Category:CORRESPONDENCE-LETTERS
MONTHYEARML20137N1591997-03-31031 March 1997 Informs That Licensee Facility Scheduled to Administer NRC GFE on 970409.Sonalsts,Inc Authorized Under Contract to Support NRC Administration of GFE Activities ML20058M0361993-04-12012 April 1993 Partial Response to FOIA Request for Documents.Forwards Records in App L Which Are Being Withheld Partially for Listed Reasons,(Ref FOIA Exemptions 5) ML20248D6521989-07-20020 July 1989 Forwards Response to Util Re Bills D0184 & D0185 for Plant OL Application Review Costs by Various Program Ofcs Through June 1984 ML20245D9621989-04-28028 April 1989 Forwards Addl Info Re Bunker Ramo Instrumentation Penetration Modules,Per 890131 Request.Util Believes That Modules Environmentally Qualified in Accordance w/10CFR50.49 & NUREG-0588,Category II ML20205C3521988-09-23023 September 1988 Final Response to FOIA Request for Documents Re Plant. Forwards App D Documents.App D Documents Also Available in PDR ML20155A7001988-06-0202 June 1988 Informs That Const on Conversion of Plant to gas-fired Facility Began on 880404 ML20155A7401988-05-18018 May 1988 FOIA Request for Documents on 850731 & 870312 Meetings Re Plant.Document Re 840314 Meeting Previously Obtained & Therefore Excluded from Request ML20237B4361987-12-14014 December 1987 Final Response to FOIA Request for Documents.App B Document, Board Notification 84-024,encl & Also Available in PDR ML20236X6141987-12-0808 December 1987 Final Response to FOIA Request All Documents.No Addl Records Subj to Request Located ML20236U2571987-11-0505 November 1987 FOIA Request for Documents Re Ball Type Main Steam Isolation Valves Used at Facilities ML20235B3081987-09-21021 September 1987 Responds to FOIA Request for Documents,Including AEC to ACRS Forwarding Safety Evaluation Re Zimmer.App a Documents Cannot Be Located.App B Documents in Pdr.App C & D Documents Withheld (Ref 10CFR2.790) ML20235M4251987-07-13013 July 1987 Partial Response to FOIA Request for Documents Re Acrs. Forwards Documents for Categories One & Three of FOIA Request.Review of 21 Addl ACRS Documents Continuing ML20235K1731987-07-0909 July 1987 Partial Response to FOIA Request for Info Re Certain Contracts Awarded by NRC for Reporting Svcs.Forwards App a & B Documents.Documents Also Available in PDR ML20234F0911987-06-26026 June 1987 Responds to Appeal Re Denial of FOIA Request for Documents. Forwards Document 5 in App F.Portions of Document 5 Withheld (Ref FOIA Exemptions 6 & 7).Other Requested Documents Withheld (Ref FOIA Exemption 6) ML20215K1981987-06-19019 June 1987 Final Response to FOIA Request for Documents Re Allegations Concerning Plant.Forwards App G & H Documents.Documents Also Available in Pdr.App H Documents Partially Withheld (Ref FOIA Exemption 6) ML20213F9351987-05-0808 May 1987 Partial Response to FOIA Request.Forwards App F Document & Weld Allegations.App G Documents Partially Withheld (Ref FOIA Exemption 6) ML20206H4951987-04-13013 April 1987 Partial Response to FOIA Request for Documents Re Bechtel Employment Discrimination.Forwards App E Documents.App D Documents Withheld (Ref FOIA Exemption 6) ML20235G2321987-04-0101 April 1987 FOIA Request for Documents Re Forged NDE Inspectors Certification Supplied by Barclay Intl for Use at Quad Cities Nuclear Station & Stated Investigations at Plants ML20211A9531987-02-13013 February 1987 Advises That Financial Info Submitted for 1987 in Util Satisfies Requirements of 10CFR140.21 That Each Licensee Maintain Guarantee of Payment of Deferred Premiums for Operating Reactors Over 100 Mwe ML20212M7651987-01-16016 January 1987 Informs That Due to Demands on Staff,Nrc Will Respond by 870430 to 850607 Request for Review of Invoices D0184 & D0185 Re OL Application Review Costs Through 840623 ML20207C0151986-12-19019 December 1986 Forwards Notice of Withdrawal of Application for OLs & Termination of Proceeding,Per Util 860711 Request & ASLB 861217 Memorandum & Order Granting Motion ML20207C1191986-12-18018 December 1986 Forwards Order Terminating CPPR-81 & CPPR-82 Based on Fact That Const of Facility Ceased,Units Inoperable & Site Environmentally Stable,Per Util 860701 Request to Withdraw Application to Amend CPs ML20215B9641986-12-0505 December 1986 Notifies Util of 870204-05 Early Emergency Responders Workshop in Chicago,Il to Discuss Lessons Learned & Current Problems in Coordination & Integration of Emergency Response Efforts.Meeting Agenda & Preregistration Form Encl ML20214Q0911986-11-24024 November 1986 Partial Response to FOIA Request for Documents Re Ofc of Inspector & Auditor Investigations.Forwards App B Documents. Documents Also Available in PDR ML20214A0761986-11-14014 November 1986 Forwards Insp & Evaluation of Plant for Adequacy of Stabilization Plan,Documenting 861015-16 Site Insp & Review & Insp of Site Stabilization Rept.Environ Stabilization Satisfactory ML20215N0241986-10-28028 October 1986 Forwards Order from DOE Economic Regulatory Admininstration Granting Exemption from Prohibitions of Power Plant & Industrial