ML20034F599
| ML20034F599 | |
| Person / Time | |
|---|---|
| Site: | Limerick |
| Issue date: | 02/26/1993 |
| From: | Eckert L, Nimitz R, Pasciak W NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | |
| Shared Package | |
| ML20034F589 | List: |
| References | |
| 50-352-93-04, 50-352-93-4, 50-353-93-04, 50-353-93-4, NUDOCS 9303040038 | |
| Download: ML20034F599 (38) | |
See also: IR 05000352/1993004
Text
_
_
..
.
U. S. NUCLEAR REGULATORY COMMISSION
REGION I
Report Nos. 50-352/93-04
50-353/93-04
Docket Nos. 50-352
50-353
License Nos. NPR-39
NPR-85
Licensee:
Philadelphia Electric Company
Eggespondence Control Desk
P.O. Box 195
Wayne. PA 19087-0195
Facility Name: Limerick Nuclear Generatine Station. Units I and 2
Inspection At: Limerick. Pennsylvania
.
Inspection Conducted: January 19-22. and February 1-3 and 8-12.1993
Inspectors:
RLN'A-
d 2@,3 _
R. L. Nimitz, CHP, Senior" Radiation Specialist
date
RLM4 &
~24 2 L113.
'
~
L. L. Eckert, Radiation Specialist
date -
C. K. Battige, Intern
Approved by:
M.
M
2-74- D
W. Pasciak, Chief, Facilities Radiation
date
Protection Section
i
Areas Insoected: Circumstances, evaluations and corrective actions associated with two.
radiological controls events that occurred on May 31,1992, and January 27,1993. The
.
.
events involved workers handling traversing incore probe (TIP) tubing under, respectively, -
the Unit I and Unit 2 reactor vessels. In addition, planning and preparation for the Unit 2
refueling outage, were reviewed with particular consideration given to identification of failed
,
fuel, organization and staffing, external and internal exposure controls, radioactive material-
j
controls, and the ALARA program.
.i
l
.9303040038 930226
i
'PDR
ADOCK 05000352
1
0
.PDR
i
d
4
i
.
2
Results: No significant intake of airborne radioactive material by, or external exposure of,
personnel, occurred during the event involving TIP tubing, although the potential for a
significant intake existed in the January 27,1993 event. With regard to the Unit 2 refueling
outage, the inspector concluded that generally effective planning and preparation, in
consideration of the failed fuel, was performed. The inspector also concluded that timely
efforts were taken to up-date radioactive waste shipping data to reflect the potential for
additional radionuclides attributable to the failed fuel. Observations during the outage
identified generally good ALARA efforts. Six apparent violations were identified. The first
apparent violation (Section 7.2.3 of this report) involved failure of the radiological controls
technician monitoring the January 1993 TIP work activity to adequately survey the area and
identify radiological contamination. Such surveys are required by 10 CFR 20.201 to comply
with 10 CFR 20. The second apparent violation (Section 7.2.5), also associated with the
January 1993 TIP activity, involved failure to adequately instruct workers in the presence or
likely presence of high levels of contamination contained within the TIP tubes and the -
precautions and procedures to minimize exposure. Three apparent violations (Sections 7.3.2
and 8.0) involved failure to adhere to radiation protection procedures as required by
Technical Specification 6.11. They involved inadequate preparation for work activities under
the Unit I reactor vessel, inadequate surveys during removal of material from the spent fuel
pool, and inadequate airborne radioactivity sampling during TIP drive work. The remaining
violation was a non-cited violation (Section 8.0) that involvea failure of four workers to sign-
in on the proper radiation work permit, a violation of T.S. 6.11. Lastly, several significant
weaknesses were also identified involving coordination, communication and work control.
,
t
t
L
&
- - _ . , -
.
DETAILS
1.0
Individuals Contacted
4
1.1
Licensee Personnel
1) 2) J. Doering, Plant Manager.
1) 3) J. Phillabaum, Licensing Engineer
1) 2) G. Murphy, Senior Heakh Physicist
1)
G. Hunger, Project Manager
T. J. Jackson, Sr. Chemist
R. C. Ragland, ALARA Engineer
T. Mscisz, Assistant Senior Health Physicist
1.2
NRC Personnel
~'
3) E. Wenzinger, Chief, Division of Reactor Projects Branch 2, RI
1) T. Eastick, NRC Resident Inspector, Limerick Station
2) T. Kenney, NRC Senior Resident
The inspectors also contacted other licensee individuals during the course of
this inspection.
1) Denotes those individuals attending the exit meeting on February 3,1993.
2) Denotes those individuals present at the January 22, and February 8 and 12,
1993, exit meetings.
3) Denotes those individuals present at the January 22, February 3 and
February 8,1993, exit meetings.
2.0
Pumose and Scope of Insnection
This was a combined inspection that included an announced radiological controls
initiative inspection; a special, reactive radiological controls inspection; and an
unannounced radiological controls inspection of outage activities. The following
matters were reviewed:
-
The initiative inspection was conducted during the period January 19-22, 1993,
.
and focused on review of the licensee's planning and preparation for the Unit
2 refueling outage, including licensee efforts to deal with failed fuel.
-
The special, reactive inspection was conducted during the period February I-
8,1993, and included review of events that occurred on January.27,1993, and
May 31,1992. Both events involved workers handling traversing incore
probes (TIPS) tubes. The January 27,1993 event involved workers
disconnecting TIPS and unknowingly introducing very high levels of
,
.
. .
.
.
.
.
.
. .
i
1
.
1
1
4
'l
radioactive contamination (measuring up to about 300 millirad /hr removable)
into their work area. The activity resulted in the potential for a significant
intake of radicactive material by the personnel involved. The May 31,1992,
event involved workers testing TIP tubes under the Unit I reactor vessel.
i
.I
-
The inspector review of the outage, conducted during the period
'
February 8-12, 1993, included the licensee's implementation of the
radiological controls program for the Unit 2 outage.
During the course of the inspection, the inspector reviewed applicable documentation,
including radiation surveys, independent licensee evaluations, training records and -
]
radiation work permits. The inspector also discussed with cognizant personnel the
j
circumstances surrounding the TIP events. The inspector observed the approximate
j
work area locations using a digital optical tour program (C-Vue) maintained by the
j
licensee. The inspector also toured work areas as appropriate and performed direct
observation of on-going work activities.
i
3.0
Plannine and Preparation for Unit 2 Outace
-
-
.!
The inspector met with cognizant licensee personnel and reviewed the licensce's
efforts in the area of planning and preparation for the upcoming refueling outage at
Unit 2. The following matters were reviewed:
-
planning and preparation in consideration of failed fuel'
-
increase in health physics staff, including station's method for ensuring
supervisory control over contracted radiological controls technicians
-
special training, including use of mock-ups
-
increased supplies, including such items as temporary shielding
-
ALARA considerations, including work package review by health physics,
1
dose reduction methods, and radwaste reduction
-
adequacy of licensee controls and monitoring of contractor work standards
-
early involvement of the health physics group and knowledge of work to be
performed.
Evaluation of the licensee's performance in this area was based on discussions with '
personnel, review of documents and independent observations of on-going activities.
The inspector's review indicated that the licensee implemented generally good
planning and preparation for the upcoming outage. The following matters were
identified
The licensee was very sensitive to the need to effectively plan for the Unit 2
-
outage in consideration of the identified failed fuel and areas for enhancement
1
identified during the last Unit I refueling outage. The licensee's radiological
i
i
..
.
,
5
,
controls organization developed a plan to deal with potential Unit 2 failed fuel
concerns. For example, the licensee implemented a special training program
(Radiation Worker Supplement Seminar) for radiation workers. About
800 radiation workers had attended the program. The training program
provided training in areas such communications, emerging issues, and fuel
i
failure concerns at Unit 2.
The licensee established and distributed a Limerick Second Refueling Outage
-
Manual. The manual included, among other information, the following:
-
proper method to change outage work scope
-
detailed organization charts
-
radiological controls points of contact
!
-
information on reporting quality concerns via the quality concern -
hotline -
-
identification of outage teams and charter for teams (pre-outage, during
outage and post-outage)
This was considered a very good initiative.
-
The licensee increased the number of contracted radiological controls
personnel brought on site to support the outage. The technicians were provided
Technical Information Notices designed to inform them of potential
radiological concerns associated with failed fuel. The licensee also provided
dedicated radiation protection supervisors to oversee activities at the refueling
floor and drywell control points.
-
The licensee established a work control center to enhance management of
outage activities.
-
The licensee developal radiological controls checklists to be used by
supervisors to oversee on-going work activities. Supervisors performed daily -
tours to observe on-going activities and correct concerns as identified using the
checklists.
'
'
-
The licensee ordered 28 new high efficiency particulate air (HEPA) filtration
units. A number of the units have the capability to be fitted with charcoal
filters for removal of iodine. The licensee also ordered 75 powered air
'
purified respirators for personnel use.
i
A Shutdown Strategy Task Force was established to plan the Unit 2 shutdown.
-
The licensee performed a modified soft shutdown to minimize crud bursts.
i
1
.
.
6
The following matter was noted:
-
The inspector selected for review three ALARA Reviews performed for
planned outage work. The three reviews were:
-
Control Rod Drive (CRD) and Support Activities
-
Main Steam Relief Valves and Modification 6101
-
Main Steam Isolation Valve Preventative / Corrective Maintenance.
The inspector's review indicated that although the Unit 2 outage had already
commenced, none of the three reviews selected had been reviewed and
approved by radiological controls and work group supervision for use. Also,
the ALARA review for the CRD work was the Limerick Unit I review from a
previous outage. The inspector's discussion with licensee representatives
indicated that, since the licensee's Unit 2 facility ran at power for about
540 days, and Unit 2 experienced failed fuel, the licensee's ALARA group
delayed approval of the ALARA reviews pending verification of radiation dose
rates. The inspector noted that the reviews were approved when the reactor
was shut down and up-to-date radiation dose rates incorporated into the
!
ALARA reviews.
No safety concerns or violations were identified.
4.0
Exposure Controls for Failed Fuel
The inspector reviewed the licensee's internal and external exposure control program
to support outage work activities. In particular, the inspector reviewed the licensee's
enhancements of the program to address potential concerns associated with leaking
fuel elements. The following matters were reviewed:
-
exposure estimates for ALARA planning purposes
-
acceptability of current dosimetry system for measuring radiation exposure
associated with failed fuel
-
instrument calibrations
-
hot particle controls
-
air sample collection and analysis
-
bioassays and assessment of intakes of airborne radioactivity
The inspector's review indicated that the licensee provided good review of potential
radiological concerns associated with failed fuel. The inspector noted that the licensee
l
penormed a comprehensive evaluation of poter.dal alpha monitoring concerns. As a
j
result of this evaluation, the licensee purchased additional alpha air sample and smear
sample counting systems, revised procedures to provide for improved air sample
,
l
i
.
