inspector and

j

others was performed by RICO QC.

Preliminary results of this

'

reinspection indicated that, although deficiencies were noted in

the work of several additional inspectors, the largest percentage and

most technically significant problems were identified on supports

inspected by the one inspector.

In fact, RICO quality management had

been aware that the work done by this individual was suspect and the

site lead QC Technician had stated this in an internal memorandum on

June 8,1982 to the RICO QA manager. The memorandum also stated that

a complete reinspection of the work performed and inspected by this

individual was proceeding. However, there does not appear to be any

documentation to consolidate the work scope of this individual nor

has all his work been completely reinspected some 15 months later.

A RIC0 review of nonconformance reports (NRs) issued between May

1982 and May 1983 revealed at least 39 NRs directly attributable to

,

III-11

,

e

v..--y.--~--

-- - . ~ , _

y v

,, - -

,---,y--,,

,--- --- ._,

~y

-,

.

,,


,,,_m,

, , - , , , , - - _ , - - - - - . - - - , - - - - - - - - -

.

.

this individual's work and 7 additional NRs that may be attributable

to him. This amounted to approximately 27". of all NRXs issued during

that period. The conditiors reported included m'issing and undersized

welds, improper configuration and inadequate documentation. Many

1

required rework or repair.

In general, the NRs identified the

unsatisfactory work as done by craftmen and inspectors no longer on

i

site. All NRs are reviewed by RICO and CEI management and CEI

quality engineers perform a trend analysis on NRs. However, neither

organizations' programs identified this significant and recurring

problem as needing timely and formal corrective action or evaluation

for reportability.

It should be noted that the current inspection

program, although not per procedure as described below, would

probably have identified the deficiencies present in currently

accepted work.

Related to the above issue, and possibly indicative of a general

weakness in procedural matters, were a number of relatively minor but

related problems identified during the NRC CAT review of in-process

turnover documentation packages. RICO procedure QCP-11-6/707 speci-

fies a three phase sequenced walkdown inspection of a duct system;

pre-leak test, post leak test and a " final" inspection. RICO QC is

performing the " final" inspection prior to the pre-leak test inspec-

tion. Due to the known problems with earlier inspections, RICO QC is

now performing a detailed inspection of supports / restraints during

the " final" walkdown. While this is a correct action to take, it is

not required or defined by site procedures.

In addition, RIC0 QC

does not have a specified or executed means to void out existing

QC inspection documentation when rework is required to QC accepted

hardv re. Also, in the review of the " final" walkdown deficiency

punalist for systems OMIS and 1M36, a number of instances were

diu. overed where conditions were being identified and closed cn the

punchlist that should have been identified on nonconformances.

Examples include missing welds on supports DS-0G-2001-and 2002,

improper washers installed on supports DS-0G-4025 and 0S-1B-3126

and undercut welds on support DS-IB-4059. Finally, the responsibili-

ties and processes for teveloping "as-built" drawings are not clearly

defined by site procedures.

Minor discrepancies were noted during the inspection of supports /

restraints,' equipment and duct runs and are summarized in Table

III-10.

c. Conclusions

(1) With the exception of undersized attachment welds, HVAC

hardware material, configuration, location and installation

appeared to generally conform to design documents.

(2) The work performed by certain craftsmen and/or inspectors

appears to have been deficient, especially as identified

with undersized structural attachment welds.

III-12

____

- _ _ - _-.

_

._ - _ _ _

_ -

.

.

.

,

(3) The quality assurance programs of both RICO and CEI failed to

'

properly and promptly identify, evaluate, correct and document

potentially significant and recurring deficiencies in instal-

led HVAC hardware.

(4) Additional attention is needed to ensure that RICO site proce-

dures are adequate and work as specified in these procedures is

correctly performed.

7. Design Change Control and Nonconformance Reports

a. Inspection Scope

Seventy NRs were reviewed in the mechanical area for technical

adequacy and to determine if the NRs were properly closed in accord-

ance with the approved disposition. Twelve hanger supports were

selected when work was in-process to determine if design changes

were properly controlled.

~

b. Inspection Findings

Nonconformance reports reviewed were dispositioned adequately. With

one exception, reports reviewed indicate proper closecut. Noncon-

formance Report CQA 136 dated 1/30/80 was improperly closed out in

that the action required for close out [i.e., the listing of compo-

nents and supports requiring the use of Code Case N-242 must be

identified in the Safety Analysis Report (SAR)] was not accomplished.

The NR required as part of its disposition that an FSAR change be

submitted. However, the NR was inappropriately closed and no FSAR

change was submitted. This NR involved the acceptance of a large

number of safety-related pipe spools.

Relative to design changes, traveler packages in the field were

reviewed te revisions on both the applicable drawing and process

sheets. This information was compared to the current information

regarding the latest design for each of the subject hangers. No

problems were identified.

!

c. Conclusions

.

Because of improper close out of CQA-126, the requirements under NRC

Regulatory Guide 1.85, Revision 16 could not be satisfied. This

l

Regulatory Guide requires that components and supports that are

accepted by the use of Code Case N-242 be identified in the SAR.

Similar examples of improper closecut of nonconformance reports are

discussed in Section VIII under Corrective Action Systems.

Design changes reviewed indicated that they were processed in

accordance with the applicant's program requirements.

III-13

.

- . - ,

.-

_ , _ _ _ _ _ . _ - ,

- _ . _ . _ . , .

,-

, , _ _ _ . ,

, _ _ _ . _ , _ _

, ,,

, . . _ , , _ . ,

_

-._

.

-

___

._

_..

..

.

.

,

TABLE III

1

PIPING INSPECTION SAMPLES AND OBSERVATIONS

ASME

Pipe

Observations

System

Isometric

Class

Diameter

(AR/NR Issued)

RHR

1E12-24

1&2

12" & 18"

RHR

1E12-38

2

12" & 18"

RHR

1E12-47*

2

8"

RCIC

1E51-7

2

8"

RCIC

1E51-1

2

12"

FPC&C

OG41-9*

3

10"

Valve F557B rotated

90 degrees (NR PPP-4005)

FPC&C

OG41-27

3

10"

.

ECC

OP42-31*

3

10"

Valve operator F445

rotated 180 degrees

(NR PPP-4005)

ECC

OP42-32

3

10"

ECC

OP42-34

3

10"

Valve operator F260

,

rotated 90 degrees

-

Additional Valves Selected for Orientation

Valve

Isometric

Observation

F140

OP43-29

,

l

F787

OP43-29

F551

OG41-39

F280

OG41-39

F285

OG41-39

F060

OP50-15

Valve rotated 86 degrees

F780

OP43-28*

Handwheel rotated 180

degrees

F150

OP50-5

Valve rotated 90 degrees

F060

OP50-8

Valve rotated 86 degrees

F785

OP43-19

,

  • "As-built certified"

III-14

_ _

..

.

.

TABLE III - 2

PIPE SUPPORTS / RESTRAINTS INSPECTION SAMPLES

Support / Restraint

Type

Class

Size

Location

1821-H006

Snubber

3

14"

Reactor

1P42-H113

U-bolt

3

10"

Control

1P42-H139

Strut

3

10"

Control

IB21-H117

Snubber

3

10"

Reactor

IP42-H148

Box / Lug

3

12"

Control

IP45-H167

Spring

3

20"

Auxiliary

1G41-H247

Box

3

12"

Intermediate

1G41-H354

U-bolt

3

10"

Intermediate

IP45-H447

Box

3

8"

Diesel

  • 1E22-H024

Snubber

2

16"

Auxiliary

1E12-H2109

Box

2

2"

Auxiliary

1E12-H138

Spring

2

18"

Auxiliary

1G41-H362

Box

3

10"

Intermediate

IP45-H147

Strut / Box

3

16"

Auxiliary

,

1821-H223

Box / Lug

3

2"

Reactor

IC11-H032

Box / Strut / Lug

2

8"

Reactor

1G36-H045

Strut

3

4"

Reactor

1G36-H065

Spring

3

8"

Reactor

IB21-H414

Box

3

12"

Reactor

  • 1E12-H1061

Box

2

11"

Auxiliary

  • 1E12-H1041

Box

2

11"

Auxiliary

  • 1E12-1062

Strap

2

3/4"

Auxilia ry

1E12-H748

Box

1

12"

Reactor

IE21-H014

Spring

1

12"

Reactor

1E12-H010

Snubber

1

12"

Reactor

1E12-H037

Restraint

1

6"

Auxiliary

1M51-H022

U-bolt

2

4"

Reactor

    • 1B33-H352A

Spring

1

16"

Reactor

  • 1P11-H059

Strut / Lug

4

8"

Reactor

IP54-H017

Box

4

4"

Reactor

  • 1P11-H098

Strut

4

12"

Auxiliary

1P11-H078

Strut

4

12"

Auxiliary

IP54-H199

Strut

4

6"

Intermediate

  • 1P11-H065

Snubber

4

8"

Reactor

IP54-H1011

Strap

4

li"

Auxiliary

  • 1P11-H056

Box

4

8"

Reactor

  • "as-built certified"

,

i

III-15

L

--

--

-_

_

.

.

TABLE III - 3

PIPE SUPPORT /RESTRAlflT INSPECTION OBSERVATIONS

Support / Restraint

Observation (AR/NR/DR Issued)

'

\\

Safety Related Samole

1821-H006

1/8" clearance to drywell liner (SCV-2544)

1G41-H354

No clearance between pipe and U-bolt (NR PPP-4135)

  • 1E22-H024

Load pin spacers 1/8" thick vs. 1/16" on drawing

Attachment plates switched in position "As-Built"

(A.B.) pin to pin dimension in error

(NRCQC-2865)

IE12-H138

Loose U-bolt nuts

,

I

  • 1E12-H1062

2 attached hangers not shown on A.B.

1E12-H748

Phase 11 checklist on file incompletely filled out

1E21-H014

Contact point on drawing has 1" gap (NR P044-2164)

1E12-H010

i" clearance to decking

Adjacent Safety Related

size U-bolt and non-safety material installed

Wrong (NRCQC-2877)

1G36-H1045

1G36-H1046

Threads on U-bolt had been extended by crafts

(NRCQC-2878)

1G36-H062

Phase III tagged, clamp bolts not staked

IP42-H225

Travel stops removed (NR PPP-4034)

1P45-H055

No washers over slotted holes (Procedure IX-6,

Rev. 8/10/82, Para. 8.4.6).

Clips for sliding

connections welded-not shown on drawing

(NRPPP-4114)

1P45-H058

No washers over slotted holes (Procedure IX-6,

Rev. 8/10/82, Para. 8.4.6).

Clips for sliding

connections welded-not shown on drawing

(NR PPP-4114)

I

.

III-16

I

.

.

I

TABLE III - 3 (Continued)

Support / Restraint

Observation (AR/NR/DR Issued)

1P45-H452

No washers over slotted holes (Procedure IX-6,

Rev. 8/10/82, Para. 8.4.6).

Clips for sliding

connections welded-not shown on drawing

(NR PPP-4114)

IP45-H458

No washers over slotted holes (Procedure IX-6,

Rev 8/10/82, Para. 8.4.6).

Clips for sliding

connections welded-not shown on drawing

(NR PPP-4114)

1E22-H100

Support disassembled, Phase II tag attached,

no Phase II checklist on file (AR 704)

Class 4 Sample

  • 1P11-H058

Clip angles installed 2}"x21"x3/8", drawing

specifies 3"x3"x3/8"

Strut angularity exceeds erection tolerances

DCC issued drawing without latest ECN Revision

As-built walkdown and drafting performed to

superceded ECN Rev (DR 2391)

  • 1P11-H098

Drawing specifies 1/16" attachment fillet weld

and shape that is not manufactured. Baseplate

is 1" thick vs. 3/4" on drawing (DR 2394)

1P11-H078

Pipe attachment location off by 4-3/4" (DR 2392)

1G36-H1024

Nowashersbetweennutandbaseplate(NRCQC2880)

  • "as-built certified"

III-17

.

.

. ..

- _ _ _ _ _ _ _ _ _ _ _ _ __

_--_ -__

-

. - -

_-_

_

.

8

O

TABLE lIl-4

i

l

CONCRETE EXPANSION ANCHOR SAMPLES AND OBSERVATIONS

Support / Restraint No.

Observations (1)

i

1G36-H1024

One nut rotated 1/8 turn

1G36-H1045

One nut rotated 1/8 turn

1G36-H048

One nut rotated 1/8 turn

1G33-H043

i

1P57-H1060

1P57-H1052

IG41-H253

One nut rotated 1/8 turn

1G41-H414

1G41-H362

Two nuts rotated 1/16 turn

!

1E21-H080

Three nuts rotated 1/16 turn

Two anchors with 3 3/4 inch standout

1E21-H030

One nut rotated 3/16 turn

One anchor with 2 1/2 inch standout

1E21-H081

Two nuts rotated 1/16 turn

1E21-H1013

IE21-H053

1E21-H021

4

1E12-H2001

1E21-H1010

,

1E12-H2002

1E21-H026

One nut rotated 1/16 turn, One nut

,

rotated 1/8 turn

1E32-H163

One anchor with 2 inch standout

1E32-H225

1E32-H152

1E12-H1059

1G36-H036

IP42-H1164

One anchor with 2 inch standout.

.

2P42-H043

One nut rotated 1/8 turn

2P42-H057

1P42-H1219

,t

NOTE:

'

(1) Observations were made.after the minimum specified torques (per ECN

10493-44-1641 Rec. C) was applied to the nuts.

i

e

l

l

l

i

l

III-18

,

!

.

. _ . _ _ . _ _ . . , . . . .._ . _ _ .

. _ . _ . . _ - . . _ _ _ _ _ . _ . . . . _

_

_ _ ,., ,_=,. .

_ . _ . .

_ . _ ,

_ _ _ _ _ _ -

_ _ _ _ _ __ . _ _ _ __ _ _ .-_.

.

.

.

.

4

TABLE III-5 - EMBEDNENT OF CONCRETE EXPANSION ANCHORS

4

Measurement (Top

Marking

Minimum

of Bolt to

Computed

Required

i

i

Support / Restraint No.

on Bolt

Length (in.)

Concrete) (in.)

Embedment (in.)

Embedment (in.)

i

1E21-H080

T

12

3 3/4 (2 bolts)

8 1/4

8 1/2

IE21-H030

R

10

2 1/2

7 1/2

8

1

1E32-H163

0

8 1/2

2

6 1/2

6 7/8

1

1P42-H1164

0

8 1/2

2

6 1/2

5 1/2

4

4

l

i

C

xL

e

l

i

o

i

I

I

i

9

.

'

,

4

'

~

j

.

_ _ _ _ _ _ _ _ _ _

.

.

TABLE III-6

MECHANICAL EQUIPMENT FSAR COMPARISONS

-

Serial #/(Actuator Model)

Operational Parameters

Field

MPL No.

Equipment

Documentation

Observation

Item

Specs.

FSAR

E51-C001

RCIC Pump

15210030

15210030

Total Pump

725gpm

725gpm

Discharge

Water Temp.

40 F to

40 F to

Range

140 F

140 F

NPSH

21 ft. min.

21 ft. min.

Developed

2980 Ft.'

2980 Ft.1

llead

610 ft.2

610 Ft.2

,,

-

)[

BilP, Not

825 IIP 3

825 llP3

o

to Exceed

150 HP4

150 llP4

l

Design

1525 psig

1525 psig

Pressure

Design

40 to

40 to

Temperature

140 F

140 F

NOTES:

8 At 1192 psia reactor pressure

2 At 165 psia reactor pressure

3 At 2980 feet developed head

'8 At 610 feet developed head

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

-

_

.

-,

.

TABLE III-6

.

MECHANICAL EQUIPMENT FSAR COMPARISONS - Cont.

Serial #/(Actuator Model)

Operational Parameters

Field

MPL No.

Equipment

Documentation

Observation

Item

Specs.

FSAR

E51-C002

RCIC Turbine

F-38176-A

38176-A

Steam Inlet

1150gsia,

1150gsia,

Pressure

min.

min.

,

'

150 min.c

150 min.6

Turbine

25 psia,

25 psia,

-

Exhaust

max.5

max.5

Pressure

25 psia,

25 psia,

.

max.6

max.C

i

l

Design Inlet

1250 psig

1250 psig

7

7

gj

Pressure

$3

Design Exhaust 165 psig

165 psig

7

7

Pressure

E51-F045

RCIC Steam Supply Valve 60810

60810

Max. Opening

15 sec.

15 sec.

(SMB-0-25)

(SMB-0-25)

and/or Closing

Time

Differential

1400 psi

1400 psi

Pressure

!

Notes:

,

S H.P. Condition

6 L.P. Condition

7 At Saturated Temperature

-

_-____

_ _ .

.

.

'

T/.8LE III-6

MECHANICAL EQUlP. MENT FSAR COMPARISONS - Cont.

Serial #/(Actuator Model)

Operational. Parameters

Field

MPL No.

Equipment

Documentation

Observation

Item

Specs.

FSAR'

E51-F063

RCIC Steam Supply

72965

72965

Max. opening

20 sec.

10 sec.

Isolation Valve

(SMB-1-60)

(SMB-1-60)

and/or closing

time

Differntial

741 psi

1177. psi

Pressure

E51-F064

RCIC Steam Supply

43512

43512

Max. opening

10 sec.

10 sec.

Isolation Valve

and/or closing

time

,

x

}l

Differential

1177 psi

1177 psi

Pressure

n>

E51-F017

RCIC Pump Suction

1

1

Relief Setting

75psig

75psig

Relief Valve

Flow

14 gpm

14 gpm

Notes:

8 At 10 percent Accumulation

,

__-. _ _ _ _ _ .

_ _ _ _ _ - _ - _ _ . _ . _ _ _ _ _ _ _ - _ _-.

. . . -

,

.

._. ..

.

.

TABLE III-6

MECHANICAL EQUIPMENT FSAR COMPARISONS - Cont.

Serial #/(Actuator Model)

Operational Parameters

Field

MPL No.

Equipment

Documentation

Observation

Item

Specs.

FSAR

E51-F022

RCIC Pump Test

60809

60809

Max. dif-

1400 psi

1400 psi

Return Valve

ferential

i

pressure

capable of

throttling

i

control

,

-

1

Closure

-

75 psi

against dif-

ferential pres-

sure of

,

-

1*

E51-F031

RCIC Pump Suction

61522

61522

Opening and

75 psi

75 psi

-

E!

Valve, Suppression Pool

(SMB-000-5)

(SMB-00-10)

closing against

j

differential

pressure of

E12-C002

RHR Pump

741-5 1410

741-5-1410

Head Capacity Some as FSAR

See FSAR

,

Curve

Fig.

5.4-15

.

2

NPSH Require- Same as FSAR

See FSAR

ment Curve

Fig.

!

5.4-15

l

Brake HP

750 HP

250 HP

!

08000 gpm

@8000 gpm

,

h

n

l

!

-_.

.

.

__

.

.

TABLE III-7

DOCUMENTATION REVIEW FOR MECHANICAL E0VIPMENT

,

Certification

Applicable

Eauipment-

Report Number

Purchase Order

Specification

RCIC Pump

Bingham-Willamette 205-AG-534 Rev. 8

21A9443AW

certification dated

Rev. 1

4-10-78

RCIC Turbine

PQC C772

205-A6-745 Rev. 1

21A9526AE

Rev. 1

RCIC Steam Supply

5618-18-39

P-1364-K

521.02

Valve (F045)

B/M RNN 261

RCIC Steam

5466-82-10

P-1364-K

521.02

Isolation

B/M RNU 209

Supply (F063)

Valve

RCIC Steam

5618-80-11

P-1364-K

521.02

Supply Isolation

B/M RNU 206

Valve (F064)

RCIC Pump Suction

9128-80-19

P-1257-K

523-4549

ReliefValve(F017)

B/M RNQ-200

RCIC Pump Test Return

5618-18-39

P-1364-K

521.02

Valve (F022)

B/M RNN 261

P-1364-K

521.02

RCIC Pump Suction Valve,

--

Suppression Pool (F031)

B/M RNN 260

RHR Pump

PQC R 239

205 A6 070 Rev. 9

21A9514AE

Rev. 3

III-24

..

- _ _ _ _ _ _ _ _ _ - _ _ _ _ _ .

__

_.

_

- -

. _ _ _

'

.

,

TABLE III-8

SUMMARY OF DISCREPANCIES

Equipment

Discrepancy

CEI Action

.

1.

RCIC Turbine

Serial # on PQC certification

Request GE confirmation

(C002)

disagrees with # in field.

that serial # in field

conforms to Purchase

Order (1)

2.

RCIC-Isolation

Valve does not meet FEAR

Will revise FSAR to

Valve (F063)

opening and/or closing

conform to purchase

requirement of 10 cec.

specifications

and differential pressure of

1177 psi.

3.

RCIC Test Return

Purchase specification does

Will revise FSAR to

Valve (F022)

not mention closure again:t

exclude 75 psid closure

75 psid.

requirement.

4.

RCIC Suction

Actuator Model Number in field

Identified this valve

.

Valve (F031)

is not the same as specification

previously along with

requirement.

approximately 100 others

as having the wrong

activator model

numbers (2)

5.

RHR Pump (C002)

Brake HP in FSAR is approximately Will revise FSAR to

1/3 of that shown in specifica-

reflect the specified

tions,

value (3)

Notes:

1 Letter, CEI to GE, PY-CEI/ GEN 168 QA, dated 9/21/83

2 Letter, CEI to Gilbert, PY-CEI/GAI-5305, dated 7/29/82

3 PNPP FSAR Change Request C/R # 51

1

$

t

,

111-25

..

.

. - .

-.

-

. .,

- . - .

. . - - -

. .

.

,

.

. . - .

-

,

- .

.

TABLE III - 9

HVAC INSPECTION SAMPLES

Supports / Restraints:

_

DS-IB-7032

DS-0G-2022

DS-IB-7072

DS-CC-1008

DS-CC-1040

DS-CC-1007

DS-IB-7062

DS-IB-3130

DS-0G-2001

DS-CC-6162

Equipment:

'

Fire dampers

FDCC-721, FDCC-756 and FDIB-308

Fans'

1M15C001A, 2M15C001A, 2M15C001B, OM40C001B,

OM40C002C

Plenums

2M15D001A, IM15D001A, 2M150001B, OM40C002B,

OM40D001C

Flow dampers

1M15F070A and 1M25F130A

Duct Segments:

QM15-739

Pieces 51-68 and 76-79

QM15-722

Pieces 67-70

.

a

III-26

.

.

_

-

.

- . . - .

. - - _ . - . - _ . . . _ . . _

- - _ , _ . _ - - _ . . _ . . _ . . _ . . . _ .

_

. - .

_

.

.

TABLE III - 10

.

HVAC INSPECTION OBSERVATIONS

ITEM

OBSERVATION ( AR/NR/DR/F0 ISSUED)

Support DS-0G-2001

Support to building structure attachment

weld undersized (1/4" vs 3/8")

Support 05-1B-3130

. Support to building structure attachment

weld undersized (1/4" vs 3/8")

Support DS-IB-3099

Support to building structure attachment

weld undersized (1/4" vs 3/8")

i

Support DS-IB-3129

Support to building structure attachment

weld undersized (1/4" vs 3/8")

Support DS-IB-3072

Support to building structure attachment

weld undersized (1/4" vs 3/8")

Support DS-IB-7072

Two duct to support welds missing

(NCR RIC0-501)

Support DS-0G-2022

"Y" dimen. specified as 2", actual = 1-i"

Plenum 0M15-D001A

One foundation nut less than full engage-

ment (approx. I thread) (FQ 31769)*

Fan OM40-C002B

Three foundation nuts less than full

engagement (approx. 1 thread) (FQ 31769)*

  • As a result of this finding RICO is reinspecting all previously installed

seismically mounted HVAC equipment for full thread engagement of foundation

fasteners.

III-27

.

.

..

.

_ _ _ _ _ _ _ _ _

.

o

.

IV.

WELDING AND NONDESTRUCTIVE EXAMINATION (NDE)

A. Objective

The objective of the appraisal of welding and NDE was to determine if work

in progress and Quality Control (QC) accepted work related to welding and

NDE activities are controlled and performed in accordance with design and

NRC requirements, SAR commitments, and applicable codes and specifications.

An additional objective was to determine if personnel performing welding

and NDE activities are adequately trained ano qualified in accordance with

established performance standards and applicable code requirements.

B. Discussion

To accomplish the above objectives, welds and welding activities for

piping, pipe supports / restraints, structural steel irstallations, pipe whip

restraints, heating, ventilation and air conditionins (HVAC) installations,

electrical supports and instrumentation and control twaing were inspected.

NDE examination activities were appraised through review of radiographs of

piping welds and observation of NDE field activities, review of NDE person-

nel qualifications, and interviews with NDE personnel. This inspection

activity involved the following contractors: General Electric (NSSS),

Pullman Power Products (piping and supports), Newport News Industrial

(containment liner), Johnson Controls (instrumentation and controls), L. K.

Comstock (electrical), Pittsburgh Bridge and Iron (structural steel), and

Robert Irsay (HVAC).

1. General Electric Company (GE)

a. Inspection Scope

The NRC CAT welding inspection activities relating to the GE con-

tracts were in the areas of piping systems welds, support / restraint

welds, welding procedures, welder's qualification, and in-process

welding. NDE procedures, personnel qualifications, and the review of

radiographic film for shop and field fabricated welds were also

included in this inspection.

(1) Welding Activities

The NRC CAT inspections of piping systems consisted of walkdcwns

of the main steam (B21) and the reactor recirculation (B33)

systems. Approximately 700 feet of pipe involving approximately

50 ASME Class 1, 2, and 3 welds were inspected (see Table IV-1).

Both field and shop welds were inspected to determine if attri-

butes such as mismatch, weld surface contour and appearance and

weld reinforcement were in accordance with the ASME Code require-

ments.

It should be noted that many of the surfaces for the

inspected welds had previously been blended for in-service

inspection.

.

IV-1

,

.

-.

.

.

. -

-

_-,.

.

.

Specification 21A2005, for shop fabrication, Specification

21A2005AD for solution heat treatment of shop welds, and Specifi-

cation CEI527 for cladding the internal diameter of field welds

were reviewed to determine if GE welding activities are being

performed in accordance with the guidance provided in the NRC

Regulatory Guide 1.31 (Rev. 3) " Control of Ferrite Content in

Stainless Steel Weld Metal," and NRC Regulatory Guide 1.44 (May

1973) " Control of the Use of Sensitized Stainless Steel".

The NRC CAT also inspected welds on 10 ASME NF Class 1 pipe

supports. These welds were inspected for weld size, length,

contour and appearance in accordance with the requirements of the

ASME Code (see Table IV-2 for a listing of the supports /

restraintsinspected).

Ten welders were observed while performing in-process welding of

piping and support / restraint welds. The supporting documentation

for the inspected welds such as filler material withdrawal and

process travelers were also reviewed for adequacy.

In addition, the qualification records of twenty-five welders

were reviewed. These welders were qualified by either bend tests

or by radiography in accordance with Specification GEP-N-004,

which was reviewed to the requirements in the latest edition of

ASME Section IX. Radiographic film and records of personnel

qualified by the radiographic option were also reviewed (see

Table IV-3 for a listing of the welder qualifications reviewed).

(2) Nondestructive Examination Activities

The NRC CAT inspection of NDE activities for GE contracts

included the review of radiographic film for snop and field

fabricated pipe welds, witnessing of in-process field NDE inspec-

tions and the review of NDE procedures and personnel qualifica-

tions.

A total of 10 shop welds involving 136 film were reviewed for

film quality, weld quality and compliance with GE's specifica-

tions and ASME Sections III and V.

These welds were fabricated

by ITT Grinnel for GE. Additionally, 15 welds which were fabri-

cated by GE and radiographically inspected by Magnaflux Corpora-

tion were also reviewed. These welds involved 106 film.

The NRC CAT inspectors reviewed the personnel qualification

records for 12 NDE technicians and witnessed in-process inspec-

tion activities performed by four Magnaflux NDE personnel. Five

pieces of NDE equipment were inspected for calibration and

compliance with governing specifications and standards.

IV-2

.

--

.

_

. - - - .

-,

,

-_

--.

. _ .

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

.

l

!

b. Inspection Findings

(1) Welding Activities

No problems were identified in the area of welding procedures

and in-process welding.

Inspected shop and field fabricated

welds met the quality standards of the ASME Code.

.

However, the review of welder qualifications revealed that

radiographic film quality does not comply with the film quality

requirements of ASME Section IX and GE's welder qualification

Procedure GEP-N-004. As a result of this finding, Action

Requests (ARs) 714, 715, 716, 717, and 721 were prepared by the

CEI (Cleveland Electric Illuminating) project organization.

(2) Nondestructive Examination Activities

No problems were identified in the area of nondestructive

examination.

c. Conclusions

With the exception of the findings previously discussed, all inspec-

ted welding and NDE activities were found to conform to the require-

ments of the applicable Code and the CEI SAR commitments.

2. Pullman Power Products (PPP)

a. Inspection Scope

The NRC CAT welding inspection activities relating to PPP contracts

were in the areas of piping system welds, support / restraint welds,

welding procedures, welder qualifications, and in-process welding.

NDE procedures and the review of radiographic film for shop and field

fabricated welds were also included in +his inspection.

(1) Welding Activity

Approximately 8,000 feet of both field and shop fabricated ASME

Class 1, 2, and 3 piping was inspected. A total of 1250 welds

were visually inspected to determine if attributes such as

mismatch, weld surface contour and appearance were in accordance

with ASME Section III requirements.

It should be noted that many

of the piping welds had previously been blended for in-service

inspections (see Table IV-1 for a listing of piping inspected).

The NRC CAT also inspected welds on 56 ASME Section III,

Sub-section NF Class 1, 2, and 3 supports / restraints.

These

welds were inspected for size, length, contour and appearance in

accordance with the requirements of the ASME Code (see Table IV-2

for a listing of the supports / restraints inspected).

IV-3

.

.

Twenty PPP welders were observed while performing in-process

welding of piping and supports / restraints. The supporting

documentation for the inspected welds such as filler material,

withdrawal slips and process travelers were also reviewed for

adequacy.

In addition, the qualification records of 22 welders were

reviewed (see Table IV-3). Welders were qualified by either bend

tests or by radiographic inspection of the test sample in accord-

ance with specification II-8, " Welder Performance Qualifica-

tions," which was reviewed for compliance with the latest

edition of ASME Section IX requirements. Radiographic film and

records of personnel qualified by the radiographic option were

also reviewed.

(2) Nondestructive Examination Activities

The NRC CAT inspection of NDE activities for PPP contracts

included the review of radiographic film for shop and field

fabricated piping welds, witnessing of in-process field NDE

inspections and the review of NDE procedures.

A total of 67 shop welds, fabricated by PPP (Williamsport, Pa.),

involving 746 film were reviewed for film quality, weld quality,

and compliance to PPP specification and ASME Sections III and V

requirements (see Table IV-4 for a listing of shop welds

reviewed).

A total of 91 field-fabricated welds involving 686 film were

reviewed (see Table IV-4 for listing of field welds reviewed).

Seventeen in-process NDE field inspections involving nine PPP NDE

personnel were observed and the radiographic film for three

welder qualifications were also reviewed for adequacy.

b. Inspection Findings

(1) Welding Activities

No problems were identified in the areas of welding procedures

and in-process welding.

Inspected piping and support / restraints

welds were found to be in compliance with the quality standards

of the ASME Code.

However, problems related to piping installation were noted in

the areas of branch piping weld joints. NX-4244 of ASME Section

III requires that a fillet size of certain minimum dimensions be

met for corner welded nozzles and branch piping connections.

PPP fabrication and inspection procedures do not specify these

ASME Section III requirements regarding a minimum specified

fillet size for branch connections.

Field inspection of piping

runs revealed that several branch connections had sizes less than

those required by the ASME Code.

IV-4

___ _ __-__ _ _ _

.-

.

As a result of this finding, CEI issued Nonconformance Reports

(NR) 2916 and 2917 respectively.

Another procedural problem regarding the welding of stainless

steel socket welds for the control rod drive (CC11) system was

also identified. Socket welds for- the control rod drive system

required additional welding to the pipe side of the socket weld

as a result of an engineering design evaluation. The weld size

on the pipe side was increased to 2 times the weld size on the

socket or fitting side of the weld. Thus, for 11 inch socket

welds, the weld length on the pipe side is approximately 3/4

inch.

Field inspection of actual socket welding revealed that

the piping is subject to higher welding heat inputs due to the

increased weld size on the pipe side. Welding Procedure WPS-29,

which was used to weld the subject welds, is qualified in accord-

ance with ASME Section IX of the Code.

It covers materials

from 1/16 to 8 inches thick with an amperage range of 50 to 175

.

amps. The amperage range of WPS-29 appears to be too broad to

control heat inputs to the relatively small mass of socket weld

as compared to an 8 inch thick weldment.

In-process field welds

observed by the NRC CAT inspectors were cherry red because of

.

this excessive heat input permitted by welding procedure WPS-29.

Sectioned samples of socket welds, welded using Procedure WPS-29,

were examined by the NRC CAT inspectors. Samples of normal (1:1

weld legs) socket welds and socket welds exhibiting weld leg size

of 2:1 (pipe leg 2 times leg of fitting) were compared.

Inspec-

tion of the internal surfaces of the sectioned specimens revealed

a heavy metal discoloration on the internal surfaces of the

socket welds with the 2:1 leg ratio. This heavy metal

discoloration indicates that excessive heat inputs were used

during the welding of this specimen. Thus, an amperage range to

ensure control of heat input to the socket welds should be

considered for incorporation into WPS-29.

The reviewed welder qualification records established that the

welders were qualified in accordance with the requirements of

Section IX of the ASME Code either by bend test of radiography.

The radiographs for two welders were found to be deficient

with respect to the film quality requirements of PPP Procedure

IX-R1-5 and ASME Section IX of the Code.

The overall welder qualification program was reviewed by the NRC

CAT and was found to conform to the requirements of the ASME Code

and existing regulatory requirements. However, the program was

also reviewed in order to assess the adequacy of existing safe-

guards needed to preclude the possible use of stand-ins for

welder qualification tests. This problem was recently addressed

in IE Information Notice 83-61 " Alleged Use of Stand-Ins for

Welder Qualification Tests". As a result of the review, the

following deficiencies were identified.

A lack of controls to insure that new hires are properly

identified.

IV-5

_ _ - _ _ _ _

. _ _ _

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

.

A lack of positive welder identiiication on weld test samples

and test coupons for qualification (new hires and regular

employees taking qualification tests).

(2) Non-Destructive Examination Activities

No problems were identified in the area of NDE procedures,

personnel qualification and in-process NDE.

However, during the review of radiographs for PPP shop welds,

three of 67 PPP shop welds were rejected by the NRC CAT inspec-

tors for weld quality problems. The three welds were identified

as 1!111-GMS-ITB, IN27-G-FW-1295T, and 1-N27-G-FW-143HB. Noncon-

NR 2362 was prepared as a result of these findings. Two welds

were rejected for violation of minimum wall thickness. Minimum

wall violations were confirmed by ultrasonic examination of these

welds and NR TAS-0057 was prepared as a result of this finding.

The review of reader sheets for PPP shop radiographic film

indicated that the sheets have not been signed by the PPP radio-

graphers. The names on the reader sheets were either printed or

initialed. AR 724 was prepared as a result of this problem.

Problems concerning shop welds fabricated by PPP at Williamsport

have been found to exist at other nuclear facilities. The NRC

CAT inspected a number of completed shop welds fabricated at PPP

during the inspection at Perry. Most of these were large bcre

piping welds and had been blended for in-service inspection.

Several deficiencies including lack of compliance for weld

quality and minimum wall violations were found in small bore

piping welds. However, the sample size for welds in small bore

piping was small in relation to the total number of piping welds

reviewed (see Table IV-4). The NRC CAT understands that the

applicant plans to review small bore shop walded piping from PPP

at Williamsport to ensure similar deficiencies do not exist at

Perry.

During the review of radiographs for PPP field welds, three of

the 91 welds were also suspected of not meeting the minimum wall

thickness requirements. These welds were identified as 0-111-9,

welds 02, 03 and 04. The welds were buried undergrour.d and the

wall thickness could not be verified by ultrasonic examination.

These welds are now under investigation and the use of radio-

graphic step wedge thickness versus film density method is being

considered as a alternative method of evaluation. NRs TAS-058,

-

TAS-059, and TAS-060 were prepared for these welds.

The radiograph for weld 0-P11-9, FW01 was rejected by the NRC CAT

inspector for failure to display the 4T hole in the penetrameter

for the subject weld. NR TAS-062 was prepared for this condi-

tion. Another radiograph was rejected for lack of fusion and NR

PPP-4021 was prepared as a result of this finding.

IV-6

)

. _ _ _ _ _ _ .

_ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

..

_ _ _ _ -

l

.

.

c. Conclusions

With the exception of the findings previously discussed, all

inspected welding and NDE activities were found to comply with

the requirements of the ASME Code ano the CEI FSAR commitments.

3. Newport News Industrial (NNIC0)

a. Inspection Scope

(1)WeldingActivities

The NRC CAT welding inspection activities relating to NNICO

included inspection of field welding (both ASME and AWS D1.1),

in-process welding, welding procedures and welder qualifications.

NDE procedures, personnel qualifications, and the review of

radiographic film for the containment liner welds were also

included in this inspection.

A total of four welding attachments to the liner plate were

witnessed and the complete documentation involving eleven welds

was reviewed in order to ascertain that the welding was

performed in accordance with the requirements of the ASME code,

specifications and drawingc.

The qualification records for six welders and the welder

qualification procedures were also reviewed for adequacy.

(2) Nondestructive Examination Activities

Radiographic film for approximately 98 feet of the liner plate

was reviewed by the NRC CAT (see Table IV-4 for a listing of the

liner plate welds reviewed).

b. Inspection Findings

Welding / Nondestructive Examination Activities

No concerns were identified in the area of inspected welding and

NDE activities.

c. Conclusions

No problems were identified in the areas of inspected NNIC0 welding

and NDE activities.

4. Johnson Controls, Inc. (JCI)

a. Inspection Scope

A total of 225 welds were inspected for compliance with the require-

ments of the ASME Boiler and Pressure Vessel Code. Welding proce-

dures and the qualification test records for 25 welders were

IV-7

._

_ _ _ _ _ _ _ _ _ _ - _ _ _ _ _

.

.

reviewed.

In addition, NDE procedures and personnel qualification

records were also reviewed.

Four NDE inspectors were observed and

evaluated for their abilities to use the ASME Code and to follow

the Johnson Control (JCI) NDE procedures.

b. Inspection Findinos

No concerns were identified in the areas of inspected welding and

NDE activities.

c. Conclusions

No problems were identified in the areas of inspected JCI welding

and NDE activities.

5. Pittsburgh Bridge and Iron (PBI)

a. Inspection Scoce

A total of 340 welds were visually inspected for compliance with the

requirements of AWS D1.1 Structural Welding Code. Welding proce-

dures, welder qualification records, NDE procedures and NDE personnel

qualifications were reviewed.

In addition, a sample of NDE inspec-

tors were observed and evaluated for their abilities to use the AWS

01.1 Code and follow the PBI NDE procedures.

'

b. Inspection Findings

(1) Eight of the sampled 340 welds were found to be undersized,

having excessive concavity or unacceptable contours and were

,

deficient with respect to the acceptance criteria stated in the

AWS D1.1 Code. As a result of this finding, the project organi-

zation issued nonconformance report (NR) PBI 981 and the welds

will be repaired and reinspected as required by the AWS D1.1

,

!

Code.

(2) Active welding procedures were found to be in accordance with the

requirements of AWS D1.1 Code.

Procedure GR-2, Revision 0 was found to be deficient with respect

,

to the AWS D1.1 Code because it included ASTM A569 material

which is not listed in Table 4.1.1 of the Code. Since this

material is not listed in Table 4.1.1, the procedure can not be

used as a prequalified procedure.

PBI indicated that procedure

GR-2 was never used in production welding and it will be removed

<

from the approved procedures list.

(3) The welder qualification records for welders were found to be in

compliance with the requirements of the AWS D1.1 Code. Welders

were qualified by bend testing except for one welder whose test

plate was qualified by radiography.

1

IV-8

_

_ _ _

,

.

The review of the qualification radiograph revealed that the

radiograph was not acceptable with respect to the film quality

requirements of the AWS D1.1 Code.

PBI re-radiographed the,

original test plate and the second radiograph was found to be

acceptable.

In addition, 20 additional welds which have been

made by this welder were visually inspected. All inspected welds

were found to be of excellent quality indicating that the work

was completed by a qualified craftsman.

c. Conclusions

With the exception of the findings previously discussed, inspected

welding and NDE activities were found to comply with the requirements

of the AWS D1.1 Structural Welding Code.

6. L.K. Comstock (LKC)

a. Inspection Scope

A total of 160 sampled welds were visually inspected in accordance

with the requirements of the AWS D1.1 Code.

Welding procedures and the qualification test records for 18 welders

were reviewed.

In addition, NDE procedures and personnel qualifi-

cation records were reviewed. Two NDE inspectors were observed and

evaluated 'for their abilities to use the AWS D1.1 Code and to follow

the LKC NDE procedures,

b. Inspection Findings

No concerns were identified in the areas of inspected welding and

nondestructive examination activities.

c. Conclusions

No problems were identified in the areas of inspected LKC welding

l

and NDE activities.

l

7. Robert Irsay (RICO)

a. Inspection Scope

Total of 160 welds were inspected comprising a sample of vendor

i

procured welds and field welds completed by RICO. Welding proce-

dures, welder qualification records, NDE procedures and NDE personnel

l

qualifications were reviewed.

In addition, two NDE inspectors were

observed and evaluated for their abilities to use the AWS D1.1 Code

and to follow the RICO NDE procedures.

.

IV-9

.

4

0

b. Inspection Findings

(1) During the visual inspection of completed field welds, some of

the welds were found to be undersized. As a result of this

finding, the project organization issued NRs RIC0-488, RIC0-489

and RIC0-490 and all deficient welds will be required to comply

with code and specification requirements.

(2) Vendor supplied multi-blade dampers were found to be tack welded

instead of the required 1" stitch weld. As a result of this

finding, the CEI project organization issued NR MCC F-40 to

address this item.

(3) The welding and NDE procedures reviewed were found to be in

conformance with the requirements of the AWS D1.1 Code.

(4) The welder and NDE personnel qualification records reviewed met

the requirements of the AWS D1.1 Code,

c. Conclusions

With the exception of the previously discussed findings, inspected

welding and NDE activities were found to comply with the requirements

of the AWS D1.1 Structural Welding Code.

.

4

1

IV-10

,

,

Table IV-1

PIPING RUNS INSPECTED

System /Name

Class

Size

IB21/ Nuclear Boiler System

3

10", 1?", 14"

1G33/ Reactor Recirculation

1

20", 28"

1C11/ Control Rod Drive

2

11", 16", 8"

1E12/ Residual Heat Removal

1,2,3

3", 4", 6," 10", 12", 18"

1E21/ Low Pressure Core Spray

1, 2

2", 12", 14", 24"

1E22/High Pressure Core Spray

1, 2

10", 12", 16", 24"

1E32/ MSIV Leakage Control

2

21", 3", 4"

1E51/ Reactor Core Isolation Cooling

1, 2

2", 4",

6", 10", 12"

1G33/ Reactor Water Cleanup

1, 3

4", 6", 12"

1G36/RWCU Filter /Demineralizer

2, 3

4", 6", 8"

1G41/ Fuel Pool Cooling and Cleanup

3

8", 10"

IG42/ Suppression Pool Drain and

Cleanup

3

8", 10"

1G42/ Suppression Pool Drain and

Cleanup

3

8", 10"

1G61/ Liquid Radwaste Sumps

2

21"

1N27/ Feed Water

1

12", 20"

1P11/ Condensate Transfer and Storage

2

10", 16"

1P42/ Emergency Closed Cooling

3

4", 10", 12"

1P45/ Emergency Service Water

3

4", 8", 10", 14"

1P47/ Control Complex Chilled Water

3

3", 6", 8", 10"

IV-11

.

.

.

_ _

_

_ _ _

- _ _ _ _ .

_.

.

- e

,

TABLE IV-2

Pipe Suoports/ Hangers Inspected

,

Supports / Restraints No.

Results

H101 B(A)-1

Welds acceptable

H101A(A)-1

"

H101A(B)-1

"

,

'

"

H1010(A)-1

"

H1028-1

"

H306A-1

"

H305A

"

H351B-1

"

H3538-1

"

H101B(B)-1

H101D(B)-1

"

"

H3568-1

NOTE: These supports / hangers listed on this page are installed by General

Electric

,

i

l

'

i

f

i

IV-12

...

,_ ... -

.

._

- _ .

_ _ _ - -

.

-

-

-

,

-

--.

_ - . , . .

,

.

TABLE IV-2

PIPE SUPPORTS / HANGERS INSPECTED - Cont.

Supports / Restraints No.

Results

IB21-H006

Welds Acceptable

IP42-H113

a

1P42-H139

"

1B21-H117

"

1P42-H148

"

1P45-H167

"

IG41-H247

"

1G41-H354

"

1P45-H447

"

1E22-H024

"

,

1E12-H2109

'

"

1E12-H138

"

1G41-H362

"

1P45-H147

"

1821-H223

"

1C11-H032

"

1G36-H045

'

"

1G36-H065

"

1B21-H414

"

1E12-H1061

"

1E12-H1041

"

1E12-H1062

"

1E12-H748

"

1E21-H014

"

1E12-H010

"

1E12-H037

"

1M51-H022

"

1P42-H345

"

1E12-H2095

"

1G41-H209

"

1P42-H099

"

1P45-H120

1P42-H345

Rejected by CEI

Phase 11 inspection

IP42-H139

Under sized fillet welds (2)

NRC 2540R11 had been prepared

for undersize welds

1E12-H1062

Welds acceptable

"

1E12-H136

"

1P42-H113

"

1P42-H148

'

"

1E12-H2109

"

1B21-H117

"

1821-H006

NOTE: The supports / restraints on this page are installed by Pullman Power

Products

IV-13

-

--

. _ . .

_

_ _

-_ , _.

. _ - . _

-

.

.

TABLE IV-2

PIPE SUPPORTS / HANGERS IINSPECTED - Cont.

Support / Hanger No.

.Results

IP45-H167

Welds Acceptable

-

"

1G41-H247

"

1G41-M354

"

1P45-H447

1C11-H614

Reviewed for welding

and Design Change

Control. Acceptable

"

IC11-H642

"

1C11-H021

"

1E12-H072

'

"

1C11-H015

"

1833-H1068

"

1P42-H1043

"

1E12-H178

"

1P45-H360

"

1C11-H516

"

1821-H107

"

1P45-H1516

NOTE: The supports / restraints listed on this page are installed by Pullman

'

Power Products

)

-

IV-14

__

. . _

_

_

. .

_ . _ ....

_

_

_

.

.

..

.

TABLE IV-3

WELDER QUALIFICATIONS

General Electric

Method of Testing /

Welder I.D.

Commments

GEP-005

RT

GEP-071

Bends

"

GEP-072

"

GEP-082

"

GEP-084

"

GEP-104

"

GEP-105

GEP-113

RT

"

GEP-118

GEP-121

Bends

GEP-132

RT

"

GEP-140

"

GEP-160

GEP-175

RT & Bends

GEP-177

RT (1)

GEP-187

RT(1)

GEP-199

RT

GEP-210

Bends

GEP-217

Bends

GEP-271

RT(1)

"

GEP-274

"

GEP-279

GEP-288

RT

GEP-290

RT (1)

GEP-297

RT

Pullman Power Products

Method of Testing /

Welder I.D.

Comments

l

l

RX

Bends

FZ

RT & Bends

'

AJV

Bends

"

X2

i

"

AGK

"

ATC

"

ARA

"

.

JT

"

ADE

"

ATH

"

ATM

IV-15

_ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

.

TABLE IV-3

WELDER QUALIFICATIONS - Cent.

'

Pullman Power Products - Cont.

Method of Testing /

-

Welder i.D.

Commments

"

ARC

"

ALN

"

E2

"

ABJ

"

ADF

"

AUH

"

ATP

"

AJK

AP

RT & Bends

"

ARD

AC4

RT (1)

AMQ

RT (1)

Newport News Industrial

Method of Testing /

Welder I.D.

Comments

018-4144

RT

"

018-488

"

441-1745

"

441-4469

"

065

"

024

Others

PBI/ Kelly Steel - A total of 57 welder qualification records were

reviewed. 56 welders were qualified by bend test

and one by radiography.

Johnson Controls - A total of 25 welder qualifications were reviewed.

All welders were qualified by bend testing.

L. K. Comstock

- A total of 18 welders were reviewed. All welders were

qualified by bend testing.

Robert Irsay Co. - A total of 17 weldres were reviewed. All welders were

qualified by bend testing.

NOTE (1): The radiographic film quality was unacceptable per ASME Code.

IV-16

i MA i

'

i

_ _ _ _ _ _ _ _ - _ _

_ _ _ _ _ _ _ _

- _ _ _ _ _ _ _ _ _ _ _ _ - _ _ ______ -_____ ___ __ _________

-_____ ___ ____ - __ _ ___

.

.

TABLE IV-4

RADIOGRAPHIC FILM REVIEW

2

General Electric (Shop Welds)

Weld I.D.

KER-1701-250

St. Seam

702-E-82-9G010

B1-LSWOL

1-821-MS-LOOPC

Weld 8012A

1-821-MS-L00PC

Weld 0038D

1-B21-MS-L00PB

Weld 0090

1-B21-MS-LOOP

Weld 4B

1-821-MS-L00PD

Weld 602

1-B21-4A-FRT-F-CL

Weld 6A

1-B21-4A-FFB

Weld 4A

1-B21-7D-MS-FCL

Weld 4A

1-821-A3-F-TRA

Held 6A

1-821-Al-1PC-1-3A

Weld 3A

1-B21-D2

1-B21-7CT1821

Weld 031

1-B21-4CT1821

Weld 026

i

1-B33-RRA19LOOPA

1-B33-RR10-A-1

'

1-B33-RR-002

Weld A-10

2-E32-GMSIV-63AB

Weld A

2-E32-GMSIV-63AB

Weld B

2-E32-GMSIV-63AB

Weld C

2-E32-GMSIV-51AB

Weld A

2-E32-GMSIV-51AB

Weld B

2-E32-GMSIV-51AB

Weld C

2-E32-GMSIV-52AB

Weld A

j

General Electric (Field Welds)

FRT(B33-1-34)

FGL-10

"

,

FRT(B33-1-38)

'

"

FGL-10

"

RCC-1-RCB33-RR

"

RCCA12G33-1-A12

"

f

l

RCCB33-1-A

"

I

V

.

l.

i

l

l

!

!

I

IV-17

(

.

.

.

TABLE IV-4

RADIOGRAPHIC FILM REVIEW - Cont.

Pullman Power Products Shop Welds (67)

Weld I.D.

    • 2$12-GRH-91AB

Weld B

'

1N27-GFW-1295T

Weld C

  • 1N27-GFW-129ST

Weld E

1E12-GRH-216HB

Weld A

1E12-GRH-216AB

Weld C

  • 1N27-GFW-143HB

Weld A

    • 2E21-GHR-91AB

Weld E

2E12-GHR-91AB

Weld D

2E12-GHR-91AB

Weld C

2E12-GHR-91AB

Weld A

1E22-GHPC-8AB

Weld B

1N27-GFW-140HB

Weld B

IE51-GRCIC-33AB

Weld F

IN27-GFW-129ST

Weld A

IN27-GFW-129ST

Weld B

IN27-GFW-136ST

Weld B

IN11-GMS-1TB

Weld A

  • INH-GMS-1TS

Weld B

2E-32GMSIV-37AB

Weld G

2E-32GMSIV-52AB

Weld A

2E-32GMSIV-56AB

Weld B

2E-32GMSIV-56AB

Weld C

2E-32GMSIV-56AB

Weld D

2E-32GMSIV-56AB

Weld E

2E-32GMSIV-56AB

Weld G

2-E12-G-RH-220AB

Weld J

2-E12-G-RH-220AB

Weld D

2-E12-GRH-4-AB

Weld E

2-E12-GRH-4-AB

Weld B

2-ER-GRH 19-AB

Weld G

-

1-E12-GMSIV-10RAB

Weld N

1-E12-GMSIV-10RAB

Weld H

1-E12-GMSIV-10RAB

Weld A

1-E12-GMSIV-10RAB

Weld A

1-E12-GMSIV-2AB

Weld A

2-E12-GGRH-4AB

Weld C

2-E12-GRH-220AB

Weld C

2-E12-GRH-7AD

Weld A

1-G-38GRWC-20-RB

Weld A

1-E21-GLPG-7-AB

Weld A

1E21-GLPC-2-AB

Weld C

1E12-RCIC-12-AB

Weld A

1E21-GLPC-8-AB

Weld A

1E21-GLPC-11-AB

Weld B

2E12-GRH-7-AB

Weld B

1E51-GRCIC-30-AB

Weld C

1E31-GRCIC-11-AB

Weld B

IV-18

.

