ML20071G097

From kanterella
Jump to navigation Jump to search
Forwards Backfitting & Regulatory Impact Cost Data for Hardware & nonhardware-related Backfits.Requirement for Adding One Addl Senior Reactor Operator to Each Operating Shift Will Cost $600,000 Per Yr
ML20071G097
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 03/04/1983
From: Reznicek B
OMAHA PUBLIC POWER DISTRICT
To: Tourtellotte J
NRC - REGULATORY REFORM TASK FORCE
References
NUDOCS 8305230588
Download: ML20071G097 (16)


Text

.

gk ME semara w. neznicen crneru nager

. Omaha Public Power District 1623 Harrieg Omaha Nebraska 68102

.402/536 4000 March 4, 1983 Mr. James R. Tourtellotte Chairman Regulatory Reform Task Force U.S. Nuclear Regulatory Commission Washington, D.C.

20555

Dear Mr. Tourtellotte:

Please find enclosed the backfitting and regulatory impact cost data from the Omaha Public Power District's Vort Calhoun Nuclear Plant. Data is presented for Nuclear Regulatory Commission requirements (TMI and other Commission imposed backfits). We have also included data for the District's initiated modifications.

A review of the data presented in the attachments to your February 8, 1983 letter reveals that only hardware and analyses costs are included. The District believes that, the "backfit" and regulatory costs involving other Ccmmission imposed requirements chould also be considered. These costs would include additions to staff, testing of equipment (e.g., hydrostatic testing and leak testing), increased training requirements, plant drills such as annual emergency plan exercises, and procedural requirements.

An example of these "non-hardware" costs is the presently proposed rule-making regarding the requirement for adding one additional Senior Reactor Operator to each operating shift. The Commission estimate that it will cost each utility $600,000 per year is probably reasonably accurate.

Projecting this annual cost for the lifetime of a nuclear plant clearly demonstrates that all major "backfit" costs certainly involve issues other than hardware.

1' l

The Omaha Public Power District supports the Regulatory Reform Task Force activities, and members of our nuclear staff are available to support your efforts in this area.

Sin rely, hY h

l B. W. Re.icek BWR/WEM/KJM/ pat G305230588 830304 PDR ADOCK 05000285 P

PDR Attachments 45 58M Employment with Equal Opportunity Male / Female

o j

i i

OMAHA PUBLIC POWER DISTRICT l

FORT CALHOUN STATION l

i i

i The. Fort Calhoun Station consists of one pressurized water reactor, with an electrical rate of 501 MWe (gross).

l The nuclear steam supply system, nuclear fuel, and turbine generator were purchased in October,1966.

The provisional constr'.tction permit was received in June, 1968 and commercial operation began in September, 1973.

t I

In addition to the $178 million construction cost for the plant, S50 million has been spent on backfitting.

Of this $50 million,

$41 million was for NRC imposed costs which included TMI related l

backfits.

The remaining $9 million in backfitting costs were for 4

those initiated by the District.

The plant value, as of

{

lj December 31, 1982, was $211 million.

The difference between the 1

initial cost of $178 million and the December 31, 1982 value of S211 million is $32 million, which is that portion of the $50 l

million that has been capitalized.

The remaining $18 million will l

be accounted for by work in progress, which will cost approxi-mately $11 million.

Operating accounts have been charged with $7 i

million.

The attached summary sheet ar.d Appendices A throuch C l

provide additional details for these costs.

It is presently estimated that near term future backfit' costs will

(

be $22 million.

Additional information on these future costs is provided in Appendix 0.

I Although not identified as an NRC imposed backfit, the Nuclear 1

Waste Policy Act of 1982 will result in a very substantial cost to. !

the District.

For the Fort Calhoun Station, it is estimated that presently accumulated liability relating to this act is $33 million and will be over $400 million by the year 2000.

t r

d t

k I

i i

i i

l1

\\

l i

T/

1

-=a-m

-'I

--w--

w ye v5 m

9w

-tv-

'i--wet

  • m r

-d-M SrTt

o

~

FORT C#tHOUN STATION COSTS OF BACKFITTING TOTAL THROUGH 12/31/82 SUMfMRY (a)

COSTS FOR NRC IMPOSED BACKFITTIflG 1.

