MONTHYEARCNL-19-066, Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis, (TS-19-02)2020-01-14014 January 2020 Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis, (TS-19-02) Project stage: Request ML20049A0322020-02-13013 February 2020 NRR E-mail Capture - SQN Hydrologic Analysis LAR Acceptance Review - L-2020-LLA-0004 Project stage: Acceptance Review CNL-20-026, Supplement to Application to Revise Sequoyah Nuclear Plant Units 1 and 2 Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis, (TS-19-02)2020-02-18018 February 2020 Supplement to Application to Revise Sequoyah Nuclear Plant Units 1 and 2 Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis, (TS-19-02) Project stage: Supplement ML20054B5532020-02-20020 February 2020 NRR E-mail Capture - Sequoyah Nuclear Plant, Units 1 and 2 - Acceptance of License Amendment Request to Modify the UFSAR Based on a New Hydrologic Analysis Project stage: Acceptance Review ML20106F1042020-04-14014 April 2020 Request for Additional Information Regarding the Hydrologic Analysis LAR Project stage: RAI CNL-20-032, Response to Request for Additional Information (TS-19-02) Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis2020-05-14014 May 2020 Response to Request for Additional Information (TS-19-02) Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis Project stage: Response to RAI ML20141L7672020-05-28028 May 2020 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML20189A2112020-07-0101 July 2020 Request for Additional Information Regarding Hydrologic UFSAR Update Project stage: RAI ML20196L6892020-07-16016 July 2020 TVA Non-Proprietary Slides for Open Session of July 16, 2020, Partially Closed Public Meeting to Discuss Sequoyah License Amendment Request Project stage: Meeting ML20203M0572020-07-16016 July 2020 Updated TVA Non-Proprietary Slides for Open Session of July 16, 2020, Partially Closed Public Meeting to Discuss Sequoyah License Amendment Request Project stage: Meeting ML20196L7922020-07-16016 July 2020 Corrected TVA Non-Proprietary Slides for Open Session of July 16, 2020, Partially Closed Public Meeting to Discuss Sequoyah License Amendment Request Project stage: Meeting ML20203M2292020-08-11011 August 2020 July 16, 2020, Summary of Partially Closed Meeting with Tennessee Valley Authority to Discuss Responses to Requests for Additional Information Regarding Updated Final Safety Analysis Report Hydrologic Analysis License Amendment Request Project stage: RAI CNL-20-057, Tennessee Valley Authority - Application to Revise Sequoyah Nuclear Plant Units 1 & 2 Updated FSAR Changes to Hydrologic Analysis - Partial Response to Additional Request for Additional Information (TS-19-02)2020-08-12012 August 2020 Tennessee Valley Authority - Application to Revise Sequoyah Nuclear Plant Units 1 & 2 Updated FSAR Changes to Hydrologic Analysis - Partial Response to Additional Request for Additional Information (TS-19-02) Project stage: Request ML20261H4162020-09-0202 September 2020 NRR E-mail Capture - Draft Request for Additional Information - Sequoyah Nuclear Plant, Units 1 and 2, Request to Revise UFSAR Hydrologic Analysis Project stage: Draft RAI ML20261H4172020-09-14014 September 2020 NRR E-mail Capture - Sequoyah Nuclear Plant, Units 1 and 2 - Request for Additional Information Regarding Hydrologic UFSAR Update Project stage: RAI ML20261H4182020-09-14014 September 2020 NRR E-mail Capture - Sequoyah Nuclear Plant, Units 1 and 2 - Audit Plan and Setup of Online Reference Portal Project stage: Other ML20293A0802020-10-28028 October 2020 Summary of October 13, 2020, Closed Meeting with TVA on Responses to Requests for Additional Information Updated Final Safety Analysis Report Hydrologic Analysis License Amendment Request Project stage: RAI ML20316A0182020-11-10010 November 2020 NRR E-mail Capture - Sequoyah Nuclear Plant, Units 1 and 2 - Audit Plan and Setup of Online Reference Portal Project stage: Other CNL-20-082, Partial Response to Request for Additional Information Regarding Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis (TS-19-02)2020-11-10010 November 2020 Partial Response to Request for Additional Information Regarding Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis (TS-19-02) Project stage: Response to RAI ML20343A1182021-01-12012 January 2021 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML21068A4082021-03-0909 March 2021 NRR E-mail Capture - Sequoyah Nuclear Plant, Units 1 and 2 - Supplement 2 to Audit Plan and Setup of Online Reference Portal Project stage: Other CNL-21-024, Partial Response to Additional Request for Information Re Application to Revise Updated Final Safety Analysis Report Re Changes to Hydrologic Analysis (TS-19-02)2021-06-15015 June 2021 Partial Response to Additional Request for Information Re Application to Revise Updated Final Safety Analysis Report Re Changes to Hydrologic Analysis (TS-19-02) Project stage: Request ML21239A1152021-08-13013 August 2021 Partial Response to Additional Request for Additional Information, (Question 2) Regarding Application to Revise Sequoyah Nuclear Plant, Units 1 and 2 Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis - Correction Project stage: Request CNL-21-095, Submittal of Application to Revise Sequoyah Nuclear Plant, Units 1 and 2, 10 CFR 50.90 Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis - Software Dedication Report 16-01 - Update .2021-12-21021 December 2021 Submittal of Application to Revise Sequoyah Nuclear Plant, Units 1 and 2, 10 CFR 50.90 Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis - Software Dedication Report 16-01 - Update . Project stage: Request CNL-23-012, Revision to the Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis, (TS-19-02)2023-04-11011 April 2023 Revision to the Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis, (TS-19-02) Project stage: Request ML24039A0792024-02-12012 February 2024 – Summary of Regulatory Audit Regarding the License Amendment Request for Hydrologic Analysis Changes to the Updated Final Safety Analysis Report (EPID L-2020-LLA-0004) - Public Project stage: Other ML24074A4252024-03-14014 March 2024 NRR E-mail Capture - Sequoyah Hydrologic Analysis License Amendment Request - Notification of Change to Estimated Completion and Hours Project stage: Other ML24040A2062024-03-26026 March 2024 Issuance of Amendment Nos. 367 and 361 Regarding Changes to the Hydrologic Analyses (EPID L-2020-LLA-0004) - Public Project stage: Approval 2020-08-11