-
7
i
counting capabilities, and reviewed calibration of instruments considering potential
changes in energy spectra of the radiation types to be encountered.
The following matter was noted:
-
The licensee calibrated beta radiation survey instruments with a depleted
uranium slab source. Discussions indicated the energy of the source is higher
than the average beta energy in the plant. As a result, the use of the source
would result in slight underestimation of beta dose rates. The licensee's -
radiological controls personnel indicated they were aware of this matter and
4
were reviewing the need to purchase new sources.
-
The licensee developed draft guidelines for use in evaluating potential intake
by personnel of alpha emitters. The guidelines would be used by personnel in
conjunction with whole body count results to estimate potential intake of alpha
emitters.
The licensee modified surveillance procedures to enhance the survey program
-
for alpha e-mitters.
The following matter was brought to the licensee's attention:
-
The inspector reviewed the licensee's program for performing skin dose
estimates of personnel contamination. The inspector was initially informed that
the general equation used for initial skin dose estimates was based on dose rate
data for Sr-90. When questioned about the adequacy of the formula and its
applicability for fuel fragment hot particles, the licensee detennined that the
equation was based on Co-60 and that no guidelines were in place for
determination of skin dose attributable to fuel fragments. The inspector's
review indicated that the equation potentially could underestimate the skin dose
by a factor of at least two.
The inspector noted however, that the equation was used for initial evaluation
and that additional, more rigorous, evaluations were performed if the initially
j
calculated exposure exceeded 75 millirem. The licensee indicated that
previous calculations would be reviewed to ensure that all appropriate skin
contamination events were reviewed more rigorously if required. The licensee
also initiated action to develop guidelines for determination of skin doses
attributable to fuel fragment hot particles.-
-
The inspector's review and discussions with in-field radiological controls
technicians indicated they did not fully understand the ramifications of the
effect of the changes in' the mix of radionuclides on interpretation of
instrument readings. For example, the inspector's review of airborne
-
-
__
..
.
1
8
'
,
radioactivity data for turbine work on February 7,1993, identified about
107 times the maximum permissible concentration (MPC) for unidentified
alpha emitters and about 80 times MPC for beta emitters. However, a gamma
scan of the same air sample identified only 6 times the maximum permissible
concentration (MPC). The technician who was controlling the work at the
turbine location was not able to inform the inspector as to the significance of
these values and/or which ones were correct and the appropriate values to use
for personnel protection purposes. The inspector noted that personnel in the
work area wore appropriate respiratory protective equipment which provided
more than adequate protection for the identified airborne radioactive
contamination.
The licensee initiated a review of the inspector's observations.
.
5.0
Part 61 Analysis
The inspector met with cognizant licensee personnel and reviewed the licensee's
efforts to update Part 61 analyses. The licensee uses the evaluations for purposes of
classifying radioactive waste shipped off site for disposal.
The inspector's review inc'icated that the licensee's radwaste personnel became aware
'
of potential changes in the radionuclide abundances via review of periodic sample
analysis results of reactor coolant samples. Discussions indicated appropriate
evaluations and modifications of their radwaste computer program were made in a
timely manner.
No safety concerns or violations were identified
6.0
bl. ARA Efforts
6.1
General
'
The inspector reviewed selected aspects of the licensee's ALARA Program.
The principal focus of the review was the observation of on-going work
activities to determine if work was performed in a manner to maintain
personnel radiation exposures as low as reasonably achievable (ALARA). The
review was with respect to general guidance and criteria contained in the
following-
!
-
Regulatory Guide 8.8, Information Relevant to Ensuring that
Occupational Radiation Exposures at Nuclear Power Stations will be As
,
Low As Is Reasonably Achievable
!
i
i
i
..
I
4
.
.
9
-
Regulatory Guide 8.10, Operating Philosophy for Maintaining
Occupational Radiation Exposures As low As Is Reasonably
Achievable
-
NUREG/CR4254, Occupational Dose Reduction and ALARA at
Nuclear Power Plants; Study on High-Dose Jabs, Iladwaste Handling
and ALARA Incentives.
-
Electric Power Research Institute (EPRI) Radiation-Field Control
Manual-1991 Revision
The evaluation of the licensee's performance was based on discussions with
cognizant personnel, independent inspector observations during tours of the
station, observations of on-going work activities, and review of documentation.
The inspector's review of on-going work activities indicated that generally
effective ALARA planning had occurred. The following observations were
made:
-
Radiation shielding was installed throughout the drywell to reduce
ambient radiation fields. Informational postings were noted posted at
various locations within the drywell to inform personnel of ALARA
low-dose wait areas and elevated general area radiation dose rates.
Personnel were provided briefings which included radiation dose rate
information.
-
The inspector noted that after shutdown of Unit 2 for the outage,
detailed radiation surveys for the drywell showed little if any significant
contamination levels or airborne radioactivity inside the drywell. This
was noteworthy considering the licensee's extensive run of the unit (@
540 days).
-
ALARA pre-job review packages were considered to be of generally
'
good quality.
The following matters were noted and brought to the licensee's attention:
i
.
-
During tours of the Unit 2 drywell, the inspector observed. tool boxes
located in elevated radiation fields on various levels of the drywell. In
one instance a worker was observed sorting tools in an elevated
radiation field at the tool box. The licensee moved the tool boxes to
.
lower radiation dose rate areas.
.
-
The inspector observed contractor personnel performing non-destructive
testing of piping in the drywell. The inspector observed the individuals
experiencing difficulty attempting to power a light for their work.
y
!
i
,
.
.
10
i
Several of the electrical outlets they tried were net powered. The
workers were searching for power in up to 35 mR/hr radiation fields.
The licensee's radiation protection personnel were aware of the concern
with apparent shortage of powered outlets and were reviewing the
matter.
6.2
Zine Iniection
Industry experience has shown that zine (Zn)in solution in the reactor water
system at BWRs has a positive effect on reducing radiation dose rates on
primary piping (i.e., piping that carries reactor coolant). Some BWRs have
installed systems to inject Zn to reduce radiation fields caused by activation
4
product buildup.
,
In many plants, Zn is already present, not as an additive, but because of brass
condensers which have leached zine into the coolant system. . If the condenser
i
is made of titanium or stainless steel, no zine is available to leach into the
system. Plants with brass condensers and deep bed demineralizers, which are
'
more effective at removing ionic impurities than powdered resin
demineralizers, do not show the beneficial effects of Zn since any Zn present
i
would be removed by the demineralizers.
During the last outage at Unit 1 (IR04), results of a specific activity survey
performed on the "B" recirculation suction line indicated Co-60 (cobalt-60)
and Co-58 contributed 77.5% of the total isotopic dose. After the first outage
at Unit 2 (2R01), a similar survey showed Co-60 and Co-58 contributed 66%
of the isotopic dose. Any cost beneficial operation which would remove or
lessen the Co coolant concentration and subsequent plate out would reduce
,
exposure to plant workers and be consistent with ALARA policies.
In an effort to better remove ionic impurities, to improve plant chemistry,
Limerick Generating Station (LGS) installed deep bed demineralizers for both
units. The new demineralizers became operable in July 1992 at Unit I and
"
will become operable at Unit 2 after the current outage (2R02). Since 2n,
which had been present because of the brass condensers, will be removed with
the new demineralizers, LGS installed the General Electric Zinc Injection
Passivation System (GEZIP) to maintain a level of Zn in solution in the reactor
coolant. The system became operational on August 10, 1992, for Unit I and
-
February 13,1992, for Unit 2. This activity is governed by LGS Procedure
No. S06.8.B, "Startup of Zinc Injection System," Rev.1, dated April 16,
1992.
The amount of zine injected to obtain the desired level is determined by LGS
Procedure No. CH-830, " Zinc Injection System Zinc Oxide Concentration
.
z
.
.
.
.
11
Calculation," Rev. O, dated January 2,1992. The target level for the
feedwater (FW) system is 60 ppm, equal to the amount historically in the FW
system. To prevent plating out of Zn on surfaces exposed to the reactor
coolant, the concentration of Zn is maintained at the level mentioned above
and the zine injection system is shut down when power is below 80%. No
problems have been encountered with the Zn-65 isotope, which has been a
concern at other BWR plants. Zn in the reactor is kept at a concentration of
approximately 1 to 2 ppm.
,
Results
No significant reductions in dose rate or coolant activity have been noted with
the GEZIP system in service. However, the licensee identified a number of
factors to explain these results. The current level of Zn (with use of GEZIP)
was essentially the same as previous operation (before deep bed demineralizer
installation). Both units, which are relatively new, have shown very low dose
,
rates compared to other BWRs from primary piping, and low levels of
contamination. Indications of potential fuel failure problems on Unit 2, as
discussed elsewhere in this report, began on September 1,1992. Fuel failure
and the resultant release of fission products into the coolant system appeared to
have overshadowed some of the positive exposure reduction effects of the
GEZIP system at Unit 2. The licensee also experience failed fuel at Unit 1.
The inspector noted however, that the licensee's efforts to install the Zn
injection system following the installation of the deep bed demineralizers was
considered a very good ALARA initiative.
No safety concerns or violations were identified.
7.0
Traversing Incore Probe (TIP) Events
t
7.1
General Descriotion of the Evgris
On January 27,1993, the licensee experienced a contamination control
problem under the Unit 2 reactor vessel during removal of traversing incore.
probe (TIP) tubes. During the event, workers removing the tubing were
unknowingly exposed to high levels of radioactive contamination. During the -
.
review of the event, the inspector became aware of a previous TIP event
which occurred at Unit 1 on May 31,1992. During the earlier event, workers
also v.are exposed unknowingly to high levels of radioactive contamination
while testing TIP tubes under the reactor vessel with a " dummy" TIP tube.
,
o
.
..
12
The inspector reviewed the two events. Evaluation of the licensee's
performance in this area was based on review of documentation, discussion
with cognizant personnel, and observations. The inspector interviewed
workers associated with the January 27,1993, event and discussed the
May 31,1992, event with cognizant radiological controls personnel.