Ha rdare 16,684,285 2.

Analytical 7,384,500 Total 24,068,785 o

(b)

COSTS FOR NRC TMI LESSONS LEARNED BACKFITTING 1.

Harda re 14,762,807 2.

Analytical 2,420,000 Total 17,182,,807 (c)

COSTS FOR UTILITY INITIATED BACKFITTING 1.

Hardare 8,043,926 2.

Analytical 1,120.500 f

Total 9,164,426 (d)

ESTIMATE NRC FUTURE BACKFITTING COST Total Cost 22,030,000 4

s O

4

- ~.....

~

_.. 1..

~~- ~' -

~

APPENDIX A (3)

COSTS FOR NRC IMPOSED BACKFITTING - DETAIL i

1.

HARDWARE 1498 Auxiliary Building Crane Mod 1,565,284 1609 Replace Main Steam Line Penetration Bellows 64,846 l

i.

1791 Steam Generator Support Mod 551.421 1878 Long Tem Core Cooling 97,011 2415 Replacanent of INC Mech. Snubbers 64,214

[

2421 Seismic Qualification of Auxiliary Feedwiter Sys.

64,479 o

2550 Seismic Restraints for a Few Aux. Bldg. Block Walls 10,375 i

3 2677 Upgrade QA V? ult 62,840 2764 Contaiment Nuclear Fire Emergency Alams/ Lights 538 t

4-2815 Radic-Chem. Lab Filters 5,993 2816 Replacanent of Aux. Coolant F1w Transformer 17,951 t

2861 Portable Office Facility 40,692 4

2866 Replacement of Waste Gas Release Valves 8,485

[

2200/

2058 Seismic Restraint Modification 6,778,261 2901 8 eta Radiation Shielding for Elec. Pene. Lead Wire 546 i

2930 Reactor Coolant Pumps Oil Collection Systen 599 2447 Replace Spent Fuel Rack 1,248,025 f

5 31 Inst, of Battery Powered Smoke Detect. Co rol Roan 161.432 532 Fire Water Loop System 344,675 533 Fire Extinguisher 42,401 536 Diesel Generators Separation 698,662' l

r i

537 Installation of Fire Rated Seals 585,330 l

552 Diesel Room Sprinkler Alams 4,714 1169 Electric Fire Pump -

24,997 1175 Relocation of Methane and Hydrogen 13,780 1176 Battery Room 54 and 55 Modifications 37,306 1218 Fire Daors ' Modification

'56,539

.A-1 r

~

APPENDIX A (a)

COSTS FOR NRC IMPOSED BACKFITTING (Continued) 1.

HARDWARE (Continued) 1242 Remote Annunciation of Warehouse Sprinkler System 2,548 1341 Fire Damper Modifications 22,146 1367 Spent Fuel Pool Emergency Cooling Cross Connection 170,428 1384 Hazardous Material Storage 1.525 1393 Total Flooding Halon 1301 Systen for Control Roan Walk In Lab and Cable Spread Room 228,496 o

1400 Fire Protection Modification 162,288

~

1455 Alternate Shutdown Capability 170,229 1

1457 Fuel Tank for Diesel Driven Fire Pump 19,037 1492 Reactor Coolant Pump Lube Oil Collection System 142,748 1582 Fire Alann Addition 1,095 1893 Fire Barrier at St' airway in Electrical Pene. Room 13.421 2441 Seismic Restraint for Cable Spreading Room Halon Sys.

1,824 2794 Cable Spread Room Halon System Dampers 162 l

2811 Pressurized Heater 437 2819 Turbine Floor Modification 10,362 i

2930 Reactor Coolant Pumps Oil Collection 599 700 Site Security 2,789,269 702 Under Voltage 76,083 4

f.

1464 79-01 Solenoid Replacement for LOCA Qualification 21,782 2l06 Replace Unqualified Limit Switches 37,855 q

2326 Replace Limit Switches in Auxiliary Building 181,038 2746 Replace and Relocate Safety Injection Flow Trans.

33,812 j

2763 Replace Containment Steam Genrator Pressure Trans.

45,655 HARDWARE iOTAL 16,684,285 l

1 -

e 1

A-2

APPENDIX A (e )

COSTS FOR NRC IMPOSED BACKFITTING - DETAIL 2.

