ML20043D368

From kanterella
Jump to navigation Jump to search
Insp Rept 50-395/90-12 on 900401-30.Violations Noted.Major Areas Inspected:Monthly Surveillance Observations,Monthly Maint Observation,Operational Safety Verification & Onsite Followup of Events at Operating Power Reactors
ML20043D368
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 05/16/1990
From: Cantrell F, Modenos L, Prevatte R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20043D364 List:
References
50-395-90-12, NUDOCS 9006070428
Download: ML20043D368 (10)


See also: IR 05000395/1990012

Text

- _ _ - -

- - - _ _ _

!

[/ pm Ath

UNIT E] ST ATES

1

,

  • o

NUCLEAR REGULATORY COMMISSION

'a

.

,8 "

rE! ION H

n

l.

g

.g

101 MARIETTA STREET,N.W.

'

l

ATLANTA, GEORGI A 30323

/

c

.....

,

Report No.:

50-395/90-12

Licensee:

South Carolina Electric & Gas Company

Columbia, SC 29218

Docket No.:

50-395

License No.:

NPF-12

a

facility Name:

V. C. Summer

Inspection Conducted: April 1 - 30, 1990

Inspectors :

[

2 ,,

.f

d

Richard L. Prevatte

/ f

'

Date Signed

'i

%dbNA

Sbdu

~

LetrM Mode'nos~

gV

Date Signed

'

<

Approved by :

AIh[f I

//

d'

Floya S. Ecntrell, ~5ecgifn Chief

Date Signed

Reactor Projects Branth 1

Division of Reactor Projects

i

l

SUMMARY

Scope:

This routine inspection was conducted by the resident inspectors onsite in the

areas of monthly surveillance observations, monthly . maintenance observation,

operational ' safety verification, onsite follow-up of events at operating power

reactors, preparation for refueling, instrumentation and testing of modifica-

tions, and other areas.

Selected tours were conducted on backshift or weekends.

Backshift or weekend tours were conducted on 19 occassions.

Results:

,

i

The plant has been- in a refueling outage for this reporting period.

A

violation, . involving failure to have adequate post maintenance and post

modification testing with two examples was identified.

The first example was

the result of the licensee identifing three electrical leads, which had been

lifted from the reactor building level transmitter since the last refueling

outage (paragraph 5b).

The second example involved reversing the polarity of

connections on the station battery prior to post maintenance testing (paragraph

7a).

One NCY was identified, involving a failure to perform a semi-annual QA

audit (paragraph Sa). Two events occurred which involved the mispositioning of

j,3f0 $$bk N'

)

'

,

O

.

e

-.

.

-2

four fuel assemblies during fuel movement and an inadvertent ESF actuation of

the emergency diesel generator when the 230 kV offsite power was lost.

Preparation for refueling was inspected with no deficiencies identified.

In

addition, work activities associated with the modifications to add a voltage

regulator and switches to the 115 kV offsite transformer were monitored with no

deficiencies identified,

j

On April 16-17, 1990 the responsible Project Section Chief, F. S. Cantrell

visited the site to meet the resident inspectcts and review progress of the

refuling outage.

On April 26 and 27, 1990, the SALP board members visited the site in prepara-

tion for the end of the SALP period and the SALP board. The reporting period

ended on April 30, 1990.

The unit ended the reporting period with 27 days

remaining in the 65 day outage.

Two examples of one violation were identified.

-

. . .

.

__

---

~

'

.

,

,

REPORT DETAILS

1.

Persons Contacted

Licensee Employees

W. Baehr, Manager, Chemistry and Health Physics

C. Bowman, Manager, Scheduling ani Modifications

0. Bradham, Vice President, Nucitar Operations

M. Browne, Manager, Systems Engineering & Performance

W. Higgins, Supervisor, Regulatory Compliance

  • S. Hunt, Manager, Quality Systems
  • A. Koon, Manager, Nuclear Licensing

G. Moffatt, Manager, Maintenance Services

  • D. Moore, General Manager, Engineering Services
  • K. Nettles, General Manager, Nuclear Safety
  • C, Price, Manager, Technical Oversite

M. Quinton, General Manager, Station Supp'Jrt

J. Shepp, Associate Manager, Operations

  • J. Skolds, General Manager, Nuclear Plant Operations
  • G. Soult, General Manager, Operations and Maintenance
  • G. Taylor, Manager, Operations

D. Warner, Manager, Core Engineering and Nuclear Computer Services.

M. Williams, General Manager, Administrative & Support Services

K. Woodward, Manager, Nuclear Operations Education and Training

Other licensee employees contacted included engineers, technicians,

operators, mechanics, security force members, and office personnel.

