05000327/LER-2019-004, Automatic Actuation of Emergency Diesel Generators Due to Loss of Power to 6.9kV Shutdown Board

From kanterella
(Redirected from ML20044D623)
Jump to navigation Jump to search
Automatic Actuation of Emergency Diesel Generators Due to Loss of Power to 6.9kV Shutdown Board
ML20044D623
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 02/13/2020
From: Rasmussen M
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LER 2019-004-00
Download: ML20044D623 (7)


LER-2019-004, Automatic Actuation of Emergency Diesel Generators Due to Loss of Power to 6.9kV Shutdown Board
Event date:
Report date:
Reporting criterion: 10 CFR 50.73(a)(2)(iv)(A), System Actuation

10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded

10 CFR 50.73(a)(2)(viii)(A)

10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition

10 CFR 50.73(a)(2)(viii)(B)

10 CFR 50.73(a)(2)(iii)

10 CFR 50.73(a)(2)(ix)(A)

10 CFR 50.73(a)(2)(x)

10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor

10 CFR 50.73(a)(2)(v), Loss of Safety Function

10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown

10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications

10 CFR 50.73(a)(2)(vii), Common Cause Inoperability

10 CFR 50.73(a)(2)(i)
3272019004R00 - NRC Website

text

Tennessee Valley Authority, Sequoyah Nuclear Plant, P.O. Box 2000, Soddy Daisy, Tennessee 37384 February 13, 2020 10CFR 50.73 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Sequoyah Nuclear Plant, Units 1 and 2 Renewed Facility Operating License No. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328 Licensee Event Report 50-327 and 50-328/2019-004-00, Automatic Actuation of Emergency Diesel Generators Due to Loss of Power to 6.9kV Shutdown Board

Subject:

The enclosed licensee event report provides details concerning an automatic actuation of the four emergency diesel generators as a result of the loss of power to a 6.9kV shutdown board.

This report is being submitted in accordance with 10 CFR 50.73(a)(2)(iv)(A), as any event or condition that resulted in manual or automatic actuation of emergency AC electrical power systems, including emergency diesel generators.

There are no regulatory commitments contained in this letter. Should you have any questions concerning this submittal, please contact Mr. Jeffrey Sowa, Site Licensing Manager, at (423) 843-8129.

Respectfully Matthew Rasmussen Site Vice President Sequoyah Nuclear Plant Enclosure: Licensee Event Report 50-327/2019-004-00 NRC Regional Administrator -

Region II NRC Senior Resident Inspector -

Sequoyah Nuclear Plant cc:

printed on recycled paper

NRC FORM 366 (04-2018)

U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0104 EXPIRES: 03/31/2020

, the NRC may not conduct or sponsor, and a person is not required to respond to. the informa ion collection.

2. Docket Number 05000327
3. Page 1 OF 6 LICENSEE EVENT REPORT (LER)

(See Page 2 for required number of digits/characters for each block)

(See NUREG-1022, R.3 for instruction and guidance for completing this form httD://wwvv.nrc.aov/readina-rm/doc-collections/nureas/staff/sr1022/r3/)

1. Facility Name Sequoyah Nuclear Plant Unit 1
4. Titie Automatic Actuation of Emergency Diesel Generators Due tp Loss of Power to 6.9KV Shutdown Board
5. Event Date
8. Other Facilities Involved
6. LER Number
7. Report Date Facility Name Sequoyah Nuclear Plant Unit 2 Docket Number Sequential Number Rev Month Day Year Year Month Day Year No.