Fuel Act of 1978 & Puc of Mi Opinion & Order Granting Relief from Commission 850329 Rate Order ML20215M8851986-10-28028 October 1986 Forwards Insp Repts 50-329/86-01 & 50-330/86-01 on 861015-16.No Violations Identified ML20211B5401986-10-0909 October 1986 Further Response to FOIA Request for Eight Categories of Documents Re Ee Kent Allegations Concerning Facilities. Forwards Documents Listed in App K ML20210S9971986-10-0202 October 1986 Requests Change in Facility Svc List Address to Ref Address. Related Correspondence ML20210S4131986-09-26026 September 1986 Further Response to FOIA Request for 16 Categories of Records Re Facilities.Forwards App D & E Documents.Documents Also Available in PDR ML20214T7431986-09-24024 September 1986 Forwards Form 8-K Filed W/Securities & Exchange Commission. Util Believes Info Presented Bears No Issues Currently Before Aslb.Related Correspondence ML20214N4541986-09-0808 September 1986 Provides List of Activities Re Remedial Soils Work Being Modified Pending Final Disposition of Issues Described in Util 860701 & Counsel s Withdrawing Request for CP Extension.W/Svc List.Related Correspondence ML20209E6621986-09-0505 September 1986 Responds to FOIA Request for Documents Re Util Response to NRC 840112 Confirmatory Order.Documents Listed on App Available in PDR IA-86-235, Responds to FOIA Request for Documents Re Util Response to NRC 840112 Confirmatory Order.Documents Listed on App Available in PDR1986-09-0505 September 1986 Responds to FOIA Request for Documents Re Util Response to NRC 840112 Confirmatory Order.Documents Listed on App Available in PDR ML20212K9061986-08-21021 August 1986 Forwards Request for Addl Info Re Environ Review of Util 860711 Request to Withdraw Applications for OL by 860828 ML20206M8311986-08-15015 August 1986 Forwards Util Response to ASLB 860716 Order.W/O Encl.Related Correspondence ML20212J1391986-07-25025 July 1986 Forwards ALAB-106 Monthly Rept for June 1986.Listed Nonconformance Repts & Addl Documents Closed During June Encl ML20207D7261986-07-11011 July 1986 Forwards Motion for Authorization to Withdraw OL Application & for Dismissal of OL & Order of Mod Proceedings & Motion for Termination of Aslab Jurisdiction.W/O Encl.Related Correspondence ML20202F9581986-07-11011 July 1986 Forwards Util Motion for Authorization to Withdraw OL Application & for Dismissal of OL & Order of Mod Proceedings & Motion for Termination of Appeal Board Jurisdiction,For Filing.W/O Encl ML20203B2351986-07-10010 July 1986 Informs That Review of 820622 Application to Receive Unirradiated Nuclear Fuel Assemblies Terminated,Per .Fission Chambers Should Be Disposed of & Licenses SNM-1904 & SNM-1905 Terminated,Per 10CFR70.38(b) ML20206T2401986-07-0101 July 1986 Advises That Since Facility Formally Abandoned as Nuclear Facility,Util Will Not Reply to Generic Ltr 86-05 Re TMI Action Item II.K.3.5 ML20202B1091986-07-0101 July 1986 Forwards Evaluation of 13 Specific Recommendations Contained in BNL Rept of Review of Surveillance & Maint Program,In Response to CE Norelius 860506 Request ML20206T4321986-07-0101 July 1986 Withdraws Application for Ols.Facility Will Be Converted to combined-cycle gas-fired Plant.Abandonment Actions & Equipment Sales Will Provide Assurance That Plant Cannot Be Used as Nuclear Facility ML20199J9181986-06-30030 June 1986 Submits ALAB-106 Quarterly Rept 51.No New Individuals Assigned quality-related Duties.Const Shut Down Since 840716 & No Const Activities Projected for Jul-Sept 1986 ML20211L0361986-06-25025 June 1986 Forwards Bechtel & B&W Nonconformance Repts for May 1986,per Memorandum & Order ALAB-106 ML20198E9051986-05-25025 May 1986 Forwards ALAB-106 Monthly Rept for Apr 1986,including Nonconformance Repts,Quality Action Requests,Equality Audit Finding,B&W Repts of Nonconformance & Audit Finding Repts. Only Nonconformance Repts Encl ML20205P9331986-05-23023 May 1986 Responds to Generic Ltr 86-10, Implementation of Fire Protection Requirements. Project in Surveillance & Maint Mode.Generic Ltr & FSAR Update Will Be Reviewed When Project Restarted ML20203Q2891986-05-0606 May 1986 Forwards BNL Technical Rept, Surveillance & Maint..., Based on NRC 851014-18 Insp.No Violations Noted.Items Identified Could Have Impact on Later Project Restart. Evaluation of Rept Recommendations Requested within 60 Days ML20203N3901986-05-0101 May 1986 Forwards Rev 2 to Tdi Owners Group App Ii:Generic Maint Matrix & Justifications. Rev Approved by Tdi Owners Group & Tdi ML20205N5861986-04-29029 April 1986 Forwards Corrected Page 1 to JW Cook to H Berkow Re Pipe Whip Restraint Design.Last Line Inadvertently Eliminated When Ltr Originally Issued 1997-03-31
[Table view] Category:ENGINEERING/CONSTRUCTION/CONSULTING FIRM TO NRC