7.2
January 27.1993. Traversine Incore Probe (TIP) Tube Event Description
7.2.1 General
Figure 1 (attached) shows a typical arrangement of the traversing incore
detector system for a boiling water reactor. The detectors (called
probes) are driven by a mechanical drive system locatal in the reactor
building. The drive system drives the probes through a hollow tube
(called TIP tubes), through a drive path selector (called an indexer) into
the reactor core. The drive system consists of five separate drives
(each capable of driving one probe and identified as drives A through
E). The system uses gamma sensitive detectors to provide an axial
indication of neutron flux.
During a refueling outage, a percentage of control rod drive
mechanisms, which enter the reactor vessel from the bottom, are
replaced. In order to remove the drives, the TIP tubes, located under
the reactor vessel, are removed. Prior to their removal, the detectors
are retracted into special shields located in the TIP Room (also located
in the reactor building).
Because the tubes are lined up in rows, the tubes are typically removed
by removing the outer rows first followed by the inner rows. The rows
are lettered A through G. Figure 1 shows the location of the TIP tubes
and the area where the workers were working.
,
,
7.2.2 Description of Event
The task of removing the TIP tubes was assigned to a Nuclear .
Maintenance Division (NMD) Reactor Services Section work group on
January 26,1993. The actual planning and preparation for the work
activity was conducted during the period January 18-22, 1993.- At that
time, the Job Foreman met with cognizant radiological engineering _
personnel and discussed the work activity and ALARA review. Matters
that were discussed included removal path of the tubes, storage
,
locations, and use of " dose bags" to minimize potential contamination.
The " dose bags" are small plastic bags typically used to contain
.
13
personnel dosimetry and preclude its contamination when working in
contaminated environments. The bags were to be placed over the ends
of the TIP tubes to prevent release of radioactive contamination from
the tubes. The bags were being used in lieu of plugs or caps specified
in procedures due to the unavailability of a sufficient quantity of plugs
or caps.
Note: The inspector determined that the radiological engineering
personnel did not expect any.significant' contamination associated
with the removal of the TIP tubes. The inspector was informed
that typical levels previously encountered were on the order of
2
50,000 disintegrations per minute (dpm) per 100 cm . The
inspector verified this by review of all post outage reports for
Units 1 and 2. It was noted during this review, however, that a
significant contamination event involving improper testing of -
TIP tubes occurred on May 31,1992, during the Unit 1 fourth
refueling outage. (See Section 7.3 of this report.)
The work crew that was to remove the TIP tubes normally worked
from 10:00 p.m. to 8:00 a.m. the following morning. At about
10:00 p.m. on January 26,1993, the Job Foreman met with the Job
Leader responsible for directing the work crew. The Job Foreman
provided a copy of the ALARA review for the task to the Job I2ader
and discussed the performance of the task. Prior to performance of the
task, the Job Leader walked down appropriate sections of the clearance
request and system tagout (Clearance No. 92007667). The Job leader
also provided a pre-job briefing to the work crew. The crew had been
selected based on their level of experience with the system.
.
Note: Inspector discussions with individual work crew members
indicated the workers either had extensive experience working
with the TIP system and/or had attended training on the TIP
system at the licensee's training center.
A radiation work permit (RWP) (No. 07027, Revision 0,
Remove / Install and Test Tip Tubes) was issued for the work activity on
e
January 22,1993. Among other controls, the permit required a survey
on breach of the system. Personnel signed in on the RWP compliance
'
sheet indicating they had read and understood the permit. The workers
also received an ALARA briefing from the radiation protection drywell
control point leader. The complete ALARA review (Removal of TIP
Tubing and TIP tube Supports, dated January 22,1993) for the task
,
was covered during the briefing. During the briefing, workers were
informed that the interiors of the TIP tubes were contaminated.
14
Subsequent to the briefing, workers signed into the work area using
" live time" computer sign-in. The workers wore one set of protective
clothing and a faceshield.
The actual removal of the TIP tubes involved two separate entries
under the reactor vessel by work crews consisting of 5 individuals.
During the entries, four individuals entered the area under the reactor
vessel to remove the tubes while the Job Ieader remained outside the
control rod drive chute to remove and store the TIP tubes.
The first entry was made at about 1:00 a.m. on January 27,1993 and
lasted about 1.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> (about 1:00 a.m. to 2:30 a.m.) A radiation
protection technician accompanied the four workers under the reactor
vessel during the entry and made general area radiation measurements
and smear checked both the inside and outside of the tubes. A cotton
swab was used to smear check inside the tubes.
Note: The inspector's discussions indicated that only two tubes
were checked inside for smearable contamination. These tubes
were apparently in the A and G row of tubes.
Note: The radiadon protection technician who accompanied the
work crew had no previous experience in oversight of removal
of TIP tubes. In addition, the review of the individual's
qualification card indicated he had not been authorized (based on
lack of a Radiation Protection Supervisor signature) to perform
work independently. The radiation protection drywell control
point leader did not know that this individual had no previous
experience in removal of TIP tubing however, he felt that he
was an experienced individual.
The survey (Reference Survey No. 93-02527) made during the work
indicated general area radiation levels of about 8-120 millirem /hr
(depending on proximity to bottom head drain line) and contamination
2
levels of less than 1000 dpm/100 cm on the exterior of the TIP tubing.
However, the interior of the TIP tubing measured up to 1600
millirad /hr (beta dose rate) on contact with the opening of a tube and
up to 4 millirad /hr per cotton swab removable surface contamination.
The workers were not informed of these latter readings. The radiation
protection drywell control point leader was informed of these readings.
The readings were not considered of concern. An air sample collected
during the entry indicated 18% maximum permissible concentration
(MPC) when field counted at 3:00 a.m. on January 27,1993.
7
15
.
The workers completed removal of 4 of 7 rows of tubes (A and B, F
and G), and exited the area about 2:30 a.m. The workers used whole
body friskers at the Unit I drywell because the Unit 2 whole body
friskers were apparently out of order. The workers' frisk indicated no
contamination was present.
The second work crew entered the area about 4:00 a.m. on January 27,
1993, and worked until about 5:30 a.m. This work c'rew consisted of
the same work crew as the previous entry with the exception that one
worker was replaced by a different worker. The new worker received
a pre-job briefing from the Job Leader. The workers were not
accompanied by a radiation protection technician and no additional:
radiation surveys or contamination checks were performed as the
workers removed the remaining rows of TIP tubes (Rows C, D and E).
Unknown to the workers, the tube rows associated with TIP drive E
were highly contaminated, with contact beta radiation readings on the
ends of the tubes measuring up to 24,000 millirad /hr. Removable
contamination inside the same tubes measured up to 1000 millirad /hr on
~
a small cotton swab.
Note: These values were based on measurements made on
January 30,1993, and have not been decay-corrected to -
January 27,1993. Because of the short half-lives of
molybdenum-99 and technetium-99m, the initial values, on
January 27,1993, would have been higher. Figures 3 and 4
(attached) provide the results of the licensee's contamination and
radiation measurements of each TIP tube.
An air sample was collected during the second entry. The sample,-
,
which ran from 5:15 a.m. until about 5:50 a.m., was analyzed and
indicated 22% MPC.
When the work crew exited the drywell and removed their protective
clothing, they attempted to use the whole body friskers at the Unit 2
drywell, but found them to be out of service. The work crew exited
Unit 2 and used the whole body frisker at the Unit I drywell control
point area. Of the 5 individuals involved in the work activity,4 were
found to be contaminated. Three of the workers exhibited nasal and
'
skin contamination.' Maximum nasal contamination. identified on any
one individual was 3000 counts per minute (cpm) per cotton swab. The
maximum skin contamination detected was about 2000 cpm using a
2
15 cm end window probe. One of the four workers who was
contaminated was believed to have become contaminated after he exited
i
.
16
the work area. The inspector noted that one of the five workers had
put on portions of street clothing (pants) prior to frisking and had
carried his other street clothes to Unit 2. This worker's clothing was
found to be contaminated.
Subsequent contamination surveys taken in the area at 6:45 a.m. on
,
January 27,1993, identified contamination levels on the grating under
2
the reactor vessel of up to 320 millirad /hr per 100 cm . A
contamination survey made at 7:00 a.m. on the same day identified
contamination levels on the grating in the area under the reactor vessel
2
ranging from 8 to 240 millirad /hr per 100 cm removable
contamination. The licensee believes a fan may have been started
which dispersed the contamination. A survey taken outside the area of
the control rod drive (CRD) chute and general areas of the 238'
elevation of the drywell identified contamination levels ranging from
2
10,000 - 300,000 dpm/100 cm . Prior to the event, these same areas
2
exhibited contamination levels less than 5,000 dpm/100 cm . The
inspector noted that portions of these areas were accessible to personnel
in street clothes who wore protective shoecovers.
Figure 2 (attached) shows the contamination levels generated following
the removal of the TIP tubes. Figures 3 and 4 (also attached) show the
levels of contamination of the TIP tubes. Figure 3 shows the data
arranged by TIP tube row. Figure 4 shows the data arranged by TIP
drive box. (Note the elevated contamination levels associated with
drive box E.)
7.2.3 January 27.1993 Event - Exoosure Controls
The inspector reviewed the external and internal exposure controls
provided for the work activity. The review was with respect to criteria
,
contained in 10 CFR Part 20, Standards for Protection Against
Radiation and applicable provisions of the licensee's Technical
Specifications. The review was also with respect to criteria contained
in the following procedures:
.
-
A-C-107, Revision 0, Radiation Work Permit and Radiological
Controlled Area Access Requirements
.
-
HP 310, Revision 25, Radiation Work Permits
-
HP-216, Revision 3, Performance of Breach Surveys
-
HP-234, Revision 2, ALARA Job Reviews
-
HP-211, Revision 6, Contamination Survey Techniques
-
HP-317, Revision 2, TIP Drive Unit Access
.
17
-
M-059-001, Revision 4, TIP Tube and Support Steel Removal and
Installation
1
The evaluation of the licensee's performance in this area was based on
i
discussions with cognizant personnel and review of procedures.
j
The inspector's discussions with personnel revealed that the work activity
involving the removal of TIP tubing had been performed previously at Unit 1
'
during the past 4 refueling outages and the past refueling outage at Unit 2.
During the previous removals, similar protective clothing (i.e., a single set of
protective clothing and a faceshield) was worn. Also, respiratory protective
,
equipment was not used during the previous removal efforts. The licensee's
radiological controls personnel did specify faceshields to be worn to preclude
inadvertent facial contamination. The inspector's discussions with the
licensee's personnel indicated contamination levels in the area under the vessel
were relatively low and the expected contamination level contained within the
2
TIP tubes was about 50,000 dpm/100 cm . No airborne radioactivity was
encountered during the previous removals.