05000328 Facility Name Docket Number 12 16 2019 2019 004 00 02 13 2020 05000 NA

9. Operating Mode 11 n This Report is Submitted Pursuant to the Requirements of 10 CFR §: (Check all that apply) 20.2201(b) 20.2203(a)(3)(i) 50.73(a)(2)(ii)(A) 50.73(a)(2)(viii)(A) 1 20.2201(d) 20.2203(a)(3)(ii) 50.73(a)(2)(ii)(B) 50.73(a)(2)(viii)(B) 20.2203(a)(1) 20.2203(a)(4) 50.73(a)(2)(iii) 50.73(a)(2)(ix)(A) 20.2203(a)(2)(i) 50.36(0(1 )(i)(A) 50.73(a)(2)(iv)(A) 50.73(a)(2)(x) 20.2203(a)(2)(ii) 50.36(0(1 )(ii)(A) 73.71(a)(4) 50.73(a)(2)(v)(A)
10. Power Level 20.2203(a)(2)(iii) 50.36(0(2) 50,73(a)(2)(v)(B) 73.71(a)(5) 100 20.2203(a)(2)(iv) 50.46(a)(3)(ii) 50.73(a)(2)(v)(C) 73.77(a)(1) 20,2203(a)(2)(v) 50.73(a)(2)(i)(A) 50.73(a)(2)(v)(D) 73.77(a)(2)(ii) 20.2203(a)(2)(vi) 50.73(a)(2)(i)(B) 50.73(a)(2)(vii) 73.77(a)(2)(iii) 50.73(a)(2)(i)(C)

Other (Specify in Abstract below or in NRC Form 366A)

12. Licensee Contact for this LER

.icensee Contact Telephone Number (Include Area Code)

[Andrew McNeil 423-843-8098

13. Complete One Une tor each Component Failure Described in this Report

Cause

System Component Manufacturer Reportable To ICES

Cause

System Component Manufacturer Reportable To ICES B

EB 51 B455 Y

Month Day Year

14. Supplemental Report Expected
15. Expected Submission Date CH Yes (If yes, complete 15. Expected Submission Date) ^ No Abstract (Limit to 1400 spaces, i.e., approximately 14 single-spaced typewritten lines)

On December 16, 2019, at 03:58 Eastern Standard Time (EST), Sequoyah Nuclear Plant Unit 1 experienced a loss of 1B-B 6.9 kilo-Volt (KV) Shutdown Board offsite power when the normal feeder breaker from the 1C 6.9 KV Unit Board to the 1B-B 6.9 KV Shutdown Board tripped. This resulted in a loss of offsite power to the 1B-B 6.9 KV Shutdown Board, which automatically started all four emergency diesel generators as designed. The 1B-B 6.9 KV Shutdown Board was automatically reenergized from its associated emergency diesel generator, and was subsequently transferred back to an alternate offsite power supply.

The cause of the feeder breaker trip was an overcurrent relay component failure, specifically a metal oxide varistor of the incorrect voltage rating, which actuated the breaker overcurrent protection. The failed relay was replaced with a new relay of the proper voltage rating. An extent of condition will be performed as plant conditions permit to evaluate any other 250 VDC rated applications that may have incorrect voltage components.

NRC FORM 366 (04-2018)

I.

Plant Operating Conditions Before the Event

Sequoyah Nuclear Plant (SQN) Unit 1 was at 100 percent Rated Thermal Power (RTP). SON Unit 2 was at 47 percent RTP conducting start-up and power ascension activities following a reactor trip on December 12, 2019.

Description of Event

A.

Event Summary; On December 16, 2019, at 0358 Eastern Standard Time (EST), SQN Unit 1 experienced a loss of 1B-B 6.9 kilo-Volt (KV) Shutdown Board (SDBD)

[EIIS; ECBD] offsite power when the non-safety related normal feeder breaker [EIIS; BKR, 52] from the 1C 6.9 KV Unit Board to the 1B-B 6.9 KV SDBD tripped. Loss of offsite power to the 1B-B SDBD automatically started all four emergency diesel generators (EDGs)

[EIIS; DG] as designed.

The 1B-B KV SDBD was automatically energized from the 1B-B 6.9 KV Diesel Generator.

All required 6.9 KV loads were sequenced back on to the 1B-B 6.9 KV SDBD as designed after the board was reenergized. The rest of the electrical system remained in a normal alignment.

A Preventative Maintenance (PM) activity on 250 Volts-Direct Current (VDC) Station Battery #1 [EIIS; BTRY] was in progress at the time of the event. During the performance of the PM activity, 250 VDC Station Battery #1 was placed on an equalizing charge with the battery in service. Upon initiation of the battery charge, the voltage rose to approximately 300 VDC and was adjusted down to 280 VDC.

The 300 VDC experienced on the 250 VDC system [EIS; El] was high enough to damage the installed Asea Brown Boveri (ABB) GR-5 Relay used in the 1722 Breaker 51G [EIIS; 51] location, causing the breaker to trip open. During post-transient investigation, it was discovered that although the relay was marked appropriately as a 250 VDC model, it had the wrong voltage rated metal oxide varistor (described from this point as varistor) installed. The installed varistors were 150 VDC rated components and were original to the relay from manufacturing, prior to its installation in 2014.

