ML20043B183

From kanterella
Jump to navigation Jump to search

Advises That Util Implementation Schedule Re Programmed Enhancement for Generic Ltr 88-17, Loss of DHR Acceptable. NRC Review of Generic Ltr 88-17 Will Be Accomplished as Insp Under Temporary Instruction 2515/103 in NRC Insp Manual
ML20043B183
Person / Time
Site: Byron, Braidwood  Constellation icon.png
Issue date: 05/17/1990
From: Shemanski P
Office of Nuclear Reactor Regulation
To: Kovach T
COMMONWEALTH EDISON CO.
References
GL-88-17, TAC-68726, TAC-69725, TAC-69727, TAC-69728, NUDOCS 9005250031
Download: ML20043B183 (4)


Text

f/

?

f

. +,4 gy, Q({[ f,; #\\[

UNITED STATES

?

NUCLEAR REGULATORY COMMISSION.

J 7p.v

,y wAssincion. o. c. 20sss F ' i g.% /

j

...+

May 17,1990 i

. Docket Nos. STN 50-454, STN 50-455 STN 50-456, STN 50-457

/
Mr. Thomas J. Kovach-I' Nuclear Licensing Manager m

Comonwealth Edison-Company-Suite 300 0 PUS West III

'1400 OPUS Place

Downers Grove, Illinois 60515 j

Dear Mr. Kovach:

4

SUBJECT:

-PROGRAMMED ENHANCEMENTS FOR GENERIC LETTER 88-17,

  • LOSS

'0F DECAY HEAT REMOVAL" BYRON UNITS 1 AND 2, BRAIDWOOD UNITS 1 AND 2, t

(TACNOS. 69725,68726,69727,69728)

The NRC t.taff has completed its review of all licensee responses regarding p

~ programed enhancements as defined in Generic Letter (GL) 88-17, " Loss of Decay Heat Renoval." The NRC staff review was based on a sampling of about one-third

.of all responses. Since the sample did not result in significant comments,.

the remainder of the responses will not be reviewed by NRR. NRC review of this phase of GL-88-17 will be accomplished as an inspection under Temporary l

Instruction (TI).2515/103 in the NRC Inspection Manual. The inspection will take place after you have made sufficient progress for NRC to make a full l assessment of your programmed enhancements. This letter constitutes the NRR report stated ~in paragraph 05.01 as a prerequisite to the inspection under 7

-TI 2515/103.

As for your implementation schedule, you indicate that all hardware-related 1 modifications will be completed by late 1991. Since this is by the end of the

=second refueling outage following receipt'of GL 88-17, your schedule is

' consistent with the GL and is acceptable. Also, you indicate that programmed i

enhancements that do not depend on hardware changes will be implemented on or

~before May.1990. This also is censistent with the GL and is acceptable..

i Additionally, you sre requested to inform the NRC in writing of any signifi-

-cant changes in the estimated completion schedule identified above. You are i

also requested to inform the NRC in writing when the action has actually been I

. implemented and the modifications are determined to be operational.

This request is covered by Office of Management and Budget Clearance Number L

3150-0011, which expires January 31, 1991. The estimated average burden-hours

)

15.4 person-hours per owner response, including searching data sources, gathering and analyzing the data, and preparing the letter. These estimated average burden-hours pertain only to the identified response-related matters iand do not include the time for actual implementation of the requested action.

Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to L

9005250031 %h ApoCF ppj gDR PDC

o i

my l^

4 ';_

e, L'

N

_Mr. Thomu J. Kovach -

2 --

liay 17,1990 g

"L the I'nformation and Records Management Branch, Division of'Information Support Services, Office of Information Resources Management, U.S., Nuclear Regulatory.

Commission,. Washington, D.C.

20555; and to the Paperwork Reduction Project (3150-0011), Office of Management and Budget, Washington, D.C.

20503.

Please contact us should you have any questions' regarding this matter.