The inspector noted that during the initial removal efforts on January 27,
1993, between about 1:00 a.m and 2:30 a.m. the licensee's radiation
i
protection technician performed contamination monitoring and noted
contamination levels of up to 8 millirad /hr per cotton swab smearable inside
,
the ends of the tubes and up to 1.6 rad /hr (beta) at the ends of the TIP tubes.
However, this individual was unaware of the expectation that the tubes
typically exhibited substantially lower contamination levels (i.e.,
2
50,000 dpm/100 cm ). The survey information was relayed to the radiation
protection drywell control point leader, but the information was not considered
of concern. As a result of the belief that the readings did not pose any
concern, the radiation protection technician decided that there was no need to
perform any further surveys during the second portion of the tube removal
I
activity.
During the second portion of the removal effort on January 27,1993, from
about 4:00 a.m. to 5:30 a.m., the workers unknowingly disconnected TIP
j
tubing that exhibited high levels of loose surface contamination. Subsequent
'
measurements made by the licensee indicated removable contamination levels,
contained within the tubing, ranged up to 24,000 millirad /hr per cotton swab.
(see Figures 3 and 4 to this report.) Although these levels were contained
within the tubing, upon disconnection at least one end of the tubing was
exposed prior to its bagging. This provided an opportunity for the
contamination to exit the tubing. The inspector noted that contamination levels
2
ranging up to 320 millirad /hr per 100 cm were identified in the work
location.
.
>
9
18
The inspector noted that 10 CFR 20.201(b) specifies that licensees shall make
surveys as (1) may be necessary to comply with the regulations in this part,
and (2) are reasonable under the circumstances to evaluate the radiation
hazards that may be present. 10 CFR 20.201 (a) defines a survey as an
evaluation of the radiation hazards incident to the production, use, release,
disposal or presence of radioactive materials or other sources of radiation
under a specific set of conditions. When appropriate, such evaluation includes
a physical survey of the location of material and equipment, and measurements
oflevels of radiation or concentrations of radioactive material present.
The inspector noted that the initial measurements made by the radiation
protection technician monitoring the removal of the TIP tubes identified
contamination levels considerably above those previously encountered during
TIP removal operations. However, neither additional measurements were
made to evaluate the extent of the radiation hazard present during subsequent
removal of TIP tubes,' nor was an adequate evaluation of the hazard presented
by the elevated contamination levels made. As a result, very high levels of
radioactive contamination were introduced into the work area of 4 workers,
and 3 of the workers sustained personnel contamination. The licensee's
evaluation indicated no significant intake of radioactive material had occurred.
The inspector noted, however, that the lack of a potentially significant intake
,
of airborne radioactivity was fortuitous and not the result of protective actions
taken by the licensee. For example, as discussed above, additional sampling
was not performed to evaluate the radiological hazard present, contamination
j
2
levels ranged up to 320 millirad /hr per 100 cm , and air currents apparently
dispersed the contamination within the undervessel area resulting in levels
2
ranging from about 8 to 240 milliradihr per 100 cm . In addition, the workers -
were working in close quarters in a hunched over fashion, making intakes of
material falling out of open tubing even more possible. The inspector noted
j
i
that although no significant intakes of airborne radioactivity occurred, the
inspector concluded that the failure to make appropriate measurements and
adequately evaluate the hazards of the presence of high levels of loose
contamination contained within TIP tubing on January 27,1993 was an
-l
apparent violation of 10 CFR 20.201(b).'(50-353/93-04-01)
The following additional matters were noted:
1
-
The radiation protection technician assigned to control the radiological
.I
work activities under the reactor vessel had not previously provided
such oversight for TIP tube removal.
J
l
-I
.-
I
.
19
The job planning within the radiation protection group was poor in that
-
it did not provide specific guidance and criteria to the radiological
controls technician controlling the job, and in particular it did not
provide specifics as to whether each tube coupling joint needed to be
surveyed when breached or what actions to take following survey
results.
The ALARA planning for the TIP removal, as discussed above was
-
based on an expected internal contamination level of the TIPS of about
2
50,000 dpm/100 cm . This was not communicated to the radiological
controls technician providing radiological oversight of the TIP removal.
Consequently, the technician was unaware of the significance of the
increased contamination levels.
-
The licensee had experienced an event involving the TIP tubes during
the fourth refueling outage at Unit 1. The event, which occurred on
May 31,1992, and is further discussed in Section 7.3 of this report,
'
involved workers testing TIP tubes prior to installation. The work
activity, which also was performed under the reactor vessel, was not
adequately evaluated by radiological controls personnel in order to
establish appropriate radiological controls for future TIP tubing work.
-
The licensee's corporate group reviewed the event and concluded that
corrective actions for previous events had not been effective in
precluding this occurrence. In addition, the inspector's review of the
May 31, _1992, TIP event indicated that, not withstanding the difference
in work activity that was performed (i.e, removing TIP tubes versus
testing of TIP tubes prior to installation), the corrective actions for the
May 31,1992, event were not effective in precluding occurrence of
-
the January 27,1993, event. Specifically, the method of contamination
control was not effective.
The inspector concluded, based on the above information, that the licensee's
!
radiological controls for the removal of the TIP tubes relied primarily on
previous experience with this work activity and that the program did not
effectively control the work activity when elevated levels of radioactive
l
contamination, substantially in excess of those contamination levels previously -
identified, were encountered. In addition, the high levels of contamination
encountered by personnel were attributed to weaknesses in the licensee's
corrective actions for a previous undervessel contamination event that occurred
in_ May 1992. These observations were considered reflective of program
weaknesses in the area of planning for and oversight of work.
,
m
.
.
.
20
.
7.2.4 E.x.J8mtre Assessment
The inspector reviewed the internal and extetnal exposure assessments
made by the licensee. The inspector reviewed this ' matter with respect
to the criteria provided in 10 CFR Part 20.
The evaluation of the licensee's performance in this area was based on
,
review of exposure results and discussion with cognizant personnel.
The inspector's review of the licensee's results indicated that personnel
did not sustain any significant intake of airborne radioactive material..
-
The initial indications of intake of airborne radioactive material were
'
attributed to personnel skin contamination. Tbc inspector noted that the
licensee needed to re-adjust the whole body counter energy
discriminators in order to readily detect the molybdenum. The skin
exposure of personnel was estimated to be negligible.
7.2.5 Iri ning and Oualifications
d
The inspector reviewed the training and qualifications of personnel
involved in the January 27,1993, undervessel contamination event.
The inspector reviewed this matter with respect to criteria contained in
10 CFR 19 and applicable licensee procedures.
The evaluation of the licensee's performance in this area was based on -
discussions with personnel and review of training records. The
inspector's review indicated the following:
The Job Foreman met with radiological engineering personnel
-
,
about one week prior to the performance of the task. and
,
discussed the task.
The Job Foreman and Job Izader discussed the work activity
-
prior to performance of the task.
The Job leader met with the work crew assigned to remove the
-
TIP tubes. The Job Leader discussed how the task was to be
performed and where the TIP tubes were to be stored.
+
The radiation protection drywell control point leader briefed the
-
workers on the expected radiological conditions. The control
'
point leader read and discussed the ALARA Pre-Job Evaluation.
(RWP LG-2-93-07027, WO No. R0458361).
,
- --
4
_
-
..
,.
.
,
w
'
'
a ,
.9-
.
j
!
y:
21
_
j
The individuals who removed the TIP tubing had either previous -
-
-
i
experience removing the tubing or had attended special training
on this task at the licensee's training center.
l
f
!
-
The workers who performed the task were appropriately.
qualified in accordance with General Employee Training and
y
Radiation Worker requirements.
j
i
'
The inspector reviewed the training and qualifications of the radiation
protection technician who provided radiological oversight of the initial
!
removal of the TIP tubing on January 27,1993. The individual met -
1
the experience requirements of Technical Specifications.' The inspector
l
noted, however, that this was the first time this individual provided
q
ra<liological oversight for removal of TIP tubing. The inspector's.
1
review of the individual's training record indicated he had completed -
j
his on-the-job training requirements. The'se requirements included '
performance of breach surveys. The inspector noted, however, that
,
Step 4 of the technician's training record had not been signed off by a -
Health Physics Supervisor. ' The signature acknowledges that the L ~
,
f
vendor technician has satisfactorily completed the vendor. qualification
sheet and can perform the above tasks without supervision.~ The -
j
-
inspector noted that the licensee's training program procedure (TQ-C-7,-
1
Revision 1,Section 7) specifies that line supervision verifies by
]
signature /date that all required entries have been completed. The
inspector indicated that failure to complete the specified' sign-offs prior'
to allowing the technician to ' perform independently was considered a
1
weakness.
'~
-
More significantly, this individual was unaware of the expectation that
the tubes typically exhibited substantially lower contamination levels .
2
(i.e.,50,000 dpm/100 cm than actually found). The actual ' survey
i
information was relayed to the radiation protection drywell control L
point leader, but the information was not considered of concern. ' As a
>
result of the belief that the readings did not pose any concern, the
j
radiation protection technician decided that there was no need to -
1
perform any further surveys during the second portion of the tube
!
removal activity.
,
The inspector's review of the information provided to the workers .
+
under the reactor vessel indicated that on January 27,1993, between
about 1:00 a.m and 2:30 'a.m. (during the first entry) the licensee's -
!
radiation protection technician performed contamination monitoring and
'
noted contamination levels of up to 8 millirad /hr per cotton swab
.
I
smearable inside the ends of the tubes and up to 1.6 rad /hr (beta) at the-
,{
a
'
.
.
,
.
h
4
22
'
,
ends of the TIP tubes. The radiation protection technician did not
inform the workers of the levels of contamination present. The
inspector's discussions with the workers indicated that the workers were
.
informed that th?. conditions under the reactor vessel were relatively
clean. The waaers were informed to place " dose bags" over the ends
of the tubing to prevent escape of contamination. Based on the
2
contamination levels encountered (up to 320 millirad /hr per 100 cm
removable) the inspector concluded that the method used to install the
dose bags, or the dose bags themselves, were not adequate.
The inspector noted that 10 CFR 19.12 requires that the licensee
c
inform workers of the storage, transfer, or use of radioactive materials
and in precautions or procedures to minimize exposure. The inspector
noted that, on January 27,1993, the licensee did not adequately inform
'
workers as to the presence of high levels of radioactive contamination
or of means to minimize their exposure to such contamination.
