Forwards 10th Edition of Integrated Implementation Schedule (Iis) for Songs,Units 2 & 3.Preliminary Cycle 9 Scope of Work Still Being Developed & Should Be Included in 11th Edition of IIs
ML20070E066
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 07/11/1994
From: Marsh W
SOUTHERN CALIFORNIA EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9407140042
Download: ML20070E066 (18)


Text

_

,,~[y Southem Califomia Edison Company 23 PAf tKEH STREET IRVINE. CALIF OHNIA 92718 July 11, 1994

,m,.m,.

WAW H CMARSH n,.u.uun,-, u.,,n,a w,,n w ~,,,

u,, m.m U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D. C.

20555 Gentlemen:

Subject:

Docket Nos. 50-361 and 50-362 Tenth Edition of the Integrated Implementation Schedule (IIS)

San Onofre Nuclear Generating Station Units 2 and 3

Reference:

Letter from W. C. Marsh (SCE) to Document Control Desk (NRC),

dated February 23, 1994; Ninth Edition of the Integrated Implementation Schedule (IIS).

Enclosures 1 through 3 provide the Tenth Edition of the Integrated Implementation Schedule (IIS) for the San Onofre Nuclear Generating Station (SONGS), Units 2 and 3. updates the Schedule A, B, and C projects Tisted in the Ninth Edition of the IIS (referenced) for SONGS 2 and 3.

Et; closure T. provides the current Schedule A, B, and C projects for SONGS 2 and 3 fo,- Cydes 7 and 8. lists the ongoing evaluations for major issues for SONGS 2 and 3.

The preliminary Cycle 9 scope of work is still being developed.

It should be included in the Eleventh Edition of the IIS.

The Westinghouse Analytical Ranking Program (WARP) was not used to rank the relative safety significance of each Schedule A and B modification because their implementation schedules have been established in separate correspondence.

If you have any questions on the Tenth Edition of the San Onofre Units 2 and 3 IIS, please let me know.

Very truly yours, Ah N Enclosures I '[ L [ [ [

cc:

L. J. Callan, Regional Administrator, NRC Region JV K. E. Perkins, Jr., Director, Walnut Creek Field Office, NRC Region IV J. A. Sloan, NRC Senior Resident Inspector, San Onofre Units 2 & 3 M. B. Fields, NRC Project Manager, San Onofre Units 2 and 3 9407140042 94o711 g

PDR ADOCK 05000361 i

P pgg

1 ENCLOSURE 1 SCHEDULE A, D, AND C UPDATES (9th Edition IIS dated 2/23/94) 1

Ehclosure 1 - 9th Edition IIS Schedule Updates Note: There are no Schedule A items identified at this tinz Schedule B Updates Update Unit Due DCP Description Comments Date Number

~

mmmmmmmmmmmmmmmemammmmmme-m-COMPLETE 2

4/29/94 6605.09 Control Room 61 Panel Modifications No Change 2

Cycle 8 6910.00 Upgrade Target Rock Generic Letter 91-15 Solenoid Valves No Change 2

Cycle 8 6988.00 Addition of Valves Generic Letter 89-04 and Drains for In Service Test Note 1 2

Cycle 8 6989.00 Annunciator Alarms Licensee Event for Containment Report 3-90-010 Emergency Sump Isolation Valves No Change 2

Cycle 8 6999.00 Intake Structure SCE to NRC letters Security Barriers February 12, 1993 and July 15, 1993 Schedule 2

Cycle 8 2060.00 Degraded Grid PCN 429 submittal Change C to Voltage to NRC September B

30,1993 COMPLETE 3

4/29/94 6605.09 Control Room 61 Panel Modifications

I I

\\

Schedule B Updates 4.4.

Update Unit Due DCP Description Comments Date Number um mmmmmmmum No Change 3

Cycle 8 6910.00 Upgrade Target Rock Generic Letter 91-15 Solenoid Valves No Change 3

Cycle 8 6988.00 Addition of Valves Generic Letter 89-04 and Drains for In Service Test i

Note 1 3

Cycle 8 6989.00 Annunciator Alarms Licensee Event for Containment Report 3-90-010 Emergency Sump Isolation Valves No Change 3

Cycle 8 6999.00 Intake Structure SCE to NRC letters Security Barriers February 12, 1993 and July 15, 1993 Note 1: Capital funding will not be used to implement this modification. Therefore, this item will no longer be included in the Integrated Implementation Schedule.

i i

Schedule C Updates Update Unit Due DCP Description Date Number ADD N/A Cycle 8 2066.00 Emergency Operations Facility Diesel Modification No Change 2

