Notifies That on-shift Personnel Will Be Trained to Perform Appropriate short-term Emergency Maint Functions by 820701 in Response to Generic Ltr 81-10,per NUREG-0654,Revision 1, Item III.A.1.2
ML20041C336
Person / Time
Site: Trojan File:Portland General Electric icon.png
Issue date: 02/19/1982
From: Withers B
PORTLAND GENERAL ELECTRIC CO.
To: Clark R
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0654, RTR-NUREG-654, TASK-3.A.1.2, TASK-TM GL-81-10, TAC-46131, NUDOCS 8203010182
Download: ML20041C336 (2)


Text

-

p E #,. 7, y" um.m

~

co Portlanci General Electric CtvTixiny 0 0 IG82 r

%g,d,, ymp/j D

i, M C:4 re,.

sy e r,m, b y

q February 19, 1982 Trojan Nuclear Plant Docket 50-344 License NPF-1

~

Director of Nuclear Reactor Regulation ATTN:

Mr. Robert A. Clark, Chief Operating Reactors Branch No. 3 s

Division of Licensing U. S. Nuclear Regulatory Commission Washington, DC 20555

Dear Mr. Clark:

Radiological Emergency Response Staffing On February 18, 1981, PGE received NRC Generic Letter 81-10, requesting a commitment to the implementation schedules for TMI Action Plan Item III.A.l.2 (Upgrade Emergency Support Facilities). Included in Item III.A.l.2 was a requestxfor a commitment to the on-shift emergency

\\

staffing guidance of Table B-1 of NUREG-0654, Revision 1.

PGE responded to Generic Letter 81-10 on April 15, 1981.

Included in the PGE response was a commitment to maintain one maintenance technician on shift to perform emergency electrical /I&C/ mechanical maintenance.

10 CiR 50.47(b)(2) requires " adequate staffing to provide initial facility accident response in key functional areas" to be maintained at all times.

After examination of this regulation and the short-term maintenance requirements following an accident, it is concluded that emergency maintenance functions ~can be performed adequately in the short te m by existing on-shi f t personnel. Therefore, an on-shift maintenance tech-nician is not required.

PGE will provide any additional training necessary to ensure that the on-shift personnel are qualified to perform appropriate short-term emergency maintenance functions which may be required prior to aug-mentation of the Plant Staff with off-shift personnel. In addition, a telephone call list will be established for maintenance personnel according to their area of specialization. This call list will ensure oh y0 P2030iO182 820219 PDR ADOCK 05000344 L Pocand.Orecpn 97204 F

PDR

Portland General ElechicCompany o

Mr. Robert A. Clark February 19, 1982 Page two that personnel with the proper skills can be called in to augment the Plant Staff within I hour following an accident.

This program will be implemented by July 1, 1982.

Sincerely, Bart D. Withers Vice President Nuclear c: