MONTHYEARML20205H9841976-07-0606 July 1976 Forwards Draft Amends 18 & 23 to Licenses DPR-24 & DPR-27, Respectively, & Safety Evaluation.Amends Revise Tech Specs to Add Surveillance Requirements & Place Limit on Max Weight of Spent Fuel Shipping Cask Used Project stage: Draft Approval ML19210A1171978-06-12012 June 1978 Forwards Corrected Sent to Reactor Licensees, Except Those in Sep,Re Heavy Loads Over Spent Fuel Project stage: Other ML19344A9031978-07-28028 July 1978 Forwards Response to Requesting Info Re Control of Heavy Loads Near Spent Fuel Project stage: Other IR 05000320/19800151980-11-24024 November 1980 IE Insp Rept 50-320/80-15 on 800901-1018.No Noncompliance Noted.Major Areas Inspected:Plant Operation,Health Physics & Environ Insp & Review Project stage: Request ML19340D0701980-12-22022 December 1980 Forwards PA Emergency Mgt Agency 801204 Response to FEMA Re Offsite Emergency Planning Contentions for TMI-1 Restart Hearings.List of Documents Initially Submitted to Regional Assistance Committee Encl.Related Correspondence Project stage: Request ML17194A9531981-02-0303 February 1981 Ltr to All Licensees of Operating Plants,Applicants for OLs & Holders of CPs Re Control of Heavy Loads.Forwards Missing Pages to Encl 3 of 801222 Generic Ltr.W/Related Info Project stage: Other ML19350E7831981-06-19019 June 1981 Provides Status of Response to NUREG-0612 Re Control of Heavy Loads.Plant Administrative Controls for Use of Lifting Devices Revised to Ref Interim Safe Load Path Drawings. Six-month Response Will Not Be Submitted Until Sept 1981 Project stage: Other ML20041C7351982-02-25025 February 1982 Forwards Tentative Schedule for Submittal of 6-month & 9-month Repts on Outstanding Response Items Concerning NUREG-0612 Re Control of Heavy Loads,Per NRC 820201 Request Project stage: Other ML20041C0691982-02-25025 February 1982 Files Prepared Direct Testimony Re Proprietary Info Issue Per ASLB Directions in 820128 Telcon.Certificate of Svc Encl Project stage: Request ML20054G6221982-06-16016 June 1982 Forwards Response to NRC Question Attachment 1-5 Re Interfacing Lift Point Evaluation.Info Provided as Revised Pages to 9-month Response to NUREG-0612, Control of Heavy Loads Project stage: Other ML20054L0981982-06-30030 June 1982 Submits Addl Info for Draft Technical Evaluation Rept on Util Response to NUREG-0612, Control of Heavy Loads, Per 820520 Telcon Project stage: Draft Other ML20069D5931982-09-16016 September 1982 Forwards Response to NRC Question Attachment 1-1 Re Manufacturer Design Info on Single Failure Proof Cranes & Revised Response to NRC Attachment 1-5 Concerning Interfacing Lift Point Evaluation Project stage: Other ML20027B3751982-09-16016 September 1982 Forwards Response to ASLB Question on Radiolysis in Sleeve/Tube Annulus,Per 820909 Conference Call.Notarized Affidavit Forthcoming.Svc List Encl Project stage: Request ML20065S1291982-10-22022 October 1982 Requests Expeditious Review & Approval of Revision 3 to Ederer,Inc Generic Rept EDR-1, Nuclear Safety-Related Extra-Safety & Monitoring (X-SAM) Cranes to Assist in Completing Auxiliary Bldg Crane Upgrade in Timely Manner Project stage: Other ML20066K0641982-11-22022 November 1982 Forwards Revised Pages 10,11 & 11a to Response to NRC Question 2.3-4-b Re Control of Heavy Loads,Including Results of Reactor Pressure Vessel Head Drop Analysis.Info Should Be Included in 9-month Response Project stage: Other ML20072K8201983-06-17017 June 1983 Control of Heavy Loads (C-10),Point Beach Nuclear Plants Units 1 & 2, Draft Final Technical Evaluation Rept Project stage: Draft Other ML20080M9231983-09-28028 September 1983 Forwards Addl Info Requested in 830810 Telcon Re Franklin Research Ctr 830617 Draft Technical Evaluation Rept on Util Response to Phase 1 of NUREG-0612, Control of Heavy Loads at Nuclear Power Plants Project stage: Draft Other ML20086T8821984-03-0202 March 1984 Control of Heavy Loads (C-10) Wisconsin Electric Power Co Point Beach Nuclear Plant Units 1 & 2 Project stage: Other 1982-10-22
[Table View] |
Forwards Tentative Schedule for Submittal of 6-month & 9-month Repts on Outstanding Response Items Concerning NUREG-0612 Re Control of Heavy Loads,Per NRC 820201 Request| ML20041C735 |
| Person / Time |
|---|
| Site: |
Point Beach  |
|---|
| Issue date: |
02/25/1982 |
|---|
| From: |
Fay C WISCONSIN ELECTRIC POWER CO. |
|---|
| To: |
Clark R, Harold Denton Office of Nuclear Reactor Regulation |
|---|
| References |
|---|
| REF-GTECI-A-36, REF-GTECI-SF, RTR-NUREG-0612, RTR-NUREG-612, TASK-A-36, TASK-OR TAC-07727, TAC-08074, TAC-7727, TAC-8074, NUDOCS 8203020521 |
| Download: ML20041C735 (3) |
|
Text
- & h 1
Wisconsin Electnc eom couem "wo Y 5
nt:a,M1
-3 231 W. MICHIGAN, P.O. BOX 2046. MILWAUKEE, WI 53201 u-
)-
February 25, g2 q
Mr. H. R. Denton, Director Office of Nuclear Reactor Regulation U.