An 8-hour non-emergency event notification (EN 54446) was completed on December 16, 2019 at 0912 EST. This event is reportable in accordance with 10 CFR 50.73(a)(2)(iv)(A) as any event or condition that resulted in manual or automatic actuation of emergency AC electrical power systems, including EDGs.

Page 2 of 6(04-2018)

U.S. NUCLEAR REGULATORY COMMISSION EXPIRES; 03/31/2020 APPROVED BY 0MB: NO. 3150-0104

, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.

LICENSEE EVENT REPORT (LER)

CONTINUATION SHEET

3. LER NUMBER SEQUENTIAL NUMBER REV YEAR Sequoyah Nuclear Plant Unit 1 05000-327 NO.
- 00 2019
- 004 B.

Status of structures, components, or systems that were inoperable at the start of the event and contributed to the event:

No inoperable structures, components, or systems contributed to this event.

C.

Dates and approximate times of occurrences

Date/Time (EST)

Description

Defective ABB GR-5 Relay installed Marchs, 2014 December 16, 2019 at 0355 Approximate time of multiple alarms received in Main Control Room indicating a possible electrical malfunction.

Unit 1 1B-B 6.9 KV SDBD experiences a loss-of-offsite power, triggering Engineered Safety Features (ESF) and starting EDGs. 1B-B 6.9 KV SDBD automatically energized from the 1B-B DG.

Main Control Room Operators entered into an abnormal operating procedure for partial loss of offsite power.

1B-B DG disconnected from 1B-B 6.9 KV SDBD, with offsite power restored.

December 16, 2019 at 0356 December 16, 2019 at 0358 December 16, 2019 at 0835 December 16, 2019 at 1458 All EDGs secured and restored to standby alignment.

December 17, 2019 Defective ABB GR-5 Relay replaced.

Manufacturer and model number of each component that failed during the event

D.

Littelfuse ABB GR-5 Metal Oxide Varistor E.

Other systems or secondary functions affected

There were no systems or secondary functions affected by this event.

F.

Method of discovery of each component or system failure or procedural error

Alarms were initially received in the Main Control Room indicating an electrical distribution related event, triggering entry into the Abnormal Operating Procedure (AOP).

G.

Failure mode, mechanism, and effect of each failed component:

The varistors provide the implementation signal for the 250 VDC 51G Overcurrent Relay protection for the affected breaker. When the varistors were subjected to a voltage beyond their 150 VDC design capability, they failed, providing signal to the 51G relay to open the affected breaker. The opening of the breaker de-energized the safety-related electrical Page 3 of 6(04-2018)

U.S. NUCLEAR REGULATORY COMMISSION EXPIRES: 03/31/2020 APPROVED BY 0MB: NO. 3150-0104

, the NRC may not conduct or sponsor, and a person is not required to respond to, the informationcollection.

LICENSEE EVENT REPORT (LER)

CONTINUATION SHEET

3. LER NUMBER SEQUENTIAL NUMBER REV YEAR NO Sequoyah Nuclear Plant Unit 1 05000-327
- 004
- 00 2019 board, generating an undervoltage signal which started the EDGs.

H.

Operator actions

Operators appropriately responded to the event by utilizing alarm response procedures and the AOP.

Automatically and manually initiated safety system responses

I.

The opening of the unit board breaker de-energized the safety-related electrical board, generating an undervoltage signal which started the EDGs.

III.

Cause of the Event

Cause of each component or system failure or personnel error:

A.

Inspection of the failed relay control board revealed improperly rated metal oxide varistors.

Relay function 51G is implemented with an ABB GR-5 solid state relay supplied "commercial grade". The GR-5 circuit board involved in the event was found to have failed catastrophically. The failed circuit board was found to have varistors installed with a manufacturer specified maximum continuous voltage of 200 VDC. The correct varistors for the application required a manufacturer specified maximum continuous voltage of 330 VDC.

B.

Cause(s) and circumstances for each human performance related root cause

There was no identified human performance related root cause.

IV. Analysis of the Event

The Class IE alternating current (AC) Electrical Power Distribution System [EIIS: EA] sources consist of the offsite power sources (preferred power sources), and the onsite standby power sources (Train A and Train B EDGs). The design of the AC electrical power system provides independence and redundancy to ensure an available source of power to the Engineered Safety Feature (ESF) systems.