  • Attended exit interview

Acronyms and initialisms used throughout this report are listed in the

last paragraph.

s

2.

Monthly Surveillance Observation (61726)

The inspectors observed surveillance activities of safety related systems

and components to ascertain that these . activities were conducted in

accordance with license requirements. The inspectors observed portions of

four selected surveillance tests including all aspects of STP 409.001,

Diesel Generator A Refueling Inspection.

The inspectors verified that-

required administrative aaprovals were obtained prior to initiating the

test, testing was accomplished by qualified personnel, required test

instrumentation was properly calibrated, data met TS requirements, test

discrepancies were rectified, and the systems were properly returned to

service.

-

.

.

,

,

2

i

-!

No violations or deviations were identified.

'

3.

Monthly Maintenance Observation (62703)

{

The inspectors observed maintenance activities of safety related systems

,

. and components to ascertain - that these . activities were conducted in

I

.

accordance with approved procedures, TS, industry codes and standards.

The inspectors determined thet the procedures used were _ adequate to

,

control the activity, and that these activities were accomplished' by

i

qualified personnel.

The inspectors independently verified that the

-l

equipment was properly tested before being returned to service.

Addi-

!

tionally, the inspectors reviewed several outstanding job orders to

!

determine that the licensee was giving priority to safety related

-j

maintenance and not developing a backlog which might affect a given

{

system's performance.

The following specific maintenance activities were

observed:

!

!

MWR 215950006

Remove existing battery rack assembly and install new

l

and

battery rack on battery B in accordance with MRF 21595 -

l

215950002

!

PMTS P0125054

Five year RCP B motor inspection / overhaul'

f

PMTS P0130733

Loop calibration for SW building SWGR room A ambient

temperature

MWR 90M0111

D/G A Replace cylinder liner and water jacket 0-rings

MWR 215950010

Rework battery cable conduit in accordance with MRF-

21595

MWR 215950008

Remove battery cable conduit support for MRF 21595

MWR 9000821

Repair, as necessary, RMA-004

No violations or deviations were identified.

.

4

Operational Safety Verification (71707)

The inspectors nonducttd daily inspections in the following areas:

!

control room stariing, access, and operator behavior; operator adherence -

to approved procedures, TS, and limiting conditions for operations;

,

examination of panels containing instrumentation and other reactor

protection system elements to determine that required channels are

operable; and review of control room operator logs, operating orders,

plant deviation reports, tagout logs, jumper logs, and tags on components

to verify compliance with approved procedures.

I

_

_$

.

~

-

.

e

3

The inspectors conducted weekly inspections in the following areas:

verification of operability of selected ESF systems by valve alignment,

breaker positions, condition of equipment or components, and operability

of instrumentation and support items essential to system. actuation- or

performance,

j

Plant tours included observation of general plant / equipment conditions,

fire protection and preventative measures, control of activities in-

1

3rogress, radiation protection controls, physical' security controls, plant

lousekeeping conditions / cleanliness, and missile hazards.

The inspectors conducted biweekly inspections in the following areas:

verification review and walkdown of safety related tagout(s) in effect;

review of sampling program (e.g. - primary and secondary coolant samples,

boric acid tank samples, plant liquid and gaseous samples); observation of

control room shift turnover; review of implementation of the plant problem

identification sy(s)em; verification of selected portions of containment

st

isolation lineup

and verification that notices -to workers are posted'

-

as required by 10 CFR 19.

Selected tours were conducted on backshifts or weekends.

Inspections

,

included areas in the cable vaults, vital battery rooms, safeguards areas,

'

emergency switchgear -rooms, diesel generator rooms, control room, auxiliary

building, containment, cable penetration areas, service water intake

structure, and other general plant areas.

Reactor coolant system leak

rates were reviewed to ensure that detected or suspected leakage from

the system was recorded, investigated, and evaluated; and that appropriate

actions were taken, if required.