.

--__

___________ _ _ _ _ _ _ _ _ _ _ _

.

.

.

.

TABLE IV-4

RADIOGRAPHIC FILM REVIEW - Cont.

Pullman Power Products Field Welds (91)

Weld I.D.

1-G33-GRWCU-20-AB

Weld A

1-E12-35-1510460

Weld 01

1-E51-2

Weld 46

1-E22-2

Weld 05

1-E22-2

Weld 09

1-E22-5

Weld 02

1-E22-5

Weld 01

1-E22-5-

Weld 04

1-E22-5

Weld 31

1-N27-1

Weld 09

1-E22-4

Weld 08

1-N27-1

Weld 15

1-E12-11

Weld 20

Cont WNI-90

15' Vert weld

1-G-23-5

Weld 02

1-G-23-6

Weld 04

1-E-51-2

Weld 09

1-E-51-2-

Weld 01

1-E-51-2

Weld 40

1-G-33-5

Weld 32

1-G-33-5

Weld 03

1-G-33-3

Weld 01

1-E-12-34

Weld 02

1-E-51-8

Weld 01

1-E-51-8

Weld 02

1-N-27-2

Wela 01

2-E-12-G-RH-220-AB

1-E-12-11

Weld 20

1-E-12-17-

Weld 10

1-E-12-22

Weld 03

1-E-12-22

Weld 05

1-E-12-22

Weld 06

1-E-12-22

Weld 07

1-E-12-22

Weld 08

1-E-12-22

Weld 10

1-E-12-31

Weld 05

1-E-12-35

Weld 01

1-E-12-36

Weld 12

1-E-12-31

Weld 06

1-E-12-12-

Weld 05

1-E-12-14

Weld 01

0-P11-9

Weld 02**

0-P11-9

Weld Ol***

0-P11-8

Weld 01

1-C41-510

Weld 44

0-Paa-9

Weld 03**

0-P11-9

-

Weld 04**

0-P11-10

Weld 01

IV-19

_. -

.-

.

TABLE IV-4

,

RADIOGRAPHIC FILM REVIEW - Cont,

Pullman Power Products Field Welds (91) - Cont.

Weld I.D.

0-P11-10

Weld 02

1-E12-20

Weld 03

1-E12-30

Weld 20

1-E12-20

Weld 03

1-E12-23

Weld 01

1-C41-4

Weld 02

1-C41-4

Weld 08

1-E12-2

Weld 10

1-E12-4

Weld 03

1-E12-5

Weld 12

1-E12-5

Weld 13

1-E12-11

Weld 03

1-E12-12

Weld 03

1-E12-15

Weld 02

1-E12-15

Weld 03

1-F12-17

Weld 01

1-E12-32

Weld 15

1-E12-33

Weld 07

1-E12-33

Weld 08

1-E12-45

Weld 05

1-E12-48

Weld 05

1-E32-7

Weld 04

1-E51-3

Weld 08

1-E51-3

Weld 01

1-E51-5

Weld 04

1-E51-6

Weld 06

1-E51-7

Weld 03

1-E51-7

Weld 03

1-E51-1

Weld 01

1-E51-1

Weld 02

1-E51-2

Weld 60

1-E21-2

Weld 03

1-E21-2

Weld 117

1-E21-3

Weld 04

1-E21-3

Weld 06

1-E12-14

Weld 09

1-E12-17

h'cid 08

1-E12-20

Weld 01

1-E12-23

Weld 02

1-E12-27

Weld 09

1-E12-24

Weld 21

1-E12-27

Weld 08

1-E12-24

Weld 05

1-E12-28

Weld 03

IV-20

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

o-

o

.

TABLE IV-4

RADIOGRAPHIC FILM REVIEW - Cont.

Pullman Power Products Field Welds

Weld I.D.

1E31-GRCIC-11-AB

Weld A

2E12-GRH-9-AB

Weld G

1E12-GRH-19-AB

Weld F

1E32-G-MSIV-10R-AB

Weld M

1E32-G-MSIV-10R-AB

Weld L

1E32-G-MSIV-10R-AB

Weld G

1E32-G-MSIV-10R-AB

Weld E

1E32-G-MSIV-10R-AB

Weld J

1E32-G-MSIV-10R-AB

Weld B

1G32-G-MSIV-10R-AB

Weld C

,

1E32-G-MSIV-10R-AB

Weld D

2E12-G-RH-4-AB

Weld A

2E12-G-RH-4-AB

Weld D

2E12-G-RH-4-AB

Weld F

2E12-G-RH-220-AB

Weld C-R1

,

2E12-G-RH-220-AB

Weld C-R2

,

2E12-G-RH-220-AB

Weld E

2E12-G-RH-220-AB

Weld E-R1

,

1-G-33GRWCU-20-AB

Weld B

1-G-33GRW-CU-20-RB

Weld C

1-G-33GRWCU-20-RB

Weld D

Welds rejected by NRC CAT for lack of compliance for weld quality

Rejected by NRC CAT for minimum wall violation

Rejected for failure to display 4T hole of the penetrameter

,

Containment Liner Review

Newport News Industrial (NNIC0)

INN 0-2(177-179) Horizontal Seam

INNI-90 Verticle Seam

Approximately 98 Ft. Film for containment liner plate reviewed

IV-21

~

. .

_ _ _ - ___

.

.

TABLE IV-5

IN-PROCESS NDE INSPECTIONS

NDE

Item

Contractor

Method

Inspected

Results

G.E.

R.T.

Piping Welds

Acceptable, Witnessed

4 R.T. Technique / setups

PPP

P.T.

Piping Welds

Acceptable, Witnessed

1 P.T. Exam

R.T.

Piping Welds

Acceptable. Witnessed

3 R.T. Exams

JCI

P.T.

Piping Welds

Acceptable. Witnessed

6 P.T. Exams

V.T.

Piping Welds

Acceptable, Witnessed

l

6 visual exams

l

l

LKL

V.T.

Structural Welds

Acceptable, Witnessed

l

2 visual exams

P.T.

Structural Welds

Acceptable, Witnessed

'

2 P.T. Exams

RICO

V. T.

Structural Wclds

Acceptable. Witnessed

,

2 visual exams

P. T.

Structural Welds

Acceptable, Witnessed

2 visual exams

j

PBI

V.T.

Structural Welds

Acceptable, Witnessed

7 V.T. Exams

M.T.

Structural Welds

Acceptable, Witnessed

7 M.T. Exams

P.T.

Structural Welds

Acceptable, Witnessed

3 P.T. Exams

U. T.

Structural Welds

Acceptable, Witnessed

1 U.T. exau

.

IV-22

I

-

.. .

-.

_ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _

_ _ _ . _ _ . _

l

.

.

V.

CIVIL AND STRUCTURAL CONSTRUCTION

A. Objective

Determine by independent evaluation of work in progress, completed work,

and by review of dccumentation whether work, inspection,. and test activi-

ties relative to the civil engineering area were accomplished in accordance

with project specifications and procedures. These objectives were met

through evaluation of the Seismic Clearance Program, concrete expansion

anchor bolts, concrete placement, in-situ concrete and reinforcing steel

placement quality, concrete and soils records, containment vessel steel,

structural steel installation activities and design changes and

nonconformance reports in these areas.

B. Discussion

1. Seismic Clearance Program

.

a. Inspection Scope

The applicant's Seismic Clearance Program provides for the identifi-

cation and review of those instances in which seismic clearance

criteria have been violated. The criteria, established by the

architect er:gineer, Gilbert Associates, Inc. (GAI), cover safety-

related components (i.e., piping and supports, HVAC ductwork and

supports, and electrical conduits and cable trays) and also non-

safety-related components which in a seismic event could affect

safety-related components. The seismic clearance inspections are to

be perf'ormed in accordance with Construction Quality Assurance

Instruction 21-1007, Rev. 1, dated 7/5/83, " Seismic Clearance Inspec-

tion." The review of the violations of seismic clearance criteria is

described in the site Procedures Manual, Volume 4, 4-0500, "GAI

'

Interfaces," dated 9/30/82. The regulatory requirements are spect-

,

fied in paragraphs C.2 and C.4 of Regulatory Guide 1.29, Rev. 3,

l

dated 9/78, " Seismic Design Classificacion."

l

A sample of 26 hardware installations in the field was reviewed

to determine the workmanship quality. The hardware reviewed were

those which had been identified as violating the seismic clearance

criteria and had been resolved by GAI engineering with or without

repair work being required. This review was performed to verify

whether the quality of workmanship was adequate for those components

for which GAI had performed analyses.

From the 26 hardware installations reviewed, an evaluation was also

performed of seven engineering calculations done by GAI which had

accepted the hardware installations. The engineering calculations

were evaluated to verify the technical adequacy of the dispositions

of the seismic clearance violations.

V-1

.

..

__

_ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ .

-_

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _

.

.

b. Inspection Findinas

For the 26 Seismic Category I, nonsafety-related hardware installa-

tions (see Table V-1), the general quality o'f workmanship (i.e., weld

appearance, nut tightness, structural integrity assessment, and

support spans) was reviewed. The review also included the inspection

of supports and components in the vicinity of the seismic clearance

violation (those conditions which could affect the engineering

analyses). Seven supports were inspected in detail for conformance

to the design drawings. The findings are detailed in Table V-1.

The significant hardware installation problems identified by the NRC

CAT were:

1) excessive lateral movement of fire protection piping

among safety-related cable trays; 2) instances of missing or poor

welds; 3) one support spring can out of alignment; and 4) excessive

piping spans with a minimal number of supports. For the sample of

hardware installations inspected by the NRC CAT, except for the fire

protection piping among cable trays, the hardware deficiencies appear

to be isolated cases and were not of a condition which would jeopar-

dize structural integrity; however, the deficiencies were of a nature

that could affect engineering analyses in other more critical appli-

cations.

Seven GAI engineering calculations were reviewed by the NRC CAT.

This review included: use of current seismic floor response spectra,

proper analytical techniques, proper analysis assumptions, and proper

evaluation of the calculation results. The calculation review

findings are summarized in Table V-1.

Twenty-two floor response

spectra curves, used as input into the calculations, were verified to

be the current response spectra. However, it was identified that the

curves were not being formally distributed to those on-site design

groups using these curves. Two significant issues were identified:

(1) The lateral movement of fire protection piping among safety-

related cable trays was not considered by the GAI engineers.

In

addition, the impacting of the fire protection piping with the

cable trays was considered in the engineer's judgment to be

"insigni ficant" .

In the actual hardware installation, the only

lateral restraint is at the branch connection at the main header

piping, allowing the fire protection piping to move laterally,

impacting cable trays or adjacent conduit.

(2) Generally, the calculations were found to be performed in r

manner not well controlled. Exgamlesare: a bolt cepacity . tot

properly evaluated for adequacy', use of differing factors oi

safety for the same component without guidance as to which fa-tor

of safety should be used and under which circumstances, differing

allowable capacities for threaded rod, assumptions for field

hardware not verified, calculation references made incorrectly,

use of the wrong size bolt (larger than actual) in a calculation,

and generic calculations which analyzed similar seismic clear-

ance violations were not based on the most limiting hardware

installation parameters.

Although, in the calculations reviewed,

no cases were identified in which the lack of detailed design

V-2

_.

_ _ _ _ _ _ _ _ _ _ _ _ - __

.

.

control caused a significant analysis error, the errors should

not have been made nor passed through the checking process

without the errors being identified.

It appeared that without

formal design / analysis guidance each GAI engineer used analysis

techniques and methods of their own choosing. This led to some

analysis inconsistencies.

In the review of an added support (CC-574-FD-4) required to

satisfyseismicclearanceviolations(SCVs),theNRCCATidenti-

fied undersized welds and weld splatter (SCV #187). Final

inspection of the added support had not been performed; however,

the violation had been already closed by GAI.

It was determined

that 29 SCVs had been dispositioned by GAI engineering as

" accept-as-is" when, in fact, the violation could only be closed

if additional work was performed (installation of supports or

removal of temporary lines). The use of " accept-as-is" vice

" repair" dispositions by GAI caused the closure of these viola-

tions prior to completion of the necessary repair work.

This practice may preclude the repair work from being properly

tracked (using a work package) and properly inspected. These

early closures of violations are contrary to the implementation

of Appendix Y (Section 2:03) to GAI Interface Procedure, Volume

4, 4-0500, dated 9/30/82, " Interfaces." As a result of the NRC

CAT finding in this area, Action Request (AR) #706, dated

9/12/83, was issued to identify and reopen those SCV's erro-

neously dispositioned " accept-as-is." This AR was closed on

9/22/83.

c. Conclusions

(1) The GAI engineering resolution for cases of fire protection

piping among cable trays (SCV 2442,2460,2492) was improper

in that lateral movement was not considered. There has been

inadequate attention to those analyses which relied mainly on

engineering judgment.

(2) Generally, GAI engineering calculations have been performed in an

inconsistent manner, and not well controlled.

In the sample of

calculations reviewed the inconsistencies and errors were not

of a magnitude to invalidate the conclusions reached. However,

this is indicative of a lack of attention to detail by the

engineer and checker.

(3) Cases of deficient installation workmanship were identified

which could be significant under other more critical situations.

(4) Seismic clearance violations were identified which had been

closed prior to the completion of the necessary repair work.

Improper dispositions by gal engineering had caused closure

prior to verification that the nonconforming conditions were

fully resolved.

V-3

-

_ _ _ - _ _ _ _ _ _ _ _ _ .

i

__ ___________ ____

o

.

2. Concrete Expansion Anchor Bolts (Hilti Bolts)

'

a. Inspection Scope

The qualification test report and installation specifications were

reviewed for the predominant type of concrete expansion anchor bolt

used at Perry (Hilti Kwik-Bolt). The inspection and installation

procedures for the Hilti bolts were also reviewed for two contractors

(Pullman Power Products and L. K. Comstock).

It was identified by the NRC CAT that concrete expansion anchor

bolts (Hilti Kwik-Bolts) are being installed in the drywell wall

through the drywell liner plate and into the concrete behind the

liner plate. The 5/8" and 3/4" diameter anchor bolts are being

used primarily to support instrumentation and control lines, electri-

cal conduits, and pipe supports. Based on discussions with the

applicant, the total number of anchor bolts anticipated to be

installed in the drywell walls are 6000-8000 per unit. Approximately

2000 were installed as of the time of this inspection,

b. Inspection Findings

On-site qualification tests for Hilti Kwik-Bolts were performed

and the results are summarized in GAI Report No. 2304, " Perry Nuclear

Power Plant: Report on Evaluation of Hilti Kwik-Bolt Qualification

Tests," dated 5/11/81. The report summarized the qualification tests

performed from November 1978 through hovember 1980. The current

installation specificatiens and installation procedures for Pullman

Power Products and L. K. Comstock were compared by the NRC CAT with

the qualification report and found to be in agreement. The following

was noted in the review of the qualification report:

(1) Torque-tension relationships were established based on the

qualification testing.

In all cases, except for 1/2" diameter

Hilti bolts, the specified inspection torque provides a preload at

least equal to the allow dle load. The installation torques are

higher than the inspectior torques. The use of 1/2" diameter

Hilti bolts was discontinued in November 1980.

(2) The 1/2" diameter Hilti bolt testing showed capacities less

than the value required by GAI specifications (8% low). However,

the GAI design practice had been to double anchor bolt loads in

order to account for base plate flexibility. For the standard

4-anchor bolt base nlate, doubling the bolt load is generally

overly conserva*'.ve and the slight reduction in the capacity of

1/2" diameter anchor bolts can be offset by the doubling of the

bolt loads. Additionally, there had been only a small number of

1/2" diameter anchor bolts installed prior to their discon-

tinuat'on. A random sample of approximately five small bore pipe

support designs were reviewed and verified by tne NRC CAT that

the anchor bolt loads were in fact doubled and proper anchor bolt

allowable loads used.

V-4

,

. .

.

-

_ _ _ _ _ _ _ _ _ _ .

--_

.

.

.

(3) The ultimate capacities used by GAI for Hilti bolts are based on

Hilti catalog recommendations. The qualification testing was

done to confirm that the Hilti recommended anchor bolt capacities

were being achieved in actual site concrete.

~

(4) The use of 1" diameter Hilti bolts has been discontinued due to

the poor test results of four 1" diameter anchor bolts in a

closely spaced pattern. The 1/2" diameter Hilti bolts showed

similar poor results in a closely spaced pattern. The problem

of anchor bolts in closely spaced patterns has been reported

previously by the licensee in a 10 CFR 50.55(e) report.