MONTHYEARML20133H8841985-09-16016 September 1985 Discusses Ee Kent Allegations Re Plant,Per Encl . Decision Reflected in NRC Should Be Reconsidered. B Garde & T Devine of Gap Unwilling to Testify for Kent.Kent & Counsel Unable to Produce Expert Witnesses ML20133H9201985-05-0909 May 1985 Discusses Ee Kent Allegations Re Quality of Engineering & Const at Plant.Region III Could Quickly Dispose of Matters Held Open in NRC .Meeting to Facilitate Closure Suggested ML20095E2211984-08-0707 August 1984 Forwards Minutes of Monthly Third Party Assessment 840712 Meeting Re Status of Independent Assessment of Underpinning & Remedial Soils Work & Status of Const Implementation Overview Program ML20093H6381984-07-24024 July 1984 Solicits Support in Resolution to Call Public,Congress & Administration Attention to Concern Over Impending Electricity Shortage Due to Unnecessary Cancellations of near-term Plants Under Special Interest Group Pressure ML20090G1971984-07-18018 July 1984 Forwards Draft Topical Rept B-84-148, Idcvp:Control Room HVAC Sys Performance Requirements ML20093J5901984-07-18018 July 1984 Forwards Const Implementation Overview Weekly Rept 57 for 840709-13 ML20093E0781984-07-0606 July 1984 Forwards Const Implementation Overview Weekly Rept 55 for 840625-29 ML20095E2591984-07-0303 July 1984 Forwards Independent Assessment of Underpinning Weekly Rept 93 for 840624-0630.Minutes of Daily Meetings Between Members of Assessment Team & Site Engineering,Const & QA Personnel Encl ML20095E3051984-07-0202 July 1984 Forwards Const Implementation Overview Weekly Rept 54 for 840618-22.Rept Includes Summary of Activities & Open Items, Nonconformance Identification Repts & Hold Points ML20093A4091984-07-0202 July 1984 Forwards Summary of 10th General Status Review 840621 Meeting in Ann Arbor,Mi on Confirmed Items & Findings Re Idcvp ML20095E2451984-06-27027 June 1984 Forwards Independent Assessment of Underpinning Weekly Rept 92 for 840617-0623.Minutes of Daily Meetings Between Members of Assessment Team & Site Engineering Const & QA Personnel Encl ML20092P3621984-06-26026 June 1984 Notifies That 840619 Meeting Re Idcvp Rescheduled for 840628 in Ann Arbor,Mi to Discuss Civil/Structural Confirmed Items ML20092H5461984-06-22022 June 1984 Forwards Rev 5 to Project QA Plan, CPC Midland Idcvp. Signed Document Ack Requested by 840702 ML20095E2891984-06-22022 June 1984 Forwards Const Implementation Overview Weekly Rept 53 for 840611-15.Rept Includes Summary of Activities & Open Items, Nonconformance Identification Repts & Hold Points ML20095E2291984-06-20020 June 1984 Forwards Independent Assessment of Underpinning Weekly Rept 91 for 840610-16.Minutes of Daily Meetings Between Members of Assessment Team & Site Engineering,Const & QA Personnel Encl ML20092C3021984-06-18018 June 1984 Forwards Nonconformace Identification Rept 037 Re Orientation & Configuration of Support in Hanger Sketch ML20092C4021984-06-14014 June 1984 Forwards Independent Assessment of Underpinning Weekly Rept 90 for 840603-09 ML20092C9451984-06-14014 June 1984 Forwards Const Implementation Overview Weekly Rept 52 for Wk of 840604-08 ML20092A5641984-06-12012 June 1984 Forwards Info Re Closed Const Implementation Overview Item 080 Re Certified Personnel Not Listed in Available Certifications ML20095E2751984-06-0808 June 1984 Forwards Const Implementation Overview Weekly Rept 51 for 840528-0601.Rept Includes Summary of Activities & Open Items,Nonconformance Identification Repts & Hold Points ML20091M8761984-06-0707 June 1984 Forwards Open Const Implementation Overview Item 087 Re Liquid Penetrant Exam on Welds ML20091N3251984-06-0707 June 1984 Forwards Const Implementation Overview Nonconformance Identification Rept Nir 023 Re Work Print Station 209,for Info ML20092C9731984-06-0606 June 1984 Forwards Independent Assessment of Underpinning Weekly Rept 89 for 840527-0602 & Minutes of Daily Meetings ML20091Q8271984-06-0606 June 1984 Forwards Signed Affidavit & Resumes for Mj Huss & Je Walker. Huss & Walker Assigned to Const Implementation Overview Staff ML20091R6611984-06-0606 June 1984 Forwards Const Implementation Overview Weekly Rept 50 for 840521-25 ML20091J8471984-06-0404 June 1984 Forwards Const Implementation Overview Item/Hold Point Notification Forms for Items 072 & 073 Re ANSI N45.2, Section 7 & B&W QA Manual,Rev 3,respectively ML20091L0321984-06-0404 June 1984 Forwards Resumes & Statements of Independence for Jm Hendrie,Jm Biggs & JW Stanley to Conduct Idcvp ML20091N0281984-06-0404 June 1984 Forwards Closed Const Implementation Overview Item 060 Re Site Auditing ML20091N0421984-06-0404 June 1984 Forwards Closed Const Implementation Overview Nonconformance Identification Repts 022 & 027 ML20091N8001984-06-0101 June 1984 Forwards Closed Const Implementation Overview Items 070 & 086 Re Status Assessment Process & Nonconformance Identification Repts 022 & 023,respectively ML20091J8521984-05-31031 May 1984 Forwards Const Implementation Overview Weekly Rept 49 for 840514-18 ML20091H3931984-05-29029 May 1984 Forwards Open Const Implementation Overview Item 082/hold Point Notification.Audit Forms/Checklists Incomplete & Some Criteria of 10CFR50,App B Not Audited ML20091E7191984-05-24024 May 1984 Forwards Closed Nonconformance Identification Rept 019 Re Fddl Printouts Including Error in