ANALYTICAL Crane Cask Drop Analysis 22,500 Cooling loop Failure Analysis 3,500 RCS Overpressure Analysis 35,000 Core Motion Signature Analysis 5,000 Reactor Vessel Support Analysis 1,000 Steam Generator Feedwiter Waterhammer Analysis 10,000 RCS LTOP Analysis 10,000 PORV Testing - RCS LTOP 21,000 Charging Pump Vibration Analysis 30,000 Engineering Analyses - Post LOCA Long Term Core Cooling 100,000 Post LOCA LTCC at Stretch Power 35,000 Asymmetric LOCA Loads Analyses 1,000,000 Operating Manual Revisions 175,000 RV Weld Material Analysis - IE Bulletin 78-12,12A 7,500 NRC Purge Valve Questions 10,000 NRC Questions on RV Fluence 20,000 Engineering Analysis / Services - IE Bulletin 79-13 95,000 SI Pump Room Ventilation Analysis 35,000 Stretch Power - Radiological Consequences 10,000 f

UT Weld Testing Per IE Bulletin 79-17 35,000 Metallographic Exam of Failed RCP Stud 8,000 Electrical Equipment Qualification 630,000 Iodine Spiking Issue 30,000 RETS -

40,000 Test RV Surveillance Baseline Samples 36,000 Miscellaneous Analyses for FLCs, etc.

20,000 ATWS 100,000 IE Bulletins 110,000 PTS 250,000 1

Seismic Restraint Modification 4,500,000 ANALYTICAL TOTAL 7,384,500

}

HARDWARE AND ANALYTICAL TOTAL 24,068,785 9

-w.

n

.b

..n

APPENDIX B (b)

COSTS FOR NRC TMI LESSONS LEARNED BACKFITTING - DETAIL 1.

HARDWARE 1658 Direct Indication of Position of Power Operated Relief Valves and Press. Safety Relief Valve 83,012 l

1665 Auxiliary Feedwater Automatic Actuation System 1,307,030 1761 Instrumentation for Detection of Inadequate Core Cooli ng 142,344 1776 Onsite Technical Support Center 1,723,608 1817 Pre:surizer Heaters 35,732 1906 Increase Range on Radiation Monitoring 274,417 1919 Containment Pressure Indication 49,848 1921 Containment Hydrogen Monitoring 176,416 1967 Improved Sampling System 186,949 1990 Plant Shielding 219,541 1999 Reactor Coolant System Ventilatior.

181,041 2004 Containnent Sump Water Level Indication 329,460 2008 Auxiliary Feedwater Flow Indication 10,478 2009 Eng. Feedwater Tank Level Indication 9,478 2552 Emergency Response Facilities Computer Systen 2,681,690 2300 Dedicated Penetrations for External Recombiner

~

on H2 Purge System 31,815 2389 Telephone Conduit Cable Additives 50,368 I

2418 Control Room Modification 68,405 2502 HVAC System in Technical Support Center 19,285 2530 Core Cooling Differential System 3,370,450 2756 Replace Unqualified Charge Converters for Valve Monitoring 11,384

~

1900 OH TMI 3,452,351 4

2458 EOF Buildi ng N.0.

348,705 HARDWARE TOTAL 14,762,807

__.___-1 B

APPENDIX B o

(b)

COSTS FOR NRC TMI LESSONS LEARNED BACKFITTING - DETAIL

.a 2.

ANALYTICAL EPRI Safety / Relief Valve Test Program 415,000 CE Owners Group Subcommittee - S/R Valves 85,000 Emergency Planning 40,000 Meteorological Analyses - Class A and B Model 100,000 Post TMI Lessons Learned 1,500,000 Auto AFW 280,000 ANALYTICAL TOTAL 2,420,000 HARDWARE AND ANALYTICAL TOTAL 17,182,807

(

d J

0 L

m 4

e e

4 J

. i.