The issue of Hilti bolts being installed through the drywell liner

plate is of concern to the NRC CAT due to the number of anchor bolts

being installed (6000-8000) and that the drywell must meet bypass

leakage limits. The method of Hilti bolt installation is to drill

holes through the liner plate and into the concrete behind to a depth

approximately 7", install the Hilti bolt, place HVAC metal air duct

sealer tape material (similar in consistency to putty) in the annular

space between the Hilti bolt and the drywell liner plate with a small

amount of overfill, install the attachment, and then torque the Hilti

bol t.

The attempt is made to restore in part the leak tightness

of the liner plate that was lost when the Hilti bolt was installed

through the drywell liner.

The leak tightness of.the drywell is questioned by the NRC CAT based

on the following discussion:

(1) The Hilti bolts, especially with the large number being

installed, could contribute to crack initiation or propagation in

seismic or dynamic loading conditions leading to unacceptable

through wall cracking.

(2) The General Electric (GE) topical report on drywell cracking,

NED0-10977, "Drywell Integrity Study:

Investigation of Potential

Cracking for BWR/6 Mark III Containment," dated August 1973, notes

in Section 2.2 that the results of the study do nut include any

construction defects (such as construction joints, honey-combing,

or rock pockets) or local effects of stress concentrations caused

by penetration or associated embedments. This GE topical report

was presented as evidence that the drywell liner was in fact not

required to minimize bypass leakage. However, embedments, such

as Hilti bolts, in the drywell wall were not addressed in the

GE study and in addition, ".e NRC has not formally accepted the

GE topical report.

Investigation of other facilities using the Mark III containment

design, shows that River Bend has a steel drywell liner but does

not install concrete expansion bolts through the drywell liner

plate. The Grand Gulf FSAR, Section 3.8, specifically indicates

that the drywell concrete is the pressure retaining structural

element and in fact does not utilize a drywell liner. However,

the FSAR does present an analysis and evaluation for drywell

concrete cracking.

V-5

.

'

'

'

' -

-

- - - - . . _ _ _ _ _ . _ _ _ _ _ . - - _ _

_

- _ - _ - _ _ _ - - _ _ _ _ _ _ _ _ _ _ _ _ _

O

e

(3) Drywell bypass leakage will be tested during the pre-operational

phase at the full drywell design pressure and periodically at a

reduced pressure of three psi differential. The allowable

leakage limits for the full pressure test is 0.168 square feet of

leakage area. This limit is equivalent to approximately 1.2*, of

the space between the 8000 Hilti bolts and the drywell liner

plate contributing to the bypass leakage not even considering

other bypass leakage paths. The periodic test at reduced pres-

sure may not detect excessive bypass leakage for the full 40 year

life of the plant.

(4) Concrete cracking is a comon phenomenon resulting primarily

from volumetric changes (drying shrinkage, creep under load, and

the mal stresses) and the loading conditions. Cracking is

rc.,gnized by the American Concrete Institute (ACI) in ACI

207.2R-73 and the ACI Comittee 224 Report, " Control of Cracking

in Concrete Structures" wherein it is realized that with the use

of large, closely spaced bars and minimum cover requirements, it

will likaly require smaller maximum aggregate sizes and wetter

mixes for placement ease. Subsequent volume changes and cracking

may therefore increase rather than decrease.

It is also recog-

nized that cracks of the magnitude of 0.009 inches will allow

some leakage (water being referred to, but applicable to air).

The ACI Committee 224 report recommends a limit on the allowable

crack width for water retaining structures of 0.004 inches.

Leak tightness can in most instances only be achieved if specific

measures are taken beforehand.

(5) Several (15 to 20) small areas of voiding behind the drywell

liner plate have been identified thus far during the Hilti bolt

installation process and docu:.cnted on nonconformance reports

(NRs). These voids have occurred in almost all cases just below

the liner plate horizontal stiffener. The voiding indicates the

difficulty in achieving complete fill and consclidation in

congested areas inside the drywell wall, increasing the potential

for through wall leakage.

In addition, two NRs from Pullman Power Products (PPP) concerning Hilti

bolts in the drywell wall (NR PPPF-3842 and PPPF-3500) were reviewed.

One NR was found to be improperly dispositioned by GAI and the other NR

had bypassed the established trending program for tracking NRs. NR

PPPF-3500 described a problem with an oversized hole for a Hilti bolt.

The proposed disposition was to grout the hole and redrill it.

GAI engineering agreed with the proposed disposition. However, it is

not standard industry practice to allow grouting and redrilling of holes

for expansion anchor bolts. The NRC CAT concern is whether the grout

will actually bond tightly to the concrete to transfer the loads into

the concrete without the pulling out of the grout portion in the hole.

This is an instance of an improper engineering disposition.

'

Project and GAI civil engineering personnel had been informally moni-

toring NRs which described problems in achieving torque for Hilti bolts

in the drywell wall. Their interest is due to the fact that the

inability to achieve torque could be indicative of voiding or honey-

V-6

_ _ _ _ - _ _ _ _ _ _ _

_ .

.

.

combing of the concrete behind the drywell liner pla, ..

It was identi-

fied by the NRC CAT that NR PPPF-3842 had not been brought to the

attention of site and GAI personnel working in this area. The repair

~

was to grout the holes and redrill them as discussed previously.

As evidenced by these two NRs, it appears that Pullman Power Products

and internally within GAI, personnel are not properly distributing to

the appropriate project and GAI engineering personnel information

concerning problems with Hilti bolts and, in particular, Hilti bolts in

the drywell wall.

Engineering review by personnel knowledgecble in the

area of Hilti bolts and Hilti bolts through the drywell liner would most

likely have properly identified these two NRs as requiru.g additional

attention,

c. Conclusions

The above findings indicate that:

(1) Hilti Kwik-Bolts have been properly qualified in accordance

with specifications and procedures for their use at Perry.

In addition their installation and inspection by contractors

,

i

has been controlled by the use of specification and procedure

changes.

(2) The NRC CAT is concerned that under normal, transient, and

accident loading conditions whether the drywell wall can maintain

its leak tight integrity over its service lifetime of 40 years

considering the large number of expansion anchors currently

being installed. The preoperational drywell bypass leakage test

is important in that it will be the first test for drywell

leak tightness. This issue is under additional NRC review.

(3) From the review of two NRs, it appears that one contractor

(Pullman) and internally within GAI, personnel have not conauni-

cated to ensure that problems with Hilti bolts are properly

dispositioned and brought to the attention of project and GAI

personnel working in this area.

3. Concrete Placement

a. Inspection Scope

The concrete placement activities for two areas were witnessed by the

NRC CAT. The areas were:

three Diesel-Generator Building construc-

tion blockouts (Pour Nos. DG0-W01-638, DG0-W02-635, DG0-WO3-638) and

,

the Unit 2 Shield Building Dome (Pour No. RB2-08C-754). These

!

placements were made by Dick Corporation during the NRC CAT inspec-

tion. The activities witnessed included: pre-placement cleanliness,

rebar and embed plate placement, batch plant activities, in-process

testing, and concrete placement and consolidation. These activities

were reviewed for conformance to specifications, regulatory require-

ments and commitments. The review of applicable specifications and

procedures included:

V-7

..

.

.

..

_

___

_

.

.

  • Dick Specifications:

SP-19-4549-00,Rev.V,(4/12/78),Constructionof

Shield Building Walls and Domes for Reactor

Buildings 1 and 2

SP-201-4549-00, Rev. 6, (6/12/78) Attachment Specification -

Placement of Structural Concrete

SP-202-454%-00, Rev. 5, (4/5/78), Attachment Specification-

Placing of Reinforcing Steel for Safety Class Structures

  • Dick Quality Control and Work Procedures:

FQC-10.1, Rev. 7, 2/3/82 - Concrete Control General

FQC-10.2, Rev. 7, 12/1/80 - Preplacement, Placement,

and Post-Placement of Concrete

FQC-10.3, Rev. 2, 11/8/76 - Reinforcing Control

CWP-10.1, Rev. 1, 2/23/77 - Pumping Concrete

CWP-10.2, Rev. 3, 12/1/77 - Placement of Concrete

  • U.S. Testing Company Quality Control Procedure:

QCP-3, Rev. 11, 1/19/82 - Quality Control Procedures

for Sampling and Testing of Concrete

b. Inspection Findings

The placement areas were reviewed prior to the actual placement

of concrete, during placing activities, and during in-process

testing. The following observations were made:

(1) Reinforcing and embedded plates were of the specified size and

grade, properly located, and secured in accordance with the

design drawings, including Engineering Change Notices and Field

Variance Authorizations. Lap splices were verified to be stag-

gered and of the specified lap length.

(2) Concrete cover distances were maintained.

(3) Forms were free of standing water and debris and were adequately

secured.

(4) Construction joint surfaces were prepared, where required, by

bush hammering to expose the coarse aggregate. A Field Question

(No. 31237) was initiated on the Shield Building Dorre placement

to determine whether the vertical construction joint with a

keyway required bush hamering. GAI engineering responded that

joint preparation was only required on the horizontal

construction joint.

(5) Wall thicknesses were maintained.

(6) Batch plant operations were observed and batch tickets

reviewed against the mix design-daily mix adjustment

sheets. Batch plant operations were continuously under QC

surveillance.

V-8

-

_ _ _ _ _ _ _ _ _ _ _ _ _ _ . _

_ _ _ _ _ _ _ _ - _ _ _ _ _ _ _

_ _ _ _ _ _ _ _

. _ _ _ _ _ .

.

o

(7) The concrete placement crews were observed during placement

operations and the number of crew members was sufficient to

control the placement operation.

Concrete placement in the forms

minimized segregation of the concrete. There was no excessive

movement of concrete by vibration. One vibrator head could not

be removed from the forms (Pour DG0-WO2-635) and it was necessary

to cut the vibrator cable and leave the head embedded in the

wall. Dick NR 215 was written for this condition. GAI engi-

neering accepted this condition and the NR is now closed.

(8) Concrete in-process testing was performed by U.S. Testing at

the concrete pump discharge or truck discharge as appropriate for

the placement. The concrete was tested for slump, air content,

temperature, and unit weight and concrete cylinders taken in

,

accordance with the frequency specified in the construction

specifications. The ccncrete in the first truck for placement

DG0-W01-638 was tested and found to have an e(cessive slump (5

3/4" vs. 5").

Procedures were followed for additional field

i

testing when the concrete was found to be out of specification

l

requirements. Since approximately three cubic yards of the high

!

slump concrete had already been placed, Dick NR 214 was issued

and accepted based on acceptable cylinder strength tests at 28

days (minimum tested strength - 6155 psi vs. minimum required

,

strength - 3000 psi). The NR is now closed.

(9) Post-placement. inspection of the pours was performed by the

applicant and areas were identified in placement DG0-WO2 and

DG0-WO3 of superficial honeycombing. These areas were documented

in Dick NR 216. As part of the NR and attached to the NR were

the Perry Review Board comments on 9/8/83 which stated, " Training

of crafts to be documented and attached 1.0 this NR prior to

closeout." However, the closeout date of Dick NR 216 is 9/14/83,

whereas the training documentation indicates that training was

not given until 9/21/83 (one week after the NR was formally

closed). AR 716 was initiated to identify the cause of the

discrepancy and the steps to prevent recurrence. This is an

example of the closure of an NR prior to completion of all the

required actions (see Section VIII).

c. Conclusions

The placement activities witnessed indicate that generally concreting

is being performed in accordance with procedures and specifications.

The problems which occurred during the placement process were

properly identified, addressed by procedures, and the procedures were

followed, except in one case concerning improper closure of a noncon-

formance report prior to completion of the required actions.

V-9

.

.

_ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ -

..

_ _ _ _ _

__

_ _ _ - _ _ _ _ _ _ _ _ _ - _ _ _ _ _

.

.

4. In-Situ Quality of Concrete and Reinforcing Steel Placement

a. Inspection Scope

Four construction access blockouts were reviewed by the NRC CAT

for proper reinforcing steel placement, cadweld quality.and concrece

quality. The blockouts are listed in Table V-2.

In addition, approximately 30 cadwelds were reviewed in the Unit 1

and 2 Reactor Building annulus areas. These cadwelds were being

installed as part of the reactor building containment fix and

included both cadwelds done in-place and those done above and then

put into the annulus area. The cadwelding was done by Dick.

b. Inspection Findings

In the four blockout areas reviewed by the NRC CAT, reinforcing

' steel placement was found to be in accordance with the design

drawings, including applicable Engineering Change Notices and Field

Variance Authorizations. Dowels into the blockout areas were the

specified length. Reinforcing steel bar size and grade were as

specified and lap splices the required length. Cadwelding in the

blockout areas and the Unit 1 and 2 annulus areas was found to have

evidence of proper centering of the cadweld sleeve, no excessive

voiding, no burn through of the sleeve, no slag at the tap hole, and

proper identification. Concrete quality was good with no areas of

honeycombing and good bonding with the reinforcing steel.

It was noted'that at some of the construction access blockouts,

reinforcing dowels had been accidentally bent probably by items

being passed through the opening.

In one case, the bent reinforcing

dowels had been previously identified in an NR; however, in another

case of bent rebar no NR had been initiated. CQC NR 2871 was issued

concerning the bent rebar during the NRC CAT inspection and remains

open pending closing of the access opening at a later date.

c. Conclusions

From the construction blockouts and annulus areas reviewed, it

appears that reinforcing steel was placed in accordance with the

design drawings, cadwelds were made properly, and concrete quality

appears acceptable.

5. Concrete and Soils Placement Records

a. Inspection Scope

The records associated with concrete and soils placements were

reviewed for conformance to construction specifications and regula-

tory requirements. The documentation reviewed included records of

inspection, in-process testing, material certification, surveillance

testing, and cadwelder qualification, performance, and surveillance

testing. The records covered 28 concrete placements (see Table V-3).

The review of the 28 concrete placement records included: all four

V-10

_ _ _ _ _ _ _ _ _

_ _ _ _ _ _ _ _ _ _ _ _ - _ _

. _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

.

contractors in safety-related concreting (National Engineering and

Contracting Company, Great Lakes Construction Company, Blount

Brothers Corporation, and Dick), a sample of 26 Receipt of flaterial

Inspection Reports (RMIRs) with their associated material certifica-

tion records (CMTRs or Certificates of Compliance), in-process

testing of concrete and aggregate, curing records, and concrete

cylinder strength testing.

In addition, the annual records for

in-process testing of cement, aggregate, and admixtures were selec-

tively raviawed primirily for the years 1976 through 1979. Three

Class A backfill inspection records and one excavation inspection

record were reviewed for conformance to the specifications and

requirements. The records were reviewed for three cadwelders

eupioyed by Dick for qualification and production testing.

b. Inspection Findings

The concrete and soils records were found to generally meet the

construction specification requirements, except in three instances.

The records were reviewed for proper frequency of testing or sur-

veillance, satisfaction of acceptance criteria. proper materials

used, material properly certified, and qualification of material and

cadwelders.

The following are the three instances in which discrepancies were

identified.

(1) In the review of monthly in-process testing of aggregates, the

NRC CAT identified one instance in which the August 1976 aggre-

gate sample was actually drawn cut on September 7,1976.

In

fact, the September 1976 sample was also drawn on September 7,

4

1976. Apparently, the aggregate sample for August 1976 was not

taken. However, material drawn on September cannot be substi-

tuted for a sample which should have been drawn the previous

month. As a result of th h finding, NR P014-2186 was initiated.

Additional investigation by the appliant of all the aggregate

sampling records revealed only three additional instances of this

occurrence.

In two instances, there was only a one day discre-

pancy and in the other case, there was a delay of only three

days. The last occurrence was in June 1979, with the others

occurring in February, April, and August of 1976. The concreting

program was initiated in 1976 in which the initial startup of the

activity could have contributed to this condition. NR P014-2186

has been closed.

(2) The review of selected US Testing records for in-process testing

of admixtures for the years 1976 through 1978 showed that in

three instances for the infrared spectrophotometric analysis

there was no documentation of the evaluation of the analysis

results. The graphical analysis was attached to the US Testing

report, however, there was no statement of the analysis evalua-

tion.

It was noted that other similar test reports did provide

an analysis evaluation. As followup to this finding, the licen-

see identified three additional instances of this occurrence

V-11

.

.

..

-___-_______ -_.

_-_

_________________________________________ __ ____

_ _ _ _ _ _ _ _ _ _ _ _ _ _ .

.

.

and US Testing was requested to perform the analysis evalua-

tion. The analyses were found to be acceptable.

It was noted that the US Testing records turned over to the

applicant had not yet been accepted. Based on discussions,

these records will be reviewed by the applicant for completeness

and adequacy prior to acceptance. As evidenced by this finding,

,

a records review for just the existence of the test report will

not be sufficient to identify any similar problems in the test

reports.

(3) A review of NR QCA-100 (Blount Brothers) identified that the

NR was voided although the specification requirements for soils

testing was not met. The specification requirements for the dry

unit weight (at 85% relative density) is a minimum of 120 pcf.

The voided NR identified test results of 119.7, 119.4, and 117.2

pcf.

It appears that this NR was voided due to a misinterpreta-

tion of the specification requirements. Based on this review, NR

CQC-2919 was initiated and GAI has accepted the test results

not meeting specifications based on actual in-place density

meeting relative density requirements. All other NRs of this

contractor were reviewed by the applicant and no additional

instances were identified. This NR is now closed.

c. Conclusions

From the concrete and soils placement records reviewed above, it

appears that these activities were performed in accordance with the

construction specification and regulatory requirements. The three

instances in which records did not meet specification requirements

can be attributed to the fact that the concrete and soils programs

were just beginning at that time and some minor problems can be

expected. Additional investigation by the applicant of two instances

shots that the problems identified were isolated cases. For the

third instance concerning US Testing test reports without analy-

sis evaluations, the NRC CAT finding should be considered prior to

the applicant's acceptance of these records.