On a regular basis, RWP's were reviewed

r

and specific work activities were monitored to assure they were being

>

conducted per the RWP's.

Selected radiation protection instruments were

periodically checked, and equipment operability and calibration frequency

i

l

were verified.

In the course of monthly activities, the inspectors included a review of

the licensee's physical security program.

The performance of various

,

!

shifts of the security force was observed in _ the conduct of daily

activities to include:

protected and. vital creas access controls;

searching of personnel, packages and vehicles; badge issuance and

1

retrieval; escorting of visitors; and patrols and compensatory posts.

No violations or deviations were identified.

!

5.

Onsite Follow-up of Events at Operating Power Reactors (93702)

a.

On March 22,1990, the licensee discovered that a scheduled six month

QA audit was not performed in the second half of 1989.

This

-

discrepancy was identified during the performance of the first half

1990 program audit.

This audit was omitted from the audit schedule,

..

. .

!

.-

1-

.

4

!

,

that is published quarterly, and subsequently not performed.

TS 6.5.2.8.c requires that an audit be performed at least once per six

months to verify the results of actions taken to correct deficiencies

i

occurring in unit equipment, structures or method of operation that

affect nuclear safety.

As a corrective action the licensee performed an audit that

considered a sample size which included nonconforming documents,

which were initiated since the previous program audit, one year ago.

No impacting deficiencies were noted.

The quarterly audit schedule

will now require verification prior to issue.

The NSRC members who

review the audit program will be placed on distribution for- audit -

schedules.

This licensee-identified violation will- not be cited

because of the criteria specified' in Section V.G of the NRC

Enforcement Policy was satisfied.

This item will be tracked as NCV

90-12-01, Failure to perform QA audit,

'

b.

On April 9,1990, while implementing MRF 21479 for refuel 5, the

licensee discovered that three electrical leads from the reactor

e

building level -transmitter LT 1976 were lifted, rendering the

transmitter inoperable.

Investigation revealed that during refuel

4~,

in November 1988, an equipment qualification inspection required

lifting of the leads to rework a Ray Chem splice. A lifted lead and

jumper sheet was initiated in accordance with SAP-300.

On November 17, 1988, the electrical job supervisor requested that

I&C reconnect the leads and clear the lifted lead and jumper sheet.

The electrical. supervisor realized that other work activities were

being performed on' LT '1976 and transferred the paper work and

responsibility to I&C.

The section of the lifted: leads- form for

retermination was marked NA and a reference was made on the-form that

the circuits would be reterminated on MWR 8810501 by I&C. The lifted

leads form was never transferred to the I&C MWR,

As it turned out

,

l

MWR 8810501 had been closed and signed as. complete on . November 8,

'

1988. Hence, the lifted leads were never reterminated.

The maintenance task sheet was signed on November 17, 1988.

In

addition to LT 1976, the other train of the reactor building level

indication, LT 1975, was also worked on. during this outage.

STP

!

135.001, Post Accident Monitoring Instruments Channel Check,

Revision 7 was specified as the post maintenance test.

The post

maintenance channel check, required by STP 135.001, uses a visual

comparison of LT 1975 and 1976.

With no water in the reactor

building sump, the level transmitter will read zero.

When the

instrument is deenergized it also reads zero. Therefore, the channel

check would not detect an inoperable system.

This is contrary to the requirements of 10 CFR 50, Appendix B,

l

Criteria V, which requires that procedures be developed and implemented

to ensure that important activities have been satisfactorily

l

i

- . . . -

.. -..

.

.

-

. - - . . . . . . - . . . -

.

.

.

'.

.

,

5

i

~

accomplisFed.

The above work activities did not contain sufficient ~

procedures or instructions to ensure that necessary post maintenance -

testing was accomplished.

This is the first example of Violation

I

90-12-02, " Failure to have adequate- post maintenance and post

j

modification testing".

c.

On April 23, 1990, the licensee experienced an ESF actuation of the

emergency diesel generator, when they lost the 230 kV offsite power.

l

An inadvertent loss of the 230 kV line was the result of relay.

'l

'

department personnel

performing preventive maintenance on

differential relays in the switch yard.