S. NUCLEAR REGULATORY COMMISSION Washington, D. C.
20555 Attention:
Mr.
R. A. Clark, Chief Operating Reactors, Branch 3 Gentlemen:
DOCKET NOS. 50-266 AND 50-301 OUTSTANDING RESPONSE ITEMS NUREG-0612 - CONTROL OF HEAVY LOADS POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 This is in response to your letter of February 1, 1982 which requested a schedule for submittal of the outstanding 4
information concerning our responses regarding NUREG-0612,
" Control of Heavy Loads at Nuclear Power Plants".
The attachment to this letter provides our expected schedule for the submittal of this information.
As you recognize, our six-month and nine-month reports have provided the substantial majority of the information requested by NUREG-0612.
We trust that the extended schedule for submission of the few items presently unavailable will not adversely affect your review effort.
The commitment dates in the attached schedule are l
dependent on a number of factors.
Of particular concern are j
the dates for the proposed submittal of information relating to the single failure proof handling system to be installed l
in the Point Beach auxiliary building (NRC question attachment i
1-1 through 1-3).
As stated in our nine-month response, sections j
2.3.1 through 2.3.3, this information cannot be completed until a vendor for this equipment has been selected and an order l
placed.
As noted in our previous submittals, our schedule for the installation of.this equipment calls for completion within two years of the date of our nine-month report.
Within this time frame, we are providing the attached estimates as to when j
the analyses requested in NRC question attachment 1-2 and 1-3 7
will become available.
.i
(
' B203020521 820225 DRADOCK05000g
Mr. H. R. Denton February 25, 1982 We will notify you if we encounter any delays in completing this outstanding information.
Please contact us if you have any questions.
Very truly yours,
/
"5 Assistant ice President C. W. Fay Attachment Copy to NRC Resident Inspector Subscribed and sworn to before me this M:d8t, day of February 1982.
M.T
_--- C o Notary PuMic, State of Wisconsin My Commission expires d /,l d f.
v
(
r J
- OUTSTANDING RESPONSE ITEMS NUREG-0612 - CONTROL OF HEAVY LGADS SIX AND NINE-MONTH REPORTS Proposed Submittal Date SIX-MONTH REPORT Section 4.3.4 Lifting Rig Compliance with ANSI N14.6-1978 (NRC Question 2.1.3.D) 06/01/82 NINE-MONTH REPORT Section 2.3.1 Manufacturer and Design Information on Single Failure Proof Crane (NRC Question -1) 09/15/82 Section 2.3.2 Analysis of Compliance to NUREG-0554 for Single Failure Proof Crane (NRC Question -2) 12/31/82 Section 2.3.3 Seismic Analysis of Single Failure Proof Crane (NRC Question Attachment 1-3) 12/31/82 Section 2.3.5 Interfacing Lift Point Evaluation (NRC Question Attachment 1-5) 06/01/82 Section 3.4.2-Reactor Vessel Head Drop Analysis (NRC Question 2.3-4-b) 09/15/82 Section 3.4.3 Exceptions taken to NUREG-0612 Guidelines in Performing Reactor Vessel Head Drop Analysis (NRC Question 2.3-4-c) 09/15/82 l
[