Cycle 7 6191.00 Turbine Building Sump Radiation Monitor Low Flow Alarms ADD 2

Cycle 7 6605.08 Control Room Human Factors COMPLETE 2

Cycle 7 6697.00 Safety Injection System Pipe Vent Relocation FROM CYCLE 2

Cycle 7 6716.00 Modify Plant Monitoring System and Core 7 TO CYCLE 8 Operating Limit Supervisory System Back-up Computer System ADD 2

Cycle 7 6742.07 Component Cooling Water Seismic Makeup COMPLETE 2

Cycle 7 6751.00 Post Accident Sampling System Skid l

Enhancements No Change 2

Cycle 7 6888.00 Modify 90-minute Emergency Control Room Lighting Battery Backup 1

i COMPLETE 2

Cycle 7 6891.00 Install Oxygen Monitor in the Full Flow Condensate Polisher Demineralizer Lab No Change 2

Cycle 8 2005.00 In-containment Post Accident Monitoring Instrumentation Improvements ADD 2

Cycle 8 2012.00 F020 Filter Replacement No Change 2

Cycle 8 2060.00 Degraded Grid Voltage ADD 2

Cycle 8 2061.00 Component Cooling Water Fuses i

L

Schedule C Updates i

Update Unit Due DCP Description Lote Number summmmmmmmmmmmmmummummmmmu a

COMPLETE 2

Cycle 8 2062.00 Talega #2 Transmission Line ADD 2

Cycle 8 2063.00 Steam Generator Distribution Box Replacement l

ADD 2

Cycle 8 2067.00 Main Steam Isolation Valve Bypass Line l

Modification No Change 2

Cycle 8 6735.03 Ladders and Platforms No Change 2

Cycle 8 6851.00 Replace Loose Parts and Vibration Monitoring System No Change 2

Cycle 8 6855.00 Install Removable Digital Polar Crane Controls No Change 2

Cycle 8 6864.00 Install Removable Refueling Machine Controls No Change 2

Cycle 8 6876.00 Containment Purge and Plant Vent Stack Radiation Monitor CANCELLED 2

Cycle 8 6877.00 T-121 Nitrogen Blanket System No Change 2

Cycle 8 6885.00 Replace Turbine Plant Secondary System Chemistry Instrumentation Note 1 2

Cycle 8 6908.00 CRA 44 Card Replacement No Change 2

Cycle 8 6914.00 Turbine Governor Valve Modifications No Change 2

Cycle 8 6926.00 Replace Nunclear Monitoring Corportion Radiation Monitors No Change C

Cycle 8 6933.00 Toxic Gas Isolation System Instrument Replacement l

l

8 Schedule C Updates Update Unit Due DCP Description Date Number CANCELLED 2

Cycle 8 6941.00 Reactor Coolant System Vacuum Fill No Change 2

Cycle 8 6946.00 Automatic Voltage Regulator Replacement No Change 2

Cycle 8 6974.00 Load Center Transformer Replacement (Safety Related portion completed)

No Change 2

Cycle 8 6984.00 Ex-core Neutron Detectors No Change 2

Cycle 8 6986.00 Reorient / Replace Component Cooling Water Containment Isolation Valves

-No Change 2

Cycle 8 6990.00 Reactor Coolant Pump Design Changes No Change C

Cycle 8 7032.00 Replace HP1000 Computer and Mateorological Equipment Enclosure No Change C

Cycle 8 7034.00 Replace High Flow Makeup Demineralizer Chemistry Analyzers ADD 3

Cycle 7 6605.08 Control Room Human Factors No Change 3

Cycle 7 6191.00 Turbine Building Sump Radiation Monitor Low Flow Alarms ADD 3

Cycle 7 6742.07 Component Cooling Water Seismic Makeup FROM CYCLE 3

Cycle 7 6716.00 Modify Plant Monitoring System and Core 7 TO CYCLE 8 Operating Limit Supervisory System Back-up Computer System COMPLETE 3

Cycle 7 6748.00 Temporary Facility Modification Incorporation

Schedule C Updates Update Unit Due DCP Description Date Number nummmmmmmmmmmmmmmmmmmmmm No Change 3

Cycle 7 6888.00 Modify 90-minute Emergency Control Room Lighting Battery Backup COMPLETE 3

Cycle 7 6891.00 Install Oxygen Monitor in the Full Flow Condensate Polisher Demineralizer Lab COMPLETE C

Cycle 7 7018.00 Upgrade Unit 2/3 Fire and Security Monitoring No Change 3

Cycle 8 2005.00 In-containment Post Accident Monitoring Instrumentation Improvements ADD 3