Unsolicited Drawings ML20091A2061984-05-23023 May 1984 Notifies of Idcvp 840531 Meeting W/Util & Bechtel in Ann Arbor,Mi to Discuss Status of Response to SEP Confirmed Items & to Obtain Info Re Standby Electric Power Sys Performance Requirements Review,Per 840530-0601 Visit ML20091E5051984-05-23023 May 1984 Forwards Closed Const Implementation Overview Item 063 Re Use of Fsk Prints Not Marked Status Assessment Print or W/Expiration Date ML20091J0021984-05-23023 May 1984 Informs That Tera Personnel Will Meet W/Bechtel in Ann Arbor,Mi on 840530-0601 to Discuss Idcvp Progress & Items Re Standby Electric Power Sys Performance Requirements Review ML20091N8801984-05-22022 May 1984 Forwards Independent Assessment of Underpinning Weekly Rept 87, for Wk of 840513-19 ML20092A6691984-05-22022 May 1984 Forwards 840510 Meeting Minutes Re Status of Independent Assessment of Underpinning & Remedial Soils Work ML20091E0691984-05-22022 May 1984 Forwards Tracked Action Item 086 Re Nir 022 & Nir 023. Requests One Reply Clarifying Initial Findings.Current Replies Provide Inaccurate & Conflicting Info ML20091E7521984-05-22022 May 1984 Forwards Closed Const Implementation Overview for Item 059 Re Failure to Maintain Audit Repts ML20091G9611984-05-22022 May 1984 Forwards Minutes of 840510 Meeting Re Third Party Assessment Activities Concerning Underpinning & Remedial Soils Work ML20091B4141984-05-21021 May 1984 Forwards Const Implementation Overview (Cio) Weekly Rept 48 for 840507-11.Rept Includes Summary of Cio Activity,Open Items,Nonconformance Identification Rept Summary & Hold Points ML20091B0711984-05-18018 May 1984 Forwards Const Implementation Overview Nonconformance Identification Rept 025 Re Inprocess Evaluation of Documents Received at Station 219.Item Closed ML20091C5691984-05-18018 May 1984 Forwards Open Const Implementation Overview/Hold Point Notification 085.Asterisked Items May Impact Phase I/Phase II Release ML20091J7711984-05-17017 May 1984 Forwards Open Const Implementation Overview Item 084 Re Verification of Quality Verification Program Activities in Module 800 E-G ML20091J7721984-05-17017 May 1984 Forwards Closed Const Implementation Overview Nonconformance Identification Repts 026 & 024 Re Deficiencies in Drawings, Including Rev 13 to Drawing C-130,Rev 7 to Drawing C-224, Drawing A-871 & Rev 17 to Drawing C-898 ML20091J9331984-05-17017 May 1984 Forwards for Action/Info,Const Implementation Overview Item 083 Hold Point Notification Re Noting on Visible Portion of Cable,Portion of Cable Not Inspected & Reason Why Cable Not Inspected ML20091C5021984-05-17017 May 1984 Forwards Independent Assessment of Underpinning Weekly Rept 86 for 840506-12.Minutes of Daily Meetings Encl ML20084R3661984-05-17017 May 1984 Forwards Open Nonconformance Identification Rept 033 Re Svc Water Pumphouse ML20090K5251984-05-16016 May 1984 Forwards Midland Nuclear Plant Units 1 & 2 Idcvp,Twelfth Monthly Status Rept for 840401-30.Next Ocr/Finding Status Review Meeting Will Be Held in mid-June.Meeting Notice & Agenda to Be Issued When Meeting Scheduled 1985-09-16
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARML20245D9621989-04-28028 April 1989 Forwards Addl Info Re Bunker Ramo Instrumentation Penetration Modules,Per 890131 Request.Util Believes That Modules Environmentally Qualified in Accordance w/10CFR50.49 & NUREG-0588,Category II ML20155A7001988-06-0202 June 1988 Informs That Const on Conversion of Plant to gas-fired Facility Began on 880404 ML20155A7401988-05-18018 May 1988 FOIA Request for Documents on 850731 & 870312 Meetings Re Plant.Document Re 840314 Meeting Previously Obtained & Therefore Excluded from Request ML20236U2571987-11-0505 November 1987 FOIA Request for Documents Re Ball Type Main Steam Isolation Valves Used at Facilities ML20216E4721987-05-28028 May 1987 Part 21 Rept 140 Re Potential Defect in Air Pressure Regulators Mfg by Bellofram.Dripwell Gasket May Fail Due to Mismachining of Gasket Seating Surface Causing Loss of Control Air & Starting Air Pressure ML20235G2321987-04-0101 April 1987 FOIA Request for Documents Re Forged NDE Inspectors Certification Supplied by Barclay Intl for Use at Quad Cities Nuclear Station & Stated Investigations at Plants ML20215N0241986-10-28028 October 1986 Forwards Order from DOE Economic Regulatory Admininstration Granting Exemption from Prohibitions of Power Plant & Industrial Fuel Act of 1978 & Puc of Mi Opinion & Order Granting Relief from Commission 850329 Rate Order ML20210S9971986-10-0202 October 1986 Requests Change in Facility Svc List Address to Ref Address. Related Correspondence ML20214T7431986-09-24024 September 1986 Forwards Form 8-K Filed W/Securities & Exchange Commission. Util Believes Info Presented Bears No Issues Currently Before Aslb.Related Correspondence ML20214N4541986-09-0808 September 1986 Provides List of Activities Re Remedial Soils Work Being Modified Pending Final Disposition of Issues Described in Util 860701 & Counsel s Withdrawing Request for CP Extension.W/Svc List.Related