Specifically, at about 2:00 a.m., workers were not informed of the
presence of high levels of radioactive contamination contained within
traversing incore detector tubes when such contamination was detected
by a radiation protection technician's measurement. This is an apparent
violation of 10 CFR 19.12 (50-353/93-04-02).
7.2.6 Licensee Assessment
The inspectors' review indicated that the licensee assembled a multi-
disciplinary team to review the event. The team leader reported
directly to the licensee's Vice President- Limerick Station. This was
considered an excellent licensee initiative to understand the root causes
of the event. The team used state-of-the-art investigative techniques.
I
The inspector noted that the team identified a number of apparent root
causes. Some of the more significant ones are as follows:
There was an insufficient understanding of the likelihood of
-
contamination.
-
There were less than adequate surveys.
-
There was less than adequate communication of survey
infonnation.
.
.m
-.
. .
.
.-.
1
23
,
7.3
May 31.1992. Undervessel Contamination Event (Unit 1)
,
s
7.3.1 Description of Event
i.
On May 31,1992, two drywell entries were made during the second
J
shift to conduct TIP work. The first entry was made at the'beginning
of the second shift (@ 2:00 p.m.). The Nuclear Maintenance
Department (NMD) held a pre-job brief concernir n TIP installation and
testing and mechanical stop installation. Radiation protection personnel
were not apprised of this meeting or included in it. However, both
tasks were discussed at the drywell radiation protection control point
and a limited discussion with radiation protection personnel occurred
there.
,
Note: At this meeting, radiation protection personnel were not
apprised that the TIP testing would be performed under the -
reactor vessel versus at the TIP indexer, which is located under
..
the floor grating on the 253' elevation of the drywell outside the
biological shield. The NMD work crew did not inform the
radiation protection control point leader that they intended to test
TIP tubing from the subpile room bridge.
At that time, radiation protection personnel waived the Radiation Work
Permit (RWP) restriction of no subpile room entry to allow movement
of a ladder (only). Workers entered the area under the Unit I reactor
vessel and performed testing of TIP tubes via insertion of a dummy TIP
probe into the tubes. The probe was used to check for any apparent
restrictions in the tubes. The first entry under the vessel occurred
,
between about 3:26 p.m.' and 6:35 p.m. The workers worked on
mechanical s'. ops for the undervessel platform and performed some TIP
testing by ranning the dummy TIP detector in and out of the TIP tubes.
The workers exited the area for lunch with no concerns noted. An air
sample collected during the period 2:30 a.m. to 4:40 p.m. that day
indicated low airborne radioactivity (< .1 times the applicable
10 CFR 20, Appendix B concentration values).
Note: Because no radiation protection personnel had been
.
informed of the planned work activity, the. workers did not have
the benefit of grab sampling for airborne radioactivity or
periodic measurement of radiation and contamination levels in
their work area.
i
,
4
s
.
.
.
.
.
.
~
24
.
Note: When the workers exited for lunch, the dummy TIP cable
and detector were brought out of the under vessel area and
placed on a frisking table at the drywell control point.
Radiation protection personnel were not informed of this action.
No radiation protection personnel were at the control point.
After exiting the drywell, two workers alarmed personnel contamination
monitor (PCM)-1B at the personnel air lock, prcc~xled to a PCM on
Unit 2 253' elevation, and cleared this monitor.
During the second entry between about 8:46 p.m. and 10:53 p.m., the
workers did not use a dummy TIP probe. An airborne radioactivity
sample, collected during the period 4:45 p.m. to 11:30 p.m. that day,
indicated .57 times the applicable 10 CFR 20, Appendix B
concentration values.
,
During this second entry, the drywell radiation protection control point
leader found the dummy TIP cable on the frisking table. Further
investigation by radiation protection personnel found that smear results
2
on the table were 60 mrad /hr per 100 cm (typically < 1,000 dpm/
2
2
100 cm ) and the cable measured 16-40 mrad /hr per 100 cm ,
,
Frisking around the normally clean areas near the frisking table showed
2
300 cpm, as measured with a direct reading GM detector (15 cm ),
Radiation protection personnel questioned NMD personnel concerning
the dummy TIP cable and received no definitive answers. After the
NMD workers exited the drywell, radiological controls personnel
pursued this matter again; the NMD workers apparently continued to
deny any knowledge conceming the dummy TIP cable.
After exiting the drywell the second time, the worker who had used the
dummy TIP cable alarmed the personnel air lock PCM-1B and the Unit
2 PCM. Radiation protection surveys found contamination on the
worker's face, neck, and knees of about 400 to 900 cpm per 15 cnf.
The worker was decontaminated and informed radiation protection
personnel that the cable was a dummy TIP cable and that his work
crew had been using it to test TIP tubing for obstructions.
The inspector noted that subsequent contamination checks under the
reactor vessel identified generally low contamination levels (generally
2
less than 20,000 dpm/100 cm ). One smear indicated 80 millitad/hr,
2
per 100 cm , but was not considered to be in the work location. This
event was documented by the licensee in Radiological Occurrence
Report (ROR)92-025. The ROR was approved on September 11,
1992.
.
25
7.3.2 May 31.1992 Event - Exposure Controls
The inspector reviewed the exposure controls implemented for under-
vessel work. The inspector noted that a radiation work permit was
issued for the work task (RWP No. 1-92-07027, Remove, Install, and
Test TIP Tubes).
The inspector noted that the maintenance work request for this activity
(R0050221), Remove TIP Tubing and Support Steel as Required,
contained as ACTIVITY 6, the task to examine TIP tubes for kinks or
restrictions. This activity, according to discussions with radiation
protection personnel, was planned and had previously been performed
at the TIP tube indexer locatei below the grating on the 253' elevation
'
of the drywell. However, the work crew decided that the activity was
to be performed under the reactor vessel. Radiation protection -
personnel were not informed of this change in location.
The inspector noted that radiation protection procedure A-C-107,
Radiation Work Permit Program and Radiological Controlled Area
Access Requirements, Revision 0, specifies in Section 7.7.5, that health
physics shall brief workers prior to RWP entry on radiological
conditions commensurate with the work to be performed and the areas
a
being accessed. The inspector noted that such instruction was not given.
because workers failed to inform the radiation protection personnel
(health physics) of the activity they were to perform and the areas to be
accessed.
,
The inspector further noted that radiation protection procedure A-C-107
specifies in Section 7.1.2 that all personnel entering the radiological
-
'
controlled area shall employ proper radiological work practices as
presented in Exhibit A-C-107.5 of procedure A-C-107. Exhibit A-C-
107.5 provided examples of proper radiological work practices, which '
included the need to prepare and plan for all radiological controlled
area work sufficiently in advance to allow proper health physics
review. The inspector noted that the maintenance personnel did not
adequately prepare for the undervessel work in advance to allow health
,
physics review in that 1) radiation protection personnel were not
included in a pre-job briefing to discuss the testing of the TIP tubes .
under the reactor vessel and 2) workers entering to perform actual TIP
testing did not inform radiation protection personnel at the drywell
control point that they would be performing TIP tube testing under the
reactor vessel.
4
.
.
.
26
The failure of the workers to properly prepare for the work activity and
'
allow for proper health physics review was considered an apparent
violation of Technical Specification 6.11, which requires adherence to
'
radiation protection procedures. (50-352/93-04-03)
7.3.3 Exposure Assessment
The inspector reviewed the exposure assessment for personnel involved -
in the May 31,1992, undervessel TIP event at Unit 1. The inspector's
review indicated one individual sustained a limited intake of airborne
radioactive material. Maximum exposure sustained by any one
individual was 28 MPC-hrs. This was well below the allowable intake
permitted by 10 CFR 20 (520 MPC-hrs).
7.3.4 Licensee Review
Foilowing the May 31,1992, event, the licensee's corporate group
reviewed the event. The licensee's reviews indicated the following:
-
There was poor communication between the work crew and
radiation protection personnel concerning work scope
-
The TIP Procedure was less than adequate as to the proper use
of t!c dummy TIP and radiological precautions
-
The pre-job briefing on radiological conditions was inadequate
in that radiation protection personnel were not present.
-
The knowledge level of the maintenance crew of the radiological
hazards associated with working on the TIP system was less
than adequate
-
The corrective actions for a previous event were less than
adequate.
-
There was a difference in the degree of radiation protection
coverage of NMD work between Peach Bottom and Limerick
i
Stations.
7.3.5 Previous Examples of Violations Associated with Inadeauate
Communications
1
The inspector noted that the licensee became aware of the May 31,
1992, TIP event when workers were identified as contaminated
following work under the vessel. The inspector noted that, in essence,
the licensee's corporate review team identified the weaknesses in
adequate planning and preparation (attributable to weaknesses in
communication between radiation pretection and maintenance
.
.
4
.
27
personnel), characterized above by the inspector as an apparent
- violation. This violation was similar in cause to a violation issued in
March 1992 (Reference NRC Combined Inspection Report No.
50-352/92-13; 50-353/92-13). The corrective actions for that previous
violation could reasonably have been expected to have prevented the -
,
May 31,1992, apparent violation.
.
8.0
Eadiological Controls
The inspector reviewed routine radiological controls implemented for the refueling
outage at Unit 2. The inspector also reviewed routine radiological controls activities
during tours of Unit 1. The inspector reviewed the following elements of the
license's radiological controls program:
,
-
training and qualification of radiological controls contractor personnel
supporting outage work activities
-
performance and adequacy of radiological surveys to support pre-planning of
work and on-going work
-
use of appropriately calibrated instrumentation to measure radiation and
contamination
-
personnel adherence to radiation protection procedures, radiation work permits
and good radiological control practices
!
-
posting, barricading and access control as appropriate, to Radiation, High
Radiation, and Airborne Radioactivity Areas
-
use of dosimetry devices
.
.i
-
airborne radioactivity sampling and controls, including installation and use of
engineering controls to minimize airborne radioactivity
use of respiratory protection devices.
-
The evaluation of the licensee's performance in this area was based on discussions
with cognizant personnel, review of on-going work activities and review of various
documents.
The inspector reviewed, among other activities, the following:
-
fuel inspection and sipping
-
control rod drive removal and replacement
-
main steam isolation and pressure relief valve work
-
removal of the E- traversing incore detector probe and cable from the E-drive
The inspector identified the following apparent violations:
Non-Cited Apparent Violation (Failure to follow RWP procedure)
.
- .
