OBallelle Pacific Northwest Laboratories P.O. Box 999 Richland, Washington U.S.A. 99352 Telephone (509) 375-6813 Telex 15-2874 May 17, 1982 Mr. Homer Lowenberg, Chief Engineer Office of Nuclear Materials Safety and Safeguards U.S. Nuclear Regulatory Commission Washington, D.C.
20555
Dear Homer:
APRIL MONTHLY REPORT ON CRBRP EIS UPDATE Attached is the April monthly report for the CRBRP EIS update.
Please contact me on FTS 509-375-6813 if you have any questions.
Very truly yours, h
l t
~
I.C. Nelson Project Manager ICN:sf cc: Office of the Director, NMSS (Attn: Program Support Branch) l l
t
(
I l'
FOIA i
ISS82-290 PDR
CLINCH RIVER BREEDER REACTOR EIS UPDATE PROGRESS DURING APRIL:
-Task 1 - Review Environmental Report Several updated versions of DOE's Amendment 13 were transmitted from the NMSS PM to PNL during April. _ As these were reviewed, the PNL PM communicated with the NMSS PM to reconcile any questions and obtain any necessary guidance.
PNL staff was provided with an ORIGEN run relating to CRBRP fuel at an April 13-14 working meeting.
Following modification to some of the input para-meters, a modified ORIGEN run was received on April 20, 1982.
Task 2 - Prepare Draft Sections of EIS Supplement A first draft of Appendix D - Environmental Effects of the Fuel Cycle, Transportation, and Waste Management was transmitted to the NMSS PM on April 9, 1982.
Various sections of Appendix E - Safeguards were transmitted during the first week in April and PNL safeguards representatives met with NRC April 7 and 8, 1962, to receive comments on this material.
PNL fuel cycle, transpor-tation and waste management staff met with NRC on April 13 and 14,1982 to obtain input on Appendix D.
As a result of these meetings, Appendices D and E-were revised and several related sections in Chapters 5 and 7 were prepared.
Task 3 - Respond to Public Comments and Prepare Draft Sections of Final EIS Supolement It is expected that the EIS Supplement will not be distributed.for public comment. Present plans call for the project to proceed to Task 4.
Task 4 - Provide Public Hearing Testimony and Support Work on this task is projected to begin in mid-July, 1982 with the prepa-ration of written hearing testimony. Actual hearings are scheduled to commence in the late August - early September time frame. At this point, the Task 3 effort will be transferred to Task 4 and a more refined estimate of Task 4 will occur when the task is better defined.
l PERSONNEL TIME EXPENDITURES:
Expenditure of time, during April by PNL staff involved with the project is as follows:
i Staff Hours I. C. Nelson 46 l
K. M. Byers 150 l
C. E. Geffen 82
.s
- 0. F. Hill I 93' R. F. McCallum.
72-P. T. Reardon 152 F. P. Roberts 4
R. E. Schreiber 48 R. J. Sorenson 56 D. L. Strenge
- 35 Secretarial /0ther.
141 TOTAL.
879 COSTS AND UNC0STED OBLIGATIONS:
Costs incurred during April totaled approximately $53K. The cumulative to date total is $103K. An estimate of costs which are expected to be incurred from May 1 - September 30, 1982 is shown below.
Month Expected Expenditure ($K)
May 27 June 15 July 15 August 20 September 20 MILESTONES:
A milestone schedule for the project is outlined below. This schedule.
assumes that PNL will not be providing responses to comments made on the draft EIS' update.
Month Milestone April 14 Second NRC/PNL working meeting, review of pre-liminary draft EIS update May 12, 13 Third NRC/PNL working meeting - further review of EIS update May 24.
PNL submit final EIS draft undate to NRC.
(llay 24-June 16 PNL will assist NRC as required.)
June 16 EIS update ready for printing August 24 Start public hearings L..