6, Containment Vessel Shell Steel Installation

a. Inspection Scope

The containment vessel shell steel installation activities performed

by Newport News Industrial (NNIC0) were reviewed. The shell steel

installations included six stiffener ring assemblies and one pene-

tration stiffener area (approximately 25 members) in Units 1 and

2 (see Table V-4).

The stiffener installations were inspected

against the design drawings for configuration, member size, and weld

size and appearance.

.

V-12

_

_ _ _ _ _ _ _ _ _ _ _

,

. _ .. . .. . . . .. _ --_ _ _______ _ _ _

o

.

b. Inspection Findings

For the shell stiffener steel installations inspected, no problem

areas were identified. The configuration and member sizes for all

items were found to be in ccnformance with the design drawings and

associated NRs. The welding was of the proper size and length and

was visually acceptable.

c. Conclusions

From the above findings, it appears that the containment vessel

steel stiffener rings and penetration stiffeners have been installed

in accordance with the applicable design drawings.

7. Structural Steel Installation

a. Inspection Scope

The structural steel installation activities of Pittsburgh Bridge

and Iron (PBI) Industries were reviewed by the NRC CAT.

Installed

and QC accepted structural steel was inspected for member size,

configuration, conformance of bolted and welded connections to the

design drawings, and structural steel bolts were tested using a

calibrated torque wrench to determine whether the bolts were properly

tightened. The building structures inspected were: Units 1 and 2

Auxiliary Building, Unit 2 Suppression Pool, Unit 2 Reactor Building,

Units 1 and 2 Control Complex, and Intermediate Building (see Table

V-5).

The structural steel installations reviewed included: 33 members and

stiffeners checked for proper size and dimensions, 26 bolted and

welded connections, and approximately 260 bolts were tested for

minimum installation torque.

b. Inspection Findings

The 33 structural steel members and stiffeners and the 26 bolted and

welded connections were found to be in conformance with the design

drawings except for one case. High strength bolts were tested to

determine whether minimum torque requirements were met. The bolts

tested included 3/4", 7/8", and 1" diameter A325 bolts tested to 355,

570, and 850 ft-lbs respectively. The test torques were compared

with those values obtained by Skidmore testing and were found to be

in general agreement. The Skidmore testing was witnessed by the NRC

CAT and specification and precedure requirements were met. The

approximately 260 bolts were found to have at least the minimum

torque requirement.

The only discrepancy identified by the NRC CAT was undersized clip

angles fcr a column to embed plate connection. The discrepancy

is at Elevation 661' of the Control Complex building at column lines

CC-6 and 3'-0" north of CC-E (column mark number 715-C3). The

installed clip angles were 5"x3"x1/2" (6" long), however, the design

drawings specified clip angles 6"x4"x1/2" (6" long). The clip angles

V-13

.

. . .. .

._ ..

_ _ _ _ _ _ _ _ _ _ _

__

__

_ _ _ _ _ _ _ _ _ - _ _ _ _ _ _

.

.

were installed in late 1979. Based on this finding, NR PBI-982 was

initiated to investigate the cause for the discrepancy and identify

any other similar discrepancies in clip angle size. Based on the

additional investigation, the following was identified:

(1) Similar discrepancies exist for five other columns. All six

column connections are located in the same structural bay and

,

elevation of the Control Complex.

(2) Additional investigation t'y the applicant and NRC CAT for proper

clip angle size revealed no discrepancies other than those

described in (1) above.

(3) Revision A to drawing D-514-301 specified the change in clip angle

size from 5"x3"x1/2" to 6"x4"x1/2". The only other work changed

in Revision A to the drawing was also for a change in clip angle

size and these clip angles were verified in the field to be the

proper size.

1

'

(4) A review of material shipment documents revealed that an insuf-

ficient number of the proper size clip angles were ordered and

also a PBI drawing revision had a typographical error in the

piece mark number for these clip angles.

j

(5) Recent changes at that time in job supervisor and inspection

personnel may have contributed to the discrepancy not being

identified in the installation process.

c. Conclusions

In general, the structural steel installation activities (member

size and configuration, connections, and bolt torque) by PBI

Industries were found to be in conformance with the design drawings.

The discrepancy of undersized clip angles appears to be an isolated

instance and not a generic concern based on the additional investi-

gations of work nearby, work done by inspection personnel, and work

affected by the same drawing revision.

8. Design Change Control and Nonconformance Reports

a. Inspection Scope

Design change control activities and nonconformance reports in the

civil engineering area were reviewed by the NRC CAT. The review

consisted of a sampling of nonconformance reports, engineering change

notices, and field variance authorizations for the contractors in the

civil area (National Mobile Concrete Corporation, U.S. Testing, PBI

Industries, Dick, National Engineering and Contracting Company, Great

Lakes Construction, NNICO, and Blount Brothers). This includes NRs

issued by the Perry project organization. The areas covered con-

crete, structural steel, containment vessel steel, and soils activi-

ties. Approximately 150 nonconformance reports, 10 engineering

change notices, and 10 field variance authorizations were reviewed

for: r^9per use of the design change documents, identification of

V-14

.

..

. .

_ _ _ _ _ _ _ _

-

_ _ _ _ __

.

.

the issue, proper engineering disposition, QC verification of the

disposition, and proper review for changes to the Safety Analysis

Report (SAR). Selected design change records were reviewed against

the current design drawings,

b. Inspection Findings

For the design change documents reviewed in the civil engineering

area, all were found to be performed in accordance with the program

requirements, except three instances previously discussed in Section

V.B.2 (PPPF NR 3842),Section V.B.3 (Dick NR 216), and Section V.B.5

(Blount Brothers NR No. QCA-100).

c. Conclusions

From the above findings, it appears that design changes and noncon-

formance reports in the civil engineering area were generally accom-

plished in accordance eith program and regulatory requirements,

except in three instances. These instances are discussed in detail

in previous paragraphs and/or in Section VIII.

V-15

..

..

_ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ .

___

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

- _ _ _ _ - _

_ _ - _ _ _ _ _ _ _ _ _ _ _ _ _

. _ _ _ _ - _

.

.

TABLE V-1: SEISMIC CLEARAf1CE PROGRAM REVIEW

Seismic Clearance

Workmanship

Calculation Review

Violation fio.

Findings

Findings

2442, 2460, 2492

Excessive lateral motion

GAI engineering did not

of fire protection piping; evaluate for lateral

in some cases lines

'

motion of fire protection

actually impact safety-

piping.

related cable trays.

821

Two supports reviewed

against design drawings;

one of two pipe supports

has missing welds.*

898

Poor weld on an adjacent

support; spring can out of

alignment on an adjacent

support (not same support

as poor weld).

1877

Only one deadweight support

for over 50 feet of floor

j

drain piping.

f

1678

Bent beam C amp.

1681

Poor support welds.

1551

Poor weld on a support

on the piping run in

vicinity of SCV #1551.

187

undersized welds and weld

GAI disposition was

splatter on repair work.

" accept-as-is" although

additional supports had

to be installed.

1182

Acceptable.

Spans used in calcula-

tions checked by HRC CAT

and found to match those

actually in field.

  • The applicant had recently identified tne missing welds and the condition was

documented on Nonconformance Report-PPPF 4066 dated 9/6/83.

V-16

I

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

.

TABLE V-1

r

SEISMIC CLEARAtlCE PROGRAM REVIEW - Cont.

Seismic Clearance

Workmanship

Calculation Review

Violation No.

Findings

Findings

2542

Acceptable.

Hilti bolt capacity check

mistake by GAI.

2519

Acceptable.

Acceptable.

1953, 1965

Acceptable.

Hilti bolt embedment

assumed for analyses,

but in some cases not

verifiable in the field

(conservative assumption

notused); improper

references to another

calculation; improper

bolt size (larger than

physically possible) used

in analysis; wrong value

used in equation allow-

able vs. actual.

2181

Acceptable; 4

supports reviewed

against design drawings.

1603

Acceptable; one

support reviewed

against design drawings.

1634

Acceptable.

Acceptable; spans used

in calculations checked

by NRC CAT and found to

match those actually

in field.

1993

Acceptable.

1970

Acceptable.

2471

Acceptable.

2306

Acceptable.

2356

Acceptable.

1630

Acceptable.

V-17

.

_ . _ _ _ _ _ _ _ _ _ _ _ _ _

.

.

.

TABLE V-1

SEISMIC CLEARANCE PROGRAM REVIEW - Cont.

Seismic Clearance

Workmanship

Calculation Review

Violation No.

Findings

Findings

2032

Acceptable.

2053

Acceptable.

Total of 26 violations

Total of 7 GAI

reviewed in the field.

calculations reviewed.

V-18

.

.

_ _ _ _ _ _ _ _

,

.

TABLE V-2

'

IN-SITU CONCRETE QUALITY

,

Placement

Drawing

Location

Pour No.

Contractors

Date

No.

Aux. #2 Roof

AX2-SO4-652

National

10/09/79

D-462-302,

Slab

Engineering

Rev. H

D-452-304,

Rev. C

.

Control

CC0-WO3-705

Great Lakes

12/07/78

D-414-524,

Complex Wall

Construction

Rev. A

Co.

Intermediate

IB0-WO5-680

National

08/14/79

D-413-118,

Building

Engineering

Rev. D Walls

Walls

0-413-182,

IBO-W16-680

National

07/25/79

Rev. A

Engineering

0-413-162,

Rev. E

.

e

V-19

- - _ . . . . . .

.

.

TABLE V-3

CONCRETE PLACEMENT RECORDS REVIEW

Date of

Contractor

Pour No.

Placement

RMIR* Reviwed

National Engineering

Bio-Shield Wall:

and Contracting Co.

RB1-HWT1-616

06/09/79

3242, 3243

RB1-HWT2-616

06/10/79

(see RB1-HWT1-616)

RB1-HWT5-654

12/07/80

3945, 3946, 3947, 3953

RB1-HWT6-654

12/13/80

(see RB1-HWT5-654)

RB2-HWT2-618

06/14/80

3822, 3825, 3826, 3827

RB2-HWT3-630

12/14/80

(seeRB1-HWTS-654)

Drywell Wall:

RB1-W01-616

06/04/79

3219-3224

RB1-WO2-630

07/13/79

RB1-WO3-645

10/16/79'

3508, 3509, 3512

RB1-W181-641

02/22/80

RB2-W01-616

07/30/82

4359, 4361

RB2-W01-648

02/06/81

RB2-W02-648

02/06/81

RB2-WO3-646

12/04/80

Great Lakes

Control Complex

Construction Co.

Basemat:

CCO-M27-575

12/15/76

CCO-M22, 28,

01/05/77

32-575

CCO-M29-568

11/30/76

CC0-M31-575

12/15/76

Emerg. SW

Pump House:

EPH-W11-585

10/04/78

2679, 2682

EPH-W1-585

08/30/78

  • RMIR - Receipt of Material Inspection Report with attached material certification

records

,

V-20

-

.

__

_

_

f

.

.

l'

l

l

l

TABLE V-3

CONCRETE PLACEMEf1T RECORDS REVIEW - Cont.

1

!

Date of

Contractor

Pour No.

Placement

RMIR* Reviwed

i

Blount Brothers Corp.

Reactor Building

l

Basemat:

RB1-M1-574

09/22/76

RB1-M4-574

11/01/76

RB2-M3-574

11/19/76

1042, 1045, 1046

RB2-MS-575

11/24/76

i

l

Dick

Shield Building-

l

'

RB1-W6-677

12/15/77

RB1-W6A-677

11/07/78

  • RMIR - Receipt of Material Inspection Report with attached material certification

records

.

d

V-21

- - -

_ - _________________

.

.

TABLE V-4

CONTAINMENT VESSEL SHELL STEEL

NNICO

Location

Assembly No.

Drawing No.-

Unit 1 - Shell Stiffeners

Ring No. 4

98-7

249716 Rev. F

99-46

249716 Rev. F

Ring No. 5

97-1

249717 Rev. D

Ring No. 6

99-9

249717 Rev. D

Unit 2 - Shell Stiffeners

99-17

249716 Rev. F

94-2

Unit 1 - Penetration Stiffeners

249923 Rev. F

Elev. 592'-2" to

249924 Rev. D

604'-11"

249925 Rev. D

Az. 23 -30' to

249926 Rev. D

32'-00'

with NR

No. P017-758

4

,

i

V-22

_ _ _ _ _ _ _ _ _ _ - _ _ - _ _ _ _ _ _ _ - _ _ _ _ _ _ _

.__

_

_l

, .

.

. . . _ . .

___

.-

.

TABLE V-5

STRUCTURAL STEEL INSTALLATION

NRC CAT Inspection Area

Structure

Drawing No.

Member Size

Unit 1 Aux. Bldg.

D-512-023

and Connections:

D-561-011

0-561-084

Unit 2 Reactor Bldg.

D-561-051

'

D-512-066

Unit 1 and 2 Control

D-514-101

l

Complex

D-514-102

D-514-011

'

.

D-514-022'

l

!

D-514-301

D-514-302

0-514-303

Intermediate Bldg.

D-513-015

D-513-018

j

Bolt Torquing:

Unit 1 and 2 Control

D-514-021

Complex

D-514-022

0-514-101

D-514-201

0-514-202

Unit 2 Aux. Bldg.

D-562-021

Unit 2 Reactor Bldg.

D-561-020

D-561-021

V-23

__ _ ______- ____.____ ___

. - - - -

- _ _ - _ _ _ _ _ _ _ _ _ _ - _ _ _ - _ _ _ _

.

.

VI.

MATERIAL TRACEABILITY, STORAGE AND MAINTENANCE

'A.

Objective

The objective of this portion of the inspection was:

to examine material

traceability and centrol, to review storage and maintenance of safety-

related equipment and material, and to determine the adequacy of the

applicant's program relative to these activities.

-

B. Discussion

The approach used to perform this part of the inspection was to identify

and select samples of installed safety-related material and equipment for

examination. Some samples of delivered material and equipment not yet

installed, but stored in warehouses or lay-down areas, were included. A

total of 178 samples were examined to varying extents.

Applicable procedures for these various activities were reviewed. Table

VI-1, " Summary of Samples", indicates the Perry Project contractors con-

tacted and the types of activities and samples examined. Table VI-2,

" Sample Breakdown By Contractors", shows the number and type of samples

applicable to the selected contractor. Table VI-3, " Weld Filler Material

,

'

Compliance", contains a list of weld filler material samples.

The following sections describe the results of the inspection in the areas

of material traceability, storage, and maintenance.

1. Material Traceability

a. Inspection Scope

_

A total of 178 samples were examined for traceability to drawings,

specifications and procurement records, if applicable. Supplier

certification, including required Certified Material Test Reports

(CMTR) or Certificates of Compliance (C of C), heat numbers or other

required documentation were reviewed. Table VI-2 indicates the

types and quantities of samples examined.

b. Inspection Findings

In general, it was noted that the applicant and contractors per-

forming safety-related work had appropriate procedures in place for

control of material and for material traceability. The applicant

utilizes a computerized Master Parts List (MPL) program to control

the identification of equipment and components on a project-wide

basis. An overall records management program had been planned and is

now being implemented to help control the flow and transfer of

documentation from the Construction to the Operation phase. Several

deficiencies involving material traceability and material control

were noted by the NRC CAT inspectors as follows:

VI-1

____ - ___________________ _

_ _ _ _ _ -

..

_

.

.

(1) Material Identification Markings on ASME Class 1 Hangers

Lack of material identification markings on parts of ASME Class 1

hangers was noted for Reactor Recirculation (B33) and Main Steam

(Nil) Systems.

The NRC CAT inspection of material traceability for General

Electric (GE) ASME Section NF Class 1 supports / restraints identi-

fled problems regarcing the lack of visible unique identification

marking of support / restraint items, marked materials not trace-

able to verification documentation and the thoroughness of the GE

material traceability reverification program.

A prior audit by the Cleveland Electric Illuminating (CEI)

project organization and follow-up activities revealed the lack

of visible unique identification marking of support / restraint

items, including the lack of visible marking after welding on 14

clevises involving 14 of 34 hangers for these systems. Two

nonconformance reports (NRs) [GE-38-0522 and GE 38-0523] were

issued requiring reverification and recording of material

identification for parts of the hangers. Samples were cut from

the 14 clevises for chemical analyses, and the results confirmed

the proper material for the clevises. Even though the two NRs

were prematurely closed out, the applicant stated that other

" reverification work was proceeding" (This early close-out of

NRs is discussed further in Section VIII). New reverification

drawings were being prepared. The NRC CAT inspection of four

hangers, however, resulted in the questioning of the clarity of

a marking on one additional clevis, and the lack of the visibility

of material identification markings on cther parts.

The applicant initiated action for a chemical analysis to be made

of a sample of material from the additional clevis, and issued a

new NR (GE 38-0708, dated 9/6/83) to require completion of material

identification and the recording of material markings for the

Main Steam and Reactor Recirculation hangers.

Also, the NRC CAT inspectors noted three clamp studs for hanger

H1028-1 marked as 055B, yet this marking was not on the appli-

cable material letter code list. The applicant indicated that

this matter had already been identified under the NR activity and

i

had not been fully resolved. A letter dated 9/2/83 -from ITT

l

Grinnell (the hanger supplier) confirmed that the material

specified was SA-36, which is designated as "A" on the code list.