-
-
-
-
-
- -
-
- -
i
e
28
-
During tours of the Unit I and 2 Refueling Floors on January 19,1993, the
j
inspector noted that the licensee recently initiated radiation work permit (RWP) .
live time computer tracking of workers on the refueling floor. Using this
!
sign-in method, workers sign a form (A-C-107.3A) indicating they have read
and understood their radiation work permit. The workers may then sign in
i
and out of the work area via computer after the radiological controls personnel
,
have authorized live time sign in and out.
At about 1:30 p.m. on January 19, 1993, the inspector observed four
individuals standing on the Unit 2 refueling bridge performing underwater
clean-up activities from the bridge. The workers were suited up in full
u
protective clothing. The following was noted:
,
-
Worker A, performing work on the refueling bridge, was signed in on
form A-C-0107.3 of Radiation Work Permit No. 7070, Operate, Survey
and Inspect Bridge, Revision 1, dated January 19, 1993, but had
actually signed in on (via live time) RWP No. 7051., revision 1,
Support Disassembly, dated January 18,1993.
-
Worker B, also performing work on the refueling bridge, had signed in
on form A-C-107.3 of RWP 7051, Revision 1, but did not sign in at all
(for the work period) on the live time computer prior to working on the
refueling bridge.
The inspector further noted that Unit 2 Technical Specification 6.11 requires
that radiation protection procedures be adhered to. Radiation protection
procedure A-C-107, Radiation Work Permit Program and Radiological
'
Controlled Area Access Requirements, Revision 0, states in Section 7.7 that
personnel are to log into the appropriate dose tracking system and sign the
RWP compliance sheet. The inspector noted that failure to sign in on the
correct RWP compliance sheet and sign in on the dose tracking system was an
apparent violation of TS 6.11. The inspector's discussions with personnel and
observations indicated the following:
<
-
The personnel were immediately removed from the area and required to
sign in on the proper RWP.
-
The workers had been directly obstved by radiological controls
personnel.
-
The workers had been briefed on the proper RWP requirements.
-
The licensee informed all appropriate work crews of this matter.
In light of the above corrective actions and minor health and safety
significance, this matter was considered a non-cited inspector-identified
,
violation.
.
.
.
,
,
29
The inspector's review noted that the two other individuals on the refueling
bridge at the time were not properly signed in on their radiation work permits.
The individuals had signed in (via live time) on Revision 1 of RWP No. 7070,
but they had actually signed Revision 0 of Form A-C-107.3. A radiation
protection technician had apparently authorized the workers to work on
revision 1 of RWP No. 7070 without noticing that they had not signed a sheet
indicating that they had read and understood Revision 1 of RWP No. 7070.
The workers had been properly briefed and, as discussed above, the
individuals were removed from the area and signed the proper documentation.
l
Despite this, the inspector concluded that the workers did not exhibit attention
to detail regarding conformance with radiation protection procedure
requirements.
The inspector's review of this matter indicated that the licensee's radiation
work permit procedures provided little guidance for actions to be taken (either
by workers or radiation protection personnel) following revision of an RWP.
The licensee immediately initiated action to change the procedure and include
the guidance.
The inspector also noted that the licensee's on-site QA group had recently
completed an audit of radiological controls activities. The inspector's review
of the draft audit findings indicated a number of weaknesses had been
identified in the radiation protection area. The inspector indicated to licensee
management that, in light of start of the Unit 2 outage, these weaknesses
should be reviewed for possible enhancements in a timely manner.
Apparent Violation (Failure to Follow RWP Procedure)
-
During observation of fuel inspection activities in the Unit I spent fuel pool at
.
2:30 p.m. on February 2,1993, the inspector observed two contractor workers
removing long handled fuel and fuel channel handling tools from the water.
About 15-20 feet of the fuel handling tool was raised out of the water and
wiped down by hand as an irradiated fuel element was raised and lowered in
the fuel inspection station. About 10 feet of the fuel channel tool was raised
from the pool as the channel was placed back over the fuel following the
inspection. The inspector noted that the radiation work permit controlling the
activity (RWP No. 2-93-07063, Revision 3, Perform Fuel Inspections) stated
in the special instructions and remarks section of the RWP that Health Physics
shall survey all items being removed from water.
The inspector's discussion with the lead radiation protection technician
,
controlling the activity indicated that the tools were surveyed, but that the
technician who had been performing the surveys was called to another location
to survey another item being removed from the pool.
. - -
- .
30
The inspector noted that the licensee's access control and radiation work
permit procedure (A-C-107, Radiation Work Permit Program and Radiological
Controlled Area Access Requirements, Revision 0) states in Section 5.0 that
all workers are to comply with the requirements of the appropriate radiation
,
work permit. The inspector noted that the two contractors did not comply
with the requirements of the radiation work permit in that health physics did
not survey the tools as they were being removed from the water. This is an
apparent violation of Technical Specification 6.11, which requires adherence to
radiation protection procedures. (50-352/93-04-03)
The radiation protection technician informed the contractor workers regarding
'
the need to survey material being removed from the water.
Apparent Violation (Failure to Follow Radiation Protection Procedures)
-
On February 11,1993, during the period 7:00 a.m. to about 10:00 a.m., the
inspector observed the set-up and preparation for the removal of the E-TIP
detector drive cable and probe. The inspector also reviewed video tapes of the
activity. The inspector noted that during the time period, workers periodically
stuck their heads and upper body into the TIP drive box. Figure 5 (attached)
shows the drive box. However, the airborne radioactivity sampler for the
workers was positioned at a distance from the workers. The inspector
concluded that the airborne radioactivity sample being collected during the
work activity was not representative of the workers breathing zone in that:
-
The sampler was located upstream of the flow of air relative to
workers.
-
The sampler was not located as close as possible to the workers (the
sampler was located about 5 feet away).
-
Workers periodically placed their heads and upper bodies inside the TIP
drive box between the source of contamination and a portable
ventilation system. (Levels of radioactive contamination in the TIP
2
drive box ranged up to 14 millirad /hr per 100 cm . See Figure 5)
-
At least one worker positioned himself between the source of
contamination and a portable ventilation system. The air sampler was
upstream of the worker and portable ventilation system.
The inspector noted that Radiation Protection Procedure HP-213, Airborne
Radioactivity Survey Techniques, Revision 9, states in Section 6.1.2, that
ventilation flow paths shall be considered while sampling the breathing zone
and that the sample is to be located as close to the worker as possible without
.
.
.
31
,
interfering with his work. Based on the above, the inspector concluded that
ventilation flow paths were not adequately considered and the sample was not
located as close to the workers as possible. This observation was considered
an apparent violation. (50-352/93-04-03)
The inspector further noted that 10 CFR 20.201 requires that' surveys be
performed that are necessary and reasonable under the circumstances to
evaluate the radiation hazartis present and comply with 10 CFR Part 20.
10 CFR 20.201(a) defines a survey as an evaluation of the radiation hazards
present and states that when appropriate, such evaluations include
measurements of the concentrations of radioactive material present. The
i
inspector noted surveys were necessary and reasonable to ensure compliance
with the respiratory use provisions and the exposure assessment provisions of-
The following additional matter was identified:
-
The inspector reviewed workers re-installing control rod drive position
,
indicating probes (PIPS). The inspector noted that the radiation work
permit that the workers were working under did not identify re-
installation of PIP probes as a " Task" to be performed. .Their
'
maintenance work request did identify the activity. The inspector's
review of the licensee's radiation work permit procedure indicated that
the procedure did not provide explicit guidance as to the scope of work
,
to be authorized to be performed under a radiation work permit. The
f
procedure also did not identify what should be entered under the RWP
" Task" section of the RWP.
The above observations and discussions with personnel indicated it was
unclear what level of detail was needed for the RWP work task
description. This was considered a program weakness.
9.0
Exit Meetings
i
The inspector met with licensee representatives (denoted in Section 1.0) on
January 22, February 3, 8 and 12,1993. The inspector summarized the purpose,
scope and findings of the inspection.
!
. )
Figure I
1
.
,
~ " , " '-yE
s
,
s-
, , .
..
g
.-
j
. g
-
i
,
.:
.-
.
,
,.
-
,
,
'
'
,:
- '
.y
.
.
I
a
.$.
,
-
.
~.
,
e
. (;
=i_
t.
I.
.
,
3
- -
.
v .,
.
,s.-
f
. .. .
.
a
.
.
g t -- *
',
,
.
g 4.)
7,
"
.
- - -
_ $-
.-
2
f~
y . .5 -.il
'
.
.
.J/
3
v$4' .
.
.
ll/
-
y=
.
Jp
-
,7 - ;
.
- n
.- Qf
,, . .
_ - ?. ';. [
p
.
..
. .
.
,
,
'
i
.
v
-
<
-
j
'
~
.
).
.
< ; r#. ,c.c
.
.
.
,
, .%..(f: &,,
h e
'
,y % 4
.
-
3
,
7
- p
7 ~37n _ .
_
o m.
..
,.h
.
- . . .
.
. . . . . .
sf
~~ *'at
-
-
' - =.'h (Q
?
'
.
g ..
-
.~,c ..L;.7c
..
.
.; .a
. _ , _
t
4
-
,
-
.
- - . . . - . .
.
.. -
v
e
.
,] .
..
.h l -
"
~
-
',
,D
' "
-
,
,
..
..
. . . .
_ _ ,
..
3
p
..
_
~
~~^*~~s.
-
~~ , ,
."..9
-
._ , ~~'
-
-
'l
..
.,
.
. ,
- . . _ ~ ~ ~
.
. _ _
n..
'
-
Depiction of TIP Probes
l
Under Unit 2 Pseactor
Vessel
l
s
s
]
i
I
'
_
-.
LCS bOR,VEY DETA SHEET 3.Fidure.2
Page __b of[
m avau 2.
R:dtt$n $ dontMinttion . Altborne
,
l_G7 9T-en<sdj . ; U' ti _1 [ . ] . UN
2'
. RADWASTE [ ] OTHER[ }
N
- N I-
h m'
S'UitVEf NO. DsIO'? SURVEY BY_
RW.P., NO.
DATE- *NlOh
TIME - 07 OO
AREA _r33 S b O b bilCE
'I M
REASON FOR SURVEY . N W $9';pnd{olOo'stnl CnM'3 M o ne,
if t'rument Type bM ' Serial No ? O SI'l Calibreddn tiweM3
RADIATION
instrument Type ' ~
Serial No.
- Calibration Due
'
, - erva
puma
serumiws
vow
g
i N
- \\-
\\
\\-
\\n
N
N-
2
N
e
sh n
a
N
\\-
\\
.
"N
\\
,KA
NN
'
4
s
M
\\
\\
\\
'~
c
N.