Correspondence ML20206M8311986-08-15015 August 1986 Forwards Util Response to ASLB 860716 Order.W/O Encl.Related Correspondence ML20212J1391986-07-25025 July 1986 Forwards ALAB-106 Monthly Rept for June 1986.Listed Nonconformance Repts & Addl Documents Closed During June Encl ML20207D7261986-07-11011 July 1986 Forwards Motion for Authorization to Withdraw OL Application & for Dismissal of OL & Order of Mod Proceedings & Motion for Termination of Aslab Jurisdiction.W/O Encl.Related Correspondence ML20202F9581986-07-11011 July 1986 Forwards Util Motion for Authorization to Withdraw OL Application & for Dismissal of OL & Order of Mod Proceedings & Motion for Termination of Appeal Board Jurisdiction,For Filing.W/O Encl ML20206T4321986-07-0101 July 1986 Withdraws Application for Ols.Facility Will Be Converted to combined-cycle gas-fired Plant.Abandonment Actions & Equipment Sales Will Provide Assurance That Plant Cannot Be Used as Nuclear Facility ML20202B1091986-07-0101 July 1986 Forwards Evaluation of 13 Specific Recommendations Contained in BNL Rept of Review of Surveillance & Maint Program,In Response to CE Norelius 860506 Request ML20206T2401986-07-0101 July 1986 Advises That Since Facility Formally Abandoned as Nuclear Facility,Util Will Not Reply to Generic Ltr 86-05 Re TMI Action Item II.K.3.5 ML20199J9181986-06-30030 June 1986 Submits ALAB-106 Quarterly Rept 51.No New Individuals Assigned quality-related Duties.Const Shut Down Since 840716 & No Const Activities Projected for Jul-Sept 1986 ML20211L0361986-06-25025 June 1986 Forwards Bechtel & B&W Nonconformance Repts for May 1986,per Memorandum & Order ALAB-106 ML20198E9051986-05-25025 May 1986 Forwards ALAB-106 Monthly Rept for Apr 1986,including Nonconformance Repts,Quality Action Requests,Equality Audit Finding,B&W Repts of Nonconformance & Audit Finding Repts. Only Nonconformance Repts Encl ML20205P9331986-05-23023 May 1986 Responds to Generic Ltr 86-10, Implementation of Fire Protection Requirements. Project in Surveillance & Maint Mode.Generic Ltr & FSAR Update Will Be Reviewed When Project Restarted ML20203N3901986-05-0101 May 1986 Forwards Rev 2 to Tdi Owners Group App Ii:Generic Maint Matrix & Justifications. Rev Approved by Tdi Owners Group & Tdi ML20205N5861986-04-29029 April 1986 Forwards Corrected Page 1 to JW Cook to H Berkow Re Pipe Whip Restraint Design.Last Line Inadvertently Eliminated When Ltr Originally Issued ML20197F8331986-04-28028 April 1986 Advises That Response to Generic Ltr 86-04 Re Engineering Expertise on Shift Inapproriate at Present Because Midland Not Currently Under Const.Commitment to Provide Info Will Be Added to Commitment Tracking Sys ML20210L2351986-04-25025 April 1986 Forwards ALAB-106 Monthly Rept for Mar 1986,including Nonconformance Repts,Quality Action Requests,Mgt Corrective Action Repts & Quality Audit Findings ML20203K8531986-04-23023 April 1986 Responds to NRC Re Allegation Concerning Adequacy of Pipe Whip Restraint Design.Project Records Placed in Storage & Personnel Performing Work Dispersed.Specific Design Approach Would Require Check of Records at Bechtel ML20203P1661986-04-21021 April 1986 Discusses 860407 Study Considering Options for Facility. Options Range from Abandonment of Facility to Completion as Nuclear Plant.Conversion of Plant to Combined Cycle gas-fired Plant Chosen as Most Favorable Option ML20209E6531986-03-28028 March 1986 FOIA Request for Documents Re Util Response to NRC 840112 Confirmatory Order ML20140F8781986-03-25025 March 1986 Forwards ALAB-106 Monthly Rept for Feb 1986,including Nonconformance Repts,Quality Action Requests,Mgt Corrective Action Repts & Quality Audit Findings ML20154H9651986-02-25025 February 1986 Forwards Nonconformance Repts Written or Closed During Jan 1986,per Memorandum & Order ALAB-106 ML20154D3581986-02-24024 February 1986 Confirms Items Agreed Upon in 860219 Telcon Re soil-related Issues.Util Will Discontinue Monitoring Dike Groundwater Wells During Shutdown & Site Maint.Authorization Given to Seal Weeping Wall Crack ML20198H2401986-01-24024 January 1986 Forwards ALAB-106 Monthly Rept for Dec 1985,including Bechtel Nonconformance Repts,Quality Action Requests,Mgt Corrective Action Repts & Quality Audit Findings ML20136F4771985-12-31031 December 1985 Forwards PNL-5718, Review of Tdi Diesel Generator Owners Group Engine Requalification Program,Final Rept, Technical Evaluation Rept ML20138Q5531985-12-31031 December 1985 Submits ALAB-106 Quarterly Rept 50.No New Individuals Assigned quality-related Duties Since 850930 Rept & No Const Activities Projected for Jan-Mar 1986 ML20136C5711985-12-20020 December 1985 Forwards Monthly Rept for Nov 1985,including Bechtel Nonconformance Repts,Quality Action Requests,Mgt Corrective Action Repts,Quality Audit Findings,B&W Repts of Nonconformity & Util Nonconformance Repts,Per ALAB-106 ML20138Q3871985-12-13013 December 1985 Ack Receipt of 851115 IE Bulletin 85-003, Motor-Operated Valve Common Mode Failures During Plant Transients Due to Improper Switch Settings. Valve