8 G

6 B-2

APPENDIX C (c)

COSTS FOR UTILITY INITIATED BACKFITTING - DETAIL 1.

HARDWARE 222 Air Supply to AC/RW Interface Valves 82,515 l

4 219 Replace Tube Bundle for Waste Evaporator 50,920 218 Reactor Coolant Level Ind. During Cold Shutdown 7,033 217 Shielding for Primary Sampling Room 49,907 212 SIRWT Level Ras Switches 5,518 j

208 Relocation of Oren Radiation Monitors 5,469 o

207 Chemical Lagoon Discharge Monitoring Inst.

7,668 i

2869 Camponent Cooling Drain Valves 526 i

2868 Personnel Air Lock Door 30,050 2867 Shutdown Cooling System 128,331 2832 Operational Interface Between HE2 and FH-12 5,682 2813 Atcor Radiation Waste Solidification System Startup 14,513 2793 Upstream Deflection Wall to Intake Structure 320,768 2792 Underwater T.V. Camera for Refueling Machine 48,908 2773 Outage ' Scheduling Roam 48,549 i

2772 Outlet Manholes in Chemical Lagoons 18,590 i

t 2771 Upgrade Access Roadand Storage Site for UF6 Fuel 32,139 i

2769 Battery Discharge Test Equipment 4,274 2747 Long CEA Handling Tool 59,476 2741 Steam Generator Instrument Root Valves 56,716

?.582 Replace Reactor Pressure Vessel Head and Seismic Skirt Insulation 249,454 2680 Reallocation of Laboratory Space 16,181 l

2669 Replacement of Feedwiter Regulator Valve 3,939 2620 Condensate Recirculation Valves 60,649 2533 Raw Water Systems Piping Erosion 33 2514 FW-8 Corrosion 58,025 5

r1

+

+w<-

y

APPENDIX C (c)

COSTS FOR UTILITY INITIATED BACKFITTING - DETAIL (Continued) 1.

HARDWARE (Continued) 2513 Installation of Platfonn for Contaiment Vents 16,388 2493 Build Gas Bottle Storage Dock 44,055 2460 Replace LCV-1199 for Heater Drains 14,434 2446 Emergency Feedwater Storage Tank Drain Valve 196 2440 Refueling Machine Grapple 15,270 2416 Isolation Valves for TCV 2897A; TCV 28978 58,686 o

2500 Remodel Health Physics Station 19,206 2424 Additional Offices 8,974

~

2456 Doorway Between Room's 45 and 46 443 2925 Construction of Sewage Lagoons 144,116 2027 N2 Purge of R.C.D.L.T. and Quench Tank Mod.

1.402 1985 Engineering and Parts for Main Stea' Valves 70,536 1993 Reactor Internals Holddown - Ring 82,602 2059 Level Transmitter Spent Resin 582 2817 Installation of an Isolation Valve to Presediment Desludge Line 147 2139 Condensate Tank Level Indication 3,273 2825 Install Retaining Rings on Condensate Pumps 51,678 2911 Hy 73 Approx. 3N of F.C. Rearrange Sec. for OPPD Crop Dryer 203 2412 Security Surveillance System 1,997 2919 underground Lawn Sprinkler 11.419 2798 Shielding Wall for CVCS Letdown Line 5,257 581 Replace Existing Flexible Duct Between VA63 and VA64 with Rigid Type 11 2970 Removable Handrail Around Reactor Pit 2,758 2500 Remodel Health Physics Changes 1,488 626 Hy 73 at F.C.P. Supply 3 No.14 W 0/S No.14 So. Street Light.

2,317 2568 Emergency Lighting for Lab and Locker Room 3,829 r?

APPENDIX C

.l (c)

COSTS FOR UTILITY INITIATED BACKFITTING - DETAIL (C'ntinued) j 1.