[Table View] |
Text
Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-20-026 February 18, 2020 10 CFR 50.90 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Sequoyah Nuclear Plant, Units 1 and 2 Renewed Facility License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328
Subject:
Supplement to Application to Revise Sequoyah Nuclear Plant Units 1 and 2 Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis, (TS-19-02) (EPID L-2020-LLA-0004)
References:
- 1. TVA Letter to NRC, CNL-19-066, "Application to Revise Sequoyah Nuclear Plant Units 1 and 2 Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis (TS-19-02), dated January 14, 2020 (ML20016A396 and ML20016A397)
- 2. NRC Electronic Mail to TVA, SQN Hydrologic Analysis LAR Acceptance Review - L-2020-LLA-0004, dated February 13, 2020 (ML20049A032)
In Reference 1, Tennessee Valley Authority (TVA) submitted a request for an amendment to Renewed Facility Operating License Nos. DPR-77 and DPR-79 for Sequoyah Nuclear Plant (SQN) Units 1 and 2, respectively. This license amendment request (LAR) revises the SQN Units 1 and 2, Updated Final Safety Analysis Report (UFSAR) to reflect the results from the new hydrologic analysis. TVA determined that the proposed changes to the SQN UFSAR require prior Nuclear Regulatory Commission (NRC) approval.
In Reference 2, NRC submitted a request for information to support the NRC acceptance review of the LAR.
Below is the list of the NRC comments and TVAs response:
NRC Comment 1 Information demonstrating that the dedication of the ArcGIS, QGIS, and PMP Evaluation Tools is conducted in accordance with the requirements of 10 CFR Part 21 under either TVAs QA program or a third-partys QA program that is Appendix B to 10 CFR Part 50 compliant.
U.S. Nuclear Regulatory Commission CNL-20-026 Page 2 February 18, 2020 TVA Response The following information supplements the description of the Topical Report Probable Maximum Precipitation (PMP) Evaluation Tool setup in Attachment A to Enclosures 1 and 5 of Reference 1.
The dedication of the PMP Evaluation Tool was performed under the Barge Design Solutions (Barge) Nuclear Quality Assurance (QA) program that complies with 10 CFR 21, 10 CFR 50, Appendix B, ASME NQA-1-2008/2009 Addenda, and Regulatory Guide 1.28, Revision 4. The Barge QA program has been audited and accepted by TVA and is on the TVA Acceptable Supplier List (ASL). The software dedication report (SDR) for the PMP Evaluation Tool, including the use of associated Python scripts, describes the dedication of the PMP Evaluation Tool.
While the ArcGIS and QGIS evaluation tools were not dedicated, the calculations performed using these tools were checked by either hand calculations or using alternative software in accordance with Barge procedures for design calculations and computer program applications, under the Barge QA program, which complies with NQA-1 Part II Subpart 2.7 Paragraph 202 and is consistent with similar TVA process control procedures under the TVA QA Program. The ArcGIS software functions that are outside of the functions included in the PMP Evaluation Tool SDR, as noted above, were checked using QGIS as the alternate software in accordance with NQA-1 Part II Subpart 2.7 Paragraph 202 under the Barge QA Program. Additional information is provided in the Gridded PMP Development calculation and the SDR, which are available for NRC review.
NRC Comment 2 Information stating that the Microsoft Excel workbook template and the Python scripts for GIS processing of gridded precipitation data were developed under TVAs QA program.
TVA Response As noted in the response to NRC Comment 1, the PMP Evaluation Tool includes the use of associated Python scripts. Therefore, the response to NRC comment 1, regarding the development of the PMP Evaluation Tool under the Barge QA program, also applies to the Python scripts for GIS processing of gridded precipitation data that were used within the PMP Evaluation Tool.
There are portions of the Python scripting that were outside of the PMP Evaluation Tool, but inside a GIS software. While the Microsoft Excel workbook and those portions of the Python scripting that were outside of the PMP Evaluation Tool were not dedicated, their associated calculations were checked by either hand calculations or using alternative software as discussed in the response to NRC Comment 1. Additional information is provided in the Gridded PMP Development calculation and the SDR, which are available for NRC review.
U.S. Nuclear Regulatory Commission CNL-20-026 Page 3 February 18, 2020 This letter does not change the no significant hazard considerations nor the environmental considerations contained in Reference 1. Additionally, in accordance with 10 CFR 50.91(b)(1),
WA is sending a copy of this letter and the enclosure to the Tennessee Department of Environment and Conservation.
Please address any questions regarding this request to Kimberly D. Hulvey, Fleet Licensing Manager, at 423-751-3275. There are no new regulatory commitments contained in this submittal.
I declare under penalty of perjury that the foregoing is true and correct. Executed on this 181h day of February 2020.
Respectfully,
- 1. Polickoski Director, Nuclear Regulatory Affairs cc: