Text
g)
]
...7 OBallelle Pacific Northwest Laboratories P.O. Box 999 Richland, Washington U.S.A 99352 Telephone 15091375-6813 Telex 15-2874 June 17, 1982 Mr. Homer Lowenberg, Chief Engineer Office of Nuclear Materials Safety and Safeguards U.S. Nuclear Reaulatory Comission Washinnton, D.C.
20555
Dear Homer:
t'.Af MONTHLY REPORT ON CRBRP EIS UPDATE Attached is the May monthly report for the CRBRP update.
Please contact me on FTS 509-375-6813 if you have any questions.
Very truly yours, N
__I_
s s
I. C. Nelson Project Manager ICN:va cc: Office of the Director, NMSS (Attn:
Program Support Branch) t l
l l
l f8d10070319 820716 3
1- ;
1 CLINCH RIVER BREEDER REACTOR EIS UPDATE LPEDGRESS DURING.MAY:
Task 1 - Review Environmental Report Another version of Amendment XIV (previously Amendment XIII) was received
-and reviewed.
Task 2 - Prepare Draft Sections of EIS Supplement' The second draft of Appendix D Environmental Effects of the Fu 1 Cycle, Transportation, and Waste Management,. Appendix E - Safeguards, and various sec-tions in Chapters 5 and 7 was transmitted to NRC on May 7,.1982. PNL fuel cycle,-
transportation, waste management, and safeguards staff met with NRC to incor-porate NRC comments 6n.the second draft on May 12-13, 1982. As a result of this working meeting, a third draft was transmitted May 17,~1982.. Further modi-fication was made to this draft and-a final draft was transmitted on May 24,'1982.
Task 3 - Respond to Public Canments and Prepare Draft Sections of Final EIS Sucolement-It is expected that the EIS Supplement will not be distributed for public comment. Present plans call for the project to proceed to Task 4.
Task 4 - Provide Public Hearing Testimony and Support Work on this task is projected to begin in mid-July, 1982 with the prepa-ration of written hearing testimony. Actual hearings are scheduled to commence in the late August - early September time frame. At.this point, the Task 3 effort will be transferred to Task 4 and a more refined estimate of Task 4 will occur when the task is better defined.
PERSONNEL TIME EXPENDITURES:
Expenditure of time, during May by PNL staff involved with the project is as follows:
Staff Hours I. C. Nelson 109 K. M. Byers 92 C. E. Geffen 134
- 0. F. Hill 132 R. F. McCallum 51 D. R. Payson 95 P. T. Reardon 126 F. P.-Roberts 24 R. J. Sorenson 26 D. L. Strenge 19 Secretarial /0ther 340 TOTAL 1148
. CO'STS AND UNC0STED OBLIGATIONS:
Costs l'ncurred during May ' totaled approximately $67K. _The' cumulative to date total is-$170K._
An estimate of costs which are expected to;be incurred from June September 30, 1982 is shown below.
Month Expected Excenditure-($K)
June 18 July 2
' August 5
-September.
S MILESTONES:
A milestone schedule for the project is outlined below.
This schedule assumes-that PNL will not be providing responses to comments made on the draft EIS update.
Month Milestone
- April 14 Second NRC/PNL working meeting, rev'iew of pre-liminary draft EIS update May 12, 13 Third NRC/PNL working meeting - further review of EIS update May 24 PNL submit final EIS draft update to NRC..(May 24-June 16 PNL will assist NRC as required.
June 16 EIS update ready for printing August 24
. Start public hearings i