The licensee stated that in resolution to this documentation

deficiency, reference would be provided consistent with the ITT

Grinnell letter.

The controls that Pullman Power Products (PPP) exercises to

maintain material control and traceability of ASME Section NF

support / restraint materials were evaluated. This evaluation

included a review of procedures, discussions with responsible

individuals, verification of records to hardware traceability for

four supports (1E21-H014, IE120-H010,1E51-H037 and 1E12-H748),

VI-2

r

L

.

_ _ _ _ _ _ _ . _ _ _ . _ _ . _

.-

- _ _ _ _ _ _ _ _

o

.

and field observations. The NRC CAT found the overall controls

regarding receiving, marking and maintenance of traceability

through installation for PPP to be in accordance with

requirements. A documentation weakness in the program had been

corrected in the latest revisicn to Pullman Procedure IX-6,

" Installation and Inspection of Pipe Supports" by specifically

requiring QC verification and recording of material heat or LCN

numbers on process sheets at installation.

(2) Weld Filler Material

Twenty-one samples of weld filler material were examined and

traceability documentation, including CMTRs and heat numbers,

were reviewed. Table VI-3 is a listing of samples reviewed

including those examined in detail. However, questions were

raised regarding the material data for three of the samples as

follows:

(a) Weld Wire ER-705-2, 1/8" x 36", 1200 lbs., GE Purchase Order

No. 380N0803-524, GE Specification GEP-PS-5011 Rev. 7 Heat

No. 401L3151. On reviewing the CMTR for this material, it

was noted that N/A is marked in the " Stress Relieved" block

under " Additional Test Results". This material, if used in

applications specifying ASME Code NB-2430 (Weld Metal Tests),

must undergo time at post-weld heat treatment for eight

hours. The applicant indicated and later confirmed that no

applications for this material were involved which required

the eight hours of stress relief prior to mechanical testing.

(b) Insert Material,1/8"x5/32", 5000 f t. , E70S-2 or 6, SFA5.18,

Pullman Purchase Order No. 7691-575, Heat No. 4644B131. On

reviewing the CMTR dated 9/3/83, it was noted that exactly

identical impact test results were listed foru ix sets of

test results. Since it is not considered probable that six

actual test results would be exactly identical, the accuracy

of the CMTR listing of test results was questioned. The

applicant proceeded to examine this matter further in an

attempt to explain the unusual impact testing values. A

welding engineer contacted the testing laboratory involved

and was advised that the six test results were actual

results, and that written confirmation would follow.

(c) Filler Material (for consumable insert rings), ER 308, Heat

No. X43724. This heat of filler material failed to have the

required delta ferrite content. GE Specification Z1A2005,

Paragraph 4.3.4, " Welding Materials," requires a delta

ferrite content of 8% minimum for the 308 filler materials.

GE CMTR for Heat No. X43724 indicates a delta ferrite content

of 6.5%.

This material was utilized for welding of at least

three details. The affected details are 1,em G010A-1,

G012A-30-1, and G011A-90-1. Although not meeting site

'

specification requirements, the subject filler material does

meet the minimum delta ferrite content of 5% specified by NRC

Regulatory Guide 1.44, and ASME Section III, Subsection NB.

Two NRs were issued to document these conditions (NRs TAS0063

andTAS0064).

VI-3

-

_ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ - _ _ _ _ _

_ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

O

(3) Fasteners

'

Examination of 32 samples of fasteners, both installed in the

plant and in contractor's bins revealed several deficient conci-

tions regarding material control as follaws:

(a) Bolts in Bin (Comstock Storeroom). A bin and a carton in the

bin were both labeled A-325. However, 1/2" x 1 1/2" long

bolts in the carton showed a marking B7 and manufacturer's

identification on the heads of the bolts. A review of

documentation revealed that the carton of bolts were of

material SA 193 Gra7 and that a CMTR was filed for these

bolts. The bin and carton were incorrectly marked for these

bol ts .

(b) Bolts for Battery Racks 1R42-S002 and 2P42-S0_0_3. The NRC CAT

3

inspectors reviewed the vendor's manual and appropriate

design documents for these installations. One document

(Flight Dynamics, Inc. Report FDI A-3-82 prepared for Exide

Power Systems Division) detailed the seismic analysis of two

step "G" size high seismic battery racks. Based upon this

report, it was determined that the 125V DC Battery racks for

the Perry Nuclear Power Plant (PNPP) had been seismically

qualified using SAE Grade 5 and Grade 2 bolting materials.

The NRC CAT inspection of the Unit 1 Division 1 battery rack

disclosed a total of forty-eight (48) bolts which were of

indeterminate material; i.e., the bolts were not marked

SAE Grade 2 as specified. The inspection of the Unit 2,

Division 2 battery rack indicated a total of seventy-four

(74) bolts with the same status.

The NRC CAT inspectors reviewed vendor (Exide) shipping

documents and receiving inspection reports to ascertain what

material types were supplied. Page 3 of the packing list,

dated 6/8/79, indicated that all bolts supplied were SAE

Grade 5 or ASTM A-449 or better. Additionally, a vendor

surveillance report (Gilbert / Commonwealth Quality Assurance

Division Report 9948-80-05, dated 2/29/80) indicated that the

vendor had supplied SAE Grade 5 or ASTM A-449 or better

bolting materials. Discussions with the installing contrac-

tor indicated that the installation had been accomplished

using only vendcr-supplied materials.

Further historical

review of the battery rack installation records and discus-

sions with the applicant did not disclose any information

that would help to clarify why bolting material other than

that specified and supplied was used in the installation of

the 125V DC battery racks. As a result of this inspection,

the applicant issued NR 0QC-307 recommending that all bolts

in question be replaced with the SAE Grade 5 material and

that the bolts in question be submitted for testing.

VI-4

.

..

. .

..

_ _ _ _ _

_ _ _ _ _ _ _ _ _ _ _ _

.

.

.

(c) Bolts for 4KV Switchgear Cabinet 1R22-5006. The vendor had

specifiec by letter. that switchgear interTrame bolting would

be accomplished with SAE Grade 2 hardware. Bolts , installed

were not marked SAE Grade 2 as specified.

The NRC CAT inspectors reviewed installation inspection

records for the equipment. These records did not indicate

deficiencies relative to bolting materials. As a result of

this inspection, the applicant initiated NRs 0QC-0324 and

0QC-0325 to address these problems.

(d) Bolts for Flanged Joints of Diesel Starting Air Liae 1R44509.

Some studs for fianged joints of the Diesel Starting Air Line had

markings, but others had no markings. Four of eight studs at one

flange joint were not marked. Some of these joints had missing

studs.

(e) Bolts for Class 1E Motor Control Center 2R24-5019.

Examina-

tion of hardware attaching adjacent cabinets of the Motor

Control Center (MCC) revealed that 1/4" round head bolts and

nuts were used.

It was noted that some of the bolt heads and

nuts were not properly seated. Some used flat washers,

others did not. The bolts appeared too small for the holes

in the cabinets and improper seating resulted. However,

examination of other Class IE cabinets revealed that larger

bolts were being used, and as in the one case of cabinet

2H13-P747 1/2" bolts had been installed (to comply with an

NR). The applicant issued four NRs on 9/19/83 to initiate

action to check and correct this improper fastener condition

(NRs 0QC-318, 0QC-319, 0QC-320 and 00C-321).

(f) Fasteners for Standard Com0066.7t Supports. The NRC CAT

inspectors observed in four areas that crafts were not

maintaining traceability of small items and threaded compo-

nents of standard component supports (catalogue items such as

struts, clamps, spring cans, snubbers, and other similar

types of components).

Paragraph 5.2.3 of Pullman Procedure

IX-6 requires items to be marked or remain attached as an

ossembly until the time of installation. The following

conditions were observed in different areas of the Auxiliary

Building, 620' elevation on September 13 and 14,1983.

. Pipe clamp for 1E32-H014 with a missing bolt

. A 12" pipe clamp with no bolts, no marks, no tags

. Pipe clamp for 1E12-H526 with a missing bolt

. Snubber clamp with a missing load pin, no tags,

or markings with support or LCN numbers

. Spring hanger 1E12-H184 with missing rod, eye-

nut, clevis, pin and pipe clamp

VI-5

c

"'

'

-

E

_._

_ _ _ _ _ _ _ _ _ _ _ _ _ _

.

.

,

I

t

C. Conclusions

The overall material control and material traceability program was

considered adequate, except for some traceability program deficien-

cies and for the material control of fasteners and small items.

Traceability program problems were identified regarding the

thoroughness of application of the traceability program procedures

for material identification markings on ASME Class 1 hangers and

the thoroughness of the contractor's revesification efforts to

satisfy site traceability program requirements for ASME Class I

hangers.

Regarding material control, six of the 32 samples of fasteners

examined revealed improper control of the application of fasteners.

Five conditions of improper control of traceability of small items

and threaded components of standard component supports were noted.

2. Storage

a. Inspection Scope

A total of 62 samples were examined for appropriate storage in

warehouses, in laydown areas and in the plant. Site storage facili-

ties themselves were also examined.

b. Inspection Findings

Warehouses and outside storage facilities were found to meet require-

ments.

It was noted that the only Class A storage facility, the

site Calibration Laboratory, utilized properly calibrated temperature

and humidity recording indicators showing conditions within required

limits. Held rod storage, issue stations and holding ovens in

various locations on tF site were examined and found to be satis-

factory.

.

Several examples of improper storage and protection (from damage and

deterioration) of safety-related equipment in the plant and in a

lay-dov:1 areas were noted. Some protective covers were missing.

Some equipment damne from nearby construction activities was noted.

Poor housekeeping was noted on or around the equipment. Also,

improper marking of safety-related steel was noted in an outdoor

lay-down area. The following is a list of samples examined:

(1) Motor Control Operated Valve 1E22-F001

(2) Motor Control Center 1R24-5024

(3) Reactor Core Isolation Cooling Pump 1E51-C001

(4) Emergency Closed Cool Pump / Motor 1P42-C001B

(5) High Pressure Core Spray Pump / Motor 1E22-C001

(6) Safety-related pre-fabricated structural steel parts for Reactor

Building No.1 in the "PBI/ Kelly" lay-dovin area.

Regarding item 6, the procedures reqire labeling of these parts for

identification and -control af ter coatings are applied. These parts

VI-6

.

.

_ - _ _ _ _ _ _ _ - -

. - - _ _ _ - . __ _

l

.

.

4

were found to be not adequately marked. The metal tag for part

239M2 was corroded and separated from the part. Tags were missing

and parts were temporarily marked with a soapstone marker for parts

240M2-L, 240 M2-L, 240 M2-R,.and 240 M2-R.

The NRC CAT inspector was informed that a Field Question (F.Q. 31006)

was issued 8/19/83 requesting Engineering direction to improve the

marking technique and remark steel prior to the onset of adverse

weather. Re-identification and re-marking of steel in storage was

authorized for the Field Question 8/22/83. The NRC CAT inspector was

informed 9/28/83 that re-identification and re-marking, with QC and

Engineering assistance, was proceeding initially for Turbine Building

steel in storage, and that re-identification and re-marking of coated

safety-related Reactor Building items would follow,

c. Conclusions

The storage and related procurement, receipt and warehouse procedures

as well as the facilities themselves met regulatory requirements,

except for storage of some safety-related material and equipment in

the plant. Five of 62 samples inspected for storage were found to be

inadequate.

3. Maintenance

a. Inspection Scope

A total of 43 samples of safety-related equipment were examined.

Maintenance requirements and history records were reviewed for items

stored in warehouses and installed in the plant.

b. Inspection Findings

Manual lists and schedules for equipment received at the central

warehouse, and determined by engineering to require maintenance, are

maintained by central warehouse personnel. Records are kept of

maintenance performed on each item.

Items issued to Comstock and

Johnson Controls are then controlled by manual lists and maintenance

schedules by these two contractors. Other material and equipment

requiring maintenance after issuance for installation are listed in

the project computerized system for scheduling and control of mainte-

nance. The applicant's computerized system used during Construction

will later evolve into the Operations mai.n.tenance control system.

As items are turned over from Comstock and Johnson Controls, such

items will also be included in the Operations maintenance control

system.

It is planned that the overall Operations maintenance

program will utilize the computerized data base, and the system will

then be further developed to meet operational maintenance needs. The

NRC CAT inspector inquired regarding the omission of computerized

control of maintenance in the central warehouse and of maintenance

performed by Comstock and Johnson Controls.

It was noted that a

recent Project Internal Audit of Maintenance identified ceficiencies

VI-7

_ _ _ _ - _ _ _ _ _ _ _ - _ _

_

.

_

_

-

-_ _

-_

_ - - _ _

.-

.

regarding the control of maintenance in the warehouses, and that this

matter is being considered further.

On examining equipment in the plant requiring maintenance control by

the applicant and reviewing maintenance records, no unsatisfactory

conditions were noted. 'However, on reviewing procedures and activi-

ties pertaining to storage and maintenance, and examining samples and

records in central warehouses #1 and #2, some celays in initiating

required maintenance provisions were noted.

An initial review of nine items revealed three with periods exceeding

10 days:

(1) over five years, (1) over thirty days, and (1) over

five months. T.his requirement is defined in " Nuclear Design and

Procurement 3-1301", Rev. 4, dated 8/16/82 which states that "the

Responsible Engineer is to forward a copy of the Storage. Maintenance

Requir.ements (SMR) form within 10 days of receipt of the Receiving

Report".

Specific examples are as follows:

Received

SMR Date

a.

~High Pressure Core Spray

12/01/77

01/25/83

Pump Bowl Assy. 2E22-C001

b.

Low Pressure Core Spray

04/20/83

05/31/83

Motor E21-C001 (Spare)

c.

Power Supply MR 20078

05/05/82

10/18/82

Further review of records for a total of 43 samples revealed 11

for which the SMR was not issued until later than 10 days.

Also, SMRs had never been issued for 18 of the 43 items, some of

which may have required maintenance,

c. Conclusions

In general, the overall project program for control of maintenance

I

was found to be adequate, except for the control' of maintenance in

I

the central warehouses. Eleven of 43 samples revealed situations

I

where the Responsible Engineer had not issued Storage Maintenance

Requirements for safety-related equipments requiring maintenance

until later than the time specified by procedure (which is within 10

days after receipt). Three of the samples revealed that receipt of

the 5torage Maintenance Requirements had not occurred for periods of

~30 days to 5 years.

VI-8

.

_ _ _ _ _ _ _

_ _ _ _ _

TABLE VI-1 - SUFF.ARY OF SAMPLES

Contractors

Activities and Samples

No. of Samples *

Pullman

Piping, hangers, weld joints,

36

welding mtl., fasteners

GE

NSSS equip., piping, hangers,

26

I

weld joints, welding mtl.,

I

fasteners, shims

)

1

Comstock

Electrical equip., cables,

30

I

hangers, weld joints, welding mtl. ,

fasteners

Johnson Controls

Instru. & Controls, racks,

22

,

welding mtl., fasteners, tubing

I

RIC0

HVAC equip., control panels,

16

hangers, weld joints, weld

mtl., fasteners

PBI

Structural mtl., weld mtl.,

23

fasterners

NNI

Liners, vessels, weld joints,

22

weld mtl., fasteners

Dick

Cadweld sleeves

3

TOTAL

178

  • NOTE: Some items served as multi-purpose samples

l

(e.g., for traceability, storage and maintenance).

l

.

VI-9

..

.

TABLE VI-2 - SAMPLE BREAKDOWN BY CONTRACTORS

Pullman

GE

Comstock JC

RICO

PBI

NNI Dick Total *

1.

Equipment

5

8

13

4

5

-

-

-

35

7

-

-

3

2. LPipe

4

-

-

-

-

-

-

15(L)

-

-

3

2

8

3.

Steel

2

(Structural)

2

1

1

5

-

9(L)

4.

Steel Plate /

-

-

-

Sheet

10

5.

Hangers /

2

5

2

-

1

-

-

-

Supports

6.

Weld Filler

6

2

3

2

2

3

3

-

21(L)

Material

7.

Weld Joints

12

4

2

2

2

4

11

37

-

3(L)

-

-

3

8.

Elec. Cables

-

-

-

-

-

- (Reel s)

9.

Fasteners

5

5

7

2

3

7

3

-

32

10. Shims

2

-

-

-

-

-

-

2(L)

-

11. Cadweld

-

-

-

-

-

-

-

3

3(L)

Sleeves

-

-

-

4

-

-

-

-

4(L)

12. Tubing

TOTALS

36

26

30

22

16

23

22

3

178

  • L = Lots

.

VI-10

_

_ _ _ - _ _ _ _ _ _ _ _ _ _ _ _

--__-

__ - ___ _ _

_ _ _ _ _ _ _

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _

..

.

TABLE VI-3

WELD FILLER MATERIAL COMPLIANCE

Material

H.T. No./

Compliance

Contractor

Designation

Material I.O.

Comments

GE

ER308R

NG460

Acceptable'

GE

ER308L

05845

Acceptable

GE

ER308L

05345

Acceptable

GE

E308L-16

06004

Acceptable

GE

E308-16

95533

Acceptable

GE

ER308

741102

Acceptable

GE

E308-16

740654A

Acceptable

GE

ER308

434788

Acceptable

GE

E308-16

741619

Acceptable

GE

-

ER308

740014

Acceptable

GE

ER308

75213

Acceptable

GE

ER308

X43724

Les: than 8%

Ferrite

'

l

GE

ER70S-2

401L3151

Acceptable

GE

E70s-2

401K0151

Acceptable

'

GE

E308L-16

8M13C Mix 22 (trace)

Acceptable

GE .