Operability Program & Rept Scheduled to Be Completed Prior to OL Issuance ML20137Z1481985-11-27027 November 1985 Advises That Response to 851029 IE Bulletin 85-001, Steam Binding of Auxiliary Feedwater Pumps, Inappropriate at Present Since Plant in Surveillance & Maint Status.Schedule for Response Will Be Provided When Status Changes ML20137F2541985-11-25025 November 1985 Forwards ALAB-106 Monthly Rept for Oct 1985,including Bechtel Nonconformance Repts,Quality Action Requests,Mgt Corrective Action Repts & Quality Audit Findings,Per 730323 Order ALAB-106 & Amend 1 to Cp.Svc List Encl ML20138J4431985-10-25025 October 1985 Forwards Monthly Rept for Sept 1985,per Memorandum & Order ALAB-106 & Amend 1 to Cp,Including Bechtel Nonconformance Rept,Quality Action Requests,Mgt Corrective Action Repts, Quality Audit Findings & B&W Repts of Nonconformity ML20138D0031985-10-14014 October 1985 Informs That Util Will Submit Schedule for Meeting Requirements of 10CFR50.62(d) Per Generic Ltr 85-06 Re QA Guidance for ATWS nonsafety-related Equipment When & If Project Reactivated ML20133F7581985-10-0808 October 1985 Informs of Plans to Physically Disable Equipment Installed in & About Evaporator Bldg to Serve Process Steam to Dow Chemical Co,Per 850925 Resolution.Equipment & Structures Abandoned Are non-Q.Related Correspondence ML20137Y7921985-09-30030 September 1985 Submits Quarterly Rept 49,per ALAB-106.No New Individuals Assigned to quality-related Duties.Const at Plant Shut Down on 840716.No Const Projected for Fourth Quarter 1985.Next Quarterly Rept Will Be Submitted by End of Dec 1985 ML20133A3141985-09-27027 September 1985 Forwards Review of Section 4.7 of Technical Evaluation Rept PNL-5600, Review of Resolution of Known Problems in Engine Components for Tdi Emergency Diesel Generators, Reflecting Views Re Crankshafts for 16-cylinder Engines ML20133H1261985-09-25025 September 1985 Forwards Bechtel Nonconformance Repts,Quality Action Requests,Mgt Corrective Action Repts & Quality Audit Findings Written or Closed During Aug 1985,per Condition of Memorandum & Order ALAB-106 ML20138S0731985-09-17017 September 1985 Advises That Addl Excavation Between Tank Farm & Auxiliary Bldg Will Be Conducted Per NRC 850826 Authorization. Excavation Needed to Provide Supplemental Cathodic Protection.Svc List Encl.Related Correspondence ML20133H8841985-09-16016 September 1985 Discusses Ee Kent Allegations Re Plant,Per Encl . Decision Reflected in NRC Should Be Reconsidered. B Garde & T Devine of Gap Unwilling to Testify for Kent.Kent & Counsel Unable to Produce Expert Witnesses ML20140G8331985-08-23023 August 1985 FOIA Request for ACRS Documents Re Facility ML20137F7061985-08-12012 August 1985 Forwards Listed Documents Written or Closed During Jul 1985, in Accordance w/730323 Memorandum & Order ALAB-106 & Amend 1 to Cp.Only Nonconformance Repts Encl ML20133L8331985-08-0909 August 1985 Forwards Attachment 1 to Revised Exhibit D of Revised Compliance Filing & Application for Authorization to Issue Securities.Plan Is Requirement of Agreements W/Banks to Restructure Outstanding Debt.Related Correspondence ML20132B1841985-07-19019 July 1985 Forwards Monthly Repts for May & June 1985 Per Condition of 730323 Memorandum & Order ALAB-106 & Amend 1 to Cp.Related Correspondence 1989-04-28
[Table view] |
Text
,
1 STONE & WEBSTER MICHIGAN, INC.
P.O. Box 2325. BOSTON. M AssAcHustTTs 02107 United States Nuclear Regulatory Commission January 12, 1984 Midland Site Resident Office '
Route 7, J.O. No. 14358 Midland, Michigan 48640 Ref. MPF 68 Attention: Mr. R. Cook DOCKET NO. 50-339/330 MIDLAND PLANT UNITS 1 & 2 INDEPENDENT ASSESSMENT OF UNDERPINNING REPORT NO. 68 A copy of the Independent Assessment of Underpinning Weekly Report No. 68 for the period of January 1, 1984 through January 7, 1984 is enclosed with this letter. Included as attachments are the minutes of the daily meetings held during the week between members of the Assessment Team and Site Engineering, Construction, and Quality Assurance personnel.
If you have any questions with respect to this report please contact me at (617) 589-2067.
A. Stanley Luc.s Project Manager Enclosures ASL/pd 8403060415 840301 PDR ADOCK 05000329 G PDR
e, '
l
." l l
J.O. No. 14358 Midland Plant Units 1 & 2 .
Independent Assessment of Underpinning !
Weekly Ecport No. 68 January 1, 1984 through January 7, 1984 Personnel on Site Stone & Webster Michigan, Inc.
P. Majeski 1/3 - 1/7 D. Benvie 1/3 - 1/7 R. Lykens 1/3 - 1/7 A. Lucks 1/4 - 1/5 Parsons Brinckerhoff, Michigan J. Oliveira 1/3 - 1/7 Meetings Attended Date Represented Purpose 1/4 - 1/6 Stone & Webster Daily Assessment Bechtel Team Meeting Consumers Power Parsons 1/4 - 1/6 NRC Review and Evaluation Bechtel of Criteria and Consumers Power Crack Mapping Stone & Webster Underpinning and Remedial Soils Activities - Construction The Stop Work Order issued October 21, 1983 continued in effect throughout the week. Rejacking and crack mapping activities were performed, as required, by the project procedures.
