ML20010B959
| ML20010B959 | |
| Person / Time | |
|---|---|
| Site: | Wolf Creek, Cooper, Arkansas Nuclear, River Bend, Waterford, South Texas, Comanche Peak, Fort Calhoun, Fort Saint Vrain |
| Issue date: | 07/21/1981 |
| From: | Seyfrit K NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| To: | ARKANSAS POWER & LIGHT CO., GULF STATES UTILITIES CO., HOUSTON LIGHTING & POWER CO., KANSAS GAS & ELECTRIC CO., LOUISIANA POWER & LIGHT CO., NEBRASKA PUBLIC POWER DISTRICT, OMAHA PUBLIC POWER DISTRICT, PUBLIC SERVICE CO. OF COLORADO, TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC) |
| References | |
| NUDOCS 8108180537 | |
| Download: ML20010B959 (2) | |
Text
- '
g
'g UNITED 3TATEC E
NUCLEAR REGULATORY COMMISSION g
j, p
REGION IV g
p ett CY AN PLAZA CT.IVE. SUITE 1000 ARLINGTON, TEXA5 76011 July 21, 1981
,f%
($ d.[11b *
, ( AU21171981> ['t u.a g y C>
1 Gentlemen:
4 e
v The enclosed IE Infannation Notice is provided as an early notification of a possibly s.ignificant matter.
It is expected that recipients will review the infonnation for possible applicability to their facility. No specific action or response is requested at this time.
If further NRC evaluations so indicate, an IE circular or bulletin will be issued to recommend or request specific licensee actions.
If you have questions regarding this matter, please contact this office.
Sincerely, i
-Q-i
'Karl [,. Seyfri Mt Director
Enclosures:
1.
IE Infonnation Notice No. 81-21 2.
List of Recently Issued IE Information Notice cc:
D. W. Warembourg, Nuclear Production Manager Fort St. Vrain Nuclear Station ainb' % 15 P. O. Box 368 f /d; Platteville, Colorado 80651 r
Of S
J. Gahm, Quality Assurance
'QO Si g
l
'l c
8108180537 81G721 5
PDR ADOCK 05000267 G
[
!l
e i
IE INFORMATION NOTICE 81-21 SENT TO THE FOLLOWING LISTED LICE'. IES:
Licensee Facility / Docket Number Arkansas Power and Light Conpany Arkansas Nuclear One, Unit 1 & 2 Little Rock, Arkansas 50-313; 50-368 Nebraska Public Power District Cooper Nuclear Station Columbus, Nebraska 50-298 Omaha Public Power District Fort Calhoun Station Omaha, Nebraska 50-285 Public Service Company of Colorado Fort St. Vrain Generating Station Denver, Colorado 50-267 Gulf States Utilities River Bend Beaumont, Texas 50-458; 50-459 Houston Lighting & Power Company South Texas' Project Houston, Texas 50-498; 50-499 Kansas Gas & Electric Company Wolf Creek Wichita, Kansas STN 50-482 I
Louisiana Power & Light Company Waterford-3 New Orleans, Loulslana 50-382 Texac Utilities Generating Company Comanche Peak Steam Electric Station Dallas, Texas 50-445; 50-446 l
l I
i l
l
~
SSIN No.:
6835 Accession No.:
810330402 IN 81-21 UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, D.C.
20555 IE Information Notice No. 81-21 July 21, 1981 Page 1 of 3 POTENTIAL LOSS OF DIRECT ACCESS TO UL164 ATE HEAT SINK Description of Circumstances:
IE Bulletin 81-03, issued April 10, 1981, requested licensees to take certain actions to prevent and detect flow blockage caused by Asiatic clams and mussels.
Since then, one event at San Onofre Unit I and two events at the Brunswick Station have indicated that situations not explicitly discussed in Bulletin 81-03 may occur and result in a loss of direct access to the ultimate heat sink.
These situations are:
1.
Debris from shell fish other than Asiatic clams and mussels may cause flow blockage problems essentially identical to those described in the bulletin.
2.
Flow blockage in heat exchangers use.high pressure drops that, in turn, deform baffles, allowing P
. low and reducing the pressure drop to near normal values.
Once.iiis occurs, heat exchanger flow blockage may not be detectable by pressure drop measurements.
3.
Change in operating conditions.
(A lengthy outage with no flow through seawater systems appears to have permitted a buildup of mussels in systems where previous periodic inspections over more than a ten year period showed no appreciable problem.)
We are currently reviewing these events and the responses of the licensees to IEB 81-03. We expect licensees are performing the actions specified in IEB 81-03 such that cooling water flow blockage from any shell fish is prevented or minimized, and is detected before safety components become inoperable.
On June 9, 1981, San Onofre Nuclear Generating Station Unit No. 1 reported that as a result of a low saltwater coolant flow rate indication and an apparent need for valve maintenance, a piping elbow on the saltwater discharge line from component cooling heat exchanger E-20A was removed by the licensee just upstream of butterfly valve 12"-50-415 to permit visual inspection.
An examination revealed growth of some form of sea mollusk such that the cross-sectional diameter of the piping was reduced.
The movement of the butterfly valve was impaired and some blockage of the heat exchanger tube sheet had occurred.
Evaluation of the event at San Onofre is continuing.
i I
IN 81-21 July 21, 1981 Page 2 of 3 However, the prolonged (since April 1980) reactor shutQ wn for refueling and steam generator repair is believed to have c.iused the problem since previous routine inspections conducied since 1968 at 18 month intervals had not revealed mollusks during normal periods of operation.
Two events at Brunswick involved service water flow blockage and inoperability of redundant residual heat removal (RHR) heat exchangers, primarily due to oyster shells blocking the service water flow through the heat exchanger tubes.