E7018

401J1571

Acceptable

NNI

E308-16

77NNI507

Acceptable

NNI

E308-16

77NNIS08

Acceptable

NNI

E309-16

77HNI509

Acceptable

NNI

E70T-G

77NNI549

Acceptable

NNI

ER308L

80NNIO97

Acceptable

NNI

E70T-1

81NNIO39

Acceptable

NNI

E308L-16

77NNI1525

Acceptable

NNI

E7018

79NNIO19

Acceptable

NNI

E7018

81NNIO55

Acceptable

NNI

E7018

77NNI589

Acceptable

NNI

E7018

115K (trace)

Acceptable

NNI

E7018

115L (trace)

Acceptable

NNI

ER309L

08544

Acceptable

PPP

E7018

70612

Acceptable

PPP

E308L-16

743927

Acceptable

PPP

ER308L

3548R308L (K shape)

Acceptable

PPP

E70S-2

065312

Acceptable

PPP

E705-2

4644B131

Identical impact

test results

FPP

E7018

4121C1391

Acceptable

JC

ER308L

07665

Acceptable

JC~

E7018

422S1961

Acceptable

PBI

E7018

33042

Not checked

PBI

AA7018

422W8351

Not checked

PBI

E709L-16

467267

Not checked

COMSTOCK

E7010-Al

614AF (trace)

Not checked

COMSTOCK

E7018

34-4B2A (trace)

Not checked

COMSTOCK

E7018

2-215C4B (trace)

Not checked

RICO

E7018 (LH)

411T1231

Not checked

RICO

E7018 (LH)

412N2851

Not checked

VI-11

_ _ _ _ - _ - _ _ _ _

--_-__

_ _____-__ -__

_ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ ,

.

.

VII. QUALITY CONTROL INSPECTOR EFFECTIVENESS

A. Objective

The objective of this portion of the inspection was to determine if quality

control inspectors function freely in performing their tasks, without

intimidation by craft personnel or supervision, and to determine if inspec-

tion personnel are qualified, trained and have the organizational freedom

to perform their tasks.

B. Discussion

1. Inspection Scope

l

Implementation of the Quality Control Program was determined from

l

discussion with the Quality Control personnel and their supervisors,

reviews of the inspector training and certification procedures, review

of the inspector training records, and review of the recording of

inspectiun results.

2. Inspection Findings

a. Inspector Support

Discussions were held with inspectors selected from the applicant and

contractor organizations performing work on the construction site. A

total of thirty inspectors were ;iected from the.Clevelond Electric

Illuminating (CEI) organization and from the eight contractor organi-

zations. The discussion subjects included the inspectors areas of

assignment, experience, education, training, and the inspectors

knowledge of any form of intimidation by craft or supervisor person-

nel.

During these discussions, certain issues were raised that could

have an effect on inspector effectiveness relative to one contrac-

tor's organization. The significance of these points will require

investigation beyond the scope of this inspection and has been

referred to the NRC Region III Office for further review.

b. Inspector Qualification / Certification

Records were reviewed to determine whether the training and certifi-

'

cation files for the inspectors interviewed contained the correct

documentation to meet the Applicant's Quality Assurance program

commitments.

(1) It was found that inspectors were certified prior to performing

inspections. Appropriate forms and documents were on file in

accordance with the applicant's commitments to ANSI N45.2.6,

" Qualification of Nuclear Pcwer Plant Inspeciton, Examination,

and Testing Personnel Requirements". These documents attest to

the inspectors experience, education and training.

VII-1

_ _ _ _____

_.

-

.

.

.(2). Training and indoctrination of inspectors was appropriately

documented. Training and indoctrination of newly hired inspec-

tors, in some instances, was done in only a fcw days, which could

be questionable. However, of the inspectors reviewed, all had

i

inspection experience at other nuclear construction sites.

1

3. Conclusions

There was no reported intimidation of inspector by craft or super-

vision. However, in one contractor organization, there were issues

,

'

raised by QC inspectors that require further review. The certifi-

cation and training of Quality Control inspectors reviewed met ANSI

standard requirements.

VII-2

. .

.

. .

..

_ - _ _ _ _ _ _ - _ _ _ _ _ - _

-

.

.

VIII. QUALITY ASSURA!!CE

A. Objective

The objective of this review was to determine the adequacy of selected

portions of the applicant's Quality Assurance (QA) Program. The program

was reviewed to establish that:

it was appropriately defined in instruc-

tions and manuals; the construction quality assurance effort was monitored

through audits and other management actions; on-site contractors work was

reviewed and monitored; on-site contractor audits were performed effec-

tively; the applicant or selected site contractors had instituted an effec-

tive corrective action system; and instructions and drawings used during

the construction process were controlled.

B. Discussion

1. Inspection Scope

Implementation of the Quality Assurance Program was determined by

reviewing: the organizational structure; the construction audit pro-

gram; the corrective action system of the applicant and selected site

contractors; and a sampling of design / installation drawings to assess

document control (current issue status).

2. Inspection Findings

a. Organization

Quality Assurance functions were performed by CEI and site organi-

zations contracted to perform construction work. The quality assur-

ance function appeared to be performed by an organization having a

sufficient degree of authority and freedom,

b. Audits

The project and contractor audit programs were reviewed to the

applicant's commitments defined in the CEI QA program.

(1) CEI Program

The CEI audit program is performed to ensure that commitments and

responsibilities at the project level are met and to ensure that

contractor commitments have been met. The program is implemented

by various corporate and project level procedures that fully

describe the program.

Audit areas were reviewed for: scheduling; development and use

of checklists; reporting; audit finding resolution; and auditor

qualification and certification.

Audits from 1981, 1982 and 1983 were selected for review.

Eighteen project level audits and forty audits of contractor

activities were selected for review. Audits of contractor activi-

VIII-1

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ .

-.

.

ties varied from a complete review of the contractor's program

compared to 10 CFR 50, Appendix B, to a review of a specific work

activity (for example, cable pulling). Although the number

varied from year to year, ir. the order of 150 audits of contrac-

tor activities and 35 audits of project activities were performed

i

each year.

The comments provided below are based on these audit reviews and

personnel interviews.

(a) Audit Scheduling

Document reviews and interviews of personnel associated with the

audits performed at the project level revealed that a system of

annual audit scheduling with quarterly review and updating was used.

Audit schedules were systematically developed and periodically

reviewed to factor in supplemental audits.

The review of completed contractor audits and the Construction

Quality Surveillance (CQS) audit status log revealed that audits

were performed on a periodic bases to monitor contractor activi-

ties.

(b) Audit Reporting

Audit reports prepared by each part of the CEI organization

provided a description of the audit scope; identification of

auditors; persons contacted; summary of results; and a descrip-

tion of any deficiencies or findings.

The NRC CAT found that Audit findings were clearly written. The

QA program i$equired that the finding be evaluated for adequacy,

and described the action taken to prevent recurrence be

described.

(c) Audit Program Effectiveness

The combination of audits performed at the project level and the

audit and surveillance inspections performed at the contractor

level in most cases monitored and controlled construction con-

tractor activities.

One weakness in the program was the length of time taken by some

l

contractors to resolve audit findings. Some contractors, Pullman

l

Power Products and L. K. Comstock for example, allowed audit

[

findings to remain unresolved for nearly a year. Some audit

I

findings were made in 1981 and 1982. CEI action was not effec-

tive in resolving this problem. There has been improvement

in the time taken to resolve audit findings in 1983. NRC RIII

had previously identified this proolem and is monitoring it as

an unresolved item (NRC Report 50-440/83-12).

VIII-2

- __ _ __________ _-__ -

_ _ _ _ _ _ _ _ _ _ _ -

!

-

.

(d) Auditor Qualification and Certification

The records and certification reports of 12 Lead Audito s in the

CEI audit program were reviewed. Lead auditors were selected

from CEI organizations auditing at the project and at the con-

tractor level of activity. The~ program was established and Lead

Auditors were certified to the requirements and applicant's

commitments as defined by ANSI N45.2.23, " Qualification of

Quality Assurance Program Audit Personnel for Nuclear Power

Plants."

(2) Contractor Audit Programs

A sampling of contractor audit programs was made to determine if

the contractor programs complied with CEI committments. The

programs.of Robert Irsay Company, Johnson Controls Inc., L. K.

Comstock, Pullman Power Products and Metalweld were reviewed.

Results of the Review

The audit program descriptions for the contractors and the audits

reviewed met the requirements of ANSI N45.2.12 " Requirements. for

Auditing of Quality Assurance Programs for Nuclear Power Plants."

Lead auditors for Johnson Controls, L.K. Comstock, and Pullman

Power Products were certified to the ANSI N45.2.23, requirements.

Audit findings, identified by Johnson Controls, were not indi-

vidually documented for follow-up and resolution as audit find-

ings prior to June 1983.

In June 1983 the program was revised to

require that Quality Nuclear Findings (QNF) be written to docu-

ment and track any findings.

Audit findings identified by L.K. Comstock were documented on

.

Audit Finding Reports (AFR). Some AFRs were opened in September

1981 and not closed until April 1983. All of the AFRs reviewed

had been closed prior to the NRC CAT inspection.

Metalweld corporate officials performed audits of on-site

activities related to 10 CFR 50, Appendix B.

Although the

auditors were not certified in accordance with ANSI N45.2.23, the

audits appeared to be comprehensive in that the observation of

work underway and work that had been performed and inspected in

the field was included. There was little completed work (hard-

ware inspection) sampling performed by the other contractors as a

final check of the installation and inspection process.

c. Corrective Action Systems

The applicant's overall corrective action and nonconformance control

program was reviewed. The provisions for the corrective action

system are included in the Corporate Nuclear Quality Assurance

Program, Section 1600, Revision 4, dated 6/1/83. The policy states

that; for conditions adverse to quality, the cause of the conditions

VIII-3

.

--

_ _ _ _ _ _ - - _ _ _ _ _ _ _ _ _

.

.

shall be determined and appropriate action taken to preclude repeti-

tion, the identification, cause, and actions taken are documented and

reported to appropriate levels of management, significant conditions

within the intent of 10 CFR 50.55(e) or 10 CFR 21 are reported to

appropriate-levels of management and to tne CEI Nuclear Quality

Assurance Department (NQAD).

Three of five contractor programs reviewed satisfied the system's

procedural requirements. Two contractors did not comply with the

procedural requirements. The program of two other major contrac-

tors were not reviewed since NRC Region III had recently reviewed

their programs. A potential problem with the corrective action

system of one of these contractors is still under review (NRC Report

No. 50-440/83-12).

Procedural problems identified are as folows:

(1) Instrumentation Contractor

There was no method identified to adequately identify and follow-

up on audit findings; therefore, the corrective action procedure

was used.

The procedural requirements for responses and for corrective

actions had not been enforced.

The CEI site organization issued AR 693 to Johnson Controls,

Inc., the contractor on 8/26/83, requiring that both the Cor-

rective Action and Auditing procedures be changed to resolve this

problem.

(2) NSSS Equipment Installation Contractor

Late in 1982 the contractor experienced difficulty with AWS

welding, in that the procedure was not being followed, which

resulted in cracking or other defects in the completed welds.

Twenty-two Nonconformance Reports (NRs) were written regarding

AWS welding problems during the first quarter of 1983, however,

the contractor, General Electric (GE), did not identify the

problem as a corrective action item nor as a reportable signifi-

cant deficiency either prior to or subsequent to action taken by

the CEI site organization.

The site organization issued Corrective Action Request (CAR)

  1. 82-28 on 1/6/83 citing the contractor for AWS welding problems.

This CAR recommended investigation of all AWS welding and proce-

dures to determine if problems also existed in other areas of

contractor work.

It was further observed that this significant deficiency was not

reported by the applicant as a 50.55(e) item. A significant

deficiency had been reported to the NRC Region III office identi-

fied as Pipe Whip Restraint Bracket Welds for 821/B33 systems

[CEI Deviation Analysis Report (DAR) 111 dated 12-21-82)]. The

VIII-4

..

.

. . - _ _ _ _ _

_ _ _ _ _

- _ _ - _ _ _ - _ _ _ - _ _ _

_ _ _ _ _ _ _ _ .

.

.

L

i

significant deficiency, however, did not describe the full scope

of the problem. The above identified welding problem was the

cause for the whip restraints unacceptability as well as for

s

other safety component welding problems (i.e., polar crane, fuel

handling crane, etc) where the same AWS procedure had been used.

Tha NRC CAT Inspector learned that the applicant had initiated

action to require contractor procedure modifications and, in

addition, planned to expand the scope of the significant deficiency

report to appropriately address the deficient condition and the

extent of impact.

'

In addition to the overall review of the applicant's corrective

action systems, the NRC CAT reviewed approximately 300 NRs as refer-

enced in other sections of this report. NRs reviewed were processed

in accurdance with procedural requirements.

In most cases, noncon-

fcrmances were being identified and dispositioned as required.

Hcwever, as described in Sections III (CQA-136),Section V (NR-215

and QCA-100), and Section VI (GE 38-0522 and GE 38-0523) of this

report, certain identified nonconformances have been closed prior to

completion of the entire scope of work required by the proposed

disposition of the NR. This has resulted in some cases of less than

adequate action taken to identied deficiencies and does not comply

with the applicant's program requirements.

d. Document Control

The system utilized on site for control of issuance of documents,

such as instructions, procedures, and drawings, including changes

thereto, was reviewed by obtaining a broad base sampling of drawings

available to craft and inspection personnel and determining the

current status as maintained by the CEI site organization. No

instance of obsolete revisions of safety-related drawings was identi-

fied in a sampling of drawings as follows:

Electrical Drawings

24 drawings

Piping Iso-drawings

14 drawings

Piping Hanger Drawings

18 drawings

Structural Drawings

32 drawings

3. Conclusions

With few exceptions, both the project and contractor audit programs

reviewed were implemented to meet CEI commitments. Generally, the audit

and surveillance program performed by CEI has provided an overview that

has identified construction problems. However, audit findings identi-

fied by CEI and contractor auditors have not always been resolved in

a timely manner.

In addition, certain key issues identified in sections

II, III, and VI of this report were not identified by the applicant's

audit and surveillance organizations as well as by the contractor audit

program.

VIII-5

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

.

.

- _ - _ - _ _ _ _ _ - _ _ _

.

The corrective action systems in use by some contractors reviewed were

,

inadequate. However, the CEI site organization has taken action to

provide control.

In some instances, NRs have been improperly closed

prior to completion of the entire scope of work required by the proposed

disposition of the NR.

The system for Document Control is being effectively employed by the

applicant at the Perry Nuclear Power Plant (PNPP) site.

.

G

VIII-6

. . . .

.____ __ -__ _ _ _ _ _ _ _

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _

-

__ _____ __ _ _ _ .

_

.

,e

ATTACHMENT A

-A.

PERSONS CONTACTED

The following list identifies the applicant's representatives, including

coordinators for specific areas, contacted during this inspection:

.

1.

Entrance or Exit Meetings

B. Barkley*

L. Beck

J. Bellack

T. Boss

M. Brown

W. Coleman

R. Davidson*

M. Edelman

J. Eppich

R. Farrell

P. Gibson

L. Hartline*

C. Hunter

R. Jadgehew

K. Kaplan

J. Kerr

J. Kline

M. Kritzer

R. Krotseng

J. Lastovka

G. Leidich

M. Lyster

'

J. Marjenin*

P. Martin

J. Mehaffey*

G. Parker

K. Pech

E. Riley

E. Shaw

C. Shuster

P. Solanios

F. Stead

E. Sterle

'

T. Swansiger*

D. Tackas*

S. Tulk

H. Waldron*

H. Walls

B. Walrath

  • Attended exit meeting only.

.

AA-1

_ _ _ ___-_--______-.

--

.,

-

ATTACHMENT A

2.

Applicant's Coordinators

a.

Civil / Structural

M. Kritzer

b.

Mechanical

R. Matthys

R. Solt

c.

Electrical, Instrumentation and Control

K. Cimorelli

~W. Morris

d.

Welding and NDE

H. Walls

e.

Material Traceability, Storage and Maintenance

M. Franchuk

C. Hubbard

f.

QA and QC Inspector Effectiveness

T. Boss

In the course of this inspection, numerous craftsmen, inspectors, engi-

neers, and supervisory personnel who are not specifically listed were

also contacted.

AA-2

_

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ .

_

.a*

<*

.

L

ATTACHMENT A

B.

' DOCUMENTS REVIEWED

The documents listed below were reviewed by the inspection team members

~

to the extent necessary to satisfy the inspection of objectives stated in

o

Section I of this report. References to specific procedures are contained

with the body of the report.

1.

Final Safety Analysis Report

2.

Quality Assurance Manuals (CE 1 and Contractors)

3.

Quality Assurance Procedures

4.

Quality Control Procedures

5.

General Electrical Specifications

6.

General Concrete Specifications

7.

General Mechanical Installation Specifications

8.

General Piping Installation Specifications

9.

Maintenance Procedures

10. Procurement, Receiving, and Storage Procedures

11. Material Traceability Procedures

12. QA Audit Reports

13. Trend Analysis Reports

14. Procedures for Initiating & Processing Field Changes

15. Procedures for Initiating & Processing Nonconformances

16. Construction Test Procedures

17. Nonconformance Reports (NRs)

18. Field Question Reports

19. Project Engineering Directives

20. As-Built Packages

21. NDE Procedures

22. Personnel Qualification Records

23. Purchase Orders

24. Drawings and Specifications

25. Receiving Reports

26. Documentation Packages

27. Storage Maintenance Requirements

1

AA-3

1