\\
\\-
\\
'
r
- \\
\\
\\
\\
e
>N
\\
\\
\\
CONT AMIN ATION
AIRBORNE
bM~ N
instrument Type
TIME S1 ART
STOP
Serial No.DRM - dalibration Due N-t-S b
AVE. FLOW RATE
CrM/ LPM
'[O
UNIDENTIFIED MPC
'"C""'
SEE ATTACHED SHEETS FOR
MPC FACTOR (NO MASK)
MPC-HRIHR
"
ADDITIONAL COUNTING DATA
REMARKS-
(T E M
Dew *n,,
w
ul- 10 0*/.
ua-o 4
i
p i o or
iv
2
V T on <-
e"*
'
&"' NP AHceA,A
ite ",
3
No<
+
- f!
- ^5
%Jann
4
Flomf
'MO ph. scm% ch;g.
- so*?? Yo '-
Y
s moe
-
.
es " gg pg
e
F lec> c
+
7
g)aj ]
!
QQR
I4 a rca g pry
ug
'
8
UJcdl
SOK
,
8
\\/Ja.H
SOK
Lc. A ~ u- o
'o
WEd l
8-to K
-
't
Ltotd th h h
Eso K
13 ~ Lend LMoA P_ax
HoK
2
i4
w
,
..
CONTAMINATION
Contamination
instrument Type FM N
Levels
Serial No.3*elW7 ~ dalibration Due N-I-9 3
Under Unit 2
doo ceu
4 go.aAinstrument ea;bround
k
Reactor
c
w-
. SEE ATTACHED SHEETS FOR
,,,_t
Vessel
A ITIONAL WNTING DATA
following
,,,%
removal of
ITEM
D"M"*'"'
- Y
TIPS and
1
F l o c>r ?
dispersal of
2
V \\ c>n-r
8
contamination
a
ptoo_c
4 b ",
WM
4
Floor
290"*!
s moe
6
F lo cy r
- $8
7
Wd)
QQK
8
()Jcd l
3OK
9
\\Mcd(
SOK
to
Wcal
NOK
Lto d f6ktn W -is
50K
't
12
L a d_ B k n E1 g
i-4 o K
13
N
14
-
,
Figure 3
Pa e No.
1
RESULTS OF UNIT 2 TIP TUBE SURVEYS
SORTED BY R0W
January 30, 1993
TIP
Contact Data
Contamination
Tube
Drive
Core
On Tube Ends
Inside Tubes
Row
Box
Location
(mrad /hr)
(dpm/Q-tip)
Comments
A
B
08-41
-
15k/40k
A
A
08-49
-
8k/6k
A
B
08-33
-
20r,/40k
A
B
08-17
24/40
200k/150k
A
B
08-25
8/-
80k 40k
B
A
16-49
-
45k 30k
1 Sli ht band
B
A
16-41
Bf 3
24k 80k
1 Sli ht bend
B
B
16-33
16/8
45k 15k
1 S14 ht bend
B
B-
16-17
8/ -
25k 8k
1 S11 ht bend, 1 Coupling:
B-
A-
16-57
-
26k 18k
B
B
16-25
-
24k 15k
2 Slf.ght bends
8k/ k
1 Singht bend
1 Coupling.
8/
/320
B
C
16-09
6000
560 mrad
Several slighf. bonds
C
E
24-41
6
4k
1 S11 ht bend
.1 Coupling
C
C
24-25
-
1 S11 ht bend, ling
6
16k
C
C
24-09
-
14 Ben
1 Coup
12
8k
C
C
24-17
-
C
B
24-33
8/-
28
10k
1 Sligbt bend
30k 35k
C
A
24-57
-
12k 25k
C
A
24-49
-
D
E
32-49
24000/12000
100
mrad
D
A
32-57
6k 5k
,
D'
C
32-25
8/-
6k 4k
1 Slight bend
D
C
32-09
-
5
4k
1 Coupling
D
C
32-17
8/16
3
3k
1 Cou ling
D
C
32-33
80/40
32 mrad
1 Sli ht bend
D
E
32-41-
1000/160
88 mrad
2 Sma 1 bends
E
C
40-09
-
8k/10k
1 Coupling
l--
E
D
40-17
-/16
80k 120k
E
D
40-25
-/8
20k 80k
E-
D
40-33
-
40k 30k
'
L
E
E
40-41
-/16
120 /300k
24k/30k
1 Slight kink 3'
from end
E
A
40-49
-
,
8k/20k
!
E
A
40-57
-
F
D
48-09
-
.20k 24k:
30
12k
l
F
D
48-17
--
l'
F
'D
48-25
-
20
16k
26
18k
.
F
D
48-33
-
l
F'
E
48-41-
12 48
88 -
ad
800-mrad /hr on' powder in bag
'
F
E-
48-49-
80 12
80 mrad
1 7 Rad /hr on powder.in bag
G
E
56-41
13 /16
130k/130k
Twisted
G
E
56-33
-
16 mrad /8 mrad
1 Slight bend
G
D
- 56-17
-
10k 10k
-1 Slight bend
12
18k
G
G
56-25.
-
.
~ .
.
,,
-
-
. .
- .
_ , _ - .
.-
. . .
. -
.
.-
...
.
. .
-
_
.
I
.,;
Figure 4
Page No.
1
'02/01/93
RESULTS OF UNIT 2 TIP TUBE SURVEYS
SORTED BY DRIVE BOX
January 30, 1993
TIP
Contact Beta
Contamination
Tube
Drive
Core
On Tube Ends
Inside Tubes
Row
Box
Location
(mrad /hr)
(dpm/Q-tip)
Commer*.s
A
A
08-49
-
8k/ k
45k 30k
1 Slight bend
B
A
16-49
-
B
A
16-41
8/8
24k 80k
1 Slight bend
B
A
16-57
-
26k 18k
30k 35k
C
A
24-57
-
C-
A
24-49
-
12k 25k
6k/ k
D
A
32-57
-
24k/30k
1 Slight kink 3'
from end
E
A
40-49
-
8k/20k
E
A
40-57
-
A
B
08-41
-
15K 40k
20k 40k
A-
B
08-33
-
A
B
08-17
24/40
200 /150k
80k 40k
8/ 8
A
B
08-25
16/
45k 15k
1 Sli ht bend
B-
B
16-33
B
B
16-17
8/-
25k 8k
1 S14 ht bend, 1 Coupling
24k 15k
2 S11 ht bends
B
B
16-25
-
C
B
24-33
8/-
28k lok
1 Sln ht bend
B
C
16-09
8/-
8k
k
1 Sla ht bend,
C
C
24-25
-
6
4k
1 S14 ht bend
1 Slidht bend, lino.1-Coupling
C
C
24-09
-
6k 16k
1 Bend [1t bend 1 Coup
C
C
24-17
-
12 /8k
'
'
1 Slig
D
C
32-25
8/-
6
4k
Sk 4k
1 Coupling
D
C
32-09
-
D
C
32-17
8/16
3k 3k
1 Coupling
D-
C
32-33
80/40
32 mrad
1 Slight bend
E
C
40-09
-
8k/10k
1 Coupling
G
D
56-17
-
10k 10k
1 Slight Dend
12k 18k
G
D
56-25
-
26k 18k
F
D
48-33
-
E
D
40-17
-/16
80k 120k
E
D
40-25
-/8
20k 80k
E
D
40-33
-
40k 30k
F
D
48-09
-
-20k 24k
F
D
48-17
-
30k 12k
20k 16k
F
D'
48-25
-
C
E
24-41
6000/320
560 mrad
Several slight bends
D
E
32-49
24000/12000
1000 mrad'
D-
E
32-41
~1000/160
88 mrad
2 Small bends
G
E
56-41
136/16
130k/130k
Twisted
16 mrad /8 mrad
1 Slight bend
-G
E
56-33
-
800 mRa/hr on powder in bagd/hr on powder in bag
F*
E
.48-49
80 12
80. mrad
1.2 Rad
F
E.
48-41-
12 48
88 mrad
E
E'
40-41.
-/ 6
120k/300k
\\
L/
- -
_
.
.
.
. .
. -
. .
. .
. -
. _ _ ,-
~.
_ _ . .
_
.
..
-
._
,
!
A
P
FIGURE 5
5
'
.
' UN'lT 2 RX-253' ELEV NORTHEAST QUADRANT
~MI
Moster Mop 2R2530, Unit 2 Areo
14
Enclosure
RX Elevotion 253
R
475
.
///, nom
Survey Type: Routine d Speciol O Cornbinotion fl Surveyor T bru >
t'n-
,
/
w-
%
i
Survey y DMN RWP f M 2%11%)1) Dole 2 Il 'l',}
Tirne .OMT
Power Level
Sll'
?.
me.i ,
..o...,
~
_ . . -
.
.
'
f
,s.'
. . . . ,
. -
- ~
$-
RlN
,
~
/
Boy
%
,/
--
--- - y _ -- -- y _
y,
f . - - ' Y
l2.
i
b
42
-'
s,
/
l.
A
$6'
1
L
99pl -
,
,-
Q ch g,
y i (, t,N
~~L.
m,_
,
% MOL
'
,
d
V.\\ ,
'h'
OL% (AN,
,
"g
pl PLM6
'
2s
A1
.).k as
y
m
e
h
IS inches () '
Generet Arco O
meor d
Contact
.---
- - - - - - - - - - - - - - - - - _- -
CONTAMINATION
AIRBORNE
Instrument Type 2 '
TIME START %D
STOP Ylid
Serial No.Y*r iT E
Calibration Due $~ 85 13
h/ LPM
AV . FLOW RATE
I
instrument Background IDD
UNIDENTIFIED MPC * b
SEE ATTACHED SHEETS F00t
""D C**
MPC FACTOR (NO MASK)
' M PC-HRlHR
f
ADDITIONAL COUNTING DATA
,
,
ITE M
DPn4000ctsi.
REMARKS-
1
~dsor6
T orrel
@ E -T5 9 ^,q a a.3 .
e
,
2
by
,g ma
g gg,g r,4 ; g a3 p,o'wdrm stre
!
3
%t
y
3, :ur5xw ex w u ,c.c m .
A
%t.