HARDWARE (Continued) g 583 Air Conditioning of Switchgear Room 23,657

[

2340 Ventilating Discharge Dew-Point Level 2,631 l

2448 Extend Ductwork in Switchgear Room 5,090 j

b 2576 Installation of Condenser Evacuation Pump Seal Water Overflow Piping 1,163

[

[o 2351 Rod Block Circuitry and Metroscope 12,709 i

1154 Containnent Sump Modification 763

[

I u

l 1152 Underwater Television System 21,930 l

I I

1108 Addition of Generator Condition Monitor 21,688 j

1107 Restrooms for Fort Calhoun Warehouse 22,371 e

f 1085 Storage Container 21.059 f

f 1043 Install Platfoms Above Condenser Water Box 16,855 1042 Relief Valye Modification on Diesel Generator No. 2 442 1041 Dual Volts Hertz Overexcitation Protection System 9,584 1037 Surveillance Capsule Removal 14.189 1016 Replace Valves HCV-2861 in Raw Water Systen 9,314 1013 Emergency Feedwater Tank Ladder Installation 2,014 1011 Alterrex De-Excitation Circuitry 5,021 995 River Temperature Indication 12,128 944 Install Jib Crane Turbine Building Deck Area 2,462 925 Control Room A/C 3,584 902 Radiation Monitor Administrative Control 6,668 791 Installation of Sigma-II Camputer 171,963 783 Flange Installation on Flow Element Section of Feed-water 43,551 738 Plastic-Relief Domes in Room 81 9,572 734 Reactor Coolant Pump Mctor Access 10,735 72'4 Modification of Pressure Transmitter for EHC 23,867 719 Storage Bracket for Long Tool FH6 '

4,285'

.. -...... -. e 1

..........- ~.

~

~

APPENDIX C (c)

COSTS FOR UTILITY INITIATED BACKFITTING - DETAIL (Continued) 1.

HARDWARE (Continued) 705 Safety Injection System Relief Valves 4,604

(

652 Replacement of 2" Piping with 4" Piping in Spent Fuel Pool 6,909 648 Analyze and Provide Additional Sup. for Existing Seismic Restraints 16,273 t

1640 I and C Shop Modification 6,502 1631 Jib Crane in Containment for CEDM Removal 40,356 1608 Replacement of Main Steam Line Penetration Bellows 10,478 1592 PORY Piping Restraints 54,904 i

1587 Modify Old Maintenance Shop 6,456 1570 Replacement of Station Batteries and Relocation of Security System Batteries 190,070 1567 Steam Generator Feedwater Bypass Control 4,572 1566 Modification to Spent Fuel Handling Machine 8,400 1537 CEDM Cooling Systen 2,655 1533 Safety Inspection Piping RES 2,299 1518 Installation of Raw Water Pump Seismic Support 11,620 1517 Installation of Cooling Fans in House Ser. Transformer 3,171 1507 Steam Generator Blowdown Processing Systen 2,093,560 1506 Steam Generator Blowdown Control 11,113 1486 Access Platfom for MS 308 1,,07.8 1452 Magnetic Unit Platfonns 9,693 1425 Spent Fuel Pool RT1 and Recorder 14,600 1343 Outdoor Radwaste Storage 1,263 1209 Steam Generator Handrails 2,002 1208 3rd AT Channel on Weather Tower 2,146 1206 Emergency Modification FC-78-65 1,859 1178 Flowmeters for Radiation Monitors 5,562 Turbine Bearing Metal 'emperature Thennocouple T

1171 Recorder 4,333 C-4

-^

APPENDIX C (c)

COSTS FOR UTILITY INITIATED BACKFITTING - DETAIL (Continued) 1.

HARDWARE (Continued) 2388 RCP No. 3C Vibration 18,636 2385 Replace Containment Sump Pumps 54,717 2384 Soil Erosion Control 46,604 2367 ENC Servo Valve Isolation 23,157 2335 Chemical Discharge Lagoon Recirculation Pump 10,670 2257 FCV 102 - 1 and 2 Power Operated Relief Valve o

Field Conver.