The onsite Class 1E AC Electrical Power Distribution System is divided into two redundant and independent load groups with two 6.9 KV SDBDs in each load group. Each 6.9 KV SDBD has a connection to a preferred offsite power source and an EDG. The 6.9 KV SDBDs in a load group (i.e., 1A-A and 2A-A, or 1B-B and 2B-B) are normally powered by the same offsite power circuit.

Each 6.9 KV SDBD can also be powered by a dedicated EDG. Two EDGs associated with one load group can provide all safety related functions to mitigate a loss of coolant accident (LOCA) in one unit and safely shut down the other unit. The Train A and Train B ESF systems each provide Page 4 of 6(04-2018)

U.S. NUCLEAR REGULATORY COMMISSION EXPIRES: 03/31/2020 APPROVED BY 0MB: NO. 3150-0104

, the NRC may not conduct or sponsor, and a person Is not required to respond to, the Informationcollection.

LICENSEE EVENT REPORT (LER)

CONTINUATION SHEET W/

3. LER NUMBER
1. FACILITY NAME
2. DCX:KET NUMBER SEQUENTIAL NUMBER REV YEAR NO, Sequoyah Nuclear Plant Unit 1 05000-327
- 004
- 00 2019 for the minimum safety functions necessary to shut down the plant and maintain it in a safe shutdown condition.

An EDO starts automatically on a safety injection (SI) signal or on a 6.9 KV SDBD degraded voltage or loss-of-voltage signal. After the EDG has started, it will automatically tie to its respective 6.9 KV SDBD after offsite power is tripped as a consequence of a 6.9 KV SDBD degraded voltage or loss-of-voltage signal, independent of or coincident with an SI signal. Following the trip of offsite power, a loss-of-voltage signal strips nonpermanent loads from the 6.9 KV SDBD. When the EDG is tied to the 6.9 KV SDBD, loads are then sequentially connected to its respective 6.9 KV SDBD by individual load sequence timers.

In this event, the 1B-B 6.9 KV SDBD was immediately reenergized by its associated EDG.

Throughout the transient, both trains of the ESF system were available as designed to provide for the minimum safety functions necessary to shut down both units and maintain them in a safe shutdown condition.

V. Assessment of Safety Consequences

There were no actual safety consequences as a result of this event.

Availability of systems or components that could have performed the same function as the components and systems that failed during the event:

A.

The alternate offsite AC source of power remained available to the 1B-B 6.9 KV SDBD during 1B-B EDG operation.

For events that occurred when the reactor was shut down, availability of systems or components needed to shutdown the reactor and maintain safe shutdown conditions, remove residual heat, control the release of radioactive material, or mitigate the consequences of an accident:

B.

The event did not occur when the reactor was shut down.

For failure that rendered a train of a safety system inoperable, an estimate of the elapsed time from discovery of the failure until the train was returned to service:

C.

The duration of the loss of offsite power to the 1B-B SDBD was 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> 39 minutes.

VI. Corrective Actions

The event was entered into the Tennessee Valley Authority Corrective Action Program (CAP) under Condition Report #1573472 and 1573726.

Page 5 of 6(04-2018)

U.S. NUCLEAR REGULATORY COMMISSION EXPIRES: 03/31/2020 APPROVED BY OMB: NO. 3150-0104

, the NRC may not conduct or sponsor, and a person Is not required to respond to, the informationcollection.

LICENSEE EVENT REPORT (LER)

CONTINUATION SHEET

1. FACILITY NAME
2. DCTCKET NUMBER a LER NUMBER SEQUENTIAL NUMBER REV YEAR NO Sequoyah Nuclear Plant Unit 1 05000-327
- 004
- 00 2019 A.

Immediate Corrective Actions

The failed GR-5 relay vyas replaced with a new relay with the proper voltage rated varistors installed.

Corrective Actions to Prevent Recurrence or to reduce probability of similar events occurring in the future:

B.

An extent of condition will be performed as plant conditions permit to evaluate any other 250 VDC rated applications that may have incorrect voltage components.

VII. Previous Similar Events at the Same Site

There were no previous similar events at SON occurring within the last three years.

VIII. Additional Information

There is no additional information.

IX. Commitments:

There are no commitments.