The relay personnel failed

to defeat the differential relay trip signals for the switch yard bus

3

3 input and output 0CB's,-except for 0CB 8892, plant feeder.

When

the test began bus 3 power was lost causing the undervoltage relays

i

on B train ESF bus to start the DG, and loss of power to the balance

of plant busses.

The relay personnel immediately realized what

happened and restored power to bus 3.

However, the IDB bus could not

!

be restored until the diesel was secured _ and the sequencer reset.

The diesel ran for cbout one hour before it was secured.

The

!

licensee is investigating root cause,

i

d.

On April 23, 1990, while-performing video inspection of the SFP fuel

!

assembly locations, prior to core reload, it was discovered that four

'

fuel assemblies (G28, G35, F30, E14) were out of position.

Fuel

assemblies G28 and G35 were located in SFP Region 3-and Region ?.

respectively, instead of the called for and required Region 1, per TS

3.9.12.

These two assemblies were new Vantage 5 fuel assemblies that

are scheduled to be reloaded into the core. The-other two assemblies

were burned fuel that was to be stored in . the- fuel pool.

The-

licensee took immediate corrective actions to verify SFP boron

!

concentration to be greater than 2000 ppm, suspended all crane-

operations within the pool, provided a SR0 to supervise movement of

fuel assemblies to correct locations, and video taped the entire fuel

i

pool to verify correct positioning of all assemblies.

Investigations

'

revealed the cause of the misposition to be an.off indexing error

while picking up G35 and a numerical transposition error from the

material transfer form while moving G28.

Prior to reload the

licensee took the following corrective measures:

a fuel movement.

i

status board-has been added in the fuel handling building to further

,

improve communications between the handling crane operator and the

special nuclear material executor; and a double set of initial

approvals prior to execution of any material transfer forms.

One example of a-violation was identified.

6.

PreparationForRefueling(60705)

The inspector completed the review of the licensee's progress on their

i

preparation for refueling.

The inspector observed equipment checkout in

preparation for the fifth refueling outage.

This included fuel assembly

i

I

- _ .

- .-

- _ _ _

'.

.

9

$

inspection, using underwater video system; fuel handling, transfer and

.

core verification.

In particular, checkout and dry run was observed for

the spent fuel bridge, upender, fuel transfer tube and safety interlocks.

Activities were monitored to ascertain they were performed in accordance

with TS or with the approved procedures.

The following procedures were

reviewed for technical adequacy:

FHP-601

Refueling Organization

FHP-602

Limitations and Precautions for Handling New and

Partially Spent Fuel Assemblies

<

FHP-604

Functional Testing.of the Fuel Handling Systems

!

FHP-608

Transfer of New Fuel Assemblies from the New Fuel Storage

Racks

The inspector verified that the licensee had the proper staffing and

i

supervision, was . in procedural compliance - and maintained good

housekeeping in the refueling area.

No violations or deviations were identified.

7.

Installation and Testing of Modifications (37828)

a.

MRF 21595 was implemented to upgrade the class IE DC system from a

two hour to a four hour rated battery to meet licensee's commitment

to NRC " Station Blackout-Rule", 10CRF 50.63. This modification will

provide sufficient capacity in the Class IE battery for four hour-

l

operations without load shedding.

Since the new batteries are of a

'

larger physical size, this modification required replacement of the

battery racks, conduit, and conduit supports.

The higher rated

,

battery also required replacement of.the molded case circuit breakers

l

in panels DPN 1HA1, DPN-1HA2, and DPN 1HBl.

The inspector reviewed

I

the modification package and supporting data, selected portions of

'

the work activities associated with the removal of battery B, the

installation of new battery racks, and the completed service test on

battery B.

The service acceptance test for the battery was performed

in accordance with surveillance test procedure, DC Battery Service

Test, STP 501.003.

The testing for the new molded case circuit

.

)

breaker was performed under molded case circuit breaker testing,

EM 280.004, Rev. 8.

After completion of the above installation on battery B, on April 12,

1990, the red clearance tag was cleared by an auxiliary operator.

The next steps specified in the MRF was to charge the battery and

perform a service test. When the DC breaker was closed, at 6:30 a.m.

on April 12, 1990, to connect the battery to the DC bus, all lights

!

.

' . .

..

