Forwards Tentative Schedule for Submittal of 6-month & 9-month Repts on Outstanding Response Items Concerning NUREG-0612 Re Control of Heavy Loads,Per NRC 820201 Request
ML20041C735
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 02/25/1982
From: Fay C
WISCONSIN ELECTRIC POWER CO.
To: Clark R, Harold Denton
Office of Nuclear Reactor Regulation
References
REF-GTECI-A-36, REF-GTECI-SF, RTR-NUREG-0612, RTR-NUREG-612, TASK-A-36, TASK-OR TAC-07727, TAC-08074, TAC-7727, TAC-8074, NUDOCS 8203020521
Download: ML20041C735 (3)


Text

& h 1

Wisconsin Electnc eom couem "wo Y 5

nt:a,M1

-3 231 W. MICHIGAN, P.O. BOX 2046. MILWAUKEE, WI 53201 u-

)-

February 25, g2 q

Mr. H. R. Denton, Director Office of Nuclear Reactor Regulation U.

S. NUCLEAR REGULATORY COMMISSION Washington, D. C.

20555 Attention:

Mr.

R. A. Clark, Chief Operating Reactors, Branch 3 Gentlemen:

DOCKET NOS. 50-266 AND 50-301 OUTSTANDING RESPONSE ITEMS NUREG-0612 - CONTROL OF HEAVY LOADS POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 This is in response to your letter of February 1, 1982 which requested a schedule for submittal of the outstanding 4

information concerning our responses regarding NUREG-0612,

" Control of Heavy Loads at Nuclear Power Plants".

The attachment to this letter provides our expected schedule for the submittal of this information.

As you recognize, our six-month and nine-month reports have provided the substantial majority of the information requested by NUREG-0612.

We trust that the extended schedule for submission of the few items presently unavailable will not adversely affect your review effort.

The commitment dates in the attached schedule are l

dependent on a number of factors.

Of particular concern are j

the dates for the proposed submittal of information relating to the single failure proof handling system to be installed l

in the Point Beach auxiliary building (NRC question attachment i

1-1 through 1-3).

As stated in our nine-month response, sections j

2.3.1 through 2.3.3, this information cannot be completed until a vendor for this equipment has been selected and an order l

placed.

As noted in our previous submittals, our schedule for the installation of.this equipment calls for completion within two years of the date of our nine-month report.

Within this time frame, we are providing the attached estimates as to when j

the analyses requested in NRC question attachment 1-2 and 1-3 7

will become available.

.i

(

' B203020521 820225 DRADOCK05000g

Mr. H. R. Denton February 25, 1982 We will notify you if we encounter any delays in completing this outstanding information.

Please contact us if you have any questions.

Very truly yours,

/

"5 Assistant ice President C. W. Fay Attachment Copy to NRC Resident Inspector Subscribed and sworn to before me this M:d8t, day of February 1982.

M.T

_--- C o Notary PuMic, State of Wisconsin My Commission expires d /,l d f.

v

(

r J

OUTSTANDING RESPONSE ITEMS NUREG-0612 - CONTROL OF HEAVY LGADS SIX AND NINE-MONTH REPORTS Proposed Submittal Date SIX-MONTH REPORT Section 4.3.4 Lifting Rig Compliance with ANSI N14.6-1978 (NRC Question 2.1.3.D) 06/01/82 NINE-MONTH REPORT Section 2.3.1 Manufacturer and Design Information on Single Failure Proof Crane (NRC Question -1) 09/15/82 Section 2.3.2 Analysis of Compliance to NUREG-0554 for Single Failure Proof Crane (NRC Question -2) 12/31/82 Section 2.3.3 Seismic Analysis of Single Failure Proof Crane (NRC Question Attachment 1-3) 12/31/82 Section 2.3.5 Interfacing Lift Point Evaluation (NRC Question Attachment 1-5) 06/01/82 Section 3.4.2-Reactor Vessel Head Drop Analysis (NRC Question 2.3-4-b) 09/15/82 Section 3.4.3 Exceptions taken to NUREG-0612 Guidelines in Performing Reactor Vessel Head Drop Analysis (NRC Question 2.3-4-c) 09/15/82 l

[