Cycle 8 2012.00 F020 Filter Replacement ADD 3

Cycle 8 2061.00 Component Cooling Water Fuses ADD 3

Cycle 8 2063.00 Steam Generator Distribution Box Replacement ADD 3

Cycle 8 2067.00 Main Steam Isolation Valve Bypass Line Modification No Change 3

Cycle 8 6683.04 Snubber Reductions No Change 3

Cycle 8 6735.03 Ladders and Platforms No Change 3

Cycle 8 6851.00 Replace Loose Parts and Vibration Monitoring System No Change 3

Cycle 8 6855.00 Install Removable Digital Polar Crane Controls No Change 3

Cycle 8 6864.00 Install Removable Refueling Machine Controls

Schedule C Updates Update Unit Due DCP Description Date Number summmmmmmmmmmmmmmmmmmum No Change 3

Cycle 8 6876.00 Containment Purge and Plant Vent Stack Radiation Monitor CANCELLED 3

Cycle 8 6877.00 T-121 Nitrogen Blanket System No Change 3

Cycle 8 6885.00 Replace Turbine Plant Secondary System Chemistry Instrumentation No Change 3

Cycle 8 6914.00 Turbine Governor Valve Modifications No Change 3

Cycle 8 6926.00 Replace Nuclear Monitoring Corporation Radiation Monitors CANCELLED 3

Cycle 8 6941.00 Reactor Cooling System Vacuum Fill No Change 3

Cycle 8 6946.00 Automatic Voltage Regulator Replacement No Change 3

Cycle 8 6963.00 Replace Circ Water Delta T Data Logger No Change 3

Cycle 8 6974.00 Load Center Transformer Replacement Note 1 3

Cycle 8 6977.00 Seismic Joint Repair No Change 3

Cycle 8 6984.00 Ex-core Neutron Detectors No Change 3

Cycle 8 6986.00 Reorient / Replace Component Cooling Water Containment Isolation Valves No Change 3

Cycle 8 6990.00 Reactor Coolant Pump Design Changes Note 1:

Capital funding will not be used to implement this modification. Therefore, this item will no longer be included in the Integrated Implementation Schedule

4 u

S l

ENCLOSL~RE 2 TENTH EDITION IIS (SONGS 2 AND 3) 1 i

l

SONGS 2&3 Integrated Implementation Schedule Tenth Edition Schedule A Unit Description 2

There are no Schedule A items identified at this time 3

There are no Schedule A items identified at this time Schedule B Unit Due DCP Description Comments Date Number 2

Cycle 8 6910 Upgrade Target Rock Solenoid Generic Letter 91-15 Vahes 2

Cycle 8 6988 Addition of Valves and Drains Generic Letter 89-04 for In-Service Test 2

Cycle 8 6999 Intake Structure Security SCE to NRC letters Bar.iers February 12,1993 and July 15, 1993 2

Cycle 8 2060.00 Degraded Grid Voltage PCN 429 submitted to NRC j

September 30,1993 j

Schedule B Unit Due DCP Description Comments Date Number 3

Cycle 8 6910 Upgrade Target Rock Solenoid Generic Letter 91-15 Valves i

3 Cycle 8 6988 Addition of Valves and Drains Generic I.etter 89-04 for In-Service Test 3

Cycle 8 6999 Intake Structure Security SCE to NRC letters Barriers February 12,1993 and July 15, 1993 i

Schedule C Unit Due Date DCP Number Description 2

Cycle 7 6191.00 Turbine Building Sump Radiation Monitor Low Flow Alarms 2

Cycle 7 6605.08 Control Room Human Factors 5

2 Cycle 7 6742.07 CCW Seismic Makeup 2

Cycle 7 6888.00 Modify 90-minute Emergency Control Room Lighting Battery Backup

Schedule C Unit Due Date DCP Number Description sammmmmu-summmmme 2

Cycle 7 6669 Auxiliary Feedwater Overspeed Trip Setpoint (Regulatory portion of this item was completed during Cycle 7 refueling outage) 2 Cycle 8 6683.04 Snubber Reduction N/A Cycle 8 2066.00 EOF Diesel Modification 2

Cycle 8 6716.00 Modify Plant Monitoring System and Core Operating Limit Supervisory System Back-up Computer System 2

Cycle 8 2005.00 In-containment Post Accident Monitoring Instrumentation Improvements 2