,

7

in the area went out and the auxiliary operator reported smoke.

The

control room ordered him to open the battery breaker.

When the

battery breaker was open, all AC power and DC control power for B

train was lost.

At the time, reactor defueling operations were in progress. Since a

e

multitude of control room annunciators and the audio count rate was

lost, a decision was made to suspend fuel movement until all power

]

and annunciators were restored.

Subsequent investigations by the licensee revealed that both the

normal and swing battery chargers, which were connected to the DC

train B bus,' received damage to various components.

Further

investigation revealed that the source of the problem was that the-

battery had been reconnected with reverse polarity.

The battery

connections were reworked and verified to be correct.

The battery

charger was also repaired and normal service was restored to B train

l

during the afternoon of April 12,.1990.

Reactor refueling operations

i;

were then completed,

j

>

'

The inspectors investigated this event and attended the-licensee's

management review board on April 19, 1990 where the event was-

discussed in detail.

t

It was determined that the cause of the error was inadequate procedural

{

requirements to verify correct polarity- of the battery when it was

i

terminated to the battery feeder cable.

A review of the MRF stated

i

that the polarity should be verified prior to energization.

3

I

However, when the old battery was disconnected, the battery field

i

cable leads were not labeled and a lifted lead and jumper form, as.

l

required by SAP 300, Conduct of Maintenance, Rev. 4, was-not filled

i

out.

!

The new battery installation consisted of a two tier battery rack

i

instead of the previous one tier rack.

After the new battery was

!

installed, the engineers responsible for the MRF noted that the

,.

feeder cable could not be easily connected to the bottom. row of the

l

battery.

He then issued MRF, Minor change notice No.-5, to change

j

-

l

the connectihis to the top row of the battery,

i

i

Field discussion, between the field and maintenance personnel

performing the work and the engineer, resulted in the engineer

,

!

showing the field personnel how to make the connection.

At that time

l

the field personnel assumed that the engineer's description of.how

l

and where to made the connections included correct polarity.

Based

i

on these discussions the field supervisor provided a sketch, on how

l

the connection should be made, to the field personnel.

The

- .

I

,

- .

. .

.-

.-

.

.

'.

-

1

.

,

7

-

f

q

in the area went out and the auxiliary operator reported smoke.

The

'

control room ordered him to open the battery breaker.

When the

battery breaker was open, all AC power and DC control power for B-

.

.

train was lost.

'

{

At the time, reactor defueling operations were in progress.

Since a

multitude of control room annunciators and the audio count rate was

lost, a decision-was made to suspend fuel movement until all power

and annunciators were restored.

!

Subsequent investigations. by the licensee revealed that both the

normal and swing. battery chargers, which were connected to the DC

train B _ bus,- received damage to various components.

Further

investigation revealed that the source of the problem was that the

battery had been reconnected with reverse polarity.

The battery

connections were- reworked and verified to be correct.

The battery

charger was.also' repaired and normal service was restored to B train

,

during the afternoon of April 12, 1990.

Reactor refueling operations

were then completed.

The inspectors ' investigated this event and attended the licensee's

management review board on April 19,1990 where the event was

discussed in detail.

It was determined that the cause.of the error was inadequate procedural

requirements to verify correct polarity'of the battery when it was

terminated to the battery feeder cable. ' A review of the MRF stated

.

that the polarity should be verified prior'to energization.

However, when the old battery was disconnected, the battery field

cable leads were not labeled and a lifted lead and jumper form, as

required by SAP 300, Conduct of Maintenance, Rev. 4, was not filled

out.

The new battery installation consisted of a two tier battery rack

instead of the previous one tier rack.

After the new battery was

installed, the engineers responsible for the MRF~ noted that the

feeder cable could not be easily connected to the bottom row of the

battery.

Pe then issued MRF, Minor change notice No. 6, to change

i

the connections to the top row of the battery.

'

Field discussion, between the field and maintenance personnel

performing the work and the engineer, resulted in the engineer

showing the field personnel how to make the connection. At that time

the field personnel assumed- that the engineer's description of how

and where to made the connections included correct polarity.

Based

on these discussions the field supervisor provided a sketch, on how

the connection should be made, to the field personnel.

The

.

l

'

. -

.