On April 25, 1981, at Brunswick Unit 1, while in cold shutdown during a maintenance outage, the normal decay heat renoval system was lost when the single RHR heat exchanger in service failed.
The failure occurred when the starting af a second RHR service water pump caused the failure of a ba'fle in the waterbox of the RHR heat exchanger, allowing cooling water to bypass the tube bundle. The heat exchanger is U-tube type, with the se*vice water inlet and oatlet separated by a baffle.
The copper nickel baffle which was welded to the copper-nickel tubesheet deflected and failed when increased pressure was produced by starting the second service wate pump.
The redundant heat exchanger was inoperable due to maintenance in prog uss to repair its baffle which had previously deflected (LER 1-81-32, dated May 19,1981).
The licensee promptly established an alternate heat removal alignment using the spent fuel pool pumps and heat exchangers.
As a result of the problems discovered Nith Unit 1 RHR heat exchangers, a special inspection of the Unit 2 RHR heat exchangers was performed while Unit 2 was at power.
Examination of RHR heat exchanger 2A using ultrasonic techniques indicated no baffle displacement but flow testing indicated an excessive pressure drop across the heat exchanger.
This heat exchanger was declared inoperable.
Examination of the 28 RHR heat exchanger using ultrasonic and differential pressure measurements indicated that the baffle plate was damaged.
The licensee initiated a shutdown using the 2A RHR heat exchanger at reduced capacity (LER 2-81-49, dated May 20,1981).
The failure of the baffle was attributed to excessive differential pressure caused by blockage of the heat exc. Sanger tubes. The blockage was caused by the shells of oysters with minor amounts of other types of shells which were swept into the heads of the heat exchangers since they are the low point in the service water system.
The shells resulted from an infestation of oysters growing primarily in the 30" header from the intake structure to the reactor building. As the oysters died their upper shells detached and were swept into the RHR heat exchangers where they collected.
Small amounts of shells were found in other heat exchangers cooled by service water.
Most of the operating BWRs use U-tube heat exchangers in the RHR system.
(The heat exchangers used at Brunswick were manufactured by Perflex Corporation and are identified as type CEU, size 52-8-144.)
The observed failures raise a question on the adequacy of the baffle design to withstand differential pressures that could reasonably be expected during long-term post accident operatien.
However, it ;hould be noted that since the baffles at Brunswick are solid copper-nickel as are the tubesheets and the water boxes are copper-nickel clad, the strength of the baffles and the t
IN 81-21 July 21, 1981 Page 3 of 3 baffle welds is somewhat less than similar heat exchangers made from carbon steel.
Therefore, heat exchangers in other BWR's may be able to tolerate higher differential pressure than that at Brunswick without baffle deflection.
(Brunswick opted for copper-nickel due to its high corrosion and fouling resistance in a salt water environment.)
The use of differential pressure (dp) sensing between inlet and outlet to deteinine heat exchanger operability should consider that baffle failure could give an acceptable dp and flow indications and thereby mask incapability for heat removal.
However, it is noted that shell blockage in a single pass, straight-through heat exchanger can readily be detected by flow and dp measurement.
Evaluation of the events at Brunswick is still continuing.
Under conditions of an inoperable RHR system, heat rejection to the ultimate heat sink is typically through the main condenser or through the spent fuel pool coolers.
This latter path consists of the spent fuel pool pumps and heat exchanger with the reactor building closed cooling water system as an intermediate system which transfers the heat to the service water system via a single pass heat exchanger.
These two means (i.e., main condenser or spent fuel pool) are not c onsidered to be reliable long-term system alignments under accident conditions.
This information is provided as a notification of a possibly significant matter that is still under review by the NRC staff.
The events at Brunswick and San Onofre emphasize the need for licensees to initiate appropriate actions as requested by IEB 81-03 for any credible type of shell fish or other marine organists; e.g., fresh water sponges, (not only asiatic r. lams and mussels).
In case the continuing NRC review finds that specific licensee actions would be appropriate, a supplement to IEB Bulletin 81-03 may be issued.
In the interim, we expect that licensees will review this information for applicability to their facilities.
No written response to this information is required.
If you need additiona' information regarding this matter, please contact the Director of the appro-priate NRC Regional Office.
t r.
IE Information Notice No. 81-21 July 21, 1981 LISTING OF RECENTLY ISSUED IE INFORMATION NOTICES Information Subject Date Issued To Notice No.
Issued 81-12 Guidance on Order Issued 3/31/81 All BWR facilities January 9, 1981 Regarding with an Operating License Automatic Control Rod (0L) or Construction Insertion on Low Control Permit (CP)
Air Pressure 81-13 Jammed Source Rack in a 4/14/81 Specified Irradiator Gamma Irradiator licensees 81-14 Potential Overstress of 4/17/81 All power reactor Shafts on FisM r Series facilities with an 9200 Butterfly Valves Operati.ig License (OL) with Expandable T Rings 81-15 Degradation of Automatic 4/22/81 All power reactor ECCS Actuation Capability facilities with an by Isclation of Instrument Operating License (0L)
Lines or Construction Permit (CP) 81-16 Control Rod Drive System 4/23/81 All power reactor Malfunctions facili'ies with an Operating License (0L) or Construction Permit (CP) 81-18 Excessive Radiation 6/23/81 Specified licensees Exposures to the Fingers of holding byproduct Three individuals Incurred licenses During Cleaning and Wipe Testing of Radioactive Sealed Sources at a Sealed-Source Mar.ufacturing Facility l
81-19 Lost Parts in Primary 7/6/81 All power reactor Coolant System facilities with an Operating License (0L) or Construction Permit (CP) 81-20 Test Failures of Electrical 7/13/81 All power reactor Pcnetration Assemblies facilities with an Operating License 10L) or Construction Permit (CP)
Enclosure
.