(g ~
@If5 f By \\Quu,go mD DcjMb.
l
5
ram
70K
3pgEA M Y Eu D 6-)"
6
El& Lenth
13 <
cw w no 3m s
x <m t
c
7
3/4 L (%dCl%%)
'/ % :d
emE h
d
i) # ' ..i y G6 ppguns )
j7g
.g ge, ,q 7ygj tp,
y pif4 , n# F J
8
'9 % -
lat
van a w tua
t
2
10
bb
(,) g -
g m e w F S E- Der:r ear L * M
11
Wu Mst
1(nmd
DE*' 5
%
y'
@ MEM E*O ** U# # DM
12
Tp4(.*J.4."(::#"fd
13
Pi , uy,,,,
p
t
34
3
NK -
h h NdTdWDgg( A
I
10
he Orm ita - 1Pr# # %euo@i
l
m
t
'
e
&
h
_
_
.
-
_
_
_
._
..
_.
__
_.
_ _ _
_
.:
_' Enclosure 2
' P&A ' 1 of rw
_
-
.,
Medman magister / vot sr..f&n 133 f Pddsy, July to, tear / Notkne
l
-
- .sgyes .
_
.
Assenesse: Seed assumente to:h .
. Soaretary of the Comumiestem. U.S. '
Naciser stagelatery thim-na.
.
,
Wealdoston.DC assas. ATIN:
,
Deckettes and Servias Bseech.
Head dehver assumente to: One White
'
. Flint North,11588 Itodnreie pike.
Itockvdle,hdD between y:45 am, to 435
-
'
pm Federalworkdays.
Copies of esammeste amey be examined
.
at the NRC public Domesent itcom. 2120
!
LStreet.NW.(Lawer level).
<
-
,
pee ousnesen asesenavisse eestract:
.
.
-
JenseIJobenssa.Dissator.OIRes of
Enfessement. U.S. Neeleer 3tegulatory .
c- Weebtegen.DC 20555
l
(301406 8F41). -
j
supptsamervaav speessaviesc
Redigmand
1he NitCe emnetydicy en
enforeement asefassenes le addrewed in
SeoemaV etthelatestrevielen to the
- General eama====e of
and
l
"
-
Precedese derBadenament
Sudessement pahey)toCFR part 2.
'
1ses)
5.
modernement
etense that. '
"undsseemans
wig mot
>
.masmally beopento the public."
.
!
,
Hewever.toComadsehenhas decided
~i
toimplementa mealpeuyento
dessemisewhoshertoseeistata the
cenemtpelky witirsegard to -
enforcement esaferseems or.to adopt a
<
'
28w paikythat wenid allow sonst ;
TWre>VeerTrM W 9er
enfassement esoferomeen to be open io
1
'
Condesting r.1peaEnfereement
attsedsmenby alimembersof the public. -
- l
consereescarnesysessensent
Feiky h
amusenNr aer .pt.a y
,
pg,g3,,
c
m
Comedenha ,
- "*"
1heIGC le 6-pla===.a.g a two-year
- J
trialpayen to aGew public
sumenesv TheNedeseRegelsemey
elusenettenof selected enforcement
r = ms
s== p m Clieteostas ele pokey eselssemene.The NitC wGI monitor the
'
steam memaemtheimplementeilseof a
P'88'en and detesmine wintiwr io
two year trial paspese es essw antamad establish a pommensetpolicy for .
-
enferoament essessemous to be span te
sendoseles
enfemument
attuadcoesby su members of the .
. ***Iunene
se en aseosoment of
generetpuhuc.This peNcy statement
' the feBowlegesteele _
describes the twoyeartrialpeepean
(t) Whelber the foot that the -
andledenne the publicof how to get
condammes wee opsaimpsoned the .
,
infensatiesse
spea
' NilC's shikty to esadent a sneeningful :
soferoament
osademons and/or mpA====t the NRCs
a
oaves:'fhis trialproyenteM on
'"I'""""8 P'*8""
July to. test,widle sommente se the
(3)Whetherthespeaconference =
propen ese beag suceived.Subsek
impacted the basesse's participation in
aa====to en er tiefere the compieden
thecad"emam
of tin treetinngres edadeled for July -
(s)Whetherthe NitCexpended a
St. seer. r'a====ea received after tids
a%=me==* emenet of resources in '
date welbs considered if it is practical
. to do me, but the G "to de able to
maldag the confeeence public: and'
(4)m exeset of publicinterest E
assure e===M-'stion only for commente .
received on or before this date.
opening the enforcement conference,
-
.
. - .
.
- - -
.
.-
.
. .
.
.
f.nclosure 2
Pd90 2 01 4
_
!
oL g No. 223 / Mday, Jidy la N 'gh
as
Federal Register u
.
..
-
t cissede rar seiseeingOpse
three c
1 of hoennese wGlbe
subjed to penemmel eczoenies.thet
.
gefassement ch
comenerdal operating reactora,
eigen, beamere, poseers. etc. not larger
be
hospitA.and other haveneeen, whide
thea ts" be ,
'i and that
7
will consist of the t===ining types of
disrupthe y====a sney be removed.
licensees.
Each reglemal adbo wiH swmema. to
oPea
. _
2a
W
lie tahan esainst as
IL A
- Open Beforcement
cadeQderoames conference
indivedmal, or if the act6en, thoesh met
Confusences '
yl
"
,
alturne
[gasa ne an
As soon as itle deteradned that an
wGl aa-Ha== to be a mes&is h
enforcement conference wGI be open to
b NRCand the beenees. Whus b
4
._ _ m _.
public oboarvation. the NRC wG1 orally
enforcement osafersece le open for
[
-g
h*
a tify the licensee that the enforcement puhuc observedea, h is am open for
involved {"kd conf: ~;.e-m wpen to p bue
pobge pe,en, sue ,
!
. hatabeIdivkl
oburvation as part of the agency's tdal
Pereens attending open enforweient
t
Prment
Program and send the Boonsee a copy of conferomoes are remiaM ed (1) b
(3)le basedonthe Sadings danNRC &le Fdud Regisawmodce ed paena swmgg
Once ofImmdgjenomejogsoport;or
the program.uoenmes wm be asked to egm
e,.,g
.e dg P"e
p[ll?e.eg g,g,,Inden or owm 6e -'
dule an
d-ge,ser w any,eeews
-
atinists the member of parecipante M
funbarseetow and may be subject to
-' =d-
ige
,aorbi,bcouidbe
m_ed
so that the NRC can sche
enferosmos aedom and(2) &e
.
Eniwamen},,,
inwhg
Nh,
"
appropetan*
NR
t
g g
overeupossess wGlbe open assuming
h
pen enforcement conferen,== or the
heebeen
Aetd-_t :'g:::l=d
- ,g ,i taw a= a - a- a *
iTre*e "rifrM.' *Illll'd ",, beuef,.
-
.
.e
1
"
" " " ' " " * "
en,.r m t.o e.In additi.m.be
edo,_=. ca.fere. css to .nce opene , abbe
wH 6e
in &ie modos. perms
Indiv6dael's nam
The NRC latende to annou
gee,- <e
- = a--
.
me.oes w
cpen to the pddio if the conference wGI normauy at least to working days in
span ht mderaces
8"m be
ida - o.,oamer e
be. conducted.by telephone or the
. .e
. be.au.ta m .
edvance.of t,he o.forcement conference
en
w
eo
mg .-
e*= wa- -mme- --Fooar
th,o,.gh . css ,oetu t. .e ,s
rei. d ,em an u.s.a.e ef.e m ,.
n No
"~
" ."."e' d .' 1 T t, $ '
T ;e i ,a we
22ll"a**"Cfww.rm
R
,e
O'***' d **
- I
II
,
enforcement conferences wtB not be
(3) Toll-free electraalc belions board
h and caseidero6an,
opentothepublictaspedalcesse
wbenegoodseems hasbeen aboom after
establishanentof thetoBitw
Deled as assiMils han, een rih day of July
beleedes thebeneSt of puhuc
mesesse eyseases, the public may anil
test.
cbeareemos agalast thepetential hopect (Stn) 4es 4r32 to 48=8a a reeertling of
for en Hadser Raedsamrys'-mo.
on the assacre enfermemmet action in a upanaeng spea enforesument
- %sment 0 Oinv
particularcase.
confer ==a== De NRC wEl tesse another s.creearyetde <*-m.
- De NRC wG1 strtve to conduct open
Fedomi Regletar m.Atee after the tou-free p Doc.so-sense rund 74 es:a4s aM
enforcement onaferences dartas the -
mesease erseems are-dh
esauses re e
two year trial progress in accordamos
To endet the NRC h seeddag
with the fauseus three goals:
a
to arrangemente to ag. pert
(1) .t .
=- dyas perant of au
pu ucobservenenetenseseement
m
eligible amieroommes confeemose
conferesses,endwiduale sannessed in
--
c demed by esNRCwCIbe open for
attendtag a panlaster enformnemt
puhuc beernoas
ca.f.e o.abeeldmostr sins. ded
CorreCilOnS
'ed"d **'
e
v
(2) At Isset ame open seiertement
id-nen=d in the noseng action
conference wd1 be conductedia each of anneandag the open enforcement
'
vel.1sr, No. tse
the reponalomcas:and
. confereses ao later thea Sve busiasse
Frtder. Idy tr. toes
(3)Open enlomassatsemieresses
days pr6er to the enforeneeset
wiu be conductedwit avenetyof the
confersone.
NUCLEAM HEtKA.ATORY
types of heenseen.
U
of Open Entwomment
Cotth81gg8088
To evoid poten6albianla the
Corderences
-
selection process and to attempt to meet
the three goele stated abees,every
in eooordemos with cement proctice.
Ttoo Yner Trtal program for-
fourth obsible safemament eenierence
enforcement conferences will continue
Censluctng OpenN
to norunnu be held at the NRC tagia 1
Conferenose; posey Statement
involving one of three categories of
r
bcensees wGimariseur be span to the
omces.Membere of the pubhc wGl be
Comredan
pubBc dertog the trial propea.
sllowed access to the NRC regional
However,in came where there le en
omos to eetend open enlare== ant
la notice dar===at 92162s3 bWng
ongotag edtudicatory proceeding with
conferences in accordance with the
on page Mrs2 h es leeue GM.
one er amore totervenore, enforcement
" Standard Opereting pmda For
}dy.181est on page 307t2.in &e
ww=d cohena.ander sans,
conferwoons lavolving teones related to
Providing Security Sapport For NRC
b subject metteraf the seemag
Hearmge And Meetings" pubhehed
la the fifth Hoa.,, July 11.19e2"
,
edjudiesdos mey also be opened.For
November,1,1 set (56 l'R Sc51). Thege
reed ") sly it im".
b purposes of this trialprogram, the
procedures provide that visitors mey be
- u-a came u
e
- - -
.
- -
-
- .
- .
.
-
- -- -
-