Assessment Team Observations The Stone & Webster CIO Team has completed their Phase III overview of the civil documents at the five Documen,t Control Stations associated with the Soils Remedial activities. As a result of the overview , Stone & Webster issued an NIR detailing nonconformances found at three of the five Document Control Stations. MPQAD issued a QAR based on nonconformances detailed in the NIR. Once the QAR is satisfactorily resolved, Stone & Webster will conduct another overview of the Soils Document Control stations.
An MPQAD audit noted document control problems similar to those identified in the NIR resulting in the preparation of a CPCo Management Corrective Action - '
Request / Report. The purpose of this report is to initiate evaluation of recurring document control problems.
An update on corrective actions being undertaken by US Testing was provided by Bechtel. A review of US Testing by Bechtel Field Engineering found that
2 J.O. No. 14358 Midland Plant Units 1 & 2 Independent Assessment of Underpinning most of the corrective action items have been implemented by US Testing.
Cross training of US Testing personnel and development of Work Instructions are the two major items that are still open. Bechtel reported that a revised schedule would be provided next week targeting completion dates for cross referencing of inspectors and development of work instructions. The Assessment Team believes that US Testing should strive to complete the work on these two items in accordance with the revised schedule.
Work Activity Packages The following Work Activity Package overview is in the open response stage or have been completed during the past week. 9 WAP No. Title Status 71 SWPS-Thru Anchor Open Bolt Holes Nonconformance Identification Reports NIR No. Description Date (Opened)(Closed) 20 Concrete Admixture 12/1/83 Dispenser Calibration Open Items Items discussed during meetings are categorized as follows:
OPEN ITEM - An item for which an action is required. The item will remain open until the required action has been taken. Tracking is required.
CLOSED ITEM - An item, usually brought forward by the Assessment Team, that is discussed and adequately responded to. No tracking is required.
INFORMATION ITEM - An item, brought forward to provide general background information regarding work, such as work status or an upcoming design change.
No tracking is required.
l OPINION ITEM - An opinion or suggestion, given by the Assessment Team, expressing an alternate construction or quality assurance technique. The opinion or suggestion is given as a possible alternate that may facilitate an operation. No response or implementation is required as a result of_an l Opinion Item. ~
CLOSES ITEM -XX-XX - This notation identifies an action that closes a previously identified open item. Tracking of the open item stops.
n
~ -
e e .
.- 3 J.O. No. 14358 l Midland Plant Units 1 & 2 Independent Assessment of Underpinning The following is a listing of all Open items from the Daily Meeting Notes with Bechtel, the Weekly Meeting with MPQAD or the text of Weekly Reports. Carry-over items from past weeks which have been Closed this week are also listed.
Item No. Description Closure WR 54, Pg. 3 Weld Tech Sheets Open 57-17 Wall Ties open WR 58, Pg. 2 Lack of Drawing Open References 58-3 Tubular Steel open Lagging 64-7 QAP Review Program Open 64-10 Trend Analysis Open WR 64, Pg. 1 US Testing Open Corrective Action 65-19 Review of Phase III Open SWO Resolution 66-30 Review of Phase III 68-6 SWO Resolution 66-50 Request for IR Open Distribution 67-15 Reference Drawing 68-12 List 4
4 P ett Eng'ineer Project Manager 1 .
1 c
i
! Notes of Daily Meeting Independent Assessment of Underpinning Midland Plant Units 1 & 2 ,
Consumers Power Company Held at Midland Site Midland, Michigan January 2, 1984 l
No meeting was held on this day. (Site Holiday) l 2
4 l
I I
. I Notes of Daily Meeting Independent Assessment of Underpinning Midland Plant Units 1 & 2 Consumers Power Company Held at Midland Site Midland, Michigan January 3, 1984 No meeting was held on this day, t
4 l
Notes of Daily Meeting Independent Assessment of Underpinning Midland Plant Units 1 & 2 l Consumers Power Company l Held at Midland Site Midland, Michigan January 4, 1984 Present For:
Consumers Power Bechtel MPQAD Stone & Webster G. Murray J. Fisher J. McMaster P. Majeski E. Cviki R. Sevo D. Benvie R. Lykens Parsons J. Oliveira
_ PURPOSE This meeting is held each day to discuss items regarding the Independent Soils Assessment at the Midland Plant , Units 1 & 2.
DISCUSSION Status Items Item 68 Stop Work Order Update.
The Stone & Webster (CIO) overview of the 5 Soils Document Control stations found non-conformances with stations, 8, 10, and 13. Stone &
Webster wrote an NIR detailing nonconformances found during the overview.
MPQAD will respond to the NIR today and Stone & Webster will again overview the above referenced three (3) stations. (INFORMATION ITEM)
Item 68 Rejacking of Piers.
J. Fisher reported that as of today, no piers were on active jacks.
(INFORMATION ITEM)
Item 68 US Testing Corrective Action.
J. Fisher stated that an update on Corrective Actions undertaken by US Testing would be forthcoming this week. (ITEM WR-64, pg. 1 REMAINS OPEN) (INFORMATION ITEM) .