Sincerely,

(-

  • w Paul C. Shemanski, Project Manager Project Directorate III-2 g

Division of Reactor Projects - III, IV, Y and Special Projects Office of' Nuclear Reactor Regulation 1

cc: See next page

.3 ES 7 DUTION,,

t mcar: F Ue d/j PDIII-2 r/f NRC & Local PDRs JZwolinski CMoore DDudley PShemanski SSands CPatel OGC EJordan ACRS(10)

Plant File CTrannell 0FFICIAL RECORD COPY Documertt ge: GL 88-17-LTR2 DI -2:LA PDIII-2:PM I-c.:PM PDII'

c. A PD C ore PShemanski:ta SSands DDud'ey 6/8/90 f/It/'/90 5 /g/90 f/s'/90-L

/

l

ru l_

,_'n

,t

~.,

s a

f Hr.LThomas sl. Kovach

. May 17,.1990.

3 the'Information and Records Management Branch, Division of Information Support Services, Office of Information Resources Management, U.S. Nuclear Regulatory

. Commission = Washington, D.C.

20555; and to the Paperwork Reduction Project-

-(3150-0011}, Office.of Management and Budget, Washington, D.C.

20503.

i

'Please contact us should you have any questions regarding this matter, t

Sincerely, Paul C. Shemanski, Project Manager-Project Directorate Ill-2 Division of Reactor Projects - 111, IV, V and Special Projects Office of Nuclear Reactor Regulation cc:- See next page E

+

b i

l l,

c._. _. _2

y-l' l.,

y j,J ;q+

3. c ->

Am. Mr.) Thomas J. Kovach Byron /Braidwood Power Station

~

'Comonwealth Edison Company

. Units 1 ar.d 2

.CC:

l Mr. Gabe Toth

- U. S. Nuclear Regulatory Comission U

Westinghouse: Electric Corporation Byron / Resident Inspectors Office -

Energy Systems Business Unit-4448 North German Church Road H

Post Office Box 355, Bay 236 West Byron,. Illinois.61010 Pittsburgh.. Pennsylvania 15230 1

Ms. Lorraine Creek j

Joseph Gallo..Esq..

Rt. 1, Box 182-(HopkinsandSutter Manteno, Illinois 60950

- 888 - 16th Street ~, N.W.

Suite 700 Mrs. Phillip B. Johnson Washington, D.C. 20006 1907 Stratford Lane-c.-

Rockford, Illinois 61107 Regional Administrator U rS. NRC, Region III

-Douglass Cassel, Esq.

799. Roosevelt Road, Bldg. #4 109 N. Derarborn Street

Glen Ellyn, Illinois 60137 Suite 1300 Chicago,. Illinois 60602-(Ms. Bridget Little Rorem m

Appleseed Coordinator David C. Thomas, Esq.

117 North Linden Street 77 S. Wacker Drive J

.Essex,' Illinois 60935 Chicago, Illinois 60601 3

Mr. Edward R.-Crass Michael Miller, Esq.-

H Nuclear. Safeguards and Licensing' Sidley and. Austin Division-One First National Plaza Sargent & Luridy' Engineers-

-Chicago, Illinois -60690

'55 East Monroe-Street-Chicago,7 Illinois-60603 George L. Edgar s'

Newman & Holtzinger, P.C.

U.- S. NuclearlRegulatory Comission 1615 L Street, N.W.

Resident Inspectors Office Washington, D.C.

20036 RRfl.: Box 79 Braceville,. Illinois 60407 Comonwealth Edison Company Byron Station Manager

- Mr. Thomas W. Ortciger, Director 4450 North German Church Road L-

Illinois Emergency Services Byron, Illinois 61010

. 'and Disaster Agency L.

.110 East Adams-Street Springfield, Illinois.62706 l

11111nois Department..of

. Nuclear Safety

. Office 'of. Nuclear Facility. Safety 1035 Outer Park Drive Springfield, Illinois 62704 i

C-

.