Crbr EIS Update, Monthly Progress Rept for Mar 1982
ML20076C151
Person / Time
Site: Clinch River
Issue date: 04/12/1982
From: Nelson I
Battelle Memorial Institute, PACIFIC NORTHWEST NATION
To: Lowenberg H
NRC OFFICE OF NUCLEAR MATERIAL SAFETY & SAFEGUARDS (NMSS)
Shared Package
ML20076B704 List:
References
FOIA-82-290 NUDOCS 8210070347
Download: ML20076C151 (3)


Text

,

s'..g l

OBaHelle Pacific Northwest Laboratories P.O. Box 999 Richland, Washington U.S.A. 99352 Telephone (5091375-6813 Telet 15-2874 April 12,1982

~

Mr. Homer Lowenberg, Chief Engineer Office of Nuclear Materials Safety and Safeguards U.S. Nuclear Regulatory Commission Washington, D.C.

20555

Dear Homer:

MARCH MONTHLY REPORT ON CRBRP EIS UPDATE Attached is the March monthly report for the CRBRP EIS update. We have included a projection of costs and a milestone schedule for the remainder of FY 1982.

Please contact me on FTS 8-509-375-6813 if you have any questions.

Very truly yours, I. C. Nelson, Project Manager ICN:RFM:sf cc: Office of the Director, NMSS (Attn: Program Support Branch) 6gg 007034[ B20756 won.

CLINCH RIVER BREEDER REACTOR EIS UPDATE PROGRESS DURING MARCH:

Task 1 - Review Environmental Report

_ The PNL project team met with the NMSS PM and cognizant NMSS staff on March 1,- 1982, 'in Silver Spring, Maryland for the purposes of initiating the work effort'and conducting a review of DOE's draft environmental report supple-ment. On March 2,1982, NRC and PNL staff met with DOE representatives and dis-cussed questions raised on the environmental report supplement and additional.

information requirements. Periodically-during March, the PNL PM communicated with the NMSS PM to reconcile questions and obtain guidance.

DOE's supplement was still in draft form at this writing. DOE has not-yet submitted an EA that presumably exists on the Demonstration Reprocessing Plant. ' Considerable staff effort was expended on interaction of'PNL and NRC Safeguards, counterparts.

Task 2 - Prepare Draft Sections of EIS Sucolement PNL project staff prepared a first draft of material to be inserted as Appendix D - Environmental Effects of the Fuel Cycle, Transportation, and Waste Management. This material was transmitted to the NMSS PM on April 9,1982.

PNL Safeguards representatives met with NRC April.'7 and 8,1982 to obtain guidance on preparation of safeguards aspects of the EIS update.

Task 3 Respond to Public Comments and Prepare Draft Sections of Final EIS Sucolement No work was performed on this task during March.

Task 4 - Provide Public Hearing Testimony and Support No' work was performed on this task during March.

PERSONNEL TIME' EXPENDITURES:

Expenditure of time, during March by PNL staff involved with the project is as follows:

Staff Hours I. C. Nelson 52 K. M. Byers 105 C. E. Geffen 100 C. M. Heeb 42

0. F. Hill 65

t R. F. McCallum 64 P. T. Reardon 124 F. P. Roberts 40 A. M. Schreiber 40 R. E. Schreiber 72 R. J.-Sorenson

'40 D. L. Strenge 67 Secretarial /Other 124 TOTAL 935 COSTS AND UNC0STED OBLIGATIONS:.

Costs incurred during March totaled approximately $50K. This is the total to date as work on the project was initiated March 1, 1982. An estimate of costs which are expected to be incurred from April 1 - September 30, 1982 is shown below.

Month Expected Expenditure ($X)

April 60 May 20 June 15 July 15 August 20 September 20 P

MILESTONES:

A milestone schedule for the project is outlined below. This schedule assumes that PNL will be providing responses to comments made on the draft EIS update.

Month Milestone April ~14 Second NRC/PNL working meeting, review of pre-liminary draft EIS update May _

Submit draft EIS upt oe to NRC August _

Respond to public coments on draft EIS update August _

Participate in public hearings 2

.-