New Items Item 68 Review of Reference Mechanical & Electrical Drawings. '
1 J. Fisher inquired as to the status of Stone & Webster's review of the '
referenced drawings required for drill & excavation permits. P. Majeski responded that the Assessment Team had completed its review of attachments to the reference mechanical & electrical drawings required for processing drill & excavation permits to support underpinning activities over the next 30 days. The review verified that attachments to the referenced drawings had adequately completed the FCR/FCN review cycle. (CLOSED ITEM) l
1 l
Notes of Daily Meeting Independent Assessment of Underpinning Midland Plant Unita 1 & 2 Consumers Power Company Held at Midland Site Midland , Michigan January 4, 1984 Item 68 Controlled Copies of Reference Electrical & Mechanical Drawings.
P. Majeski inquired if there were controlled copies of reference electrial
& mechanical drawings required for processing of drill & excavation permits available at the FSO controlled drawing station. J. Fisher responded that he would determine whether or not these reference drawings are available. (OPEN ITEM)
Response Items Item 68 Review of Phase III SWO Resolution.
P. Majeski stated that since Stone & Webster (CIO) has started its Phase III overview of the five (5) Soils Document Control Stations, Item 66-30 can be closed. (CLOSES ITEM 66-30) l l
l' l
l
Notes of Daily Meeting Independent Assessment of Underpinning Midland Plant Units 1 & 2 Consumers Power Company Held at Midland Site Nudland, Michigan January 5, 1984 Present For:
Consumers Power Bechtel MPQAD Stone & Webster None J. Fisher J. McMaster P. Majeski E. Cviki G. Carpenter D. Benvie W. Brandes R. Lykens Parsons J. Oliveira PURPOSE This meeting is held each day to discuss items regarding the Independent Soils Assessment at the Midland Plant Units 1 & 2.
DISCUSSION Status Items Item 68 Stop Work Order Uedate.
As a result of the NIR issued yesterday detailing nonconformances found during Stone & Webster's (CIO) overview the 5 Soils Document Control Stations, a QAR will be issued today. After the QAR is resolved, Stone & Webster will again overview Stations 8,10, and 13 (INFORMATION' ITEM)
Item 68 Rejacking of Piers.
J. Fisher reported that no piers were on active jacks. (INFORMATION IIEM)
New Items No new items were discussed.
Response Items Item 68 Controlled Copies of Reference Electrical & Mechanical Drawings.
J. Gaydos reported that as of this date reference mechanical & electrical drawings required for,processir.g drill & exesvations permits to support underpinning activities over the next 30 days were available at the FSO drawing station. J. Gaydos stated that in the near future FSO will have a complete set of reference electrical & mechanical drawings at their drawing station. (CLO3ES ITEM 68-5)
Notes of Daily Meeting Independent Assessment of Underpinning Midland Plant Units 1 & 2 Consumers Power Company Held at Midland Site Midland, Michigan January 6, 1984 Present For:
Consumers Power Bechtel MPOAD Stone & Webster G. Murray E. Cviki J. McMaster P. Majeski D. Puhalla J. Fisher G. Carpenter D. Benvie J. Gaydos B. Lykens N. Swanberg ;
R. Cleary Parsons I
. erner J. Oliveira PURPOSE This meeting is held each day to discuss items regarding the Independent Soils Assessment at the Midland Plant, Units 1 & 2.
DISCUSSION Status Items Item 68 Stop Work Order Update.
A QAR was issued yesterday as a result of the NIR written by Stone & Webster (CIO) detailing overview findings of the 5 Soils Documents Control Stations. '
When the QAR is resolved, Stone & Webster will again overview the 5 Soils Document Control Stations. An MPQAD audit noted similar document control problems, resulting in preparation of a CPCo Management Corrective Action l Request / Report. This report was prepared to initiate evaluation of recurring document control problems by CPCo and Bechtel. (INFORMATION ITEM)
Item 68 Update on US Testing Corrective Action.
R. Cleary and J. Werner provided a status report on Corrective Actions being undertaken by US Testing. J. Werner reported that new personnel in key positions (i.e. site manager) have been assigned to the site to implement c orrective a etions. Also it was reported that cross training of technicians is ongoing and will be for the forseeable icture. It was agreed that a schedule will be issued next week targeting a realistic completion date for cross training of inspectors on site.
J. Werner stated that US Testing is in the process of developing a total of 60 Work Instructions for use by US Testing personnel in performing required inspections. These work instructions are being prepared to simplify procedures presently being used by US Testing to perform inspections. It was agreed that a schedule will be provided next week showing completion dates for the Work Instructions. Bechtol reported that a restatus on Corrective Action taken by US Testing would be issued next week. (ITEM WR-64, Pg. 1 REMAINS OPEN) (INFORMATION ITEM)
l Notes of Daily Meeting Independenc Assessment of Underpinning Midland Plant Units 1 & 2 Consumers Power Company Held at Midland Site 1 Midland, Michigan l January 6, 1984 New Items Item 68-11 - Cracking on the Tontrol Tower el. 685' Slab.
Three cracks were found yesterday in the control tower on the el. 685' slab. These cracks were found in an area of the control tower that was not previously included in the crack mapping program. It is not known whether these cracks existed prior to or are a result of underpinning activities. One 3.5 in. diameter core was taken at a crack location and is presently being evaluated by Bechtel. Initial examination of the core has shown the cracks to be at least 12 in. deep. (INFORMATION ITEM)
Response Item Item 68 Reference Drawing List.
The Assessment Team has completed review of attachments to the referenced electrical & mechanical drawings required for processing drill & excavation permits needed to support underpinning activities over the next 30 days.
The review verified that attachments to the referenced drawings have adequately completed the FCR/FCN review. Also grout plans formulated to date for the SWPS and the excavation permit required to implement the grouting program have been received by Stone & Webster. (CLOSES ITEM 67-15)
--