Cycle 8 2012.00 F020 Filter Replacement 2

Cycle 8 2061.00 Component Cooling Water Fuses 2

Cycle 8 2063.00 Steam Genera or Distribution Box Replacement 2

Cycle 8 2067.00 Main Steam Isolation Valve Bypass Line Modification 2

Cycle 8 6735.03 Ladders and Platforms 2

Cycle 8 6851.00 Replace Loose Parts and Vibration Monitoring System 2

Cycle 8 6855.00 Install Removable Digital Polar Crane Controls 2

Cycle 8 6864.00 Install Removable Refueling Machine Controls 2

Cycle 8 6876.00 Containment Purge and Plant Vent Stack Radiation Monitor 2

Cycle 8 6885.00 Replace Turbine Plant Secondary System Chemistry Instrumentation r

n -

i Schedule C Unit Due Date DCP Number Description 2

Cycle 8 6914.00 Turbine Governor Valve Modifications 2

Cycle 8 6926.00 Replace Nuclear Monitoring Corporation Radiation Monitors C

Cycle 8 6933.00 Toxic Gas Isolation System Instrument Replacement 2

Cycle 8 6946.00 Automatic Voltage Regulator Replacement 2

Cycle 8 6965.00 Replace Circ Water Delta "T" Inst.

2 Cycle 8 6974.00 Imd Center Transformer Replacement (SR portion completed) 2 Cycle 8 6984.00 Ex-core Neutron Detectors 2

Cycle 8 6986.00 Reorient / Replace Component Cooling Water Containment Isolation Valves 2

Cycle 8 6990.00 Reactor Coolant Pump Design Changes C

Cycle 8 7032.00 Replace HP1000 Computer and Meteorological Equipment Enclosure C

Cycle 8 7034.00 Replace High Flow Makeup Demi.neralizer Chemistry Analyzers 3

Cycle 7 6605.08 Control Room Human Factors 3

Cycle 7 6191.00 Turbine Building Sump Radiation Monitor Low Flow Alarms 3

Cycle 7 6742.07 Component Cooling Water Seismic Makeup

Schedule C Unit Due Date DCP Number Description 3

Cycle 7 6888.00 Modify 90-minute Emergency Control Room Lighting Battery Backup 3

Cycle 7 6869 Auxiliary Feedwater Overspeed Trip Setpoint (Regulatory portion of this item was completed during Cycle 7 refueling outage) 3 Cycle 8 6683.04 Snubber Reduction 3

Cycle 8 2005.00 In-containment Post Accident Monitoring Instrumentation Improvements 3

Cycle 8 2012.00 F020 Filter Replacement 3

Cycle 8 2061.00 Component Cooling Water Fuses 3

Cycle 8 2063.00 Steam Generator Distribution Box Replacement 3

Cycle 8 2067.00 Main Steam Isolation Valve Bypass Line Modification 3

Cycle 8 6683.04 Snubber Reductions 3

Cycle 8 6716.00 Modify Plant Monitoring System and Core Operating Limit Supervisory System Back-up Computer Systems 3

Cycle 8 6735.03 12dders and Platforms 3

Cycle 8 0851.00 Replace Loose Parts and Vibration Monitoring System 3

Cycle 8 6855.00 Install Removable Digital Polar Crane Controls 3

Cycle 8 6864.00 Install Removable Refueling Machine Controls 3

Cycle 8 6876.00 Containment Purge and Plant Vent Stack Radiation Monitor l

6 I

i Schedule C Unit Due Date DCP Number Description f

1 3

Cycle 8 6885.00 Replace Turbine Plant Secondary System Chemistry Instrumentation 3

Cycle 8 6914.00 Turbine Governor Valve Modifications 3

Cycle 8 6926.00 Replace Nuclear Monitoring Corporation Radiation Monitors 3

Cycle 8 6946.00 Automatic Voltage Regulator Replacement 3

Cycle 8 6963.00 Replace Cire Water delta T Data Logger i

3 Cycle 8 6974.00 Load Center Transformer Replacement 3

Cycle 8 6984.00 Ex-core Neutron Detectors 3

Cycle 8 6986.00 Reorient / Replace Component Cooling Water Containment Isolation Valves 3

Cycle 8 6990.00 Reactor Coolant Pump Design Changes

ENCLOSURE 3 ONGOING EVALUATIONS OF MAJOR ISSUES (SONGS 2 AND 3) i i

ONGOING 5 VALUATIONS OF MAJOR ISSUES (SONGS 2 and 3)

GL 88-20, SUP 4 Individual Plant Examination of External Events (IPEEE), to be completed by 6/01/95.

GL 89-10 The initial safety related Motor Operated Valve (MOV) Testing and Surveil'sace will be completed for Units 2 and 3 by the end of their respective Cycle 8 refueling outages. Periodic verifications of MOV operability will follow.