21,957 2218 Storage Deck 19,247 2064 Stretch Power Rating for Fort Calhoun 590,073 2049 Actuator for HCV 712A 11,531 2046 RPS Matrix Logic Relay Replacement 21,173 2030 Seal Water Modification for Circulating and Raw Water Pumps 123,959 2010 Raw Water Isolation Valve Replacement 653,028 1944 Maintenance Shop Sprinkler System 2,348 1907 Mine Spray Valves 2,574 1890 Installation of Steam Dump and Bypass Valve Position Indicator 8,112 1836 Reactor Coolant Pump RC-3C Seal / Cooling Water Piping Vibration 2,495 1824 Main Feedwater Pump Recirculation Valve 95,188 1666 Chemical Pond Design Modification 18,665 1650 Secondary Plant Sampling System 19,947 1646 Emergency Alarm for Computer Room 529 1642 Roan 31 Alternate Egress 15,401 o

638 Add Welding Receptacles in Turbine Room.

7,612 637 Modification to the Handholes and Manways of Steam Generators A and B 9,050 633 Construct Maintenance Shop Addition 886,769 609 Radiation Dose Rates from Containment _ Basement Sump 29,792 C-5 9 -

APPENDIX C (c)

COSTS FOR UTILITY INITIATED BACKFITTING - DETAIL (Continued) 1.

HARDWARE (Continued),

487 RPS Computer Output Modifications 7,576 477 Waste Processing i.aundry Waste 6,104 435 Installat16n of Charcoal Filter Operating Timers 667 l

434 Concentrated Boric Acid Tank Level Indication 3,182 i

4 31 Replacement of Component Cooling Heat Exchanger Raw Water Inlet and Outlet 101,049 423 Relocation of Radiation Roam 059 7,847 324 Modification to the Charging System 183,482 312 Structural Steel and Grating Around Hign Pressure Section of Turbine 8,999 4

311 Installed a Recirculation Line to Clarifier Softner and Presedimentation 687 307 Modification to Feedwater Heater Pipe Supports 1,478 306 Steam Lead Drain Valve Circuit Modification 3.283 1'

302 Local Controls and High Level Alann Indication 2,541 295 Construct Cafeteria Storage Room 6,134 278 Installation of Surge Arrestors on 4160/480 V Dry Type Transformer

$4,607 274 Purchase of Salt and Sand Spreader OPPD No. 9788 1,268 238 Main Generator Phase Connection Modification 18,011 228 Modification of Chemical Waste Lagoon System 4,127 226 Modify Heater and Moisture Separator Pumps 13,139 224 Containnent Sump Level Instrumentation 3,638.

HARDWARE TOTAL 8,043,926 1

C-6

==

+a*--d w

ss

. L,,

APPENDIX C (c)

COSTS FOR UTILITY INITIATED BACKFITTING - DETAIL 2.

-ANALYTICAL Physics Uncertainty Analysis 50,000 Guide Tube Wear Inspections 30,000 Stretch Power Studies and Support 730,000 Incore Detector Interim Tech. Spec.

50,000 FSAR 50,000 CEA Inspections 130,000 CVCS Bypass Analysis 3,500 QA Program Evaluation 7,000 Mr.in Steam Vibration Analysis 60,000 Equipment Hatch Shielding Analysis 5,000 Replacement Spent Fuel Storage Rack Analysis 5,000 ANALYTICAL TOTAL 1.120,500 HARDWARE AND ANALYTICAL TOTAL 9,164,426 1

h n

I 4

i l

t

(*7. - _. _ -.

..L

-4

APPENDIX D (d)

ESTIMATE NRC FUTURE BACKFITTING COST Seismic Analysis Evaluation and Modifications 2,150,000 Seismic Qualification of Mechanical Equipment 1,500,000 Mechanical Qualification of Mechanical Equipment for LOCA 1,500,000 Third Auxiliary Feedwater Pump 350,000 Systematic Evalution Plan 3,000,000 Qualification of Backup Contaimient Instrumentation 481,000 Long Tenn Core Cooling 115,000 Modifications of PORV and Safety Valve Piping 100,000 Chemical Detection System / Control Room Habitability 622,000 Additional Spent Fuel Storage 1,857,000 Radioactive Waste Processing System 1,130,000 Procure and Install Emergency Response Facility Camputer 725,000 Purchase of Simulator 2,500,000 P.T.S.

2,500,000

_ ATWS 3,500,000 TOTAL COST 22,030,000

'N 4

9 9

e 1

4 0-1

--