8

'

'

. connection was made based on that sketch instead of the drawings

'

included in the MRF package.

At no time was the circuit " rung out"

or meters used to verify correct polarity.

This work.was also

covered by - QC,

Even the _ QC procedures required independent

,

verification of correct termination of the battery.

QC inspectors

used the same sketch, and- discussions with the installation

personnel, as' verification that- the cables were connected correctly.

,

This is contrary to the requirements of 10 CFR 50, Appendix _ B,

Criteria V,

which requires that procedures be developed: and

4

implemented to ensure that the important ' activities have_ been

i

satisfactorily accomplished.-

The above indicated: that the MRF did

not contain sufficient procedures or instructions to ensure that the

'

.

necessary post modification check-out testing'was accomplished.

The

1"

QC inspector also failed to follow the procedural requirements

4

contained in Inspection Checklist for Terminations OSP, Attachment 1.

This is the second example of Violation 90-12-02, " Failure to have

.i

adequate post maintenance and post modification testing".

'

b.

The inspectors continued _to follow the work activities associated

i

.

with the modifications to add a voltage regulator and switches to the

,

115 kV offsite power transformer XTF-4. The work activities observed-

'

on this modification included the receipt and installation of the

voltage regulator and switches which was completed during the week of

April 9 _13,1990.

The inspectors also reviewed the: start-up and

operational tests planned on this unit.

No deficiencies were

<

identified with these activities,

j

,

One example of a violation was identified.

8.

ActiononPreviousInspectionItems(92701,92702)

(Closed)

Inspector Follow-up Item 89-05-02: Lack of followup on ALARA

action items by the ALARA review committee.

A review of ALARA committee

meeting minutes showed that action items to reduce dose that were approved

by the committee were not always discussed at meetings nor were their

status updated.

The inspector reviewed 1990 ALARA committee meeting minutes and noted that

all action items were discussed at the- meeting and the status toward

completion for each item was updated. This item is closed.

9.

Other Areas

On April 26 and 27,1990, the SALP board members visited the site for an

update on the status of the plant and a presentation by the licensee on

their NUCLEX program for the upcoming SALP.

The SALP reporting period

ended on April 30, 1990.

4

. . . . .

..

. . . .

.

. . . .

.

.

. . . . . .- . . -

'

-

.

.

t

9

i

l

.1 01

ExitInterview(30703)

i

The inspection scope and findings were summarized on April 30, 1990, with

-

those persons indicated in paragraph 1.

The inspectors described the

areas inspected ~and discussed the inspection findings. The NCV associated

!

with the failure to perform a semi-annual QA audit was discussed. The two

i

part violation assciated with the lifted leads. found. on the reactor

!

building level transmitter from the fourth refueling -outage, and the

reverse polarity on the DC batteries were discussed in detail. as

inadequate post maintenace and post modification testing problems. -The-

licensee took prompt corrective actions on the battery issues prior to

working the other train during the outage.

Two other events discussed

i

were the mispositioning of four fuel . assemblies in the spent fuel pool

during fuel movement and the ESF actuation of the A diesel generator when-

-!

230 kv offsite was lost.

!

!

No dissenting comments were received from the licensee. The licensee did

not identify as proprietary any of the materials provided to or reviewed

by the inspectors during the inspection.

11. Acronyms and Initialisms

,

DG

Diesel Generator

EM

Electrical Maintenance

,

ESF

Engineered Safety Feature

FHP

Fuel Handling Procedure

LER

Licensee Event Reports

MRF

Maintenance Request Form

MWR

Maintenance Wcrk Request

,

NCV

Non-cited violation

NRC

Nuclear Regulatory Commission

NRR

Nuclear Reactor Regulation

i

NUCLEX

Nuclear Excellance Program

OCB

011 Cooled breaker

!

PMTS

Preventive Maintenance Task Sheet

QC

Quality control

RCP

Reactor Coolant Pump

RCS

Reactor Coolant System

,

RCSLK9

Reactor Coolant System Leak Rate

RWP

Radiation Work Permits

SAP

Station Administration Procedures

SFP

Spent Fuel Pool

SPR

Special Reports

SRO

-Senior Reactor Operator

STP

Surveillance Test Procedures

- '

SW

Service Water

TS

Technical Specifications

. _.